MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Mar 29, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

MBC   ‐ 2015  716.1  AND  NFPA  80  

REQUIREMENTS

Swing Type Fire Door Inspections Initial and 

Annual

Page 2: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Course Description

This one hour course reviews how building owners shall ensure the publics safety for fire rated means of egress swing type fire doors, provide initial and annual inspection reports to the AHJ, and how this meets the  MBC and NFPA‐80.

Page 3: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Course Objective

Discuss Building Code Correlations regarding need to inspect swing type fire doors.

Review NFPA‐80 requirements for initial and annual inspections.

Roles of the Authority Having Jurisdiction (AHJ), Building Owner, and Certified Fire Door Inspector.

Deliverables to the Owner and AHJ.

Page 4: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be
Page 5: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Michigan Building Code

Where in the Michigan Building Code‐2015 is NFPA 80 referenced?

Page 6: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Michigan Building Code

Where in the Michigan Building Code‐2015 is NFPA 80 referenced? Chapter 7, Section 716.5 ties swing type fire doors and shutter assemblies to NFPA 80‐2013, which states…….

Page 7: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Michigan Building Code

Where in the Michigan Building Code‐2015 is NFPA 80 referenced?

Chapter 7, Section 716.5 ties swing type fire doors and shutter assemblies to NFPA 80‐2013, which states…….

716.5 Fire doors and shutter assemblies.  Approved fire door and fire shutter assemblies shall be constructed of any material or assembly of component materials that conforms to the test requirements of Section 716.5.1, 716.5.2, or 716.5.3 and the fire protection rating indication in Table 716.5  Fire door frames with transom lights, side lights, or both shall be permitted in accordance with Section 716.5.6.  Fire door assemblies and shutters shall be installed in accordance with the provisions of this section and NFPA 80.

Page 8: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Michigan Building Code

Also, Chapter 35 references NFPA 80‐13 is based from Chapter 716.5 requirement.

Page 9: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

NFPA 80‐13

NFPA states: “Use of NFPA documents for regulatory purposes should be accomplished through adoption by reference.  These include both use, by reference, in laws and regulations, and use in private self‐regulation, standardization, and the promotion of safe practices and methods…”

Page 10: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

NFPA 80‐13

Section 5.2 Inspection and Testing 5.2.1 Upon completion of the installation, door, shutters, and window assemblies, shall be inspected and tested in accordance with 5.2.4.

5.2.2A record of all inspections and testing shall be signed by the inspector and kept for inspection by the AHJ.

5.2.2.1 Records of acceptance tests shall be retained for the life of the assembly.

5.2.2.2 Unless a longer period is required by Section 5.4, records shall be retained for a period of at least 3 years.

5.2.2.3The records shall be on a medium that will survive the retention period.  Paper or electronic media shall be permitted.

Page 11: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

NFPA 80‐13

Section 5.2.2.4  A record of inspections and testing shall be provided that includes, but is not limited to, the following information:1. Date of Inspections2. Name of facility.3. Address of facility.4. Name of person(s) performing inspections and testing.5. Company name and address of inspecting company.6. Signature of inspector of record.

Page 12: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

NFPA 80‐13

Section 5.2.2.4  A record of all inspections and testing shall be provided that includes, but is not limited to, the following information:7. Individual record of each inspection and tested fire door 

assembly.8. Opening identifier and location of each inspected and 

tested fire door assembly.9. Type and description of each inspected and tested fire door 

assembly.10. Verification of visual inspection and functional operation.11. Listing of deficiencies in accordance with 5.2.3 Section 5.3, 

and Section 5.4. 

Page 13: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

NFPA 80‐13

5.2.3 Acceptance Testing 5.2.3.1 Acceptance testing of fire door and fire window assemblies shall be performed by a qualified person with knowledge and understanding of the operating components of the type of assembly being subject to testing.

5.2.3.2 Before testing a visual inspection shall be performed to identify any damaged or missing parts that can create a hazard during testing or effect operation or resetting.

