Managing CPAS Architecture and Requirements Volatility NASA Project Management Challenge 2010 Michael Hazen Jacobs Technology Used with permission
Managing CPAS Architecture and Requirements Volatility
NASA Project Management Challenge 2010 Michael Hazen Jacobs Technology
Used with permission
2
Introduction
Complex systems frequently see requirements and architecture volatility.
These kinds of volatility can be aggravated when multiple contractors and government agencies are working to interdependent but loosely coupled schedules.
Recent experience on CPAS is used to illustrate some high value / low cost systems engineering approaches to help identify areas of volatility and to address these kinds of issues in a direct manner.
3
Background
The Crew Exploration Vehicle (CEV) will land using parachutes much like Apollo did in the 1960s era.
NASA decided to provide the parachute portion of the landing system, referred to as CPAS (CEV Parachute Assembly System) as GFE (Government Furnished Equipment) based on NASA Johnson Space Center (JSC) experience with the X-38 and other parachute programs.
4
Background (continued) JSC chose Jacobs Technology from ESCG
(Engineering and Science Contract Group) to manage the overall program development.
After a detailed selection program, Jacobs chose Irvin Aerospace (now Airborne Systems) to provide the parachutes and mortars for CPAS.
5
CPAS Architecture at Project Inception
6
Can we just re-use the Apollo design?
Some believe that the CPAS design should just be an Apollo carbon copy. Some things have changed since the 1960s technology used by Apollo: Use of modern materials (Kevlar, Vectran and
Spectra) that did not exist in the Apollo era Drogue parachutes updated to Variable Porosity
Conical ribbon. Main parachute design updated from ringsail
technology of the 1960s to the Irvin Quarter –Spherical technology.
Numerous CPAS requirements were significantly more demanding than those levied on Apollo.
7
Generation 1 CPAS Requirements and Architecture
Requirements that significantly exceeded those levied on Apollo: Deployment envelope (max altitude of
72,000 feet vs. 40,000 ft.) Unprecedented vibration levels Reliability requirement twice that of
Apollo The requirements management
paradigm has also changed since the days of Apollo
8
Systems Engineering “Engine” (Ref. 1)
9
$
$ $ $System dependencieswithin asingleorganization
Systems with interdependenciesAcross multiple organizations
System Dependencies (Ref. 2)
10
Interdependency Context Diagram (Ref. 2)
11
CPAS Mandate
Operational parachutes are required to support early program Pad Abort tests. Pad Abort 1 is scheduled for early 2010.
More parachutes required to support Ascent Abort tests and early Orbital tests.
This mandate for CPAS was challenging with the still draft and evolving parent requirements for Orion.
12
Early Requirements Volatility
As the prime contractor prepared for a System Requirements Review, CPAS closely monitored the proposed content of the SRD (System Requirements Document)
As the Orion requirements were proposed, lower level requirements were articulated. The following slide illustrates the state of CPAS parent requirements at the CPAS SRR .
13
CPAS PTRS Requirements TraceabilityCxP 70000 Constellation Architecture Requirements Document
CxP 72000 Orion System Requirements Document
CEV T-31000 LM Spacecraft Specification
CEV T-31100 LM Crew Module Requirements Specification
CEV T-31209 LM Landing and Recovery Systems Requirements
Subsystem Specification
JSC Design And Procedural Standards JPR
8080.5A
LM-ORN-0080 Interim Requirements Specification for CPAS
CEV T-035208 LM Landing and Recovery Systems Interface
Requirements Document
JSC-64355 CPAS PTRS Assumptions Document
JSC-63497 CPAS Project Technical Requirements
Specification
DraftInterim Release
Legend.
.
