MGMT 483 – Week 2
Dec 15, 2015
MGMT 483 – Week 2
Focus on criteria and analytical tools for project selection Project selection models and evaluation
factors Non-numeric models Numeric models
▪ Profitability models▪ Scoring models (using weightings)
Risk and uncertainty analysis Project proposals – the procurement process
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Companies considering projects fall into two broad categories:
1. Companies looking at projects to do for others (ie. for external clients)
2. Companies looking at projects to do for themselves (internal projects)
Both types of company must have some kind of criteria to help them decide where to focus their efforts
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Must select which projects they will bid on Generally based on…
Their own expertise and track record Resources they have available Their chance of winning the bid
Preparing a bid is expensive
They do not want to waste that effort on bids where they are unlikely to be successful
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Must decide which potential projects they will pursue (sometimes among many competing projects)
Available capital is the major constraint
Profitability is often the major criteriaMust evaluate approaches when
there is more than one project that can accomplish a particular business goal
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Each project has different risks, benefits and costs – often much uncertainty
Companies need to be able to evaluate and select those projects that most closely fit the firm’s strategic objectives – always done in the context of competing for limited resources
Project selection models are used Models abstract the relevant issues about a problem
from the mass of detail in which the problem is embedded
Models help to make rational decisions
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Numeric Use financial metrics such as cash flow, profit etc
Non-numeric Do not use numbers as inputs into the model,
but other data or considerations The tendency to rely solely on numeric
profitability models can be a serious mistake
If the estimated level of goal achievement is sufficiently large, the project is selected
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Table 2-1 on page 44
Production factorsMarketing factorsFinancial factorsPersonnel factorsAdministrative and Miscellaneous
factors
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
The Sacred Cow (the boss wants to do it)The operating necessity (the basement
is flooded)The competitive necessity (we will lose
sales if we don’t change)The product line extension (will it fit?)Comparative benefit model (how does it
look in the context of other projects)
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Models that return a numeric value for a project that can be easily compared with other projects
Two major categories of numeric models:
1. Profit/profitability2. Scoring
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Models that look at costs and revenues – there are several models, we will look at two in a bit more detail
Payback period (PB)
Discounted cash flow (NPV)
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
4000,25$
000,100$PeriodPayback
FlowCash Annual
CostProject PeriodPayback
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
The lower the payback period the better – exposure / risk to the firm is minimized
The Payback Period = the length of time until the original investment has been recouped by the project
Problem 1, page 85
1. Does not consider time value of money2. More difficult to use when cash flows
change over time3. Less meaningful over longer periods of
time (due to time value of money)4. It ignores any cash flows beyond the
payback period
However, it is relatively simple to calculate and understand
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
The current worth of a stream of future cash inflows and outflows in today’s dollars, given a specified rate of return (the discount rate)
Widely used to evaluate projects Includes the time value of money (the
value of money figuring in a given amount of interest for a given period of time)
Includes all inflows and outflows, not just the ones through to the payback point
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Requires a percentage to use to reduce future cash flows – the discount rate
The discount rate may also be know as a hurdle rate or cutoff rate
There will usually be one overall discount rate that is used as the standard for a company (set internally and used to evaluate all projects)
Cash flows are likely to vary over the life of a project
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
A0 Initial cash investmentFt The cash flow in time period t (negative
for outflows)k The discount ratet The number of years of life
A higher NPV is better The higher the discount rate, the lower the NPV
n
t tt
k
FA
101
(project) NPV
Initial investment of $100,000 with a net cash inflow of $25,000 per year for 8 years, a required rate of return of 15%, and an inflation rate of 3% per year, we have:
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
The present value of the inflows is greater than the present value of the outflow – the NPV is positive. Therefore the project is acceptable.
939,1$
03.015.01
000,25$000,100$ (project) NPV
8
1
t
t
Read through this and note the examples
Then do Problem 3 on page 85
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
The undiscounted models (such as Paybabck Period) are easy to use and understand
Based on readily available accounting data and forecasts
Familiar and well understood by business decision makers
Can give a go/no-go indication, because they are based on “absolute” inputs
Some models can an be modified to include risk
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
They ignore non-monetary factors except risk Some ignore time value of money Discounting models are biased to the short-
term because they reduce cash flows to present value
Payback models ignore cash flow after payback They rely on accurate estimations of cash flow
(which can be difficult) They cannot deal with a lot of the complexity
of the modern firm – reliance on financial data only
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Scoring models attempt to overcome some of the disadvantages of probability models by incorporating additional decision criteria
Two broad categories of scoring models1. Unweighted factor model2. Weighted factor model
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Uses a set of relevant factors as determined by management
Each factor is weighted the same Less important factors are weighted
the same as important ones Easy to compute - just total or average
the scores The major disadvantage is that the
model assumes that all factors are equally important
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Figure 2-2Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
When numeric weights reflecting the relative importance of each individual factor are added ,we have a weighted factor scoring model Weighting allows important factors to stand out
A good way to include non-numeric data in the analysis
Factors need to sum to one All weights must be set up so higher
values mean more desirable Small differences in totals are not
meaningfulMeredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Read through this and note the examples
Then do Problem 9 on page 85
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Figure BMeredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
They allow multiple criteria to be used for evaluation
Weighted models recognize that some criteria are more important than others
Structurally simple and relatively easy to understand
They are a direct reflection of management policy
Easily altered to accommodate change in management policy or priorities
They allow for sensitivity analysis, because trade-off between factors is easily observable
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Ease of use can lead to the inclusion of too many criteria
The output of a scoring model is strictly a relative measure rather than an absolute go/no go indication
Unweighted scoring models assume all criteria are of equal importance – this is seldom the case
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Everything to do with projects is risky Some projects, like R&D, are more risky
than others, like construction Risks include…
The timing of the project and its associated cash flow
Risk regarding the outcome of the project Risk about the side effects
Risk can be assessed by a number of methods, including simulation
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Risk applies to events that have a known (or estimated) probability of occurrence.
Uncertainty applies to events where there is insufficient data to estimate the probability of occurrence.
For effective project management, decisions should be treated as risks rather than uncertainties.
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
The project proposal is the document that contains the information needed to evaluate and score a project proposal
From the point of view of the bidder preparing proposals is substantial work Which proposals should we bid on? What resources should be spent on writing
the proposal? What should be bid price be? What is the
bid strategy?Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
Large organizations put out bids for projects RFP (request for proposal) RFI (request for information) RFQ (request for quotation)
Electronic tendering / procurement In Canada, public sector work is put out to bid via
Merx and / or via online sites such as BC Bid
Firms respond to the competitive process with project proposals
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
1. The technical approachA general description of the problem to be
solved or the project to be undertaken The general proposed approach / solution
2. The implementation plan Estimates of the time required, materials
and other resources to be used, aggregate costings
Gantt charts, network diagrams etc to show project timeline and milestones
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.
3. The plan for logistic support and administration
A description of the ability of the proposer to supply the routine facilities, equipment and skills needed
How subcontractors will be dealt with Nature and timing of project reports and
deliverables
4. Past experience of the proposer A list of key project personnel and their experience
and credentials (usually full CVs)
Meredith & Mantel (2009) Project management: a managerial approach. 7th ed. Wiley.