2021-2025 Financial Plan Overview BOARD BUDGET WORKSHOP October 21, 2020 41787852 Section 1.1 Metro Vancouver Board Budget Workshop
2021-2025 Financial Plan OverviewBOARD BUDGET WORKSHOP
October 21, 202041787852
Section 1.1
Metro Vancouver Board Budget Workshop
Short-term Relief for HouseholdsLeverage supported tools to create a short-term action plan (1-3 years)
Maintain current goals and objectivesContinue work on strategic and long-range plans
Realize New OpportunitiesPartner on projects to increase affordable housing Reduce GHGs Help drive economic recovery
Board Direction from June Workshop
2Metro Vancouver Board Budget Workshop
3
Budget Adjustments
$967.5 M Prior Projection for 2021 Budget
$42 Increase for the average household in 2021(Water: $7, Liquid Waste: $26, Solid Waste: $3, MVRD: $6)
$602 Average annual costs for all Metro Vancouver services
$939.5 M Proposed 2021 Budget
$17 Increase for the average household in 2021(Water: $2, Liquid Waste: $8, Solid Waste: $0, MVRD: $7)
$577 Average annual costs for all Metro Vancouver servicesMetro Vancouver Board Budget Workshop
4
Overall Household Impact 2021-2025
2020 2021 2022 2023 2024 2025
Water District $172 $174 $178 $182 $197 $217
Liquid Waste $264 $272 $289 $310 $344 $385
Solid Waste $61 $61 $63 $65 $67 $70
Regional District $63 $70 $73 $77 $81 $82
Total Household Impact $560 $577 $603 $634 $689 $754Recommendation (30 yr) % Change 3.2% 4.2% 5.2% 8.8% 9.4%
Alternative (15 yr) % Change 3.2% 6.4% 7.3% 9.9% 11.5%
Prior Year % Change 7.4% 9.0% 8.0% 6.7%
Prior Year Forecast $602 $655 $708 $755Metro Vancouver Board Budget Workshop
5
Metro Vancouver Historic Population Growth
Metro Vancouver Board Budget Workshop
6
Metro Vancouver Projected Population Growth
Mod
ellin
g ye
ar
Metro Vancouver Board Budget Workshop
7
Timeframe
2021 Budget Approval (Oct)
Strategic Plan Update (Feb 2021)
Board Budget Workshop (Spring
2021)
• 2022 Budget Cycle will continue to prioritize:o Continuous improvement to realize cost savings and efficiency
gains, including delivery mechanisms for capital projectso Exploring alternatives to building new infrastructure i.e. demand side
management strategieso Sound fiscal managemento Understanding of municipal challengeso Early direction from Boards and Committees
Metro Vancouver Board Budget Workshop
8
Financial Plan Overview
View of VancouverMetro Vancouver Board Budget Workshop
9
Drivers:• Increase in Operations averages 2.2% over 5 years• Debt servicing reflective of the capital program, but
favorable rates and 30 year amortization in 2021/22• Easing Contribution to Capital in 2021/22/23 - Refocusing
in 2024/25
M E T R O VA N C O U V E R O P E R AT I N G B U D G E TE X P E N D I T U R E S
Overview:• 2020 Operating Budget: $894.3M• 2021 Operating Budget: $939.5M (5.1%)• $28M less than previously projected for 2021
$-
$100
$200
$300
$400
$500
$600
$700
$800
$-
$200
$400
$600
$800
$1,000
$1,200
$1,400
2020 2021 2022 2023 2024 2025
Mill
ions
Operations Contribution to Capital Debt Service Household Impact (Prior) Household Impact (Current)Metro Vancouver Board Budget Workshop
10
M E T R O VA N C O U V E R O P E R AT I N G B U D G E TR E V E N U E
Overview:• Primary funding sources - water sales, sewer
levy, tipping fees, rents, MVRD requisition• Expecting relative stability for primary sources• Continued focus on alternate sources
Drivers:• Assumed Water DCC revenue received and applied
starting in 2023• Assumed partner funding for upcoming major capital
projects, reduces pressure on levies/rates• Assume return to the Financial Management Policy in
2024/25
$-
$200
$400
$600
$800
$1,000
$1,200
$1,400
2020 2021 2022 2023 2024 2025
Mill
ions
Water Sales Liquid Waste Services Levy Solid Waste Tipping Fees MVRD Requisitions Housing Rents Other RevenuesMetro Vancouver Board Budget Workshop
$1,414.7 $1,524.7
$1,321.5 $1,416.1
$1,585.3 $1,523.7
$-
$200
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
$1,800
2020 2021 2022 2023 2024 2025
Mill
ions
Housing Regional Parks Solid Waste Liquid Waste Water
11
Drivers:• Capital project in progress carried forward• Reviewed for deferrals and savings• Project risks and scope provisions
Overview:• 2020 Capital Budget: $1.41B• 2021 Capital Budget: $1.52B• Increase: $110.0M (7.8%)
M E T R O VA N C O U V E R C A P I TA L B U D G E TE X P E N D I T U R E S
11Metro Vancouver Board Budget Workshop
12
Drivers:• Reducing Contribution to Capital increases
borrowing• Water DCC’s applied directly starting 2023• Partner funding for Iona 2024/25
Overview:• Primary funding – Borrowing and Contribution to
Capital • Most recent debentures issued at 1.28%• External partner funding a priority
M E T R O VA N C O U V E R C A P I TA L P R O G R A MF U N D I N G
12
$1,414.7 $1,524.7
$1,321.5 $1,416.1
$1,585.3 $1,523.7
$-
$200
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
$1,800
2020 2021 2022 2023 2024 2025
Mill
ions
External Funding Reserves DCC Applications Contribution to Capital New External BorrowingMetro Vancouver Board Budget Workshop
13
Recommendation:That the MVRD Board direct staff adopt a 30-year amortization for borrowing for 2021 and 2022 only and then return to a 15-year amortization period as per the Financial Management Policy.
Alternatively: maintain the 15-year amortization period for borrowing in the 2021 to 2025 Plan as per the Financial Management Policy.
