PRESENTATION ON BANGALORE METRO RAIL PROJECT - PHASE 2 10 th September 2012 BANGALORE METRO RAIL CORPORATION LTD .
PRESENTATION ON
BANGALORE METRO RAIL PROJECT - PHASE 2
10th September 2012
BANGALORE METRO RAIL CORPORATION LTD.
Bangalore City : Fact File
Population 8.5 million
Metropolitan Area 741 Sq Kms.
Elevation 920- meters
Moderate climate min of 12 Deg C max of 34 Deg C
India's Third most populous city
Garden City & Silicon Valley of India.
One of the top four global technological hubs
Home to over 500 MNCs.
Major health care, higher education and research centre.
OUTLINE OF PRESENTATION
INTRODUCTION
STATUS POSITION OF PHASE 1
PHASE 2 – An Overview
Bangalore Metro Rail Project
INTRODUCTION
Bangalore Metro Rail Corporation Limited (BMRCL), a joint venture of Government of India and
Government of Karnataka is a Special Purpose Vehicle entrusted with the responsibility of
implementation of Project.
The Phase 1 is 42.3 KM and the completion cost is expected to be
Rs 11609 Cr
Bangalore Metro Rail Project
PHASE 1
EAST – WEST CORRIDOR 18.10 KMS
NORTH-SOUTH CORRIDOR 24.20 KMS TOTAL 42.30 KMS
Elevated Stations 33
Underground Stations 7
Total 40
GAUGE Standard Gauge
TRACTION 750V dc Third Rail
SPEED Max 80Kmph ; Avg. 34Kmph
TRAVEL TIME 33 / 44 Mins.
Bangalore Metro Rail Project
Bangalore Metro Rail Project
REACH 1 : The 7 km of Reach 1 is commissioned on 20th
Oct 2011. So for 75 Lakh trips have been made.
Bangalore Metro Rail Project
REACH 2
93% of Viaduct is completed.
Remaining work on Viaduct is expected
to be complete by Feb 2013
58% of progress is recorded in the
stations and civil works are estimated
to be complete by June 2013
Bangalore Metro Rail Project
REACH 3
Launching is almost coming to completion.
96% of the work already has been completed.
With regard to stations around 60% of
progress is completed and remaining civil
works are estimated to complete by Dec 2012.
The commencement of trials will begin
latest by Jan -Feb 2013
Bangalore Metro Rail Project
REACH 3A
94% progress has been achieved in
the construction of Viaduct.
With regard to stations, 65% of civil
works is completed.
The commencement of trials will
begin by March 2013
Bangalore Metro Rail Project
REACH 3B
86% of Viaduct has been
completed.
Regarding stations, 40% of civil
works are over and expected to be
completed by September 2013
The commencement of trials will
begin by October 2013
Bangalore Metro Rail Project
REACH 4
Viaduct works have been
completed. The roads are made good
for public under the viaduct.
Around 85% of progress has been
achieved in stations. Off road structure
are under progress.
Bangalore Metro Rail Project
REACH 4A
86% of Viaduct is completed. Pile
caps, pier construction and erection
of segments are at various stages of
progress for the remaining work.
Overall 35% of Progress has been
achieved in stations.
The commencement of trials will
begin by June 2013.
Bangalore Metro Rail Project
Underground Section
East-West Corridor .
Tunneling and civil works at stations are
progressing well . The Tunnel between Majestic
and Central college has been completed. Overall
44% Progress has been achieved.
North-South Corridor
Civil works at ramps and for the shaft are under
progress. Tunneling work will start soon.
