Top Banner
Michigan Department of Transportation 5100B (03/18) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB NUMBER (JN) CONTROL SECTION (CS) DESCRIPTION MDOT PROJECT MANAGER: Check all items to be included in RFP. WHITE = REQUIRED ** = OPTIONAL Check the appropriate Tier in the box below CONSULTANT: Provide only checked items below in proposal When applicable, Best Value scoring criteria is listed separately in the RFP. TIER 1 ($50,000 - $150,000) TIER II ($150,000-$1,000,000) TIER III (>$1,000,000) Understanding of Service ** Innovations Organizational Chart Qualifications of Team Quality Assurance/Quality Control ** Location: The percentage of work performed in Michigan will be used for all selections unless the project is for on-site inspection or survey activities, then location should be scored using the distance from the consultant office to the on-site inspection or survey activity. N/A N/A Presentation ** N/A N/A Technical Proposal (if Presentation is required) 7 pages (MDOT Forms not counted) 14 pages (MDOT forms not counted) Total maximum pages for RFP not including key personnel resumes. Resumes limited to 2 pages per key staff personnel. PROPOSAL AND BID SHEET E-MAIL ADDRESS – [email protected] GENERAL INFORMATION Any questions relative to the scope of services must be submitted by e-mail to the MDOT Project Manager. Questions must be received by the Project Manager at least five (5) working days prior to the due date and time specified above. All questions and answers will be placed on the MDOT website as soon as possible after receipt of the questions, and at least three (3) days prior to the RFP due date deadline. The names of vendors submitting questions will not be disclosed. MDOT is an equal opportunity employer and MDOT DBE firms are encouraged to apply. The participating DBE firm, as currently certified by MDOT’s Office of Equal Opportunity, shall be listed in the Proposal. MDOT FORMS REQUIRED AS PART OF PROPOSAL SUBMISSION 5100D – Request for Proposal Cover Sheet 5100J – Consultant Data and Signature Sheet (Required for all firms performing non-prequalified services on this project.) (These forms are not included in the proposal maximum page count.) N/A N/A N/A 3 pages (MDOT Forms not counted) Resumes will only be accepted for Best Value Selections. The Consultants will receive an e-mail reply/notification from MDOT when the proposal is received. Please retain a copy of this e-mail as proof that the proposal was received on time. Consultants are responsible for ensuring that MDOT receives the proposal on time. * Contact Contract Services Division immediately at 517-373-4680 if you do not get an auto response.
22

Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

May 06, 2018

Download

Documents

vokiet
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Michigan Department of Transportation

5100B (03/18) CHECKLIST TO DESIGNATE AREAS OF EVALUATION

FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2

REQUISITION NUMBER DUE DATE TIME DUE

MDOT PROJECT MANAGER JOB NUMBER (JN) CONTROL SECTION (CS)

DESCRIPTION

MDOT PROJECT MANAGER: Check all items to be included in RFP.

WHITE = REQUIRED ** = OPTIONAL

Check the appropriate Tier in the box below

CONSULTANT: Provide only checked items below in proposal When applicable, Best Value scoring criteria is listed separately in the RFP.

TIER 1 ($50,000 - $150,000)

TIER II ($150,000-$1,000,000)

TIER III (>$1,000,000)

Understanding of Service **

Innovations

Organizational Chart

Qualifications of Team

Quality Assurance/Quality Control **

Location: The percentage of work performed in Michigan will be used for all selections unless the project is for on-site inspection or survey activities, then location should be scored using the distance from the consultant office to the on-site inspection or survey activity.

N/A N/A Presentation **

N/A N/A Technical Proposal (if Presentation is required) 7 pages (MDOT

Forms not counted) 14 pages (MDOT forms not counted)

Total maximum pages for RFP not including key personnel resumes. Resumes limited to 2 pages per key staff personnel.

PROPOSAL AND BID SHEET E-MAIL ADDRESS – [email protected]

GENERAL INFORMATION

Any questions relative to the scope of services must be submitted by e-mail to the MDOT Project Manager. Questions must be received by the Project Manager at least five (5) working days prior to the due date and time specified above. All questions and answers will be placed on the MDOT website as soon as possible after receipt of the questions, and at least three (3) days prior to the RFP due date deadline. The names of vendors submitting questions will not be disclosed.

MDOT is an equal opportunity employer and MDOT DBE firms are encouraged to apply. The participating DBE firm, as currently certified by MDOT’s Office of Equal Opportunity, shall be listed in the Proposal.

MDOT FORMS REQUIRED AS PART OF PROPOSAL SUBMISSION

5100D – Request for Proposal Cover Sheet 5100J – Consultant Data and Signature Sheet (Required for all firms performing non-prequalified services on this project.)

(These forms are not included in the proposal maximum page count.)

N/A

N/A N/A

3 pages (MDOT Forms not counted) Resumes will only

be accepted for Best Value Selections.

The Consultants will receive an e-mail reply/notification from MDOT when the proposal is received. Please retain a copy of this e-mail as proof that the proposal was received on time. Consultants are responsible for ensuring that MDOT receives the proposal on time.* Contact Contract Services Division immediately at 517-373-4680 if you do not get an auto response.

Page 2: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

MDOT 5100B (03/18) Page 2 of 2

The Michigan Department of Transportation (MDOT) is seeking professional services for the project contained in the attached scope of services.

If your firm is interested in providing services, please indicate your interest by submitting a Proposal, Proposal/Bid Sheet or Bid Sheet as indicated below. The documents must be submitted in accordance with the latest (Consultant/Vendor Selection Guidelines for Services Contracts.”

RFP SPECIFIC INFORMATION

ENGINEERING SERVICES BUREAU OF TRANSPORTATION PLANNING OTHER

THE SERVICE WAS POSTED ON THE ANTICIPATED QUARTERLY REQUESTS FOR PROPOSALS NO YES DATED ____________________ THROUGH __________________

Prequalified Services – See the attached Scope of Services for required Prequalification Classifications.

Non-Prequalified Services – If selected, the vendor must make sure that current financial information, including labor rates, overhead computations, and financial statements, is on file with MDOT’s Office of Commission AuditsThis information must be on file for the prime vendor andall sub vendors so that the contract will not be delayed. Form 5100J is required with proposal for all firms performing non-prequalified services on this project.

For all Qualifications Based Selections, the selection team will review the information submitted and will select the firm considered most qualified to perform the services based on the proposals. The selected firm will be asked to prepare a priced proposal. Negotiations will be conducted with the firm selected.

For a cost plus fixed fee contract, the selected vendor must have a cost accounting system to support a cost plus fixed fee contract. This type of system has a job-order cost accounting system for the recording and accumulation of costs incurred under its contracts. Each project is assigned a job number so that costs may be segregated and accumulated in the vendor’s job-order accounting system.

Qualification Based Selection / Low Bid – Use Consultant/Vendor Selection Guidelines. See Bid Sheet instructions for additional information.

For Qualification Review/Low Bid selections, the selection team will review the proposals submitted. The vendor that has met established qualification threshold and with the lowest bid will be selected.

Best Value – Use Consultant/Vendor Selection Guidelines, See Bid Sheet Instructions below for additional information. The bid amount is a component of the total proposal score, not the determining factor of the selection.

Low Bid (no qualifications review required – no proposal required.)

BID SHEET INSTRUCTIONS

Bid Sheet(s) are located at the end of the Scope of Services. Submit bid sheet(s) with the proposal, to the email address: [email protected]. Failure to comply with this procedure may result in your bid being rejected from consideration.

MDOT and ACEC created a Partnership Charter Agreement which establishes guidelines to assist MDOT and Consultants in successful partnering. Both the Consultant and MDOT Project Manager are reminded to review the ACEC-MDOTPartnership Charter Agreement and are asked to follow all communications, issues resolution and other procedures and guidance’s contained therein.

Qualification Based Selection - Use Consultant/Vendor Selection Guidelines.