Metro Vancouver Board Budget Workshop
14
LIQUID WASTE SERVICESGREATER VANCOUVER SEWERAGE & DRAINAGE DISTRICT
Lulu Island WWTP
Metro Vancouver Board Budget Workshop
15
Advanced treatment for North Shore and Vancouver Sewerage AreasExpansion of key infrastructure in the Fraser Sewerage Area in response to growthSource control actions to manage flows and Compounds of Environmental ConcernMaintain infrastructure to continue meeting the service expectations of the region
Liquid Waste over the next 5 yearsLIQUID WASTE OVERVIEW
North Road Trunk Sewer, Coquitlam Annacis Island WWTP
Douglas TrunkSewer, Burnaby
Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
16
PERFORMANCE METRICS
Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
17
Sanitary Sewerage Overflow EventsPERFORMANCE METRICS
0
10
20
30
40
50
60
70
80
90
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
# Ev
ents
Dry Wet <1:5 year return period Wet >1:5 year return period Projection
Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
18
Assets not Meeting Capacity or Regulation within 10 YearsPERFORMANCE METRICS
Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
19
Biosolids Annual Production / Stockpile VolumePERFORMANCE METRICS
0
50,000
100,000
150,000
200,000
250,000
300,000
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
2041
2042
2043
2044
2045
2046
2047
2048
2049
2050
2051
Annu
al P
rodu
ctio
n / S
tock
pile
Vol
ume
(wet
tonn
es)
Total Production Iona Stockpile
Iona Island Tertiary
North Shore Tertiary
Iona Island Dewatering
Metro Vancouver Board Budget Workshop
Initiative Outcomes
20
Biosolids – Fraser Valley Aggregates Gravel Pits Reclamation
AIWWTP Cogeneration System Expansion - Energy Reduction
LIWWTP Green Biomethane Facility
Liquid Waste Services Financial Plan
$1,700,000
$1,500,000
$860,000
CONTINUOUS IMPROVEMENT
In-House Engineering and Design for Capital Projects $500,000
O&M Operations Reviews $360,000
Initiative 2021 Savings GHG Reductions
Increased Analytical Testing Capacity and Lab Efficiency $45,000
2,300 t / year
250 t / year
2,200 t / year
-
-
-
Metro Vancouver Board Budget Workshop
Initiative Outcomes
21
WWTP Contract Services (Digester Cleaning, Small Projects)
Linear System Inspections
Employee Training (travel component)
Liquid Waste Services Financial Plan
$715,000
$410,000
$250,000
OPERATING EXPENDITURES – OTHER REDUCTIONS
WWTP Facilities Upkeep $210,000
WWTP Optimization of Chemical and Utilities $140,000
Operating Program / Activity 2021 Budget Reduction
Linear System Performance Monitoring $120,000
Metro Vancouver Board Budget Workshop
Initiative Outcomes
22
Capital Plan (Debt Service Increase / Contribution to Capital Decrease)
IIWWTP Biosolids Stockpile / Sludge Lagoon Decommissioning
MoE Wastewater Treatment Plant Fee Increase
Liquid Waste Services Financial Plan
$12,000,000 increase
$4,000,000 increase
$2,500,000 increase
OPERATING EXPENDITURES – DRIVERS FOR CHANGE
AIWWTP Stage 5 Liquid Stream Commencement of Operations $1,300,000 increase
IIWWTP Dewatering Facility Commencement of Operations $1,100,000 increase
Driver 2021 Budget Impact
Metro Vancouver Board Budget Workshop
Budget Year Initiative Description
23
2021 Annacis Island WWTP Stage 5Iona Island WWTP DewateringLulu Island WWTP Green Biomethane
Liquid Stream commissioning and handoverFacility commissioning and handoverFacility handover and sale of Biomethane
2022
2023
2024
Development Cost Charges (DCCs)Hydrothermal Liquefaction
Liquid Waste Management Plan
North Shore WWTPIona Island WWTP
Update of DCC ratesCommencement of biocrude production
Completion of update of LWMP
Facility commissioning and handoverBiosolids stockpile removal complete
Liquid Waste Services Financial PlanOPERATING HIGHLIGHTS
Metro Vancouver Board Budget Workshop
24
Liquid Waste Services Financial PlanCapital Program Review
Line-by-line reviewo 19 projects adjusted for budget managemento $150,000,000 capital costs deferred in 2021-2023
Deferred: Biosolids Dryer - 2 years Large Projects managed by Project Delivery Department
o Specialized expertise in management of complex projectso 3 of 124 Projects transferred representing 55% of total capital spend
Metro Vancouver Board Budget Workshop
Budget Year Capital Project Description
25
Liquid Waste Services Financial PlanCAPITAL PROGRAM HIGHLIGHTS
2021 Sapperton Pump StationIona Island WWTP Dewatering
Facility commissioning and handoverFacility commissioning and handover
2022
2023
2024
2025
North Shore WWTPBurnaby Lake North Interceptor
Annacis Island WWTP
Annacis Island WWTP OutfallGolden Ears Forcemain
North Surrey Interceptor
Conveyance pump station and pipeline completedWinston Section completed