Slum Rehabilitation
STATUS POSITION OF PHASE 1
Physical Progress – 63%
Financial Progress – 66%
15.00
4.00
1.00
8.00
4.50
12.00
5.00
3.00
1.50 2.00 2.00
7.00
8.00
2.00
16.00
1.00
8.00
14.90
3.96
0.95
7.55
3.10 3.56
1.47 1.52
0.20
2.00 1.65
3.25
4.54
1.05
11.78
0.28
1.40
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
Ten
der
Fin
alis
atio
n
Lan
d
Uti
litie
s
Elev
ated
Str
uct
ure
s (V
iad
uct
)
Stat
ion
s -
Elev
ated
&
at G
rad
e Tun
nel
s
Stat
ion
s -
UG
Per
man
ent
Way
Ven
tila
tio
n a
nd
A
irco
nd
itio
nin
g
Dep
ot
Bai
yap
pan
ahal
li
Dep
ot
Pee
nya
Trac
tio
n a
nd
Po
wer
su
pp
ly
Sign
allin
g an
d
Tele
com
mu
nic
atio
n
Au
tom
atic
Far
e C
olle
ctio
n
Ro
llin
g St
ock
Esca
lato
rs a
nd
Lif
ts
Fin
al T
esti
ng
and
C
om
mis
sio
nin
g
Bangalore Metro Rail Project
Peenya Depot - Yeshwanthpur -
Sampige Road
March 2013
Peenya Depot - Hessarghatta cross June 2013
U/G Section E-W corridor December 2014
City Station - Mysore Road December 2014
K.R.Market - R.V Road - Puttenahalli
cross
December 2014
Commissioning Schedule
PHASE 2
It consists of Four Extensions to the existing
lines and Two New Lines, The Route Length
is 72.1 KM with 61 Stations
The Phase-I (42.3 km) and Phase-II (72.10 km), together will
create a Metro Network of 114.40 km, with 101 Stations (80
Elevated, 19 Underground and 2 At-Grade)
1.Baiyappanahalli to ITPL – Whitefield (Extension of E-W Line)
2.Mysore Road Terminal to Kengeri (Extension of E-W Line)
3.Hesaraghatta Cross to BIEC (Extension of N-S Line)
4.Puttenahalli Cross to Anjanapura (Extension of N-S Line)
5.R.V. Road to Bommasandra (E-W New Line)
6.Gottigere - IIMB - Nagawara (N-S New Line)
PHASE 2 CORRIDORS
Namma Metro Phase 2
Mysore Road
Hesarghatta Cross
Puttenahalli
Cross
BIEC
Anjanapura Township
Kengeri
Nagawara
IIM(B)
Bommasandra
RV
Road
Arabic College
Venkateshpura
Tannery Road
Pottery Town
Cantt Rly
JP Nagar IV Phase
KR
pu
ram
Nara
ya
nap
ura
Ma
had
eva
pu
ra
Ga
rud
ac
harp
aly
a
Ra
gi G
ud
da
Te
mp
le
Hebbagodi
Banashanka
ri
JPNagar
Anjanapura Road
Krishnaleela Park (ISCKON0
Vajrahalli Thalaghatapura
Nayandahalli
Rajarajeshwarinagar Bangalore university
RV College
Hulimavu
Gottigere
MGRd
Phase -1
East West Line
North South Line
Phase-II Extension of
Phase-1 North South & East West
Lines
RV Road to
Bommasandra
Gottigere to
Nagavara
Underground
section of Gottigere to Nagavara line
BANGALORE METRO PHASE-2
SN Alignment Length of the line in Km
At grade Elevated UG Total
1. Mysore road station to Kengeri
Terminal station.
0.000 6.465 0.000 6.465
2. Baiyappanahalli station to
Whitefield station
0.000 15.500 0.000 15.500
3. Hessaraghatta cross station to
BIEC station
0.000 3.770 0.000 3.770
4. Puttenahalli cross station to
Anjanapura Township station
0.000 6.290 0.000 6.290
5. RV Road station to
Bommasandra station
0.000 18.820 0.000 18.820
6. Gottigere station to Nagavara
station .
0.480 6.980 13.790 21.250
Total in Km.
0.480
57.825
13.790
72.095
BANGALORE METRO PHASE-2 Sl. Alignment Number of stations.
At grade Elevated UG Total
1. Mysore road station to
Kengeri Terminal station.
0 5 0 5
2. Baiyappanahalli station to
Whitefield station
0 14 0 14
3. Hessaraghatta cross station to
BIEC station
0 3 0 3
4. Puttenahalli cross station to
Anjanapura Township station
0 5 0 5
5. RV Road station to
Bommasandra station
0 16 0 16
6. Gottigere station to Nagavara
station .
