Executive Summary With all of the activity currently going on within the walls of the sixth floor, it’s hard to believe that only a month has gone by since our last update. Finish work is in full swing throughout the project. Drywall crews are completing their very last sections with painters following closely behind applying prime and finish coats. Within the patient rooms, bathroom tile is being laid, case- work is being set, and plumbing fixtures are getting installed. Exciting times are approaching as several areas are revealing their completed form. The nature of the jobsite during this final phase is very busy and fast paced. Tradesmen are literally working on top of one another in order to complete an area and move to the next. The peak in worker activity makes it more impor- tant than ever to continue our full time infection control duties. Looking forward, our completion date is within sight. Finish work will con- tinue, gradually moving from one end of the floor to the other. Meanwhile, many workers will be terminating and putting the final touches on a variety of low voltage systems. As you’ll see in the pictures on the following page, this is going to be a very beautiful unit when it’s all finished. Saint Mary’s Health Care—Psychiatric Medical Unit The Inside Scoop Progress Report Joe Novakoski—(616) 836-1810 Upcoming Milestones Low Voltage Wiring Start Ceiling Grid Complete Wall Tile Begin Installation of Flooring June 2012 Vice President / Senior Project Manager Project Progress and Major Milestones Casework Flooring Demolition Ceilings Drywall Painting Rough-in
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Executive Summary With all of the activity currently going on within the walls of the sixth floor, it’s hard to believe that only a month has gone by since our last update. Finish work is in full swing throughout the project. Drywall crews are completing their very last sections with painters following closely behind applying prime and finish coats. Within the patient rooms, bathroom tile is being laid, case-work is being set, and plumbing fixtures are getting installed. Exciting times are approaching as several areas are revealing their completed form.
The nature of the jobsite during this final phase is very busy and fast paced. Tradesmen are literally working on top of one another in order to complete an area and move to the next. The peak in worker activity makes it more impor-tant than ever to continue our full time infection control duties.
Looking forward, our completion date is within sight. Finish work will con-tinue, gradually moving from one end of the floor to the other. Meanwhile, many workers will be terminating and putting the final touches on a variety of low voltage systems. As you’ll see in the pictures on the following page, this is going to be a very beautiful unit when it’s all finished.
Saint Mary’s Health Care—Psychiatric Medical Unit
The Inside Scoop Progress Report
Joe Novakoski—(616) 836-1810
Upcoming Milestones
Low Voltage Wiring
Start Ceiling Grid
Complete Wall Tile
Begin Installation of Flooring
June 2012
Vice President / Senior Project Manager
Project Progress and Major Milestones
Casework
Flooring
Demolition
Ceilings
Drywall
Painting
Rough-in
Project Photos
Spotlight on Safety
Safety is always a high priority and continues to chal-
lenge us all with opportunities. Currently, there are up
to 35+ workers on site. They are on ladders as well as
using a variety of saws, drills and other power tools.
Our intensive safety training has taught the workers on
our site how to work safely and effectively and we
have avoided serious injuries. In fact, E&V currently
has over 1,800 days without any lost time injuries!
Bathroom cabinet and shower in patient room.
Bathroom sink and faucet in patient room.
Storage in corridor has fresh paint color on it.
A Look Ahead Everyone is working very hard on the finishes of the project. At this point we are
installing tile, casework, and smoothing out the old concrete floors so we can
install new sheet vinyl. Also, the preparation for the new ceilings has started.
Follow us:
Quality Corner
We work diligently to create a
quality project from the very be-
ginning so when we reach the
point of critiquing the fine details
of the finishes, we don’t have to
make major changes. We also
have Progressive AE available to
cross check details, and Adam Ro-
galla, with his tremendous amount
of experience, has helped the pro-
ject through multiple details.
elzinga-volkers.com
facebook.com/ElzingaVolkers
Joe Shashaguay—(616) 836-2439 Field Manager
Spotlight
This month we’d like to spotlight Ritsema’s Flooring Division. The products that
they install make up a large portion of the finished surfaces of the unit. Over the
past month or so, Ritsema has been very busy laying a combination of ceramic
and glass wall tile in all the patient bathrooms. Now they are preparing the old
concrete floors to accept thousands of square feet of sheet vinyl. With flooring
remaining as one the last items to be installed, Ritsema is a critical player in the
success of the construction team as we look toward completion.