Top Banner
May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)
43

May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

Dec 15, 2015

Download

Documents

Katy Busby
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

May 11, 2006

Hydropower Refurbishment –Alstom’s Methodology and Case Studies

Presented By

Naresh Patel ( Electrical)

Sreenivas.V ( Mechanical)

Page 2: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 2 -

Introduction

Alstom Power – Hydro Products

• Descended from Neyrpic, ASEA, BBC, Alsthom• Over 100 years experience in hydro industry• Eng’g & Mfg’g in Americas, Europe & Asia• Presence in Asia Includes:

• Turbine, Generator, Hydro Mech, P&S, BoP• Design & Mfg’g in Tianjin, China• Design & Mfg’g in Vadodara, India

Page 3: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 3 -

Repair, Modernize & Uprate• Repair – Equipment failure results in units

out of service / operating at derated output• Most compelling of refurbishment drivers• Issue – Return to full service quickly• Solution – Often a temporary “band-aid”• If ‘quick fix’ not possible, modernize and

uprate options should be considered

The Need for Refurbishment

Page 4: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 4 -

We should have done this last year as a planned outage!

Page 5: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 5 -

Repair, Modernize & Uprate• Modernize – Apply new technology,

materials and calculation techniques• Normally done in conjunction with other

refurbishment work• Example – Uprate field-coil insulation

during a stator rewind• Example - Install self-lubricating bushings

during runner replacement

The Need for Refurbishment

Page 6: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 6 -

Repair, Modernize & Uprate• Uprate – Increase the output capability of the

generating unit• Most economically feasible of drivers• Typically 15 to 40% uprate without civil-works

modification• Minimum scope usually involves runner

replacement and new stator core & winding• BoP modifications have to be considered

The Need for Refurbishment

Page 7: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 7 -

GENERATOR LIFE CYCLE

Page 8: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 8 -

General Philosophy

• Refurbishment presents more challenging design requirements than that of new units

• Interfaces between old & new equipment have to be considered

• Existing unit must be synthesized

• Collection of reliable data for existing units is absolutely necessary for a successful project

Refurbishment Methodology

Page 9: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 9 -

Data Collection• Review of specification and data from spec• Site visit absolutely necessary for:

• Measurements and visual inspection of unit• Assess the installation environment & limitations• Collection of additional data, eg maintenance records,

test & operational data, OEM drawings, etc.• Discussion of refurbishment requirements and Q & A

with customer engineers• Duration of site visit is scope dependent and can last from a

few hours to a few days

Refurbishment Methodology

Page 10: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 10 -

Proposal Design

• Refurbishment of the generator and turbine parts will be presented here separately, but the shaft coupling is an important interface for matching of capability and maximum speed. Generator and turbine design are performed together

• Relatively short time for design

• Synthesis of existing design required with accurate model of components to be kept

• Model of existing design is modified for refurbished parts

• Modeling is only rigorous enough to ensure the solution will work and to guarantee performance

Generator Specific Methodology

Page 11: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 11 -

Basic and Detailed Design

• Continuation of the proposal design

• A second site visit is essential

• Additional generator testing may be required to validate the model of existing unit

• Analysis is much more rigorous and can include electromagnetic & mechanical FEM studies

• Interface issues are resolved during detailed design

Generator Specific Methodology

Page 12: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 12 -

Synthesis of Existing Generator• Required data are rarely all available• Physical model is created from dimensions given in spec

and from site visit• Electromagnetic model, including excitation requirements

and reactances are correlated to test & operational data• Thermal model, including ventilation configuration and

airflow are correlated to measured temperatures & losses• Throughout the synthesis, measured data are used to

deduce unknown dimensions and material properties• Additional tests may be required after award of contract

Generator Specific Methodology

Page 13: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 13 -

New Winding• Small scope with very little design space• Optimize temperature (output) and efficiency• Slot dimensions are fixed so the only variables are:

• Insulation thickness (design for hipot or VET)• Strand dimensions

• Typically a 15% uprate is possible if replacing asphalt bars or coils

• Upgrade field insulation during outage

Modeling of the Refurbishment

Page 14: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 14 -

New Core & Winding

• This scope allows a change in winding configuration

• Important to identify core-replacement need at time of tendering through inspection or El Cid test or by the age of the core