14
Meeting the Mandate ! Team Collaboration between CPAS and
Lockheed Martin was a big enabler to stop the requirements “tail chasing” by coming up with an explicit set of key requirements that would allow CPAS to proceed with Gen 1 design
This set of requirements (without TBDs) was labeled as an “Interim Requirements Memo”, also dubbed “The Prouty Memo”, named after its primary author from Lockheed Martin, Chris Prouty. The memo also included key interface requirements
15
Stakeholder Expectations Clear?A separate assumptions document was
developed to: Identify areas of disagreement with
interim parent requirements Add needed details where existing
requirements were incomplete Articulate perceived interface requirements
on the vehicle side of the interface Serve as a stakeholder expectations
baseline, formally approved by the program.
16
Beyond Stakeholder Expectations Definition
Requirements and architecture volatility can happen within a project too.
A clearly defined Architecture and Requirements baseline to capture derived requirements and architecture decisions is essential
A Design Guidance & Direction Document was developed to communicate key technical decisions and ground rules within the project and to ensure stakeholders were kept fully informed.
17
EXAMPLE Design Guidance & Direction Document Entry
Main Chute Deployment AltitudeDesign Item: 09-009aOwner: CPAS SE&I IPTDate: 05/07/2009Issue: Main Chute Deployment AltitudeGuidance: CPAS will use 8,000 ft MSL to determine if it meets the performance and functional requirements.Discussion: The Aerodynamic Decelerator System specification, the PTRS, and the assumptions document do not specify the deployment altitude of the main parachutes. Without an assumed deployment height on nominal and high altitude aborts, it is impossible to determine if CPAS meets its functional and performance requirements. LM GN&C indicated during the CPAS summit that 8,000 ft would likely be the main chute deployment altitude.Disposition: Use through PDR.Modified: 06/15/09Approval: Tim Fisher CPAS SE&I IPT Chair
18
Getting Program Buy-In
Getting CEV program concurrence at each step of the requirements and architecture volatility management process is a key enabler.
The GFE Equipment and Materials Control Panel (GEMCP) was empowered to provide directives to CPAS to formalize CPAS Generation 1 requirements.
This concurrence allowed parachute development to proceed without undue risk and with direct involvement of key stakeholders.
19
Architecture Changes due to Stability Concerns
Significant oscillations of the crew module under drogues could result in a “flipped” crew module which would amount to a backwards (or apex forward) parachute deployment.
Confirmed by early drop tests Confirmed by extensive simulations
using evolving Orion aerodynamics data base.
20
Step Back to Look at the “Big Picture”
A proposal was brought forward for a significantly different parachute architecture to address these stability concerns.
21
Alternate Parachute Architecture
21
Drogues deploy thru FBC
Drogues separate FBC from CM
FBC deploys mains and confluence fitting
CM descending under mains
Assess candidate architecture using an “architecture first” approach (Ref. 3)
Elicit Architectural Requirements Document the architecture Analyze the architecture
Stakeholders / scenarios Independent reviewers Prove Architecture will meet stated
requirements
Realize the architecture Maintain the architecture
22
Drogue Mortar & Mains Installation Inside the Forward Bay Cover
24
Exercise architecture first approach process
CPAS now owns FBC separation and recontact avoidance.
Mains just too heavy for effective deployment using forward bay cover – so move to forward bay cover deployed pilot chutes which in turn will deploy mains.
Benefits of moving to alternate architecture starting to degrade.
IDAT team commissioned to sort out the real “big picture” including not only CPAS, but the entire vehicle.