0 6 12 18
Total in Numbers
0
49
12
61
Sl.
No.
Corridor Length
in kms Total in Cr
1. Hessarghatta Cross to Bangalore
International Exhibition Centre (BIEC) on
Tumkur Road
3.77 1168.22
2. Puttenahalli to Anjanapura Township (Nice
Road)
6.29 1765.88
3 Mysore Road Terminal to Kengeri on
Mysore Road
6.47
1867.95
4. Extension of East West Line from
Baiyappanahalli to ITPL
15.50 4845.00
5. North-South line from Gottigere IIMB /
Nagavara
21.25 11014.00
6. R V Road Terminal to Bommasandra 18.82 5744.09
Total 72.10 26405.15
BANGALORE METRO PHASE-2
BANGALORE METRO PHASE-2
Construction Methodology
Elevated viaduct consisting of prestressed concrete “U” shaped/Box
shaped single cell/I-Section Girders on Single pier/Portal with
pile/Open foundations.
Elevated stations-Portal type and cantilever type.
Underground tunneling by TBM, Stations by Cut & Cover.
BANGALORE METRO PHASE-2 Traction power supply (Note: Exact number of TSS will get finalised after detailed design.)
Particulars Four extensions RV Road –
Bommasandra line
Gottigere-Nagavara
line
Traction system voltage. 750V DC Third rail 750V DC Third rail
25 KV AC
Current collection. Third rail bottom
collection
Third rail bottom
collection
OHE
Power substation. Anjanapura, Kengeri and
ITPL
Naganathpura and RV
Road
Hulimavu and Nagavara
Power supply source. 66 KV AC 66 KV AC 66 KV AC
Number of receiving
substations
3 2 2
Number of traction
substations
14 8 2
SCADA system Provided Provided Provided
In respect of New Line - IIMB - Nagawara, Axle load will be 16 t
Rolling Stock
The Rolling Stock will be 2.88 m wide with stainless steel body
Standard Gauge.
•Axle load - 15 t
•Seating arrangement - Longitudinal
•Capacity of 3 Coach Unit - 975 Passengers
•6 Coach Unit - 2004 Passengers
•Class of accommodation - One
BANGALORE METRO PHASE-2
Communication System:
Four Extensions to EW &NS lines in Phase – 2 will have following sub-systems as already
adopted in Phase – 1.
• Fibre Optic Transmission system (FOTS), GE and SDH.
• Telephone system (EPABX & direct lines).
• Radio system (TETRA).
• Broad Band Radio System (BBRS).
• Closed Circuit Television system (CCTV).
• Passenger Information Display System (PIDS).
• Public Address system (PAS).
• Master Clock system.
• Telecom- Supervisory Control and Data Acquisition (T-SCADA).
New lines between Gottigere - Nagawara and R V Road – Bommasandra will also have the
above features.
BANGALORE METRO PHASE-2 AFC system:
Extensions to EW &NS lines of Phase -1 will have the following features:
Technical features
• Central Computer (upgradation if existing vendor, else new CC).
• Station Computers.
• Station equipment viz. Automatic Gates, TOM, Customer Care & RVCT.
• Automatic TVMs.
• Interface with Banks and other operators for add-value function.
• Contactless Fare Media.
New Developments
• Common Fare Media (MORE Bangalore) interoperable on BMRCL, BMTC, KSRTC, Cabs,
Micro payments.
• Integration with Transaction Settlement House.
• NFC deployment.
• New lines between Gottigere - Nagawara and R V Road – Bommasandra will also have the
above features.
BANGALORE METRO PHASE-2
Maintenance facilities
Particulars Four extensions RV Road –
Bommasandra line
Gottigere-
Nagavara line
Maintenance
Depot
Baiyappanahalli depot on E-W,
Peenya depot on N-S
( Both provided in Phase-1).
A new depot is proposed to be
provided at Kengeri in Phase-2.
Hebbagodi depot.
Augmentation in
existing infrastructure
at Peenya depot.
Kothanur depot.
