Top Banner
8/15/2019 MF50-Planning Table Change http://slidepdf.com/reader/full/mf50-planning-table-change 1/9  Planning Table Definition:- Detailed Plan for any given period will be maintained in the Planning table in Repetitive manufacturing. Any distribution of the manufacturing quantity across different production version will be done with the planning table. Objective :- Production plan is  available and one has to schedule the plan across different production version and resources using the planning Table. At the end of this document one will be able to perform planning using planning table. Prerequisites:- Production Plan Production versions and Resources Menu path :- Logistics  Production  MRP  Planning  Planning Table  MF50 - Change Mode
9

MF50-Planning Table Change

Jul 05, 2018

Download

Documents

mayura mulla
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: MF50-Planning Table Change

8/15/2019 MF50-Planning Table Change

http://slidepdf.com/reader/full/mf50-planning-table-change 1/9

 

Planning Table

Definition:-

Detailed Plan for any given period will be maintained in the Planningtable in Repetitive manufacturing.Any distribution of the manufacturing quantity across differentproduction version will be done with the planning table.

Objective :-

Production plan is available and one has to schedule the plan acrossdifferent production version and resources using the planning Table.

At the end of this document one will be able to perform planning usingplanning table.

Prerequisites:-

Production PlanProduction versions and Resources

Menu path :-

Logistics → Production → MRP → Planning → Planning Table → MF50- Change Mode

Page 2: MF50-Planning Table Change

8/15/2019 MF50-Planning Table Change

http://slidepdf.com/reader/full/mf50-planning-table-change 2/9

 

1.  Press Twice MF50 – Change Mode.

Page 3: MF50-Planning Table Change

8/15/2019 MF50-Planning Table Change

http://slidepdf.com/reader/full/mf50-planning-table-change 3/9

Page 4: MF50-Planning Table Change

8/15/2019 MF50-Planning Table Change

http://slidepdf.com/reader/full/mf50-planning-table-change 4/9

 

Note:For repetitive production, ensure Rate-based planning button isselected and ifthe products are subject to PPPI, ensure detailed planning button isselected.

6.  Select Forward scheduling in dropdown to ensure that theplanning table shows the dates calculated from start times.

7.  Press tab Control data .

8.  Press checkboxes Only mats with production and Only mats withreqmts.

9.  Press Planning table Button .

Planning Table for Repetitive Manufacturing: Change Mode

Page 5: MF50-Planning Table Change

8/15/2019 MF50-Planning Table Change

http://slidepdf.com/reader/full/mf50-planning-table-change 5/9

 

Note: The top part of the table shows the work centers. The bottom part of the screen shows the products that can bemanufactured at the work centers and the present productionschedule.

Note: To optimize the production , sequence of production may bemanaged by moving scheduled quantities forwards or backwards. Youmay do this as shown in the example below.

10.  For the material you want to plan, select the Production Versionrows and the date columns you want to modify.

Planning Table for Repetitive Manufacturing: Change Mode

11.  Press .

Page 6: MF50-Planning Table Change

8/15/2019 MF50-Planning Table Change

http://slidepdf.com/reader/full/mf50-planning-table-change 6/9

 

Planning Table: Choose Period

12.  Press

Selection Days

13.  Enter the required Start and Fin. dates

14.  Press

Note: Following example shows how to schedule producito to tadifferent work center.

Page 7: MF50-Planning Table Change

8/15/2019 MF50-Planning Table Change

http://slidepdf.com/reader/full/mf50-planning-table-change 7/9

 

15.  Select the Production version rows and the date columns youwant to modify.

Planning Table for Repetitive Manufacturing: Change Mode

16.  Select to move the load to different production versions.

Distribute Prod. Quantities

Page 8: MF50-Planning Table Change

8/15/2019 MF50-Planning Table Change

http://slidepdf.com/reader/full/mf50-planning-table-change 8/9

 

17.  Update the following required and optional fields:

Field Name ValuesQuota (VR1) Enter value in

Column Quota.

Quota (VR2) Enter value inColumn Quota.

18.  Press Copy Button .

Planning Table for Repetitive Manufacturing: Change Mode

Page 9: MF50-Planning Table Change

8/15/2019 MF50-Planning Table Change

http://slidepdf.com/reader/full/mf50-planning-table-change 9/9

 

19.  Press Save .