25
IDAT (Integrated Design and Architecture Team) membership
Crew Module Office / CPAS/ Airborne (Irvin) / Lockheed Martin
Non-advocate technical experts Consultants (includes Apollo era
experts) NESC (NASA Engineering Safety
Center) JPL (Jet Propulsion Laboratory)
26
Alternate Architecture Challenges Integrated system challenges
were identified in baseline design (606G) of Orion Entry, Descent, and Landing (EDL) architecture First openly discussed at May 2009
“CPAS Summit” Issues were symptomatic of a
highly coupled architecture
Alternate Architecture Issues
606G Baseline Issues Main chute volume FBC near-field re-contact Drogue load mass threats (chute
inflation, mortar kick-loads) Drogue harness extraction thru TPS Aux chute packaging and deployment Reliability – probability of loss of
crew
27
28
IDAT Recommendations
Forward Bay Volume Backshell Outer Mold Line change from
32.5 to 30 degrees
Steel risers for both mains and drogues to enable “any attitude” parachute deployment
Forward Bay Cover – 6 Segments Launch Abort System (LAS) Abort
Conops - Straight to Mains
29
Straight to Mains Sequence
Touchdown, Main Chute Cutaway, CMUS Airbag Inflation
Main Line Stretch
Blunt End ForwardLAS Jettison
Segmented FBCJettison
Straight to Main Deploy(using chosen
ParachuteArchitecture)
29
• A blunt-end-forward LAS jettison approach was chosen for the Generation 2 CPAS architecture
• Used for Pad aborts and low altitude aborts
Parachute Architecture Selection
Parachute Architectures Considered Modified Apollo (three point drogue harness) 3 Drogues 3 mains concept where each drogue
would extract one of the main chutes at the right time
Ultimately selected “classic Apollo”
30
31
Classic Apollo Drogues
2 each attached to flower pot gusset
Each cut away with single dual-initiated cutter
Main parachutes 3 each attached to
flower pot gusset Each deployed by use
of individual mortar deployed pilot parachutes
31
32
Classic Apollo?
Isn’t that where we were when we started this journey for CPAS? Yes and No – we did not start with an
integrated design solution and architecture.
Smooth sailing now? No – we still have some unprecedented
requirements that will likely result in additional requirements and architecture volatility
Using test planning to explicitly address key risks (not only identify the risks but take concrete action to abate)
Role of Testing in Managing Requirements and Architecture Volatility
33
34
Test and Verification influences on requirements & architecture volatility
Engineering development unit tests are key in validating requirements and candidate architectures Extensive Monte Carlo simulations are
anchored by test data. Assessment of which tests are architecture
specific helps to zero in on testability aspects of candidate architectures
Early validation of performance requirements revealed several problems and risks
Risk Assessment
Extensive brainstorming sessions were conducted with grey beards from the Apollo era and parachute experts from both industry and the government
This enabled identification of requirements and architecture attributes which posed the greatest risk.
35
Example architecture and requirements risk areas identified
Architecture High Risk: Drogue Harness Deploy,
Pilot off-angle deployment Medium Risk: Drogue confluence, Pilot
deployment and inflation Low Risk: Two drogue chute / two aux
chute performance
36
Example architecture and requirements risk areas identified
Requirements High Risk: Drogue High Altitude, two
mains Medium Risk: high body rate
deployment, riser abrasion, skipped reefing stages
Low Risk: Main riser twist, one drogue and two mains
37
38
Requirements related enablers
Master Verification Plan –ask specifically “how can that requirement be verified?”
NESC proposed statistical “design of experiments” test approach associated requirements impact
NESC proposed component level verification assessment – are end item specs needed?
Looking Ahead
A stakeholder-wide Entry Descent and Landing Focus Integration Team (EDL FIT) has been established to ensure future design decisions reflect truly integrated solutions
39
40
Closing Comments
Requirements & architecture volatility is part of the job
The techniques described in this presentation helped CPAS to ensure the right system (right requirements and architecture) is built BEFORE anyone’s life depends on the successful operation of CPAS
Part of Systems Engineering’s role is acting as the project’s “technical conscience” as requirements and architecture volatility issues are addressed
References
1. NPR 7123.1A, NASA Systems Engineering Processes and Requirements. March 2007
2. Department of Defense System of Systems Challenges, JSC Systems Engineering Seminar Presentation. Dr. Judith Dahlman. August 2007
3. Architecture First Approach, DACS (Department of Defense Data & Analysis Center for Software) https://www.goldpractices.com/practices/afa/index.php
41
Questions?
Contact Information Michael HazenJacobs EngineeringJSC Engineering and Science [email protected]
42