Alignment No. of Trees to
be cut
No. of Trees
proposed to be
planted
Extensions
Hesaraghatta Cross to BIEC
432
4320 Baiyappanahalli to ITPL – Whitefield
Mysore Road Terminal to Kengeri
Puttenahalli cross to Anjanapura Township
(up to NICE Road)
New Lines
R.V. Road to Bommasandra 126 1260
IIMB to Nagawara 206 2060
Metro Rail Project does not require Environmental Clearance. However,
Environment Impact Assessment is necessary to assess the impacts. Accordingly,
DMRC, as part of the DPR, has made Environmental Impact Assessment.
ENVIRONMENTAL ISSUE
Alignment Estimated Cost of
land acquisition(
in Crore)
No. of Properties
proposed for
demolition
Hesaraghatta Cross to BIEC 152.60 32
Baiyappanahalli to ITPL – Whitefield 363.23 151
Mysore Road Terminal to Kengeri 110.52 57
Puttenahalli cross to Anjanapura Township
(up to NICE Road)
126.49 71
R.V. Road to Bommasandra 687.10 211
Gottigere – IIMB – Nagawara 537.24 *
Total 1977.18 522
In Gottigere – IIMB – Nagawara Line the area of demolition as shown in DPR is 67784.00 sq. mtrs.
LAND ACQUISITION AND DEMOLITION OF PROPERTIES
Sl.
No.
Name of Metro Corridor Equity Sub. Debt Senior Term
Debt (45%)
Total
GOI
(15%)
GOK (15%) GOI (10%) GOK (15%)
1 E-W – Baiyappanahalli to Whitefield 726.75 726.75 484.50 726.75 2180.25 4845.00
2 E-W – Mysore Road to Kengeri 280.19 280.19 186.80 280.19 840.58 1867.95
3 N-S – Puttenahalli to Anjanapura 264.88 264.88 176.59 264.88 794.65 1765.88
4 N-S – Hesaraghatta Cross to BIEC 175.23 175.23 116.83 175.23 525.70 1168.22
Sub-total for 4 extensions 1447.05 1447.05 964.72 1447.05 4341.18 9647.05
5 R.V Road to Bommasandra 861.61 861.61 574.41 861.61 2584.85 5744.09
6 Gottigere - IIMB-Nagawara 1652.10 1652.10 1101.40 1652.10 4956.30 11014.00
Sub-total for 2 new lines 2513.71 2513.71 1675.81 2513.71 7541.15 16758.09
Grand Total 3960.76 3960.76 2640.53 3960.76 11882.33 26405.14
FINANCING PLAN It is proposed to fund with a mix of equity, interest free subordinate debt and institutional
credit. The proposed funding is based on that in Phase–I works as detailed below:
(Rupees in Crore)
Financial Indices
Line EIRR FIRR
Four Lines 13.40% 6.30%
R.V. Road to Bommasandra 16.70% 4.40%
Gottigere - IIMB - Nagawara 13.20% 4.00%
BANGALORE METRO PHASE-2 Innovative sources of Finance devised by BMRCL/ GoK.
The GoK has approved additional resource mobilisation measures by way of
the following.
1. Development Cess: Levy of development cess on new layouts and
property developments in Bengaluru City. This is estimated to yield revenue
of Rs. 1250 crore in five years.
2. Cess on additional floor area ratio (FAR): Allowing Additional Floor area
Ratio (FAR) in the influence areas on either side of the metro alignments in
the Phase-1 and Phase-2. This is estimated to yield Rs. 430 crore in five
years.
3. TDR in lieu of compensation for Land: This will reduce the acquisition
cost of land.
Issue of tax free Bonds.
BANGALORE METRO PHASE-2 Differential pricing in fare.
The two lines viz. Baiyappanahalli to ITPL-Whitefield and R.V. Road
Bommasandra via Electronic City will help the IT industry in a big way. A
slightly higher fare than normal fare could be fixed in respect of certain
specified stations for the trips originating or ending in such stations. Similarly,
a higher fare in the peak hours on these two lines as well as on other lines
will be explored to improve the fare box collections and thereby enhance
financial sustainability of the project.
As regards Hessaraghatta cross to BIEC section, the intension is to provide
connectivity to BIEC as the huge facility at present is underutilized because
of lack of quick connectivity. However, in order to make this alignment more
viable, it is proposed to charge ‘differential fare’ for BIEC station.