Trickling Filters media replacement completed
Facility commissioning and handoverForcemain and river crossing completed
Odour control system commissioning and handover
Metro Vancouver Board Budget Workshop
2020 2021 2022 2023 2024 2025
26
$330.2
$274.2
$883.4
$264
$353.4
7.0%
$288.2
5.1%
$934.5
$272
3.1%
9.6%
$379.4
7.4%
$311.0
7.9%
$692.9
$289
6.0%
11.4%
$414.5
9.3%
$339.6
9.2%
$741.1
$310
7.2%
9.1%
$470.3
13.5%
$383.9
13.0%
$924.5
$344
11.1%
5.9%
$543.2
15.5%
$437.0
13.8%
$912.2
$385
11.9%
N/A
LIQUID WASTE SERVICES FINANCIAL PLAN SUMMARY
Total Expenditures ($ Millions)
% Change
Liquid Waste Levy ($ Millions)
% Change
Total Capital Expenditures ($ Millions)
Household Impact ($)
% Change
Prior Cycle Household Impact Change (%)
Metro Vancouver Board Budget Workshop
2020 2021 2022 2023 2024 2025
27
$99.2
$85.4
$89.5
$308
$104.6
5.5%
$90.1
5.4%
$65.2
$320
3.9%
6.8%
$111.0
6.1%
$97.8
8.6%
$91.2
$343
7.1%
6.4%
$115.9
4.4%
$102.9
5.3%
$120.7
$355
3.7%
5.2%
$126.1
8.8%
$115.8
12.5%
$218.1
$394
10.8%
3.1%
$140.6
11.4%
$130.4
12.6%
$330.5
$437
11.0%
N/A
LIQUID WASTE SERVICES FINANCIAL PLAN SUMMARY - VSA
Total Expenditures ($ Millions)
% Change
VSA Liquid Waste Levy ($ Millions)
% Change
Total Capital Expenditures ($ Millions)
Household Impact ($)
% Change
Prior Cycle Household Impact Change (%)
Metro Vancouver Board Budget Workshop
2020 2021 2022 2023 2024 2025
28
$28.6
$26.1
$347.3
$339
$31.4
9.7%
$28.6
9.8%
$404.4
$368
8.5%
10.8%
$35.3
12.4%
$32.5
13.4%
$115.0
$412
12.1%
16.8%
$40.5
14.9%
$37.4
15.3%
$147.3
$469
13.8%
11.6%
$47.8
17.9%
$44.9
20.0%
$44.5
$557
18.6%
12.8%
$55.6
16.3%
$52.7
17.4%
$9.0
$646
16.0%
N/A
LIQUID WASTE SERVICES FINANCIAL PLAN SUMMARY - NSSA
Total Expenditures ($ Millions)
% Change
NSSA Liquid Waste Levy ($ Millions)
% Change
Total Capital Expenditures ($ Millions)
Household Impact ($)
% Change
Prior Cycle Household Impact Change (%)
Metro Vancouver Board Budget Workshop
2020 2021 2022 2023 2024 2025
29
$27.4
$24.7
$37.7
$242
$28.9
5.4%
$25.6
3.8%
$55.7
$247
1.9%
11.6%
$30.2
4.4%
$26.9
5.0%
$45.9
$254
3.2%
12.6%
$32.8
8.7%
$29.2
8.5%
$6.9
$271
6.7%
9.4%
$35.5
8.4%
$32.0
9.7%
$7.9
$293
8.0%
6.6%
$40.4
13.8%
$36.9
15.3%
$11.3
$333
13.5%
N/A
LIQUID WASTE SERVICES FINANCIAL PLAN SUMMARY - LIWSA
Total Expenditures ($ Millions)
% Change
LIWSA Liquid Waste Levy ($ Millions)
% Change
Total Capital Expenditures ($ Millions)
Household Impact ($)
% Change
Prior Cycle Household Impact Change (%)
Metro Vancouver Board Budget Workshop
2020 2021 2022 2023 2024 2025
30
$172.8
$135.9
$408.9
$235
$186.2
7.8%
$141.7
4.3%
$409.2
$239
2.0%
11.2%
$200.7
7.8%
$151.7
7.1%
$440.8
$250
4.7%
13.0%
$223.0
11.1%
$167.9
10.6%
$465.8
$271
8.3%
11.0%
$258.6
15.9%
$189.0
12.6%
$653.4
$299
10.2%
5.9%
$304.3
17.7%
$214.7
13.6%
$560.8
$332
11.3%
N/A
LIQUID WASTE SERVICES FINANCIAL PLAN SUMMARY - FSA
Total Expenditures ($ Millions)
% Change
FSA Liquid Waste Levy ($ Millions)
% Change
Total Capital Expenditures ($ Millions)
Household Impact ($)
% Change
Prior Cycle Household Impact Change (%)
Metro Vancouver Board Budget Workshop
2020 2021 2022 2023 2024 2025
31
$2.2
$2.1
$2.3
2.6%
$2.2
4.4%
$2.2
(2.4%)
$2.1
(2.4%)
$0.0
$2.3
1.0%
$2.2
1.0%
$0.4
$2.3
2.1%
$2.2
2.2%
$0.6
$2.3
1.7%
$2.3
1.8%
$0.6
LIQUID WASTE SERVICES FINANCIAL PLAN SUMMARY - DRAINAGE
Total Expenditures ($ Millions)
% Change
Drainage Liquid Waste Levy ($ Millions)
% Change
Total Capital Expenditures ($ Millions) $0.0$0.0
Metro Vancouver Board Budget Workshop
32
PROJECT DELIVERY
Delivery of highest-value, highest-risk and complex Liquid Waste and Water infrastructure valued at $3.9B over 2021-2025:• Iona Island WWTP Program • North Shore WWTP Project• Northwest Langley WWTP Projects • Coquitlam Water Supply Project• Annacis Water Supply Tunnel • Second Narrows Water Crossing
Organization-wide Asset Management
Enhanced project delivery and training support for all departments
Metro Vancouver Board Budget Workshop
33
CAPITAL BUDGET MANAGED BY PROJECT DELIVERY
46%42%
48%56%
67%
-
200
400
600
800
1,000
1,200
1,400
1,600
1,800
2021 2022 2023 2024 2025
Cap
ital B
udge
t Dol
lars
(in M
illion
s) Other Capital
Project DeliveryCapital
Metro Vancouver Board Budget Workshop
34
MAJOR PROJECT TIMELINE1990 2000 2010 2020 2030
Iona Island WWTP Upgrade
North Shore WWTP Upgrade
Northwest Langley WWTP Expansion
Annacis WWTP Stage 5 Expansion
Second Narrows Water Supply Tunnel
Annacis Water Supply Tunnel
Cambie Richmond Water Supply Tunnel
Stanley Park Water Supply Tunnel
Coquitlam Water Main Planning/Design Construction
Planning/Design Construction
LW
WSCoquitlam Lake Water Supply
2021-2025BUDGET
Original Completion Date?