PARTNERSHIP CHARTER AGREEMENT

Page 3: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

PROPOSAL REQUIREMENTS

Proposals must be submitted for this project electronically. Proposal submittal requirements are

listed in PART IV – INSTRUCTION FOR SUBMITTING PROPOSALS

at the following link http://www.michigan.gov/documents/MDOT_Consultant-

Vendor_Selection_Guidelines-0106_145222_7.pdf?20150707153457

FINANCIAL REQUIREMENTS FOR NON-PREQUALIFIED VENDORS

http://www.michigan.gov/documents/mdot/Financial_Requirements_for_Non_Prequalified_Ven

dors_605817_7.pdf

E-VERIFY REQUIREMENTS

E-Verify is an Internet based system that allows an employer, using information reported on an

employee’s Form I-9, Employment Eligibility Verification, to determine the eligibility of that

employee to work in the United States. There is no charge to employers to use E-Verify. The

E-Verify system is operated by the Department of Homeland Security (DHS) in partnership with

the Social Security Administration. E-Verify is available in Spanish.

The State of Michigan is requiring, under Public Act 200 of 2012, Section 381, that as a

condition of each contract or subcontract for construction, maintenance, or engineering services

that the pre-qualified contractor or subcontractor agree to use the E-Verify system to verify that

all persons hired during the contract term by the contractor or subcontractor are legally present

and authorized to work in the United States.

Information on registration for and use of the E-Verify program can be obtained via the Internet

at the DHS Web site: http://www.dhs.gov/E-Verify.

The documentation supporting the usage of the E-Verify system must be maintained by each

consultant and be made available to MDOT upon request.

It is the responsibility of the prime consultant to include the E-Verify requirement documented in

this NOTIFICATION in all tiers of subcontracts.

DIGITAL SIGNATURE OF CONTRACTS

On January 1, 2018, Contract Services Division intends to fully implement the use of CoSign as

the exclusive software for digitally signing all consultant contracts and consultant contract

related documents. All other digital signing methods will no longer be accepted.

Prior to using CoSign, all external partners must apply for a free digital signature user account by

submitting a MDOT Digital Signature Certificate Request Form.

Page 4: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

2017 Insurance Update – MDOT 3.9.17

At a minimum, the insurance types and limits identified below, may be required from the selected consultant, prior to contract award.

.

Required Limits Additional Requirements

Commercial General Liability Insurance

Minimal Limits:

$1,000,000 Each Occurrence Limit

$1,000,000 Personal & Advertising Injury Limit

$2,000,000 General Aggregate Limit

$2,000,000 Products/Completed Operations

Consultants must have their policy endorsed

to add “the State of Michigan, its

departments, divisions, agencies, offices,

commissions, officers, employees, and

agents” as additional insureds

Automobile Liability Insurance

Minimal Limits:

$1,000,000 Per Occurrence

Workers' Compensation Insurance

Minimal Limits:

Coverage according to applicable laws

governing work activities.

Waiver of subrogation, except where waiver is

prohibited by law.

Employers Liability Insurance

Minimal Limits:

$500,000 Each Accident

$500,000 Each Employee by Disease

$500,000 Aggregate Disease

Professional Liability (Errors and Omissions) Insurance

Minimal Limits:

$1,000,000 Per Claim

The Insurer shall provide at least thirty (30) days written notice of cancellation. The Prime Consultant will be responsible to verify subconsultant(s) compliance with MDOT’s insurance requirements.

Page 5: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 1 of 12 Revised Posted Scope: 4.9.18

Michigan Department of Transportation

SCOPE OF SERVICE

FOR

DESIGN SERVICES

Railroad Bridge Inspection and Load Rating Revised on 04/09/2018

CONTROL SECTION(S): 33014

JOB NUMBER(S): 202638

PROJECT LOCATION: Services will be performed at 21 28 locations along the Michigan Department of

Transportation (MDOT) owned railroad corridors in the lower peninsula. A specific list of

bridges requiring inspection and load rating has been included in Attachment 1. Attachment 1

contains location and general bridge information.

PROJECT DESCRIPTION:

To perform special bridge inspections of MDOT owned railroad bridges in accordance with

the National Bridge Inspection Standards (NBIS). Confirm and/or collect all applicable

Structure Inventory and Appraisal (SI&A) data. Conduct a detailed, in-service safety

inspection above or below the water level to identify any deficiencies and complete a Bridge

Safety Inspection Report (BSIR). When appropriate or necessary to fully ascertain the

existence of or the extent of any deficiencies, nondestructive field tests may need to be

performed. Sufficient measurements of bridge members and member components shall be

taken to allow for accurate load rating of the bridge’s as-inspected condition.

Fracture critical members identified in the field during the special bridge inspection shall be

inspected in accordance with the NBIS. NBIS 650.305 defines fracture critical member

inspection as a hands-on inspection of a fracture critical member or member components that

may include visual and other nondestructive evaluation. Generate a fracture critical inspection

report (FCIR).

To perform load rating of MDOT owned railroad bridges in accordance with the American

Railway Engineering and Maintenance-of-way Association (AREMA) Manual for Railway

Engineering based on a Cooper E – loading with and without fatigue, and for both the as-built

and as-inspected conditions.

Prepare a bridge inspection report of the findings for each bridge. The report shall be signed

and sealed by a Michigan Registered Professional Engineer as defined by Article 20 of the

Occupational Code, P.A. 299 of 1980, as amended and shall include a cover with an electronic

photo of the bridge, table of contents, executive summary, bridge location, bridge description,

method of investigation, bridge condition, rating, recommendations, estimate to improve load

to meet current industry loading, SI&A, BSIR, FCIR, drawings, sketches, plan index, and

photographs.

Page 6: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 2 of 12 Revised Posted Scope: 4.9.18

PRIMARY PREQUALIFICATION CLASSIFICATION:

Design –Bridges: Scoping

SECONDARY PREQUALIFICATION CLASSIFICATION: Design – Bridges: Railroad

Design – Bridges: Load Rating (Precautionary)

ANTICIPATED SERVICE START DATE: July 31, 2018

ANTICIPATED SERVICE END DATE: March 29, 2019

DBE REQUIREMENT: NA

MDOT PROJECT MANAGER:

Ryan Hoensheid, P.E.

Railroad Infrastructure – Bridge Engineer

Van Wagoner Building

425 West Ottawa Street

PO BOX 30050

Lansing, Michigan 48909

Mobile: (517) 290-6376

E-mail: [email protected]

PURPOSE:

The bridges in question are suspected to not meet present freight loading demands at desired

timetable speeds and are considered functionally obsolete. Two of the bridges are deck truss,

pin connected superstructures and are required to have hands-on bridge safety inspections

performed every ten (10) years per the MDOT Railroad Bridge Management Program adopted

in accordance with Code of Federal Regulations Title 49, Part 237, Bridge Safety Standards.

The deliverables for this project will be the bridge inspection report for each bridge. The report

shall be signed and sealed by a Michigan Registered Professional Engineer as defined by

Article 20 of the Occupational Code, P.A. 299 of 1980, as amended and shall include a cover

with an electronic photo of the bridge, table of contents, executive summary, bridge location,

bridge description, method of investigation, bridge condition, rating, recommendations,

estimate to improve load to meet current industry loading, SI&A, BSIR, FCIR, drawings,

sketches, plan index, and photographs.

DURATION & SCHEDULE

A. Work Plan & Schedule

The CONSULTANT must review the Scope of Service to develop a Work Plan that details

the inspection dates and process of inspecting the specific elements for a typical bridge.

Submittal of the Work Plan is required as part of the Priced Proposal. Submit any changes

to the Work Plan in writing to MDOT’S PROJECT MANAGER (PM) for review and approval.

The CONSULTANT must be prepared to begin the field inspection work within two (2) weeks

after receiving the Notice to Proceed (NTP).

Page 7: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 3 of 12 Revised Posted Scope: 4.9.18

B. Meeting Dates

The CONSULTANT is required to attend a Project Initiation Meeting and Progress Meetings.

Shown below are the expected periods for these meetings. MDOT, however, reserves the

right to adjust these periods.

Project Initiation Meeting: One (1) week after NTP (prior to any fieldwork)

The intent of the Project Initiation Meeting is to exchange information regarding the

general procedures for communication, review the schedule, discuss emergency

procedures and communication, railroad flagging protection, and discuss any open

questions that remain. Additional MDOT Office of Rail and operating railroad staff may

attend the meeting.