5.2.3.3 Acceptance testing shall include the closing of the door by all means of activation.

5.2.3.4A record of these inspections and testing shall be made in accordance with 5.2.2.

Page 14: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

NFPA 80‐13

Page 15: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

NFPA 80‐13

Section 5.2.4 Periodic Inspections and Testing5.2.4.1 Periodic inspections and testing shall be 

performed not less than annually.5.2.4.2 As a minimum, the provisions of 5.2.3 shall be  

included in the periodic inspection and testing procedure.

5.2.4.3 Inspections shall include an operational test forautomatic‐closing doors and windows to verify that the assembly will close under fire conditions.

5.2.4.4The assembly shall reset after an actual test.5.2.4.5 Resetting of the release mechanism shall be done in

accordance with the manufacturers instructions.5.2.4.6 Hardware shall be examined, and inoperative hardware,

parts, or other defective items shall be replaced without delay.

Page 16: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

NFPA 80‐13

Page 17: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

NFPA 80‐13

Who can perform these inspections? The 2007 edition of NFPA 80 (and all subsequent editions) requires fire door assemblies be inspected each year by someone knowledgeable about the type of assembly being inspected. The 2013 edition added a requirement for the inspections to be performed by a “qualified person,” defined as follows:

Page 18: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

NFPA 80‐13

Who can perform these inspections? The 2007 edition of NFPA 80 (and all subsequent editions) requires fire door assemblies be inspected each year by someone knowledgeable about the type of assembly being inspected. The 2013 edition added a requirement for the inspections to be performed by a “qualified person,” defined as follows:

3.3.96 Qualified Person. A person who, by possession of a recognized degree, certificate, professional standing or skill, and who, by knowledge, training, and experience has demonstrated the ability to deal with the subject matter, the work, or the project.

Page 19: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

MBC and NFPA 80 Roles

This information is not meant to provide any legal advice or set precedent.  None of this material on the role function or jurisdictional authority cited in this course is to be used or referenced as legal counsel or advice.

Page 20: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

MBC and NFPA 80 RolesAuthority Having Jurisdiction

Role of the AHJ‐The AHJ is ultimately responsible for interpreting whether or not an application, situation or installation is code compliant and has the authority to decide under common and legislated law precedents.

The AHJ should review each inspection report submitted by the Certified Fire Door Inspector (CFDI) once submitted to the owner.  

The owner should work with the AHJ to ensure non‐compliant items are remedied to the satisfaction of the AHJ and  re‐inspections are completed and on file.

Page 21: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

MBC and NFPA 80 RolesBuilding Owner

Role of the Owner –The building owner is tasked with ensuring that all of their listed fire door assemblies are compliant under the NFPA 80‐2007 edition (or later) of the Standard for Doors and Other Opening Protectives.  The owner may choose a “Responsible Person in Charge” who oversees the adherence to the required inspections.

The owner has two options: 1 – Hire a Fire Door Inspector 2‐ Solicit the AHJ for approval of an employee to be responsible for the 

Annual Fire Door Inspection.

Page 22: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

MBC and NFPA 80 RolesBuilding Owner

Caution to owner: employee acting as the  fire door inspector. This may cause a conflict of interest with performing the 

inspections, filing reports and performing the necessary repairs. Best practice for the AHJ usually will be to have an outside agency 

perform the inspections and provide the report to eliminate any conflicts of interest.

The  Building Owner or Responsible Person in Charge is responsible for giving access to the facility, providing plans or blue prints, safe working environment, and identifying which doors are to be inspected based on the approved final plans for the building.

Page 23: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

MBC and NFPA 80 RolesBuilding Owner

Responsible for working with the AHJ to determine which, if any, of the non‐compliant doors will need to be repaired.

Provide a work plan acceptable to the AHJ to remedy any no‐compliant matters noted in the report.

Page 24: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

MBC and NFPA 80 RolesFire Door Inspector

Role of the Fire Door Inspector Inspecting listed and labeled fire door assemblies according to the 

guidelines set forth in the NFPA‐80 standards for Doors and Other Opening Protectives.

Provide a professionally written report with concise details of any discrepancies clearly annotated.

