METODE KONSTRUKSI (2015) PROGRAM S1 NON REGULER DIKERJAKAN OLEH: DOSEN PENGAMPU : IR. ARY SETIAWAN, S.T., M.Sc., Ph.D. JEREMY IWADA S G. I1114047 KURNIAWAN DILIARISTIANTO I1114048 LANARIA PANGESTU I1114049 ZUHDI FADHLI I1114052
34

Metode konstruksi (2015)

Aug 12, 2015

Download

Engineering

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Metode konstruksi (2015)

METODE

KONSTRUKSI (2015) PROGRAM S1 NON

REGULER

DIKERJAKAN OLEH:

M.

DOSEN PENGAMPU : IR. ARY SETIAWAN, S.T., M.Sc., Ph.D.

JEREMY IWADA S G. I1114047

KURNIAWAN DILIARISTIANTO I1114048

LANARIA PANGESTU I1114049

ZUHDI FADHLI I1114052

Page 2: Metode konstruksi (2015)

PENGERJAAN

PEKERJAAN

RIPPING/CLEARING

DATA LAHAN

PEKERJAAN

PEMUATAN

PEKERJAAN

PENGANGKUTAN

PEKERJAAN

PEMADATAN

1

5

4

3

2

REKAPITULASI

6

Page 3: Metode konstruksi (2015)

DATA LAHAN YANG DIKERJAKAN

Nama Pekerjaan : Lahan Parkir Jurusan

Tek.Sipil, Univ. Sebelelas

Maret, Surakarta.

Lokasi : Surakarta, Jawa

Tengah.

Panjang : 35 m

Lebar : 15 m

Tebal tanah : 1,7 m

Elevasi lahan : + 93 m

Page 4: Metode konstruksi (2015)

Sketsa lahan

DENAH

POT. A-A

Note : Dalam satuan meter

Page 5: Metode konstruksi (2015)

KONDISI AKSES - JALAN

Page 6: Metode konstruksi (2015)

KONDISI

LAHAN

HOME

Page 7: Metode konstruksi (2015)

1.Pekerjaan ripping/clearing

METODE

ALAT YANG DIGUNAKAN

ESTIMASI/ PERHITUNGAN

PRODUKSI ALAT, DURASI DAN

BIAYA

PENJELASAN

Page 8: Metode konstruksi (2015)

PENJELASAN RIPPING Yaitu pemotongan bagian atas permukaan

tanah agar bersih dari rumput maupun tanah yang

kurang baik.

METODE

Page 9: Metode konstruksi (2015)

Alat yang dipergunakan

Wheel Bulldozer

Caterpillar D8U

Akses dan Medan :

Lingkungan universitas

Lebar jalan ± 3m

jarak gusur rerata

60 m

Page 10: Metode konstruksi (2015)

ESTIMASI/PERHITUNGAN

A. PRODUKSI ALAT (CARA GRAFIK) No. Uraian Crawler Wheel

1. Operator: a. baik sekali

b. sedang c. buruk

1.0

0.75 0.60

1.0

0.75 0.60

2. Bahan: a. stock pile

b. sulit dipotong

dengan tilt silinder tanpa tilt silinder

dengan kabel kendali

c. keras dipotong/digusur (kering/non-

kohesif) d. batu hasil ledakan

1.20

0.80

0.70

0.60

0.80 0.60-0.80

1.20

0.75 -

-

0.80 -

3. Dengan metode slot dozing 1.20 1.20 4. Dengan metode berdampingan (side by side

dozing)

1.15-1.25 1.15-1.25

5. Penglihatan pada waktu operasi berdebu, kabut, gelap dan hujan

0.80

0.70

6. Efiseiensi kerja: a. 50 menit/jam b. 40 menit/jam

0.84 0.67

0.84 0.67

7. Direct drive trans. (fixed time 0.01 menit) 0.80 -

8. Bulldozer: a. A blade

b. C blade

c. D5 (sempit)

d. U blade e. Bowl blade

0.50-0.75

0.50-0.75

0.90

1.20 1.30

-

0.50-0.75

-

1.20 1.30

FAKTOR KOREKSI

Page 11: Metode konstruksi (2015)

FAKTOR % KEMIRINGAN : -

2%

FAKTOR KOREKSI

KEMIRINGAN LAHAN : 1.2

Page 12: Metode konstruksi (2015)

Dari grafik

produksi alat

didapat produksi

ideal = 410

m3/jam (LM)

Page 13: Metode konstruksi (2015)

koreksi berat tanah :

Jadi produksi nyata = 410 * 0.80 * 1.2 * 1.20 * 0.75 *

0.84 * 0.856

= 254,713 m3/jam (LM)

Vol. tanah ripping :

Panjang : 35 m

Lebar : 15 m

Tebal tanah max ripping: 0,3 m

Vol. tanah : 157,5 m3 (BM) = 157,5*1,25=

196,875 m3 (LM)

Page 14: Metode konstruksi (2015)

B. DURASI DURASI : VOL.TERSEDIA/ PRODUKSI ALAT

: 196,875 m3 (LM)/ 254,713 m3/jam (LM)

: ± 47 MENIT ~ 1 JAM

C. BIAYA (SEWA)

BIAYA SEWA : DURASI * BIAYA SEWA PER JAM

: 1 * RP 200.000 (ALL IN)

: RP 200.000,-

HOME

Page 15: Metode konstruksi (2015)

PEKERJAAN

PEMUATAN ALAT YANG

DIGUNAKAN

ESTIMASI/ PERHITUNGAN

PRODUKSI ALAT, DURASI

DAN BIAYA

PENJELASAN

METODE

Page 16: Metode konstruksi (2015)

PENJELASAN Yaitu usaha memuat hasil CLEARING/STRIPPING ke

dalam alat pengangkut.