Metro Vancouver Board Budget Workshop
35
NORTH SHORE WWTP & CONVEYANCE
North Shore WWTP – Digesters
REGULATORY COMPLIANCEBenefits• Supports 19,000 Jobs• Protects marine environment• Anticipates future regulatory changes• Enhances energy and resource recovery
$ 2021-2025 Cashflow$ 686 million
Construction began – 2017Completion - 2024
Metro Vancouver Board Budget Workshop
36
IONA ISLAND WWTP PROGRAM
Iona Island WWTP – Current Site
REGULATORY COMPLIANCEBenefits• Supports 36,000 Jobs• First Nations cooperation• Enhances seismic and climate resiliency• Parkland and aquatic habitat enhancement
$ 2021-2025 Cashflow$750 million
Schedule to be reviewed
Metro Vancouver Board Budget Workshop
37
NORTHWEST LANGLEY WWTP PROJECTS
Golden Ears Pump Station– Indigenous Art Rendering
ACCOMMODATE GROWTH
Benefits• Supports 24,000 Jobs• Accommodates growth in North-East• Protects marine environment
$ 2021-2025 Cashflow$1.05 billion
Construction began – 2018Completion – 2027
Metro Vancouver Board Budget Workshop
38
That the GVS&DD Board:a) endorse the 2021 Budget and 2021-2025 Financial Plan for Liquid Waste Services, as
presented; andb) direct staff to prepare the necessary budget information to be presented at the
October 30, 2020 GVS&DD Board meeting for consideration
That the GVS&DD Board Chair write a letter to the Honourable George Heyman, Minister of Environment and Climate Change Strategy, requesting that the Minister consider the deferral or graduated application of the $2,479,807 fee increase in 2021 for Metro Vancouver’s five wastewater treatment plant authorizations.
Metro Vancouver Board Budget Workshop
39
WATER SERVICESGREATER VANCOUVER WATER DISTRICT
Capilano Reservoir
Metro Vancouver Board Budget Workshop
40
Maintain Metro Vancouver’s world-class clean, safe drinking water systemEnsure the long-term resilience of the regional drinking water systemPrioritize conservation efforts to defer capital growth projects
Water Services over the next 5 yearsWATER SERVICES OVERVIEW
Tilbury Junction Chamber
Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
41
Peak day per capita water use (litres)
628
Number of leak repairs in water transmission system piping per 100 kilometers of pipe
3.18
Annual volume of drinking water treated and delivered (in billion litres)
387
PERFORMANCE METRICS
593
<3.1
389
Metro Vancouver Board Budget Workshop
Initiative Outcomes
42
Application of expanded Building Information Modelling
Watershed Protection Program Improvements
Efficiency Improvements in Procurement of Capital Works
Reduce costs by reducing potential design conflicts and need for change orders during construction.
Improvements include watershed gate hardening, fencing enhancements, camera upgrades and increased presence at key boundary locations.
Pre-qualified pool of consultants to meet project work load spikes and contractors to reduce project tender time. Developed standardized method for linear projects to minimize community impacts and improve schedule.
CONTINUOUS IMPROVEMENT
Metro Vancouver Board Budget Workshop
Budget Year Initiative Description
43
2021 Update the Drinking Water Management Plan
Updated plan with our members will be a key part of how GVWD plans for the future
2022
2023
2024
2025
Develop Facility Master Plans
Environmental Management System for Water Services
Review Drinking Water Conservation Plan
Reservoir Isolation Valve Automation
Facility Master Plans will map future growth aligned with Metro Vancouver’s Water Supply Outlook 2120
Will document our commitment to environmental protection and regulatory compliance
Continue collaboration with our members to implement. Potential updates in 2024 following new restrictions first implemented Summer 2018
To improve network control and operational response times during emergencies
OPERATING HIGHLIGHTS
Metro Vancouver Board Budget Workshop
Budget Year Capital Project Description
44
2021 Central Park Main No. 2 Construction
Replacing existing main with high leakage rate which is at end of service life
2022
2023
2024
2025
Coquitlam Intake Tower Seismic Upgrade Construction
Rechlorination Station Upgrades Construction
Coquitlam Water Treatment Plant Ozone Backup Power
Whalley Kennedy Main No. 2 Detailed Design
Seismic upgrade to enable tower to withstand expected earthquake
Upgrade aging chemical piping, tanks and equipment to maintain level of service
Backup power construction to enable continued operation during a power outage
New main required to increase transmission capacity south of the Fraser River
CAPITAL PROGRAM HIGHLIGHTS
Metro Vancouver Board Budget Workshop
2020 2021 2022 2023 2024 2025
45
$310.4
$0.7836
$397.5
$172
$318.6
2.6%
$0.8110
($0.020)
$431.3
$174
1.7%
4.2%
$327.4
2.8%
$0.8341
($0.071)
$462.6
$178
1.8%
7.7%
$338.9
3.5%
$0.8633
($0.132)
$469.5
$182
2.4%
8.8%
$372.3
9.8%
$0.9440
($0.151)
$499.7
$197
8.4%
9.2%
$414.1
11.2%
$1.0508
N/A
$497.6
$217
10.0%
N/A
WATER SERVICES FINANCIAL PLAN SUMMARY
Total Expenditures ($ Millions)
% Change
Blended Water Rate ($/m3)
Blended Water Rate Change From Prior Cycle ($/m3)
Total Capital Expenditures ($ Millions)
Household Impact ($)
% Change
Prior Cycle Household Impact Change (%)