Progress Meetings: Biweekly during the Field Inspection Phase (Some may be done by

conference call)

The CONSULTANT will provide a summary of the previous week’s activities and a two week

look ahead schedule to the MDOT PM, which will be reviewed and discussed in the meeting.

Pre-Final Bridge Inspection Report Meeting: One (1) month after the Field Inspection

Phase and two (2) weeks after the submittal of the “Pre-Final” bridge inspection reports.

This meeting is intended as a review of MDOT comments on the “Pre-Final” bridge

inspection reports.

Project Closeout Meeting: One (1) month after submission of the final bridge inspection

report

This meeting is intended as a review of any outstanding contract requirements and final

presentation of the deliverables. The completed “Consultant Performance Evaluation”

form will be given to the CONSULTANT and reviewed.

The CONSULTANT will keep notes of these meetings and provide minutes to the MDOT PM within

one (1) week after the meeting.

Page 8: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 4 of 12 Revised Posted Scope: 4.9.18

TEAM REQUIREMENTS: The CONSULTANT firm will provide a team of individuals that will be technically qualified and

cost effective. For safety reasons, all site visits will be done with at least a two-person team.

The CONSULTANT must staff the project with the number of teams necessary to complete the

inspections in the allotted time. The requirements listed below are in addition to the

prequalification requirements.

A. Project Manager, PM

The CONSULTANT will provide a PROJECT MANAGER (PM) who will be responsible for

overall coordination of the project and all administrative aspects of the project including

invoice preparation. The CONSULTANT PM will coordinate the daily activities of all project

members and will be the primary contact with the MDOT PM. The CONSULTANT PM will

also perform contract Quality Control in accordance NBIS Section 650.313 (g) and the

CONSULTANT’S Quality Control plan. The CONSULTANT PM shall comply and ensure all

project team members comply with the Code of Federal Regulations Title 49, Part 214,

Railroad Workplace Safety. Only one manager level position will be allowed and paid for

on this project.

The following are the minimum qualifications for this position:

1. Michigan Registered Professional Engineer as defined by Article 20 of the

Occupational Code, P.A. 299 of 1980, as amended, or have ten years of documented

bridge inspection experience

2. Five years of documented project supervision.

3. A thorough understanding of the National Bridge Inspection Program, the National

Bridge Inspection Standards, and the AREMA Bridge Inspection Practices.

4. Documented skills in technical writing.

B. Railroad Bridge Inspector, RBI

The prequalified CONSULTANT will provide a RAILROAD BRIDGE INSPECTOR (RBI) that will

be responsible for planning, preparing, and performing the inspections of individual

bridges as well as the day-to-day aspects of the inspection. The CONSULTANT RBI shall be

technically competent to view, measure, report, and record the condition of the bridge and

its individual members. The CONSULTANT RBI shall be present at all times during each

special inspection.

There are four alternative ways to qualify as a RAILROAD BRIDGE INSPECTOR:

1. Have the qualifications specified for the PROJECT MANAGER.

2. Have five years of documented railroad bridge inspection experience.

3. Have the following:

a. A bachelor’s degree in engineering from a college or university accredited by

or determined as substantially equivalent by the Accreditation Board for

Engineering and Technology;

b. Successfully passed the National Council of Examiners for Engineering and

Surveying Fundamentals of Engineering examination; and

c. Two year of documented bridge inspection experience, or

4. Have the following:

Page 9: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 5 of 12 Revised Posted Scope: 4.9.18

a. An associate’s degree in engineering or engineering technology from a college

or university accredited by or determined as substantially equivalent by the

Accreditation Board for Engineering and Technology; and

b. Four years of documented bridge inspection experience.

C. Railroad Associate Bridge Inspector, RABI(s)

The prequalified CONSULTANT will provide RAILROAD ASSOCIATE BRIDGE INSPECTORS

(RABI(S)) that will assist the RAILROAD BRIDGE INSPECTOR in day-to-day aspects of the

inspection. Training is not required but it is recommended.

D. Railroad Bridge Rating Engineer (RBRE)

The prequalified CONSULTANT will provide RAILROAD BRIDGE RATING ENGINEER that will

be responsible for structural analysis and rating of the bridge members and member

components.

The following are the minimum qualifications for this position:

1. Michigan Registered Professional Engineer as defined by Article 20 of the

Occupational Code, P.A. 299 of 1980, as amended, or have ten years of documented

bridge inspection experience or

2. Have the following:

a. A bachelor’s degree in engineering from a college or university accredited by or

determined as substantially equivalent by the Accreditation Board for Engineering

and Technology;

b. Successfully passed the National Council of Examiners for Engineering and

Surveying Fundamentals of Engineering examination; and

c. Two years of documented bridge rating and/or design experience.

Changes made to the CONSULTANT PROJECT MANAGER/RAILROAD BRIDGE INSPECTOR that

occurs after contract award must be submitted in writing for MDOT’S PROJECT MANAGER (PM)’S

approval. Failure to comply with this requirement may result in termination of the contract.

DESCRIPTION OF THE WORK

Special bridge inspections, fracture critical member inspections, and load ratings are required

to ensure that the structural integrity of bridges that carry railroad tracks are preserving their

capability to safely carry the traffic operated over them and reduce the potential risk of human

casualties, environmental damage, and disruption to the nations’ railroad transportation system

resulting from catastrophic bridge failure. To accomplish this, the National Bridge Inspection

Standards (NBIS), AREMA Manual for Railway Engineering, AREMA Bridge Inspection

Handbook, AASHTO Manual for Bridge Evaluation (MBE), FHWA Bridge Inspection

Reference Manual (BIRM), FHWA Fracture Critical Inspection Techniques for Steel Bridges,

MDOT NBI Rating Guidelines, Michigan Structure Inspection Manual (MiSIM), MDOT

Bridge Advisories, FRA 49 CFR 237 Bridge Safety Standards, and FRA 49 CFR 214 Railroad

Workplace Safety are to be used as guidance to complete the inspection and provide necessary

information.

For the purposes of this project, the scope is separated into six phases: bridge file review,

special inspection of the bridge in the field, fracture critical member inspection in the field,

Page 10: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 6 of 12 Revised Posted Scope: 4.9.18

load rating, completion of the report, and communication of the findings to the MDOT PM. The

CONSULTANT must be capable to perform and complete all phases for successful completion

of the project.

A. Bridge File Review

In this phase of the work the CONSULTANT will review each bridge file and become familiar

with the documentation for each bridge. Arrangements to review the bridge files will be

made with the MDOT PM. Note: The Office of Rail bridge inventory is currently not

incorporated in the MiBRIDGE web-based application and all bridge files are retained by

the MDOT PM.

The CONSULTANT team will visit each bridge site and perform a special bridge and fracture

critical member inspection. This will be done with a visual/hands-on inspection and non-

destructive tests (NDT). Several reports, described below, will be completed by the

CONSULTANT RBI while performing this inspection.

B. Special Bridge Inspection

The special bridge inspection shall be performed by the CONSULTANT RAILROAD BRIDGE

INSPECTOR (RBI) whose qualifications have been submitted to and approved by the MDOT

PM The CONSULTANT RBI is required to supply all the equipment necessary to perform the

special bridge inspection and prepare the report. The CONSULTANT RBI shall confirm

and/or collect all applicable Structure Inventory and Appraisal (SI&A) data. Conduct a

detailed, in-service safety inspection above and below the water level to identify any

deficiencies and complete a Bridge Safety Inspection Report (BSIR). The CONSULTANT

RBI shall inspect substructure elements submerged in water to a depth of three (3) feet or

less by visual inspection and probing. For substructure elements submerged in water

greater than three (3) feet in depth, the CONSULTANT RBI shall notify the MDOT PM for the

need of Special Underwater Inspection for each of the substructure portions below three

(3) feet, which is not included in this Scope of Work.

