MICE Project Progress Update Cable Management Basic tray & trunking layout complete Drawing sheets 1 to 7 issued –Installation can now proceed Main MICE Hall cable routes & to LCR design complete Cable schedule complete for magnet power converters Mains distribution for power converters & LCR complete Mains distribution boards to be purchased & installed LCR tray work design complete –Rack support frames to be manufactured –Tray work to be installed –Raised floor to be installed Phase 2 electrical requirements under review –Detailed information for all systems required
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
MICE Project Progress Update Power Converters
• Rack housing MQ1 to MQ3 magnet power converters – Marshalling for all other
quadrupole & dipole units – Houses controls VME crate &
magnet ON lamp monitoring– Awaiting delivery of monitoring
crate. Due end July-07– Rack 95% complete– Wiring & Termination drawings
complete– Electrical & controls checkout
w/c 30-July-07
MICE Project Progress Update Decay Solenoid
• Solenoid power supply tested & ready for return to RAL– To be located on mezzanine floor– Mezzanine floor requires
– Installation can now proceed• Main MICE Hall cable routes & to LCR design complete• Cable schedule complete for magnet power converters• Mains distribution for power converters & LCR complete• Mains distribution boards to be purchased & installed• LCR tray work design complete
– Rack support frames to be manufactured– Tray work to be installed– Raised floor to be installed
• Phase 2 electrical requirements under review– Detailed information for all systems required
MICE Project Progress UpdatePersonnel Safety Rack
• Internal wiring 75% complete• Terminals & relays installed • Control crates in build• UPS on order• Testing at DL mid-August• Delivery to RAL end August