Metro Vancouver Board Budget Workshop
46
WATER SUPPLY TUNNEL PROJECTSCONSTRUCTION
• Second Narrows Water Supply Tunnel• Annacis Water Supply Tunnel• Stanley Park Water Supply Tunnel
Benefits• Supports 24,000 Jobs• Growth, Maintenance and Seismic Resilience
$ 2021-2025 Cashflow$932 million
Second Narrows2021-2024
AnnacisTunnel2021-2025
Stanley Park2022-2025
Tunnel Boring Machine – Port Mann South ShaftMetro Vancouver Board Budget Workshop
47
WATER SUPPLY TUNNEL OPTIONS
Cambie-Richmond Tunnel Alignment Options
PLANNING AND DESIGN• Lulu Island Delta Water Supply Tunnel• Cambie-Richmond Water Supply Tunnel
Benefits• Supports 15,000 Jobs• Enhances seismic resilience
$ 2021-2025 Cashflow$86 million
ConstructionLulu Island Delta Tunnel 2022-2026
Cambie-Richmond Tunnel2027-2031
Metro Vancouver Board Budget Workshop
48
COQUITLAM LAKE WATER SUPPLY PROJECT DEFERRAL
ACCOMMODATE GROWTHBenefits• Supports 48,000 Jobs• Doubles our ability to access, treat and
distribute water from Coquitlam Lake• Secures water supply for future generations• Enhances climate change resilience
$ 2021-2025 Cashflow$99 million
Schedule to be reviewed
Coquitlam Water Supply Project Rendering Metro Vancouver Board Budget Workshop
49
COQUITLAM MAIN WATER PROJECTACCOMMODATE GROWTH
Benefits• Supports 14,000 Jobs• Accommodates population growth• Enhances climate change and system
reliability• Improves seismic resilience
$ 2021-2025 Cashflow$308 million
Schedule to be reviewed
Coquitlam Water Main Proposed Route Metro Vancouver Board Budget Workshop
50
WATER CONSERVATIONIncentivizing additional water conservation through adjusted pricing approach
Existing Approach• Peak and non-peak water rates currently differentiated by a ratio of 1.25
• Proposed 2021 rates:• Non-peak - 0.7369 • Peak - 0.9211
For Consideration• Apply all of the increase to the peak rate
• Non-peak rate would remain the same as 2020, at 0.7119• Peak rate would go from 0.8899 to 0.9546, a 7.2% increase
Metro Vancouver Board Budget Workshop
51
That the GVWD Board:a) endorse the 2021 Budget and 2021-2025 Financial Plan for Water Services, as
presented; b) direct staff to calculate the water rates applying the 2021 increase wholly to the
peak rate; and,c) direct staff to prepare the necessary budget information to be presented at the
October 30, 2020 GVWD Board meeting for consideration
Metro Vancouver Board Budget Workshop
52
SOLID WASTE SERVICESGREATER VANCOUVER SEWERAGE & DRAINAGE DISTRICTMetro Vancouver Board Budget Workshop
53
Solid Waste Services 2021 Budget Highlights• 2021 Tipping Fees increase $4 per tonne (previous cycle
projection $7 per tonne)
• Per household cost unchanged from 2020 at $61 per household
• Budget projected to increase at 4.9% per year over five years – driven by debt for capital projects
• Priorities: zero waste and circular economy; greenhouse gas reduction and customer service
Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
54
Recycling Rate (percent of solid waste diverted from final disposal)
64%
Waste Disposed (tonnes) per Capita
0.48
Annual solid waste flows in Metro Vancouver system (tonnes)
920,000
PERFORMANCE METRICS
66%
0.45
860,000
Metro Vancouver Board Budget Workshop
Initiative Outcomes
55
Waste-to-Energy Facility District Energy
Bottom ash beneficial use
Reduced program expenditures: professional services, administrative efficiencies, Extended Producer Responsibility agreements
Up to 70,000 tonnes/year GHG reduction
Reduced landfill disposal of 40,000 tonnes per year, or 5% of regional solid waste quantities.
Operating budget savings of $700,000 per year
CONTINUOUS IMPROVEMENT
Metro Vancouver Board Budget Workshop
Budget Year Initiative Description
56
2021 Solid waste management plan update
Review and update of the region’s solid waste management plan
2022
2023
2024
2025
New transfer stations
Bottom ash beneficial use
Transfer Station expanded recycling
Waste-to-Energy Facility Operating Contract
New Coquitlam and Surrey Transfer Stations fully operational
Bottom ash beneficial use fully underway
New recycling depots at the Langley and Surrey Transfer Stations
Procurement for the Waste-to-Energy Facility operating and maintenance contract
OPERATING HIGHLIGHTS
Metro Vancouver Board Budget Workshop
57
Projected Tipping FeesProjected Tipping Fees
for Municipal Solid Waste ($/tonne)
2020 2021 2022 2023 2024 2025
Municipal Tipping Fee $113 $117 $121 $128 $135 $142
Small Vehicles (0-1t) $147 $151 $155 $162 $169 $176
Medium Vehicles (1-8t) $125 $129 $133 $140 $147 $154
Large Vehicles (>9t) $99 $103 $107 $114 $121 $128
Household Impact ($) 2020 2021 2022 2023 2024 2025
Household Impact $61 $61 $63 $65 $67 $70
% Change 0.0% 2.8% 3.5% 4.0% 4.2%
Metro Vancouver Board Budget Workshop
58
Implications of Not Increasing Tipping Fees• Significant reduction in projected surplus to account for
inbound waste tonnage, uncertainty may require funding from reserves.
• $2.9M revenue reduction.
• Return to currently anticipated tipping fee projection in 2022.
• Per household impact reduced from $61 (in 2020) to $59 (in 2021).
• Budget still projected to increase at 4.9% per year over five years – driven by debt for capital projects.