There must be sufficient comments for each member and member component in the reports

to outline its condition and to justify the rating given. Some of the previous reports may

not have complete comments. The lack of previous information does not exempt the

CONSULTANT RBI from providing sufficient comments for each member and member

component to outline its condition. Follow the MDOT NBI Bridge Rating Guidelines,

unless there are circumstances, particularly if they are safety related, that in the judgment

of the CONSULTANT RBI do not fit within these guidelines. In this case, the inspector will

document the reason for the deviation in the respective comment section.

The results of the inspection shall be documented using photographs, sketches, and

appropriate commentary. The documentation shall include system-wide indexing of

individual members. System-wide indexing of individual members means that there is a

unique label for each component, such as girder G1 or stringer S10. If there is a unique

label for each component in the erection diagram found in the plans, then the erection

diagram labeling shall be used. If not, then a unique labeling system in accordance with

the MDOT Railroad Bridge Management Program shall be used.

Page 11: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 7 of 12 Revised Posted Scope: 4.9.18

The CONSULTANT RBI shall report indications of overload or failure in any part of the

bridge. The CONSULTANT RBI shall observe the general behavior of the bridge during

passage of live load, where practical, noting excessive vibrations, deflection, side sway,

and movement at pier supports.

If a condition jeopardizing safe passage of railroad traffic is discovered, the CONSULTANT

RBI shall immediately notify the MDOT PM of the situation and follow up with a detailed

written report. The CONSULTANT RBI shall recommend a remedy to correct the situation.

In order to facilitate rating of the bridge, sufficient measurements shall be taken from

running rail to bridge to determine eccentricity (if any) between track centerline and bridge

centerline. Sufficient measurements shall be taken to determine depth of ballast (ballast

dead load) for ballasted deck bridges. Two overall photographs of the bridge (one in each

direction) shall be taken at track level. Sufficient information shall be provided about any

other superimposed dead loads such as walkway platforms, access roads, etc. Information

shall be provided whether tracks are curved or tangent, and whether deck is open or

ballasted. The condition of any ballast retainers shall be noted. Three overall sketches

showing plan, elevation and cross section shall be included in the report.

Measurements shall be taken, and sketches made for all primary steel members, such as,

but not limited to, stringers, floorbeams, troughs, girders, truss members, columns and

cross girders. Measurements shall be taken to verify cross section information found in

the plans and to measure section loss. Sufficient measurements shall be taken in order for

the CONSULTANT RBI to load rate the bridge. It shall be made clear whether measurements

are remaining section or estimated loss. Cross-sections differing from those indicated on

the plans, and undocumented repairs shall be described in detail. Connections for these

members shall be inspected in-depth and descriptions shall indicate whether they are

pinned, riveted, bolted, or welded. The condition of rivet heads shall be noted. The

location and length of any cracks shall be noted. The presence of trough or deck weep

holes shall be noted.

Other track supporting primary members, such as solid timber decks, concrete slabs,

masonry piers, and abutments, and secondary members shall be inspected. Their condition

shall be described in detail in the report. Location of structural defects, significant

deterioration and/or member section loss shall be noted.

No permanent marks are to be made on the bridge. Temporary marks needed to identify

or highlight deficiencies for photographs may be made provided they are removed prior to

the completion of the inspection. A copy of all plans shall be available for referral at the

bridge during the inspection. If a copy of a plan is used for note keeping, the recorded

information shall be legible and included in the report.

In addition to structural members and member components of the bridges to be evaluated,

the CONSULTANT RBI shall also note the presence of debris which can impede water flow

around the substructure elements.

All photographs shall be taken with a digital camera. An overall photograph shall be taken

of each type of primary member. A photograph shall be taken of each member inspection

Page 12: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 8 of 12 Revised Posted Scope: 4.9.18

and a detailed description shall be provided. Two overall photographs (side views) of the

bridge (one in each direction) shall be taken.

Information on scour must be reported on the Bridge Safety Inspection Report (BSIR). If

there is loss of bearing or undermining of a footing that is a safety concern, this must be

reported to the MDOT PM and a detailed written report generated. If the loss of bearing is

sufficient to be of immediate concern for the component to structurally support the bridge,

the CONSULTANT RBI will notify the MDOT PM on an emergency basis.

During the special bridge inspection, the CONSULTANT RBI will evaluate the bridge for

long- and short-term maintenance and repairs and record this information on the “Work

Recommendations” form of the BSIR and document in the report.

AASHTO Element level condition state assessment is not required

C. Fracture Critical Member Inspection

Fracture critical members identified during the special inspection shall be inspected in

accordance with the FHWA Bridge Inspection Reference Manual (BIRM), AASHTO

Manual for Bridge Evaluation (MBE), and the inspection procedures provided in FHWA

Fracture Critical Inspection Techniques for Steel Bridges (Publication No. FHWA NHI 02-

037) January 2002 (Revised March 2006).

D. Load Rating

The CONSULTANT RAILROAD BRIDGE RATING ENGINEER (RBRE) shall rate the members of

the bridge based on a Cooper E - loading in accordance with the AREMA Manual for

Railway Engineering, with and without fatigue, and for both the as-built and as-inspected

conditions. The results of the rating shall be included in the report in tabular form.

The rating table shall include columns for: Span Number, Member and/or Member

Component, Span Length, Full Impact, Normal and Maximum Ratings for Bending, Shear

and Axial Tension & Compression, if any, and Fatigue.

If the results of the rating indicate that the bridge fails to meet present freight loading

demands at desired timetable speeds, the CONSULTANT RBRE will provide

recommendations to the MDOT PM on how to achieve present freight loading capacity at

desired timetable speeds. Recommendations will be documented in the report.

E. Bridge Inspection Report (BIR)

As stated in the PURPOSE, the deliverables for this project will be the bridge inspection

report of the findings for each bridge. The BIR shall be signed and sealed by a Michigan

Registered Professional Engineer as defined by Article 20 of the Occupational Code, P.A.

299 of 1980, as amended and shall include a cover with an electronic photo of the bridge,

table of contents, executive summary, bridge location, bridge description, method of

investigation, bridge condition, rating, recommendations, SI&A, BSIR, FCIR, drawings,

sketches, plan index, and photographs.

Each BIR created by the CONSULTANT will be assembled in a binder. The cover of the

binder will include an electronic photo of the bridge, general bridge inspection, and be

Page 13: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 9 of 12 Revised Posted Scope: 4.9.18

signed and sealed by a Michigan Registered Professional Engineer as defined by Article

20 of the Occupational Code, P.A. 299 of 1980, as amended. Each BIR shall be prefaced

stating that the inspections have been performed in accordance with this scope of services,

and that all appropriate procedures and guidelines have been followed.

The MDOT PM may conduct periodic QA checks on the CONSULTANT’S work

(approximately five (5) percent of the bridges listed in the work package). If these

evaluations, in the judgment of the MDOT PM, show that the CONSULTANT does not adhere

to the policies and guidelines noted above the contract can be terminated and the balance

of the bridges to be inspected will not be paid for.

DELIVERABLES SCHEDULE

The CONSULTANT shall submit field notes containing primary steel member sketches, system-

wide indexing plan and overall sketches showing plan, elevation, and cross section within

seven (7) calendar days of completion each bridge field inspection. MDOT will review these

submittals and respond to the CONSULTANT within seven (7) calendar days of their receipt.

The CONSULTANT shall prepare and submit a “pre-final” report to MDOT within thirty (30)

calendar days of completing the physical inspection of each of the bridges. MDOT will review

the draft report and respond to the CONSULTANT within fourteen (14) calendar days of the

receipt of each of the draft reports.

The CONSULTANT shall resubmit for review only those parts of the report, which need to be

modified due to MDOT’s comments. This will be done within fourteen (14) calendar days

upon receipt of draft report comments.

MDOT will review these modified parts of the report within seven (7) calendar days upon

receipt of those report sections from the CONSULTANT.

If no further revisions to the report are required, five (5) copies of the final report will be

submitted to MDOT within fifteen (15) calendar days upon the receipt of MDOT’s final

comments. In addition, a DVD, CD-ROM or USB Flash Drive will be provided with the final

report in Adobe Acrobat 9.0 PDF format.