Provide the owner with access to this report. Provide the AHJ with access to this report. Professional Fire Door Inspectors are governed by a code of ethics with 

duties to the Public, Continuing Education, and to the Profession.

Page 25: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

MBC and NFPA 80 RolesFire Door Inspector

Role of the Fire Door Inspector Continuing Education‐

Responsible to keep knowledge up to date of the fire door assemblies manufactures of listed hardware.

Be current in knowledge of the existing codes as well as past building codes and fire codes.

Most importantly, the Fire Door Inspector works for the AHJ, even though they are hired by the building owner.

Page 26: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Types of Inspections

There two types of inspections:1. Performance based inspections.2. Periodic Inspections.

Page 27: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Types of Inspections

1. Performance based inspections. Permitted to be inspected, tested, and maintained under a written 

performance‐based program. Will perform its intended function when exposed to fire conditions. Technical justification for inspection, testing and maintenance shall be 

documented in writing. Shall include historical data acceptable to the AHJ. The AHJ is the approval authority when the performance based option is used 

in lieu of the annual inspection cycle. Goals established under a performance‐based program shall provide 

assurance that the fire door assembly will perform it’s intended function when exposed to fire conditions. 

Technical justification for inspection, testing and maintenance intervals shall be documented in writing.

The performance‐based option shall include historical data acceptable to the AHJ.

Page 28: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Types of Inspections

2. Periodic Inspections  Annual Inspections,  written report by a qualified person (CFDI) with 

access to the Owner and the AHJ. All non‐compliant assemblies shall be re‐inspected after remedied 

and the report noted of same.

Page 29: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Care and Maintenance

Page 30: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Care and Maintenance

Operability – shall be operable at all times and shall be in the closed and latched or arranged for automatic closing.

Field modifications – only those modifications permitted by the manufacturer or listing agency will be allowed. This will require field labeling to be applied by certified persons or companies for the specific modification.

Non‐fire rated doors placed in rated openings shall be replaced with the properly rated door.

Fire rated doors removed or no longer used, the opening shall be filled in to maintain the required rating of the wall.

Page 31: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Care and Maintenance

Page 32: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Care and Maintenance

Prevention of door blockage.

Maintenance of closing mechanisms.

Repair of damaged or inoperable assembly items.

Fill all holes with metal fasteners, or with same material as door.

Gasketing shall be included in inspection if required by the certifying agency.

Page 33: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

13 Point Inspection

Page 34: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

13 Point Inspection

1. Labels are clearly visible and legible.2. No open holes or breaks exist in surfaces of either the door 

or the frame.3. Glazing, vision light frames and glazing beads are intact and 

securely fastened and properly rated.4. The door, frame, hinges, hardware and non‐combustible 

threshold are secured, aligned and in working order.5. No parts are missing or broken.6. Door clearances‐ left edge, right edge, top edge, bottom 

edge and center pair.

Page 35: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

13 Point Inspection

7. The self closing device is operational, that is, the active door completely closes when operated from the full open position.

8. If a coordinator is installed, the in‐active leaf closes before the active leaf.

9. Latching hardware operates and secures the door when it is in the closed position.

10. Auxiliary hardware items that interfere or prohibit operation are not installed on the door or frame

11. No field modifications to the door assembly have been performed that void the label. 

12. Gasketing and edge seals, where required, are inspected to verify their presence and integrity. 

13. Signage affixed to a door meets the requirements listed in 4.1.4‐area is less than 5%, attachment is adhesive not mechanical, not on glazing, and does not impair door assembly operation .

Page 36: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

13 Point Inspection

Page 37: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

13 Point Inspection

Page 38: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Sample Inspection Excerpts

Page 39: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Sample Inspection Excerpts

Page 40: MBC 2015 716.1 AND NFPA 80 REQUIREMENTS · NFPA 80‐13 Section 5.2 Inspection and Testing 5.2.1Upon completion of the installation, door, shutters, and window assemblies, shall be

Swing Type Fire Door Inspections

Questions and answers. Closing comments. Thank you for your time.