Modeling of the Refurbishment

Page 15: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 15 -

Allatoona Stator Core ~ 45 Years Old

Page 16: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 16 -

New Core & Winding

• This scope allows a change in winding configuration

• Important to identify core-replacement need at time of tendering through inspection or El Cid test

• Possible to achieve large increase in efficiency

Modeling of the Refurbishment

Page 17: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 17 -

STATOR-STEEL QUALITY

Page 18: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 18 -

New Core & Winding

• This scope allows a change in winding configuration

• Important to identify core-replacement need at time of tendering through inspection or El Cid test

• Possible to achieve large increase in efficiency

• Possible to eliminate noise problems

• Keying and clamping system should be replaced

• Effective soleplate modifications not usually possible unless frame also replaced, i.e. new stator

Modeling of the Refurbishment

Page 19: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 19 -

New Poles and Field Coils

• In conjunction with a new stator & ventilation modifications, can allow up to a 40% uprate

• Torque transmission of other components plus BoP has to be checked explicitly for >15% uprate

Modeling of the Refurbishment

Page 20: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 20 -

Refurbishment with Larger Scope

• Begins to look like design for a new machine with fewer interfaces, fewer dimensional and performance limits

• In these cases, the limits are given by the civil works and balance-of-plant components

• Optimization of performance and output has much higher opportunity

Modeling of the Refurbishment

Page 21: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 21 -

Rocky Reach, Units 1-7

• Customer – Chelan County PUD, Washington State

• Existing unit - 120 MVA, 15 kV, 90 rpm, 0.95 pf

• Airgap instability

• Stator-core buckling

• Increase of efficiency

• Some units noisy, > 95 dB

• Life extension / increased availability

• Scope – new stators & rotors - everything except shaft, brackets & bearings

Generator Case Studies

Page 22: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 22 -

Design Requirements

• High efficiency – main design driver

• US$55k / kW evaluation, US$70k / kW penalty

• Airgap shape tolerances one half of IEC/CEA standard

• Low audible noise, <80 dB 1 m from housing

• High evaluation for short outage

Rocky Reach, Units 1-7

Page 23: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 23 -

Design Solutions – High Efficiency

• 30% more active material than benchmark,

• Increase frame OD to accommodate larger core & frame – radial clearance in housing reduced to limit

• Losses & temperatures very low, so ventilation system can be optimized for efficiency not cooling

• Airgap reduced to allowable SCR limit of 0.8

• Relative to existing machine, the efficiency was increased by 0.5% to almost 99%

Rocky Reach, Units 1-7

Page 24: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 24 -

Design Solutions – Airgap Stability & Shape

• Rim shrunk for full, off-cam runaway speed

• Oblique elements used on spider and frame

• Double dovetail design used for precise setting of stator keybars

• Rotor poles individually shimmed to high circularity tolerance

Rocky Reach, Units 1-7

Page 25: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 25 -

Design Solutions – Noise & Outage Time

• Frame & stator core stiffened with radial depth and higher core clamping pressure

• Outage reduced by constructing both rotor and stator in erection bay

• Last (fourth) unit had only 45 days between commercial service of existing and refurbished units