All CONSULTANT submission stated above shall be sent to the designated MDOT PM.

MILESTONE SCHEDULE

Service Start Date July 31, 2018

Notice to Proceed August 3, 2018

Project Initiation Meeting August 13, 2018

Begin Field Inspection August 20, 2018

End Field Inspection October 5, 2018 October 12, 2018

Submit Pre-Final Bridge Inspection Report November 7, 2018 November 14, 2018

Pre-Final Bridge Inspection Report Meeting November 21, 2018 November 28, 2018

Submit Final Bridge Inspection Report January 18, 2019 January 25, 2018

Project Close Out Meeting February 20, 2019 February 27, 2018

Service End Date March 29, 2019

Page 14: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 10 of 12 Revised Posted Scope: 4.9.18

EQUIPMENT

The CONSULTANT will be responsible for providing all the necessary inspection equipment.

Some of the items that CONSULTANT will want to include for inclusion in their proposal are:

1. All safety equipment to comply with MIOSHA requirements. Hard hats, safety glasses,

safety shoes, and safety vests must be worn in the field at all times. Life vests are

required while working in or above water.

2. Vehicle equipped with high visibility lighting to transport personnel and inspection

equipment to the site.

3. Laptop computer or tablet with Microsoft Excel, Word, and Adobe Acrobat.

4. Digital camera that captures clear photographs.

5. Tools required for inspection such as a ladder, waders, rock pick hammer, tape

measure, lighting, marking paint, etc.

6. Global Positioning Device (GPS) to locate bridges.

7. Cell phone so the CONSULTANT RAILROAD BRIDGE INSPECTOR (RBI) may be contacted

during normal working hours.

8. Harnesses, tripods, air monitor, air supply, etc. for the proper entry of MIOSHA defined

permit-required confined spaces.

9. Ultrasonic thickness gauge, calipers, dye penetrant kit, chain drag, and sounding

hammer for Non-Destructive Testing (NDT).

10. Boat to gain access to the underside of bridges.

11. Rigging equipment that may be used to access floor systems and main load carrying

members on bridges that do not have the capacity to support an inspection vehicle.

12. Under bridge inspection and aerial lift road-rail (hi-rail) vehicle.

RAILROAD COORDINATION

The CONSULTANT shall follow the safety requirements specified by the railroad operator and

ensure a railroad flagger is on site when necessary. Written confirmation must be provided to

MDOT that advance notice has been provided and all safety provisions will be adhered to

during the inspection. The CONSULTANT shall provide the railroad a minimum of three (3)

working days advanced notice prior to flagging services being required. The railroad flagging

will be provided at no cost to the CONSULTANT. THE CONSULTANT shall be required to execute

MDOT form 0772 and comply with all the terms and conditions except for the $400.00

processing fee. MDOT form 0772 has been included in Attachment 2.

Page 15: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 11 of 12 Revised Posted Scope: 4.9.18

CONFIDENTIALITY CLAUSE

MDOT will furnish the CONSULTANT access to any available, pertinent information related to

the bridge(s) proposed for inspection. Information furnished to the CONSULTANT is not to be

released or distributed to anyone outside of MDOT. The CONSULTANT is not allowed to make

copies of the information in the bridge files unless given written approval from the MDOT PM.

Failure on the part of the CONSULTANT firm to maintain security of records could result in legal

penalties.

PROJECT QUALITY CONTROL

The CONSULTANT will submit a project quality control plan with their proposal that will

accomplish at a minimum the following:

1. Confirm that Project Manager and Railroad Bridge Inspector(s) have the required

documents and certificates to substantiate their qualifications.

2. Confirm that the inspection process and procedures meet the requirements of the NBIS.

3. Review 5% of the completed work to ensure that all reports are complete, accurate, and

consistent.

RESPONSIBILITIES OF MDOT

The following activities and information will be provided by the MDOT PM, where applicable,

to the CONSULTANT.

1. Provide railroad contact information.

2. Provide access to the hard copy bridge files.

3. Provide car loading diagrams.

Page 16: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

Page 12 of 12 Revised Posted Scope: 4.9.18

CONSULTANT PAYMENT – Actual Cost Plus Fixed Fee:

Compensation for this project shall be on an actual cost plus fixed fee basis. This basis of

payment typically includes an estimate of labor hours by classification or employee, hourly

labor rates, applied overhead, other direct costs, subconsultant costs, and applied fixed fee.

The fixed fee for profit allowed for this project is 11.0% of the cost of direct labor and

overhead.

All billings for services must be directed to the Department and follow the current guidelines.

The latest copy of the "Professional Engineering Service Reimbursement Guidelines for

Bureau of Highways" is available on MDOT's website. This document contains instructions

and forms that must be followed and used for billing. Payment may be delayed or decreased

if the instructions are not followed.

Payment to the Consultant for services rendered shall not exceed the maximum amount unless

an increase is approved in accordance with the contract with the Consultant. Typically, billings

must be submitted within 60 days after the completion of services for the current billing. The

final billing must be received within 60 days of the completion of services. Refer to your

contract for your specific contract terms.

Direct expenses, if applicable, will not be paid in excess of that allowed by the Department for

its own employees in accordance with the State of Michigan’s Standardized Travel

Regulations. Supporting documentation must be submitted with the billing for all eligible

expenses on the project in accordance with the Reimbursement Guidelines. The only hours

that will be considered allowable charges for this contract are those that are directly attributable

to the activities of this project.

MDOT will reimburse the consultant for vehicle expenses and the costs of travel to and from

project sites in accordance with MDOT’s Travel and Vehicle Expense Reimbursement

Guidelines, dated May 1, 2013. The guidelines can be found at

http://www.michigan.gov/documents/mdot/Final_Travel_Guidelines_05-01-

13_420289_7.pdf?20130509082418. MDOT’s travel and vehicle expense reimbursement

policies are intended primarily for construction engineering work. Reimbursement for travel

to and from project sites and for vehicle expenses for all other types of work will be

approved on a case by case basis.

MDOT will pay overtime in accordance with MDOT’s Overtime Reimbursement

Guidelines, dated May 1, 2013. The guidelines can be found at

http://www.michigan.gov/documents/mdot/Final_Overtime_Guidelines_05-01-

13_420286_7.pdf?20130509081848. MDOT’s overtime reimbursement policies are

intended primarily for construction engineering work. Overtime reimbursement for all

other types of work will be approved on a case by case basis.