Metro Vancouver Board Budget Workshop
Budget Year Capital Project Description
59
2021Coquitlam Transfer Station and Surrey Recycling and Waste Drop-Off
Completion of two new transfer stations and updated recycling depot funding model
2022
2023
2024
2025
Biosolids Management at Waste-to-Energy Facility
Surrey and Langley Transfer Station Recycling Depot Expansion
Waste-to-Energy Facility Capital Replacements
Alternative Fuel and Recyclables Recovery Centre
Processing of 25,000 tonnes per year of biosolids at the Waste-to-Energy Facility
New full service recycling depots ahead of the scales
Ongoing replacement of end-of-life capital works
Construction of a new facility to recover materials for higher use
CAPITAL PROGRAM HIGHLIGHTS
Metro Vancouver Board Budget Workshop
2020 2021 2022 2023 2024 2025
60
$114.1
$105.8
$88.5
$61
$118.5
3.9%
$108.5
2.5%
$96.3
$61
0.0%
5.0%
$124.7
5.2%
$113.0
4.1%
$76.3
$63
2.8%
3.5%
$131.1
5.2%
$118.2
4.7%
$65.6
$65
3.5%
3.2%
$137.5
4.8%
$124.3
5.2%
$30.8
$67
4.0%
3.8%
$144.7
5.2%
$131.3
5.6%
$29.9
$70
4.2%
N/A
SOLID WASTE SERVICES FINANCIAL PLAN SUMMARY
Total Expenditures ($ Millions)
% Change
Tipping Fees ($ Millions)
% Change
Total Capital Expenditures ($ Millions)
Household Impact ($)
% Change
Prior Cycle Household Impact Change (%)
Metro Vancouver Board Budget Workshop
61
That the GVS&DD Board:a) endorse the 2021 Budget and 2021-2025 Financial Plan for Solid Waste Services, as
presented; andb) direct staff to prepare the necessary budget information to be presented at the
October 30, 2020 GVS&DD Board meeting for consideration
Metro Vancouver Board Budget Workshop
62
METRO VANCOUVER HOUSING CORPORATION
Lynden Court
Metro Vancouver Board Budget Workshop
63
MVHC OVERVIEW
VisionBe a leader in providing safe, affordable housing to support healthy, engaged communities across the region
Guiding Principles• Social: support tenant well-being through quality housing & community building• Financial: ensure long-term affordability through financial sustainability• Environmental: strive to enhance environmental and energy sustainability
Key Directions• Provide (affordable rental housing for families, seniors and others) • Preserve (housing on 49 sites for 9,400 residents)• Expand (through strategic redevelopment and partnerships)
Metro Vancouver Board Budget Workshop
64
Household Impact• MVHC operations have no financial impact ($0) on the region; operations
are primarily supported by rents
Revenue Sources for Operations • Tenant Rents – 93%• BC Housing Subsidies – 5%• Site services – 2%
FINANCIAL CONTEXT
Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
65
% of units rented at Rent-Geared-to-Income
35% of portfolio
Communities supported by tenant associations
28 sites (58%)
Reduce greenhouse gas emissions
10.2 grams CO2 emissions / sq. meter
PERFORMANCE METRICS
34% of portfolio
31 sites (63%)
7.45 grams CO2 emissions / sq. meter
Metro Vancouver Board Budget Workshop
Initiative Outcomes
66
Develop and deliver a wide range of tenant programs
Improve building energy efficiency and reduce consumption
Explore and incorporate new technologies
Support healthy engaged communities through the delivery of tenant programs and public initiatives e.g. community gardens, health and wellness programming, free food program
Full building rehabilitations preserve affordable housing while improving energy efficiency and improving tenant comfort; Net Zero study; Step Code possibilities for Rehabilitations
Embrace new technologies that will support effective and efficient building operations and maintenance; in-suite water monitoring
CONTINUOUS IMPROVEMENT
Metro Vancouver Board Budget Workshop
67
Welcher Ave., Kingston Gardens Tender & Construction
2022
2023
Kelly Court & Evergreen Downs
Heather Place B
Welcher Ave. & Kingston Gardens
Construction of full building rehabilitations
Begin construction
Complete and hand over to Operations
Year Initiative Description
OPERATING AND CAPITAL HIGHLIGHTS
2025 Heather Place B Complete and hand over to Operations
New and Redevelopment Projects Finalize design
New and Redevelopment Projects Construction
2024 New and Redevelopment Projects Construction
New and Redevelopment Projects Tender architectural services and begin designHeather Place B Continue design
New and Redevelopment Projects Construction
2021
Metro Vancouver Board Budget Workshop
2020 2021 2022 2023 2024 2025
68
$52.3
$40.4
$25.3
$53.7
2.7%
$41.3
2.3%
$39.6
$54.7
1.8%
$41.8
1.2%
$61.3
$57.6
5.3%
$44.4
6.1%
$109.3
$58.4
1.5%
$44.8
0.9%
$96.1
$62.1
6.4%
$47.4
5.9%
$48.2
Total Expenditures ($ Millions)
% Change
Housing Rents
% Change
Total Capital Expenditures ($ Millions)
MVHC FINANCIAL PLAN SUMMARY
Metro Vancouver Board Budget Workshop
69
That the MVHC Board:a) endorse the 2021 Budget and 2021-2025 Financial Plan for Metro Vancouver
Housing Corporation, as presented; andb) direct staff to prepare the necessary budget information to be presented at the
October 30, 2020 MVHC Board meeting for consideration
Metro Vancouver Board Budget Workshop
70
METRO VANCOUVER REGIONAL DISTRICT
Burnaby, BC
Metro Vancouver Board Budget Workshop
71
• Housing Planning & Policy• Regional Planning• Electoral Area Services• Regional Parks• Air Quality• E911 Emergency Telephone Service• General Government Administration
• General Government Zero Waste Collaboration Initiatives• Regional Economic Prosperity• Regional Employer Services• Regional Emergency Management• Regional Global Positioning System• Sasamat Fire Protection Service
MVRD OVERVIEW
Metro Vancouver Board Budget Workshop
2020 2021 2022 2023 2024 2025
72
$87.3
$71.8
$63
$95.3
9.1%
$80.9
12.7%
$70
10.6%
8.8%
$98.9
3.8%
$86.4
6.7%
$73
4.9%
7.1%
$104.8
6.0%
$92.8
7.5%
$77
5.5%
5.9%
$111.0
5.9%
$99.0
6.6%
$81
4.9%
5.7%
$114.0
2.7%
$102.2
3.2%
$82
1.5%
N/A
REGIONAL DISTRICT FINANCIAL PLAN SUMMARY
Total Expenditures ($ Millions)
% Change
MVRD Requisitions ($ Millions)
% Change
Household Impact ($)
% Change
Prior Cycle Household Impact Change (%)
Total Capital Expenditures ($ Millions) $19.9 $23.1 $28.4 $30.7 $34.2 $35.8
Metro Vancouver Board Budget Workshop
That the Metro Vancouver Regional District Board:
a) endorse the 2021 Budget and 2021-2025 Financial Plan for the Regional District Service Areas, as presented;
b) endorse the 2021 Budget and 2021-2025 Financial Plan for the Electoral Area A Service Area, as presented;
c) endorse the 2021 Budget and 2021-2025 Financial Plan for the SasamatFire Protection Service, as presented; and