• All guaranteed performance requirements were met

Rocky Reach, Units 1-7

Page 26: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 26 -

Crystal Power Plant, Unit 1

• Customer – US Bureau of Reclamation, Colorado

• Existing unit - 28 MVA, 11.0 kV, 257 rpm, 1.0 pf

• Realize uprate potential

• Increase reactive capability for black-start, line charging

• Generator and turbine refurbishment for reduced maintenance costs

• New rating – 35 MVA, 0.9 pf

Generator Case Studies

Page 27: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 27 -

Design Requirement

• Contract requirement for 80 K field-temperature rise

• Existing unit had 75 K limit, which it could not meet

• 25% increase in MVA

• Power factor change from unity to 0.9 over excited

• 12.5% increase in MW

Crystal Power Plant, Unit 1

Page 28: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 28 -

Interface Requirements / Design Space Restrictions

• Existing soleplates

• Housing diameter

• Rotor outer diameter and axial length

• Upper bracket and deck plates

Crystal Power Plant, Unit 1

Page 29: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 29 -

Design Solutions – Field Temperature-Rise Limit

• Do all possible to reduce excitation requirements

• Re-insulate field with Class F material

• Increase series turns by 20% - tooth x-section reduction more than compensated

• Increase radial depth of stator core

• Reduce airgap length

• Performance testing last year measured a field- temperature rise of 78 K

Crystal Power Plant, Unit 1

Page 30: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 30 -

Turbine

Page 31: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 31 -

Turbine methodology

Tender stage– Simplified analysis of main components (Spiral case,

stay vanes, distributor, runner and draft tube);– Geometrical comparison between existing design and

manufacturing references;– Hydraulic transient calculation;– Cavitation studies;– Search solutions for specifics problems (frequent

mechanical failures, silt abrasion, operational instability and others)

– Define the future turbine performance (guarantees)

Short term analysis (Basic studies with simple tools)

Page 32: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 32 -

Turbine methodology

Design stage– Measurement of existing performance– Deeply inspection of all components of machine– Fluid Dynamic analysis of the static components

(Spiral Case, Stay Vane, Distributor and Draft tube)– Design of some new profiles to improve the flow

behavior (stay vane, wicket gates and draft tube)– Comparison of existing and new design (CFD)– Development of new runner (genetic algorithm)– Model test to validate the results

Deeply analysis and experience of specialist to reach targets

Page 33: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 33 -

Turbine methodology

CFD remain the main tool for analysis

Stay vane and Wicket Gate Optimization

Page 34: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 34 -

Draft tube study

Flow velocity in a sectional

elevation view of the

existing draft tube elbow.

Turbine methodology

Stream Line analysis

Existing Modified

When technically available modification in Draft tube provide good results

Page 35: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 35 -

“Classical” runner

Blade profile is developed using an evolutionary algoritm and the experience of a hydraulic engineer

Turbine methodology

Runner development

“Final” runner

Good Accuracy between CFD calculation and model test

Page 36: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 36 -

St-Lawrence Rehab Project

St-Lawrence Power Project– 32 propeller units (16 NYPA and 16 OPG)

Ambitious targets

Two turbine designs : BLH : 8 runners Ø5.8m (229 in.) 77.5 85 kHp

(63.4MW)

AC : 8 runners Ø6.1m (240 in.) 79 kHp

Targets:- Increase overall efficiency- Translation of the peak efficiency to higher load- Reduction of erosion by cavitation- Increase of the stability of the turbine

Page 37: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 37 -

St-Lawrence Rehab Project

Main modification New Runner

Runner developed to reach targets and solve the old design problems

• Development using the Alstom methodology

• Twisted blade shape

Page 38: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 38 -

Sigma break curve at full load up to the maximal flow allowed by contract near the rated net head for the refurbishment of

ST. LAWRENCEST. LAWRENCE Power Plant.

St-Lawrence Rehab Project

Page 39: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 39 -

New & Existing runnerNew & Existing runner for St. LAWRENCESt. LAWRENCE power plant at the rated net head, full load and plant sigma value

(model runner manufactured by ASTRÖ).

New runner Old runner

Acceptance model test : cavitation

St-Lawrence Rehab Project

Page 40: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 40 -Accurate manufacturing the reach the results

St-Lawrence Rehab Project

Page 41: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 41 -After commissioning confirmation of targets

St-Lawrence Rehab Project

New rated output : 63.4 MW

Cavitation behavior improved

Better stability

Best efficiency in the higher load

Page 42: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 42 -

Conclusion

• Refurbishment is required to extend life of aging equipments and increase the value of equipment to the owner in terms of performance (higher output and efficiency, greater availability)

• Presented Alstom case studies demonstrate the methodology success

• Integration between Generator and Turbine is essential for good results in refurbishment projects

• Alstom methodology has been efficient for projects in all the corners of the world

Page 43: May 11, 2006 Hydropower Refurbishment – Alstom’s Methodology and Case Studies Presented By Naresh Patel ( Electrical) Sreenivas.V ( Mechanical)

- 43 -