Page 17: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

MDOT STRUCTURE NUMBER FEATURE LATTITUDE LONGITUDE LENGTH SPAN OWNER OPERATOR DISTRICT OPERATIONAL STATUS REGION  COUNTY MATERIALB01‐47061.11 HURON RIVER 42*27.27.25 83*49.53.74 73' 1 MDOT OoR GLC ANN ARBOR R posted for other load‐capacity restriction 06 ‐ University 47 ‐ Livingston 3 ‐ Steel, simple or CantileverB06‐47070.85 GENOA DRAIN 42*34.27.04 83*54.18.07 23' 1 MDOT OoR GLC ANN ARBOR R posted for other load‐capacity restriction 06 ‐ University 47 ‐ Livingston 3 ‐ Steel, simple or CantileverB03‐47082.03 SHIAWASSEE RIVER 42*43.30.84 83*56.43.14 68' 1 MDOT OoR GLC ANN ARBOR R posted for other load‐capacity restriction 06 ‐ University 47 ‐ Livingston 3 ‐ Steel, simple or CantileverB01‐76087.20 BARNUM DRAIN 42*47.53.25 83*57.10.52 21' 1 MDOT OoR GLC ANN ARBOR R posted for other load‐capacity restriction 04 ‐ Bay 76 ‐ Shiawassee 3 ‐ Steel, simple or CantileverB02‐76089.37 SHIAWASSEE RIVER 42*49.46.84 83*57.16.13 111' 1 MDOT OoR GLC ANN ARBOR A open, no restriction (A) 04 ‐ Bay 76 ‐ Shiawassee 0 ‐ OtherB02‐83350.66 MANISTEE RIVER 44*29.49.91 85*25.31.80 213' 9 MDOT OoR GLC NORTHERN A open, no restriction (A) 02 ‐ North 83 ‐ Wexford 7 ‐ TimberB01‐28014.90 BOARDMAN RIVER 44*38.48.43 85*32.51.86 74' 4 MDOT OoR GLC TRAVERSE CITY R posted for other load‐capacity restriction 02 ‐ North 28 ‐ Grand Traverse 3 ‐ Steel, simple or CantileverB02‐28025.00 BOARDMAN RIVER 44*45.22.12 85*36.31.22 281' 20 MDOT OoR GLC TRAVERSE CITY R posted for other load‐capacity restriction 02 ‐ North 28 ‐ Grand Traverse 3 ‐ Steel, simple or CantileverB10‐73079.93 DEER CREEK 43*12.41.84 84*07.22.27 31' 1 MDOT OoR GLC ST. CHARLES R posted for other load‐capacity restriction 04 ‐ Bay 73 ‐ Saginaw 3 ‐ Steel, simple or CantileverB01‐73082.20 CARSON DRAIN 43*14.38.69 84*07.41.77 31' 1 MDOT OoR GLC ST. CHARLES R posted for other load‐capacity restriction 04 ‐ Bay 73 ‐ Saginaw 3 ‐ Steel, simple or CantileverB07‐29125.44 DRAINAGE DITCH 43*09.13.81 84*26.28.23 21' 1 MDOT OoR GLC CADILLAC R posted for other load‐capacity restriction 04 ‐ Bay 29 ‐ Gratiot 3 ‐ Steel, simple or CantileverB08‐29125.58 DRAINAGE DITCH 43*09.19.60 84*26.33.69 21' 1 MDOT OoR GLC CADILLAC R posted for other load‐capacity restriction 04 ‐ Bay 29 ‐ Gratiot 3 ‐ Steel, simple or CantileverB10‐29126.41 DRAINAGE DITCH 43*09.54.67 84*27.08.50 25' 1 MDOT OoR GLC CADILLAC R posted for other load‐capacity restriction 04 ‐ Bay 29 ‐ Gratiot 3 ‐ Steel, simple or CantileverB12‐29126.84 DRAINAGE DITCH 43*10.12.66 84*27.27.66 21' 1 MDOT OoR GLC CADILLAC R posted for other load‐capacity restriction 04 ‐ Bay 29 ‐ Gratiot 3 ‐ Steel, simple or CantileverB13‐29129.49 BEAR CREEK/CATTLE PASS 43*12.01.62 84*29.23.61 40' 2 MDOT OoR GLC CADILLAC R posted for other load‐capacity restriction 04 ‐ Bay 29 ‐ Gratiot 3 ‐ Steel, simple or CantileverB01‐29134.15 BAD RIVER DRAIN 43*15.13.01 84*32.47.61 43' 1 MDOT OoR GLC CADILLAC R posted for other load‐capacity restriction 04 ‐ Bay 29 ‐ Gratiot 3 ‐ Steel, simple or CantileverB01‐37154.85 SALT RIVER 43*30.30.21 84*41.12.31 66' 1 MDOT OoR GLC CADILLAC R posted for other load‐capacity restriction 04 ‐ Bay 37 ‐ Isabella 3 ‐ Steel, simple or CantileverB06‐37169.22 SALT RIVER 43*40.53.44 84*46.22.28 30' 1 MDOT OoR GLC CADILLAC R posted for other load‐capacity restriction 04 ‐ Bay 37 ‐ Isabella 3 ‐ Steel, simple or CantileverB02‐18201.10 MUSKEGON RIVER 44*01.51.26 85*02.18.39 135' 2 MDOT OoR GLC CADILLAC R posted for other load‐capacity restriction 04 ‐ Bay 18 ‐ Clare 3 ‐ Steel, simple or CantileverB03‐83227.63 CLAM RIVER 44*15.17.11 85*24.29.22 21' 1 MDOT OoR GLC CADILLAC R posted for other load‐capacity restriction 02 ‐ North 83 ‐ Wexford 3 ‐ Steel, simple or CantileverX02‐30055.06 HALLET STREET 41*54.45.73 84*38.55.44 104' 6 MDOT OoR INNE FREEMONT E open, temporary structure in place 06 ‐ University 30 ‐ Hillsdale 3 ‐ Steel, simple or CantileverB02‐79086.46 CASS RIVER 43*22.22.65 83*34.37.15 151' 2 MDOT OoR H&E VASSAR R posted for other load‐capacity restriction 04 ‐ Bay 79 ‐ Tuscola 3 ‐ Steel, simple or CantileverX01‐79086.50 CASS STREET 43*22.27.12 83*34.39.43 80' 3 MDOT OoR H&E VASSAR R posted for other load‐capacity restriction 04 ‐ Bay 79 ‐ Tuscola 3 ‐ Steel, simple or CantileverB01‐79086.55 MOORE DRAIN 43*22.31.48 83*34.42.72 20' 1 MDOT OoR H&E VASSAR R posted for other load‐capacity restriction 04 ‐ Bay 79 ‐ Tuscola 8 ‐ MasonryX02‐79086.74 GRANT STREET 43*22.35.26 83*34.46.79 36' 1 MDOT OoR H&E VASSAR R posted for other load‐capacity restriction 04 ‐ Bay 79 ‐ Tuscola 3 ‐ Steel, simple or CantileverX01‐79000.40 GRANT STREET 43*22.35.46 83*34.39.50 59' 3 MDOT OoR H&E CARO R posted for other load‐capacity restriction 04 ‐ Bay 79 ‐ Tuscola 3 ‐ Steel, simple or CantileverB04‐79005.65 UNKNOWN DRAIN 43*30.09.36 83*24.06.93 24' 1 MDOT OoR H&E CARO R posted for other load‐capacity restriction 04 ‐ Bay 79 ‐ Tuscola 3 ‐ Steel, simple or CantileverB06‐79021.80 STATE DRAIN 43*36.27.17 83*24.23.17 58' 1 MDOT OoR H&E CARO R posted for other load‐capacity restriction 04 ‐ Bay 79 ‐ Tuscola 3 ‐ Steel, simple or Cantilever

Attachment 1: General Bridge Information

Page 18: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

APPLICATION TO USE MDOT CONTROLLED FREIGHT RAILROAD PROPERTY (EXCLUDES DEARBORN-KALAMAZOO ACCELERATED RAIL CORRIDOR)

Use this form to request the use of a state-owned rail corridor, including utility crossings (aerial or subsurface) and

vehicular crossings. Mail three copies of the entire application, plans or other attachments, proof of insurance and

processing fee (if necessary) to: Michigan Department of Transportation, Office of Rail, P.O. Box 30050, Lansing, MI 48909.

• Please be specific as possible when describing the details and location of the proposed use. For example, proposed usecould include “jack and bore gas service line under the railroad tracks” or “install 75KV electrical line over the tracks”. Thelocation description should include the County, and City/Township and a fixed point of reference to identify the exactlocation of the request. A fixed point may include a distance from a road intersection, bridge, milepost, culvert, or a survey.Any documents utilized to identify the location of the request should be on an 8 1/2 “x 11” sheet of paper to accompany theapplication. Also attach engineering plans to provide sufficient details regarding any proposed facilities.

• All construction must comply with the applicable Supplemental Standard Specifications for construction activities(attached). Additional guidance is available on MDOT’s website for private crossings and trail-use applications.

• During permitted right-of-entry or construction activities, the applicant or its contractors shall procure and maintaininsurance as listed below. For some types of facilities, insurance will be required for the life of the facility. Current limits arelisted in the below tables, but are subject to change at MDOT’s discretion. Self-insurance may be an acceptable alternativeto the insurance policies listed below. A sample ACORD form is available on MDOT’s website.

• Approved access will be governed by permits and, as applicable, sales agreements. No easements will be issued on MDOT's railroad property. However, in some cases, MDOT can include language in a permit that provides for the conversion to an easement in the event MDOT's ownership interest should change. This option is only available for crossings that do not constrain the rail right-of-way and at locations that MDOT is the underlying property owner (in fee). Applicants are required to make this request at the time of application, and MDOT will need additional time to confirm its ownership interests in advance of the permit's issuance.