d) direct staff to prepare the necessary budget information to be presented at the October 30, 2020 Metro Vancouver Regional District Board meeting for consideration
73Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
74
Approval for 1,350 homes into development (10 Year Target)
304 units approved through 2020
Pursue funding partnerships to support development projects
2 projects funded
MVHC comprehensive policy review / updates
25% complete
PERFORMANCE METRICS: HOUSING PLANNING & POLICY
805 units approved (cumulative)
5 projects funded
80% complete
Metro Vancouver Board Budget Workshop
Initiative Outcomes
75
Implement 10-Year Plan – e.g. Redevelopment priorities and new sites
Sustainability – e.g. feasibility studies / grants -Net Zero Energy in new buildings
Best practice guides and researche.g. What Works Guide: Housing Agreements
Progress towards providing, preserving and expanding the housing portfolio on several fronts including endorsement of priority sites for new & redevelopment
Reduced GHG emissions and energy consumption to support regional objectives
Coordinating and convening municipal stakeholders to research and develop best practices that benefit all regional members
CONTINUOUS IMPROVEMENT: HOUSING PLANNING & POLICY
Metro Vancouver Board Budget Workshop
Budget Year Initiative Description
76
2021 Initiation of two-to-four new & redevelopment projects
Continue work to advance projects
2021
2021
2022
2023
Seek funding partnerships
Support regional planning & policy on housing related issues
Develop project concepts and funding partnerships
Target funding opportunities to support the development of affordable housing
Undertake best practice research to support regionally developed objectives; Metro 2050 Policy
Explore opportunities for new developments through concept development and funding partnerships
OPERATING HIGHLIGHTS: HOUSING PLANNING & POLICY
Continue to support 10 Year Plan implementation
Potential additional EOI, partnerships for higher density sites
Metro Vancouver Board Budget Workshop
77
CONTAIN GROWTHPERFORMANCE METRICS: REGIONAL PLANNING
Target to 2040
98%of growth within the Urban Containment BoundaryPerformance
98%Metro Vancouver Board Budget Workshop
78
GROWTH TO CENTRESPERFORMANCE METRICS: REGIONAL PLANNING
Targets to 2040
40%dwelling unit growth
Performance 39%
Metro Vancouver Board Budget Workshop
Target to 2040
28%dwelling unit growthalong the Frequent Transit Network
Performance 25%Based on current FTN
79
GROWTH TO TRANSIT CORRIDORSPERFORMANCE METRICS: REGIONAL PLANNING
Metro Vancouver Board Budget Workshop
80
PROTECT IMPORTANT LANDSPERFORMANCE METRICS: REGIONAL PLANNING
Target to 2040Minimize Conversion
AgriculturalIndustrialEmployment
Performance Minor Losses
Metro Vancouver Board Budget Workshop
Initiative Outcomes
81
Metro 2050
Regional Industrial Lands Strategy
Housing + Transportation Cost Burden Study
• Apply climate / resiliency and social equity lenses • Improve alignment with Transport 2050• Fill gaps identified through 9 years implementation
• Implement priority actions adopted July 2020• Conduct regional land use assessment, develop
trade-oriented overlay, improve regional policies
• Update 2016 study to support ongoing dialogue about affordability
CONTINUOUS IMPROVEMENT: REGIONAL PLANNING
Metro Vancouver Board Budget Workshop
Budget Year Initiative Description
82
2021
2021
2021
2021
2021
Metro 2050 Complete draft strategy, circulate for comment, engagement and approvals
Housing + Transportation Cost Burden Study
Regional Industrial Lands Strategy Implementation
Regional Agricultural Land Use and Sensitive Ecosystem Inventories
Data / Projections Validation
Update 2016 to inform policy re affordability
Implement priority actions – Regional Land Use Assessment; Regional Policy
Update inventory and identify changes in land use
Projections for Metro 2050 and align with T2050
OPERATING HIGHLIGHTS: REGIONAL PLANNING
Metro Vancouver Board Budget Workshop
Budget Year Capital Project Description
83
2022 Metro 2050 Adopt the updated Regional Growth Strategy
2022
2022
2023
2024
New Land Use Model
Transit Oriented Affordable Housing Study
Metro 2050 Implementation
Frequent Transit Corridor Study
Demographics module to support updated projections and model land use change
Complete Phase III
Complete Implementation Guidelines, Census Updates, Land Use Inventories
Support land use objectives aligned with transit provision
OPERATING HIGHLIGHTS: REGIONAL PLANNING
Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
84
Number of public meetings andengagement events
8
Number of visits to the Electoral Area A Website
12,000
PERFORMANCE METRICS
8
10,000
Electoral Area Financial Plan
Metro Vancouver Board Budget Workshop
Initiative Outcomes
85
2020: Pitt Lake Barge Cleanup Event
2021: Geotechnical study for portion of Electoral Area A where Metro Vancouver provides building inspection services
2020-2021: Fire Protection Services Feasibility Study for Howe Sound
Assisted residents in recycling large items Reduced the risk of environmental contaminationFuture events included in the five-year work plan
Increased understanding of geo-hazards in EA APotential cost-savings for residents applying for building permits
Potential fire protection for EA A communitiesPotential lower fire insurance rates for residents
CONTINUOUS IMPROVEMENT: ELECTORAL AREA
Metro Vancouver Board Budget Workshop
2020 2021 2022 2023 2024 2025
86
$808,417
$376,943
$58
$683,901
$394,411
$61
4.6%
5.8%
$768,551
$406,883
$63
3.1%
6.6%
$682,881
$411,213
$63
1.0%
4.2%
$698,948
$431,865
$67
5.0%
3.5%
$705,930
$450,847
$69
4.4%
N/A
ELECTORAL AREA FINANCIAL PLAN SUMMARY
Total Expenditures ($)
% Change
Household Impact ($)
Prior Cycle Household Impact Change (%)
Electoral Area Requisition ($)
% Change
(15.4%) 12.4% (11.1%) 2.4% 1.0%
4.6% 3.2% 1.1% 5.0% 4.4%
% Change
Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
87
Visits to Regional Parks 3-year average: 11,856,000
Participants in Regional Park programming
3-year average:62,798 (Projected COVID-19 2020- 8,000)
Area of Regional Parks Land 2019: 13,632 ha2018: 13,557 ha*2017: 14,588 ha*reflects changes with Regional Parks Service boundary Abbotsford)
PERFORMANCE METRICS: REGIONAL PARKS
16,500,000
10,000 participants
13,650 hectares (33,730 acres)
Metro Vancouver Board Budget Workshop
Initiative Outcomes
88
Land Acquisition and Ecological restoration of Burns Bog, Parkland acquisitions at Widgeon Marsh in Coquitlam and Codd Wetland in Pitt Meadows.