METODE

Page 17: Metode konstruksi (2015)

Alat yang dipergunakan

WHEEL LOADER

(BACKHOE) KOMATSU

PC 220-1

Page 18: Metode konstruksi (2015)

ESTIMASI/PERHITUNGAN

A. PRODUKSI ALAT (CARA TEORITIS)

BC yang digunakan = 0,9

Page 19: Metode konstruksi (2015)

Bucket factor

tanah

lempung

digunakan 0,8

Page 20: Metode konstruksi (2015)
Page 21: Metode konstruksi (2015)

B. DURASI DURASI : VOL.TERSEDIA/ PRODUKSI ALAT

: 196,875 m3 (LM)/ 75,35 m3/jam (LM)

: ± 2 JAM 37 MENIT = 2,61 JAM

C. BIAYA (SEWA) (SUMBER : INTERNET) BIAYA SEWA : DURASI * BIAYA SEWA PER JAM

: 2,61 * RP 200.000

: RP 522.000,-

HOME

Page 22: Metode konstruksi (2015)

PEKERJAAN PENGANGKUTAN

ALAT YANG

DIGUNAKAN

ESTIMASI/ PERHITUNGAN

PRODUKSI ALAT, DURASI

DAN BIAYA

PENJELASAN

Page 23: Metode konstruksi (2015)

Yaitu usaha memindahkan hasil CLEARING/STRIPPING

ke lokasi pembuangan/pemanfaatan (DUMPING).

PENJELASAN

Alat yang dipergunakan

Dump Truck Kapasitas bak

4 m3

(untuk faktor keamanan

diisi 3,5 m3)

Page 24: Metode konstruksi (2015)

ESTIMASI/PERHITUNGAN

A. PRODUKSI ALAT (CARA TEORITIS)

Kapasitas buket loader = 1m3

Waktu pemuatan = 2,79 menit ( 3,5 m3 hingga

bak terisi)

Fixed time = 3 menit Cycle time per rit = 0,8 menit (2,79/3,5)

Page 25: Metode konstruksi (2015)

Mencari nilai Vessel

C : Kapasitas Vessel

Kapasitas buket loader (KB) = 1m3

BF = 0,85

C = 3,5 m3

N = 3,5/(1 * 0,85) = 4,12 ~ 4 kali

(penggunaan 1 dumptruck)

• Mencari nilai Dumptruck Cycle Time

Page 26: Metode konstruksi (2015)

CT = (4*0,8)+1,44+0,82+1,2+0,3

= 6,96 ~ 7 menit

• Mencari nilai Faktor Koreksi Total

Page 27: Metode konstruksi (2015)

PRODUKSI : (3,5*60*0,5)/7 = 15 m3/jam (LM) MENGGUNAKAN 1

BUAH DUMPTRUCK

B. DURASI DURASI : VOL.TERSEDIA/ PRODUKSI ALAT

: 196,875 m3 (LM)/ 15 m3/jam (LM)

: ± 13JAM 7,5 MENIT = 13,125 JAM

C. BIAYA (SEWA) (SUMBER : INTERNET) BIAYA SEWA : DURASI * BIAYA SEWA PER JAM

: 13,125 * RP 200.000

: RP 2.625.000,-

HOME

Page 28: Metode konstruksi (2015)

PEKERJAAN PEMADATAN

ALAT YANG

DIGUNAKAN

ESTIMASI/ PERHITUNGAN

PRODUKSI ALAT, DURASI

DAN BIAYA

PENJELASAN

METODE

Page 29: Metode konstruksi (2015)

Yaitu usaha untuk memadatkan tanah agar

didapatkan daya dukung tanah yang disyaratkan.

PENJELASAN

METODE

Page 30: Metode konstruksi (2015)

ALAT YANG DIGUNAKAN

Penggilas roda tiga

(three sheet roller)

berat 8 ton

lebar efektif compactor

60 cm,

kecepatan operasi 2

km/jam

Page 31: Metode konstruksi (2015)

ESTIMASI/PERHITUNGAN

A. PRODUKSI ALAT (CARA TEORITIS)

LUAS LAHAN : 475 m2

Jumlah pass = 10 kali

/lapis/jam2m 9010

0.75*2000*0.60F

Vol. = F* ketebalan per lapis (0,1 m)

= 90 * 0,1 = 9 m3 / jam

Page 32: Metode konstruksi (2015)

B. DURASI

C. BIAYA (SEWA) (SUMBER : INTERNET)

HOME

DURASI : Luas TERSEDIA/ 1PRODUKSI ALAT

: 196,875 m3/ jam : 9 m3/jam (CM)

: ± 22 JAM

: ± 3 hari (8 jam kerja/hari)

BIAYA SEWA : DURASI * BIAYA SEWA PER JAM

: 22 * RP 200.000

: RP 4.400.000,-

Page 33: Metode konstruksi (2015)

REKAPITULASI

NO PEKERJAAN ALAT DURASI BIAYA

PER JAM BIAYA

1 RIPPING/

CLEARING

BULLDOZER Caterpillar

D8U ± 1 JAM RP 200.000,- RP 200.000,-

2 PEMUATAN (LOADING)

WHEEL LOADER

(BACKHOE) KOMATSU PC

220-1

± 2 JAM 37 MENIT

RP 200.000 RP 522.000,-

3 PENGANGKUTAN

(DUMPING)

Dump Truck

Kapasitas bak 4 m3

± 13JAM 7,5 MENIT

RP 200.000,- RP 2.625.000,-

4 PEMADATAN

(COMPACTING)

Penggilas roda tiga

(three sheet roller)

± 22 JAM RP 200.000,- RP 4.400.000,-

END

Page 34: Metode konstruksi (2015)

SELESAI