• Please enclose a check or money order (made payable to the “State of Michigan”) for the $400.00 processing fee. Theprocessing fee is waived for governmental agencies. NOTE: Additional costs will be associated with property sales, aswell as permits for private and commercial facilities constructed on the property. In these cases, the applicant willbe required to utilize State-approved appraisers to determine fair-market value if the use is approved.

• To request the use of the Dearborn-Kalamazoo Accelerated Rail Corridor, refer to MDOT Form 1444.

• Contact the Office of Rail at (517) 335-2926 with questions.

*

Commercial General Liability Insurance

Minimal Limits: $1,000,000 Each Occurrence Limit $1,000,000 Personal & Advertising Injury Limit $2,000,000 General Aggregate Limit $2,000,000 Products/Completed Operations

Endorsed to add additional insureds listed below with waivers of subrogation in their favor.

Coverage must not have exclusions or limitations related to working within 50-feet of a railroad track (CG 24 17 1001 endorsement).

Statutory Worker’s Compensation and Employers Liability Insurance

Minimal Limits: $1,000,000

Endorsed to add additional insureds listed below with waivers of subrogation in their favour

Railroad Protective Liability InsuranceMinimal Limits: $2,000,000 Per Occurrence $6,000,000 General Aggregate

Minimal Limits: $500,000 Per Occurrence

Endorsements: The [name of operating railroad], including employees and affiliates, the Michigan Department of Transportation, Michigan State Transportation Commission, and the State of Michigan, its departments, divisions, agencies, offices, commissions, officers, employees, and agents, are named additional insured waiver of subrogation in their favor for commercial general liability, worker's compensation and employer's liability insurance. Coverage does not have exclusions or limitations related to work within 50-feet of a railroad track (CG 24 17 1001 endorsement). Umbrella liability insurance follows form.

Railroad Protective Liability Insurance

Automobile Liability Insurance

Michigan Department of Transportation

0772 (02/18) Page 1 of 5

INSURANCE REQUIREMENTS FOR CONSTRUCTION & RIGHT-OF-ENTRY ACTIVITIES

hoensheidr
Typewritten Text
Attachment 2
hoensheidr
Typewritten Text
hoensheidr
Typewritten Text
Page 19: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

* Endorsements: The [name of operating railroad], including employees and affiliates, the Michigan Department ofTransportation, Michigan State Transportation Commission, and the State of Michigan, its departments, divisions, agencies,offices, commissions, officers, employees, and agents, are named additional insured with waiver of subrogation in their favorfor commercial general liability, worker's compensation and employer's liability insurance. Coverage does not have exclusionsor limitations related to work within 50-feet of a railroad track (CG 24 17 1001 endorsement). Umbrella liability insurancefollows form.

Homeowners Liability Insurance

Minimal Limits: $500,000 Combined Single Each Occurrence

$1,000,000 Personal Liability Limit Annual

Endorsed to add additional insureds listed below.

Coverage must not have exclusions or limitations related to railroad protective liability. If excluded from the policy, Railroad Protective Liability Insurance will be required at the same minimum limits.

Automobile Liability Insurance

Minimal Limits: $500,000 Combined Single Limit Per Occurrence

Endorsed to add additional insureds listed below.

Endorsed to include Hired and Non-Owned Automobile coverage.

Minimal Limits: $1,000,000 Each Occurrence Limit $1,000,000 Personal & Advertising Injury Limit $2,000,000 General Aggregate Limit $2,000,000 Products/Completed Operations

Deductible Maximum: $50,000 Each Occurrence

Endorsed to add additional insureds listed below with waivers of subrogation in their favor.

Coverage must not have exclusions or limitations related to working within 50-feet of a railroad track (CG 24 17 1001 endorsement). If excluded from the policy, Railroad Protective Liability Insurance will be required at the same minimum limits.

Minimal Limits: $500,000 Each Occurrence

Endorsed to add additional insureds listed below.

Endorsed to include Hired and Non-Owned Automobile coverage.

Minimal Limits: $1,000,000 Each Occurrence Limit $1,000,000 Personal & Advertising Injury Limit $2,000,000 General Aggregate Limit $2,000,000 Products/Completed Operations

Deductible Maximum: $50,000 Each Occurrence

Endorsed to add additional insureds listed below with waivers of subrogation in their favor.

Coverage must not have exclusions or limitations related to working within 50-feet of a railroad track (CG 24 17 1001 endorsement).

Minimal limits: $1,000,000 Each Occurrence $2,000,000 Annual Aggregate

Endorsed to add additional insureds listed below.

Coverage must be applicable to work being performed, including completed operations equal to or exceeding statute of repose

Coverage must not have exclusions or limitations related to Transportation (upset overturn, spills during loading or unloading), Hazardous Materials Handling, and Non -Owned disposal site liability.

RESIDENTIAL DRIVEWAYS

PIPELINES

COMMERCIAL DRIVEWAYS

Environmental and Pollution Liability (Errors and Omissions) (Requirement for certain types of pipelines)

Commercial General Liability Insurance

Automobile Liability Insurance

Commercial General Liability Insurance

Page 2 of 5 MDOT 0772 (02/18)

FACILITIES WITH ON-GOING INSURANCE REQUIREMENTS

Page 20: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

FOR MDOT USE ONLY

CONTROL SECTION NO.

DATE RECEIVED

FEE INS

OWNERSHIP

MDOT 0772 (02/18) Page 3 of 5

APPLICATION TO USE MDOT CONTROLLED FREIGHT RAILROAD PROPERTY

(EXCLUDES DEARBORN-KALAMAZOO ACCELERATED RAIL CORRIDOR)

Use of this form to request the use of state owned or controlled railroad real estate for utility crossings (aerial or subsurface), vehicular crossings or other situations where it is necessary to use or occupy such property. Please complete all items 1 through 5 in accordance with the attached instruction cover sheet. Mail three copies of the entire application, plans or other attachments, proof of insurance and processing fee (if necessary) to: Michigan Department of Transportation, Office of Rail, P.O. Box 30050, Lansing, MI 48909. Put “Request to use MDOT Controlled Freight Railroad Property” at the top of each page and number the pages (page number/total pages).

1. NAME AND MAILING ADDRESS OF APPLICANT / FACILITY OWNER PHONE

FAX

E-MAIL ADDRESS

2. NAME AND MAILING ADDRESS OF AUTHORIZED AGENT (If other than applicant) PHONE

FAX

E-MAIL ADDRESS

3. NAME AND MAILING ADDRESS OF CONSTRUCTION CONTRACTOR (If available) PHONE

FAX

E-MAIL ADDRESS

4. LOCATION OF PROPOSED USE (Give city/township and county; also give railroad milepost, if available, or distance and direction from nearestlandmark, center line of intersecting road, etc. – from recognizable point to recognizable point; attach sketch and, if available, certificate of survey.)

5. PROPOSED USE (Include a description of the type of facility and construction activity, as applicable. Attach plansand additional sheets if necessary. As appropriate, refer to MDOT's guidance on longitudinal-use and privatecrossings and address accordingly.)

ACTIVITY START DATE

ACTIVITY END DATE

The signature below certifies the application and any subsequent information that is supplied to MDOT related to this application accurately reflects the proposed use and will comply with MDOT requirements specified as a condition of use in the permit.

SIGNATURE OF APPLICANT OR AUTHORIZED AGENT DATE

APPROVAL ENGINEERING APPROVAL DATE REAL ESTATE DATE

RAILROAD APPROVAL DATE INSPECTOR DATE

MDOT does not hold fee ownership and cannot convey any property rights. You must obtain authorization to enter the property from the fee title holder.

If approved, this application and attached plans will be part of a permit issued by MDOT, which is valid only if it is on file with MDOT and the proposed use begins within one year of its issuance.

Page 21: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

MDOT 0772 (02/18) Page 4 of 5 APPLICATION TO USE MDOT CONTROLLED FREIGHT RAILROAD PROPERTY SUPPLEMENTAL SPECIFICATIONS

General Conditions

Excavation is not allowed within: 20 feet from either rail; the front slopes; or the load influence zone as described by a 1-on-1 slope descending from the ends of the ties, except where specifically authorized in writing by the Department.