Indigenous Relations for Regional Parks
Strategy and Management Plan Development (e.g. Regional Greenways Strategy, Campbell Valley Management Plan, Buildings Strategy, Programming and Interpretation Strategy)
Sequestration of carbon, protection ecosystems and help people connect with nature. Primary contributor to achieving corporate MVRD carbon neutrality. (Value of $4.1M in carbon credits)
Implementation of the Belcarra Regional Park Cultural Planning and Cooperation agreement as a model of relationship building towards reconciliation for municipal indigenous relations for local and regional parks.
Developing region-wide strategic and policy documents to provide management strategies for natural area protection, resiliency and for the management of facilities for residents to connect with regional parks.
CONTINUOUS IMPROVEMENT: REGIONAL PARKS
Metro Vancouver Board Budget Workshop
Budget Year Initiative Description
89
Park Capacity and Parking Lot management system
Trial programs to manage visitation traffic and parking capacity issues
Regional Parks Systems Plan
Widgeon Marsh Regional Park
Asset management plan implementation
Updating the Regional Parks plan and developing a system wide resource management plan
Major park development (2021-2023), commence operations and opening 2023
Advancement of asset management plan system wide
OPERATING HIGHLIGHTS: REGIONAL PARKS
Delta/South Surrey Greenway
2021
Management plan implementation and operations
2022
2023
2024
2025
Metro Vancouver Board Budget Workshop
Budget Year Capital Project Description
90
Widgeon Marsh Regional Park Development (2021-2023)
Development and opening of Widgeon Marsh Regional Park (626.5 hectares or 1548 acres)
Grouse Mountain Regional Park Improvements (2021-2024)
Delta Nature Reserve & Delta South Surrey Greenway (2023-2024)
Campbell Valley Management Plan implementation
Belcarra South Day Use Area and Admiralty Heights
Trails, open space, ecological enhancements (Investing in Canada Infrastructure Grant)
Major Greenway development, Delta Nature Reserve Boardwalks, ecological enhancements
Perimeter trails, public amenity upgrades and passive area development
New beach access, open space, trails and parking
CAPITAL PROGRAM HIGHLIGHTS REGIONAL PARKS
Ongoing Land Acquisition Implementation of the Land Acquisition Strategy
2021
2022
2023
2024
2025
Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
91
Regional Greenhouse Gas Emissions (tonnes CO2e/capita)
6.3 to 4.8 tonnes per capita per year
Corporate Greenhouse Gas Emissions (tonnes CO2e)
60 – 100% carbon neutral
Days under air quality advisory 0 – 7 days(impacted by wildfires outside of region)
PERFORMANCE METRICS: AIR QUALITY
4.2 tonnes per capita
100% carbon neutral (0 tonnes CO2e)
0 days
Metro Vancouver Board Budget Workshop
Initiative Outcomes
92
Climate 2050, roadmaps
Air quality bylaws, regulations, permits
Air quality standards and objectives
Dynamic, evolving roadmaps moving us towards a carbon neutral, resilient regionExpanding portfolio of corporate climate action and carbon credit projects, to maintain corporate carbon neutrality
Improved emissions control technologies, and lower emitting equipment and industrial processes
More stringent standards, supported by regularly updated monitoring technology
CONTINUOUS IMPROVEMENT: AIR QUALITY
Metro Vancouver Board Budget Workshop
Budget Year Initiative Description
93
2021 Climate 2050Clean Air PlanBylaws and regulations
Initial roadmaps, annual reportBoard adoptionFees bylaw, non-road diesel engines
2022
2023
2024
2025
Climate 2050Bylaws and regulationsMonitoring and indicators
Climate 2050Bylaws and regulations
Climate 2050Bylaws and regulations
Climate 2050Bylaws and regulations
Continue roadmap implementation; assess IPCC reportOutreach on residential wood burningNext regional emissions inventory
Continue roadmap implementation; SIF projectsDevelopment per 5 year plan and as new priorities arise
Continue roadmap implementation; SIF projectsDevelopment per 5 year plan and as new priorities arise
Continue roadmap implementation; SIF projectsDevelopment per 5 year plan and as new priorities arise
OPERATING HIGHLIGHTS: AIR QUALITY
Metro Vancouver Board Budget Workshop
Key Performance Past Performance (Average) Expected Performance 2021
94
Collective Agreements Serviced 49
National Zero Waste Council Events
10
GPS Service Uptime – 24/7 x 365
97%
MVRD OtherPERFORMANCE METRICS
50
15
98%
Metro Vancouver Board Budget Workshop
Initiative Outcomes
95
Next Generation 911 System
Improvements to the myRES Portal
Virtual Zero Waste Conference
MVRD Other
Full digital system with enhanced text, video and location functions.
Phase 3 – Increased access to on-line tools, data and customized reporting.
The 2020 Zero Waste Conference has been pivoted to continue to provide a valued conference experience in a virtual environment.
CONTINUOUS IMPROVEMENT
Metro Vancouver Board Budget Workshop
Budget Year Initiative Description
96
2021 Emergency Preparedness Conduct Regional exercises that focus on decision making.
2021
2021/22
2021
2023
Regional Workforce Strategic Initiative (RWSI)
911 System Upgrade
National Zero Waste Conference
Fire Services
Formalize the RWSI as a Regional Service.
Implement Next Gen 911 system upgrade with E-Comm.
Plan and host 2 day Zero Waste Conference.
Convert Fire Chief to a full time position.
MVRD OtherOPERATING HIGHLIGHTS
Metro Vancouver Board Budget Workshop
97
REGIONAL DISTRICT FINANCIAL PLAN
$87.3 $95.3 $98.9
$104.8 $111.0 $114.0
$-
$10
$20
$30
$40
$50
$60
$70
$80
$90
$-
$20
$40
$60
$80
$100
$120
2020 2021 2022 2023 2024 2025
Milli
ons
2021 - 2025 Regional District Financial Plan
Regional Parks Air Quality Housing Planning and Policy Regional PlanningOther Household Impact (Current) Household Impact (Prior)
Metro Vancouver Board Budget Workshop
98SUMMARY
Metro Vancouver Board Budget Workshop
99
2021 Budget Summary
$939.5 M Proposed 2021 Budget
$17 Increase for the average household in 2021(Water: $2, Liquid Waste: $8, Solid Waste: $0, MVRD: $7)
$577 Average annual costs for all Metro Vancouver services
Metro Vancouver Board Budget Workshop
Thank you
Pitt River Greenway
Metro Vancouver Board Budget Workshop