Top Banner
MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma Science & Fusion Center Oct 5, 2005
16

MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

Dec 18, 2015

Download

Documents

Jean Gregory
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

MERIT Hg SystemFinal Design Review

Hg Target System Design Interfaces

V.B. Graves

P.T. Spampinato

T.A. Gabriel

MERIT Collaboration Meeting

MIT Plasma Science & Fusion Center

Oct 5, 2005

Page 2: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Primary Hg System Interfaces

Facility

Optical diagnostics

Magnet

Page 3: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Facility Interfaces

Require 30kW power supply 460V/3PH U.S. 380V/3PH CERN Delivery system will have on-board 110V, 24V power

supplies

Anchor baseplate to floor?

Page 4: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Primary Containment As Fabricated

No reflector, no optics or optics mounting shelf

Interface drawings will be provided to BNL

Page 5: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Optical Viewing Windows 2mm Quartz backed by 4mm Lexan

Can Lexan be used alone?

Face seals

Mechanical fasteners

Assemblies provided on both sides of primary containment as part of delivery system fabrication

Page 6: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Optical Reflector Windows

BNL to provide mirror and adjustment mechanism

Mechanically attaches to viewport cover plate

Interface drawing to be provided by ORNL

Page 7: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Optical Components

BNL to provide splitters, prisms, lenses, bracket, mounting hardware & adjustment mechanisms

Page 8: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Fiber Bundle Bulkhead Fittings

Eight connector holes provided based on BNL-supplied info

BNL provides connectors

Page 9: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Z=0 Section Cut

Page 10: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Magnet Bore Bore'd Out

Magnet designed with G-10 bore tube to insulate inner wall during cooling cycle

G-10 tube did not allow enough room for optics

Removal of bore tube requires a substitute insulator covering the upstream 20cm of the bore

Current approach uses a Watlow kapton heater foil Thickness = 0.2mm (0.007inch)

Page 11: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Solenoid Interface Clearance

Magnet ID = 162mm Secondary OD = 157mm (157.5mm with foil)

Centering secondary containment within bore will require some sort of annular wedges, perhaps mechanical fastening to magnet end plate

Page 12: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Hg System / Magnet Alignment Baseplate has jackscrews to precisely adjust cart axial

position

Flex metal hoses may allow nozzle to move relative to magnet Add means of attaching secondary containment to magnet end

plate

Page 13: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Integrated Systems Testing

Prefer to perform prototypic installation sequence where magnet will be operated Target transporter, common baseplate, tilt & elevate

If physical constraints at MIT prevent prototypic operations, we should conduct installation-only tests at another MIT location

Page 14: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Magnetic Force Analysis

P. Titus performed Ansys analysis of attractive forces between magnet and single iron cylinder

Force nearly 13000lb

Further analysis showed force decreases significantly with separation distance > 1m

Page 15: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Possible Solutions Restrain Hg system and magnet

Increase separation distance Design concept initiated

Use non-magnetic hydraulic cylinders, at higher cost Chose this option after reviewing syringe vendor quotes

Page 16: MERIT Hg System Final Design Review Hg Target System Design Interfaces V.B. Graves P.T. Spampinato T.A. Gabriel MERIT Collaboration Meeting MIT Plasma.

OAK RIDGE NATIONAL LABORATORYU. S. DEPARTMENT OF ENERGY

Final Interface Issues

Final dimensions of secondary containment not known until syringe vendor completes design Design review required to be held within 30 days of

award

Vertical dimensions the most critical and may slightly change some baseplate dimensions