Construction equipment and excavated material shall not be stored within 20 feet of the track and in such locations that inhibit drainage, create a hazard or interfere with rail operations, or clear vision for motorists at road intersections. Under no circumstances shall any heavy equipment, especially machinery with caterpillar treads or cleated tracks, be allowed upon the railroad track or front slopes, without approved special provisions for protecting the track structure and front slopes.

Construction Methods

Bore/Jack Installation 1. Where the method of installation consists of pushing the casing pipeinto the sub grade section with a boring auger rotating within the pipe to remove the spoil, the auger shall not be advanced more than one-half the diameter of the casing pipe, where the auger and casing advancement is coordinated. Where the auger is advanced separately, the auger shall not precede the casing pipe.

2. A bore/jack installation shall have a push hole essentially the sameas the outside diameter of the pipe plus protective coating. If voids should develop creating a hole diameter greater than 1 in. plus the pipe diameter, grout shall be used to fill such voids. The auger shall be removable from within the pipe in the event an obstruction is encountered. When an obstruction is encountered that stops the forward advancement of the pipe, operations shall cease and the pipe shall be abandoned in place, cut flush with the front slope, and filled completely with grout before any further bore attempts are made.

3. Where field welding is required, the steel pipe ends shall beprepared and a minimum of three complete circumference passes or three overlapping beads of weld shall be applied at seams or joints. During field welding, water shall not be present inside the pipe and must be a sufficient distance below the pipe to allow a quality weld.

Other Installation Methods 1. The use of jetted water is strictly prohibited for excavating under thetrack

2. Directional boring/drilling, which utilizes bits with jets, may be usedin certain conditions only when specifically authorized in writing. Wet directional boring will be reviewed for approval for longitudinal installations and transversely at grade separation locations only. For transverse installations directly under railroad roadbed, only dry directional boring will be allowed.

3. Sheeting, shoring, and/or dewatering shall be used to prevent caving,slides, or undermining of the foundation material supporting the track structure, ballast section, or any other railroad structures (culverts, signals, switch stands, etc). When water is present or anticipated, ow shall be maintained at the site. When dewatering, the railroad embankment, tracks, and facilities shall be closely monitored for settlement or displacement.

4. The installation of a sub-surface crossings by cutting or removing railand trenching is prohibited unless specifically approved. Approval of open trench installation will require additional special provisions not contained herein.

Backfilling 1. All trenches, holes, and pits shall be backfilled with an approvedmaterial, placed in successive layers not more than 9 in. in depth, and thoroughly compacted to within 95percent of maximum unit weight. Maximum unit weight and compaction shall be determined by: the M•DOT One-PointT-99 (Proctor) Test for materials having more than 15 percent loss-by-washing; the One-Point Michigan Cone Test for materials having less than or equal to 15 percent loss-by-washing; M•DOT approved nuclear gage methods; or approved method.

2. Backfill material shall consist of approved bank-run sand and gravelor Class II granular material per MDOT Standard Specifications for Construction, pass through a screen having 2-3/8 in. square openings, and contain no cementitious properties unsuitable for water percolation nor deleterious or organic materials.

Restoration 1. All surplus or unsuitable material shall be properly disposed outsideof the limits of the railroad right-of-way, unless the approved application provides for designated disposal locations on railroad property. Any permitted disposed material shall be leveled and trimmed in an approved manner.

2. Sod and topsoil shall be stored separately from other excavatedmaterial and shall be used for turf establishment. Turf restoration shall begin within one week of completing the installation. Restore the grade by placing sod or seed, fertilizing and mulch. Mulch which has become displaced prior to complete seed germination shall be restored.

shivalingaiahm
Sticky Note
Unmarked set by shivalingaiahm
shivalingaiahm
Sticky Note
Unmarked set by shivalingaiahm
Page 22: Michigan Department CHECKLIST TO DESIGNATE …€¦ · CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL ... Low Bid (no qualifications review required ... Safety

MDOT 0772 (02/18) APPLICATION TO USE MDOT CONTROLLED FREIGHT RAILROAD PROPERTY

DESIGN CRITERIA

Subsurface Crossings

Steel Pipe - Either: ASTM A53-Type E or S, Grade B; or ASTM A139 - Grade B, and have a minimum yield strength of 35,000 psi.

Casing pipe and non-encased carrier pipe shall have the following wall thickness. Numerical values are in inches.

WALL PIPE WALL THICKNESS DIAMETER .188 = 3/16 12-3/4 and under .250 = ¼ 14 .282 = 9/32 14, 16 .313 = 5/16 18 .344 = 11.32 20 .375 = 3/8 22 .407 = 13/32 24 .438 = 7/16 26 .469 = 15/32 28, 30 .500 = ½ 32 .532 = 17/32 34, 36 .563 = 9/16 38, 40, 42

Grout - A mixture of Portland cement and sand in any proportion which does not have more than 50 percent sand by volume.

HAZARDOUS, HIGH PRESSURE

Where a hazardous or high pressure (greater than 60 psi) substance is conveyed in a pipeline, a casing pipe is required. A steel casing pipe is required for all flammable substances. Casing pipes made of material other than steel or leak proof C-76 Class V reinforced concrete must provide a minimum cover of 6-1/2 ft. from base of rail to top of pipe.

ELECTRICAL, TELEPHONE, FIBER OPTICS

Electrical, telephone, or fiber optic cable do not require a casing pipe.

CULVERTS, GRAVITY SEWERS

Pipes shall have a minimum of two (2) feet of cover from the base of rail to the top of pipe. The pipe shall be of leak proof construction and shall be a minimum10 gauge steel and capable of supporting E-80 loading capacity, with no joints under the roadbed from drainage ditch to drainage ditch.

DEPTH OF PIPE

Casing or carrier pipes shall be placed at a depth that will provide not less than 5' 0''. of cover from bottom of tie to top of pipe and provide a minimum of 3 ft. of cover below proposed ditch bottoms.

LENGTH OF CASING

PIPE Length of pipe shall be the greatest distance as measured at right angles to the track: 3 ft. beyond toe of slope; 3 ft. beyond the ditch; or a minimum distance of 25 ft. from the near rail, when the end of casing is belowground.

BORE PITS

A minimum of 20 feet (perpendicular measurement) shall be maintained from the near rail to any bore pit, unless specifically authorized in writing by the Department. Bore pit dimensions, depth, distance to each near rail, and to the toe of slope for each front slope must be shown on the plans.

Aerial Crossing

VERTICAL CLEARANCES

The minimum vertical clearance, including sag, from top of rail to utility line directly over the track(s) shall be:

26 ft Communications 27 ft 0 – 750 Volts 28 ft 750V – 15 KV 30 ft 15 KV – 50 KV 32 ft 50 KV – 100 KV 33 ft 100 KV – 150 KV 35 ft 150 KV – 200 KV 37 ft 200KV – 250 KV

HORIZONTAL CLEARANCES

No poles or guy wires are allowed in Right-of-Way unless approved by the Michigan Department of Transportation – Office of Rail.

Required Information for All Crossings

A cross-sectional view of the proposed crossing shall be included with the application, and shall include the following topographical information, as applicable:

Adjacent utilities, obstructions or adjacent structures; actual cross-section elevations at the proposed crossing location measured at 0.1 ft increments relative to the top of rail and elevations at 5 ft intervals 50 ft. each side of centerline; ditch and rail profiles at 25 ft. intervals for 300 ft. each direction from crossing (or as necessary to describe drainage); dimensions of bore pits; the closest distance of bore pits to each near rail; and the location relative to a railroad milepost and/or nearby road crossings.

Longitudinal Occupancy

Depth of cover and offset from the track will be considered on an individual basis. Casing requirements can be waived where there is sufficient depth of cover and lateral offset from the track structure.

Utility Structures

No above or below ground structures are allowed in Right-of-Way unless approved by the Michigan Department of Transportation – Office of Rail.

Page 5 of 5

MATERIALS