BANGALORE METRO PHASE-2
Public Private Partnership (PPP).
• It is proposed to explore possibility of Public Private Partnership in
respect of two new lines i.e. Gottigere to Nagavara and RV Road to
Bommasandra.
• The civil infrastructure is proposed to be established by BMRCL
including meeting the cost of land and property and utility shifting.
The PPP Partner is expected to meet the System Costs such S&T,
Rolling Stock, track and traction, and O&M cost.
• The model envisages to bring in private sector efficiencies, while
ensuring that the ownership of the assets remains with the
Government
• GoI will be approached for VGF.
• If the PPPs come through the project cost is expected to come
down by Rs.6065 Crore.
BANGALORE METRO PHASE-2 • Status Position- PRELIMINARY WORKS OF PHASE-2.
1. The Interim Consultancy for priority-1 lines
• Total length of 40.785 Km has been entrusted to M/s. RITES Limited in July 2011
for Reach-1 Extension, Reach-2 Extension and Reach-5 line (RV Road-
Bommasandra).
• The General Arrangement Drawings for all the three lines have been finalised after
final location survey.
• The land plans have been prepared for all the three lines. The preliminary
notification for acquisition for all the three lines will be completed in stretches in
a period of 1-2 months.
BANGALORE METRO PHASE-2
2. The Interim Consultancy for priority-2 lines.
• Total length of 31.310 Km has been entrusted to M/s. RITES Limited in July 2012
for Reach-3 Extension, Reach-4 Extension and Reach-6 line (Gottigere-Nagawara).
• The survey work has started and will be completed in five months period.
3. The Geotechnical Investigation work for first three lines
• The work has been awarded to M/s. SECON Private Limited for R1 extension, M/s.
Consulting Engineers Group for R2 extension and M/s. L&T Limited for R5 (RV
Road-Bommasandra).
• The agencies have mobilised their Rigs and work is in progress in all the three lines.
• Presently progress of 35% is achieved and balance will be completed by Dec-12/Jan-
13. However, tender drawings and tender documents can be prepared with 50%
bore logs available.
Status Position.
BANGALORE METRO PHASE-2
4. Geotechnical Investigation for balance three lines.
The Tenders have been invited and opened on 14.09.2012. The evaluation of
Technical Package is in progress. The work will be awarded by October 2012. The
completion period is 4-6 months.
5. The DDC (Detailed Design Consultancy) for viaduct and stations of five
elevated lines
The Tenders have been invited and Technical bids have been opened already. The
evaluation of Technical Package is in progress. The work will be awarded by October
2012.
The five elevated lines are R1 extension, R2 extension, R4 extension, R5 line (R.V.
Road-Bommasandra) and R6 elevated line (Gottigere-Swagath Cross Road).
Status Position.
BANGALORE METRO PHASE-2 Status Position.
Sl Section GAD
position
Reqd
Borehole
data
DDC
tenders
LOA for
DDC
Tender
document
ready by
1 R2 Extn (Mysore Rd to Kengeri Ready Sept 12 Opened Oct 12 Jan 13
2 R1 Extn (Baiyappanahalli to
Whitefield) Ready Oct 12 Opened Oct 12 Feb 13
3 R5 (R.V.Road to Bommasandra) Ready Oct 12 Opened Oct 12 Feb 13
4 R4 Extn (Puttenahalli cross to
Anjanapura Township) By Nov12 Jan 13 Opened Dec 12 Mar 13
5 R6 Elevated (Gottigere to
Swagath cross Road) By Jan13 Jan 13 Opened Dec 12 Mar 13
6 R3 Extn (Hessaraghatta Cross
to BIEC) By Dec12 Jan 13 - Jan 13 Apr 13
BANGALORE METRO PHASE-2
General Consultancy services:
The GC staff requirement for Civil works, E&M works, System Group etc have been
assessed for all four extensions consisting of total length of 32.025 Km.
The present GC consortium will be continued for the Four extensions.
Negotiations will be conducted and supplementary agreement will be executed in
November 2012.
For the Two independent lines, separate GC/continuing same GC is under
discussion.
Bangalore Metro Rail Project