STORAGE: MAXITILE products must be stored flat and off ground prior to installation. Protect products from direct weather exposure. To prevent damage, keep roofing products in the original packaging until it is ready to install. Use the plastic bonnet provided to keep the product dry and to prevent moisture from setting on the surface. If MAXITILE products are stored outside, they should be protected with an additional waterproof covering. MaxiLITE P7 TM , RAKE TILE, HIP AND RIDGE TILE: Field tiles, Rake tiles, Hip and Ridge tiles must be installed with a minimum 4 inches head lap. Twenty one pieces of field tile cover one square (100 sq. ft.), 5 squares per pallet. 216 Rake, Hip or Ridge tiles per pallet, covers 360 lineal feet. One barrel sidelap 4” Headlap 24” 20” 34.8” 39.2” Shaded area indicates exposed part of tile P7 FIELD TILE 7.35” 24” 7.87” Hip and ridge tile type “S” Rake tile Trim tile for rake, hip and ridge 4.4” LAP ROOFING INSTALLATION GUIDE MaxiLITE P7 TM Read all instructions prior to installing any roofing product. Failure to install and finish this product in accordance with all local building codes, regulations and MAXITILE written application may lead to personal injury, affect system performance, violate local building codes, and void the product warranty. We suggest that you read these instructions at least twice.
10

Maxilite P7 Installation Instructions

Mar 10, 2016

Download

Documents

Maxitile

View or download our lap roofing installation guide.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Maxilite P7 Installation Instructions

STORAGE:

MAXITILE products must be stored flat and off ground prior to installation. Protect products from direct weather exposure. To prevent damage, keep roofing products in the original packaging until it is ready to install. Use the plastic bonnet provided to keep the product dry and to prevent moisture from setting on the surface. If MAXITILE products are stored outside, they should be protected with an additional waterproof covering.

MaxiLITE P7TM, RAKE TILE, HIP AND RIDGE TILE:

Field tiles, Rake tiles, Hip and Ridge tiles must be installed with a minimum 4 inches head lap. Twenty one pieces of field tile cover one square (100 sq. ft.), 5 squares per pallet. 216 Rake, Hip or Ridge tiles per pallet, covers 360 lineal feet.

One barrel sidelap 4” Headlap

24”

20”

34.8”39.2”

Shaded area indicates exposed part of tile

P7 FIELD TILE

7.35”

24”

7.87”

Hip and ridge tile type “S” Rake tileTrim tile for rake, hip and ridge

4.4”

LAP ROOFING INSTALLATION GUIDE

MaxiLITE P7TM

Read all instructions prior to installing any roofing product. Failure to install and finish this product in accordance with all local building codes, regulations and MAXITILE written application may lead to personal injury, affect system performance, violate local building codes, and void the product warranty. We suggest that you read these instructions at least twice.

Page 2: Maxilite P7 Installation Instructions

BIRD STOP, HIP AND RIDGE SEAL:

The MaxiLITE P7TM bird stop is 37 inches long and made of metal. Install only one bird stop at a time. If there is an alignment problem, the next piece can be slid or right to get the proper fit with the tile. The bird stop can also be cut in shorter lengths to further ease alignment. Hip and Ridge seals are plastic and come in black only.

Metal bird stop

Lap

Gap

Refer to the Material Safety Data Sheet (MSDS) for important safety practices prior the using any roofing product.

 MAXITILE recommends that all cutting of products be performed outdoors. Use mechanical ventilation when possible.

 For irregular cuts and holes, use a jig saw or a hole saw with a masonry blade. Special round openings can be made by drilling several holes around the circumference of the desired opening and tapping out center. Always cut over the top of a barrel of tile.

 For score-and snap cutting, use carbide tipped scoring tool or a sharp knife:

- Using a straight edge as a guide, carefully draw the scoring tool several times towards yourself, applying even pressure.

- Bend upwards and break.

 A HEPA vacuum should be used when cleaning up dry debris and dust from cutting area. Do not use compressed air, broom or brush. If you consider sweeping, wet down the floor and debris with a fine mist to suppress dust during sweeping. All scrap, cutoffs and debris should be disposed of in a covered container protected from the elements according to local codes. No special handling is required.

WARNING: AVOID BREATHING SILICA DUST.MAXITILE roofing products may contain trace amount (< 0.5%) of crystalline silica, which is known to the State of California to cause cancer and is considered by IARC and NIOSH to be a cause from some occupational sources. Breathing excessive amounts of respirable silica dust can also cause a disabling and potentially fatal lung disease called silicosis, and has been linked with other diseases. Some studies suggest smoking may increase these risks. During installation or handling: (1) work in outdoor areas with ample ventilation; (2) use fiber cement shears for cutting or, where not feasible, use a dust-reducing circular saw attached to a HEPA vacuum; (3) warn others in the immediate area; (4) wear a properly-fitted, NIOSH-approved dust mask or respirator (e.g. N-95) in accordance with applicable government regulations and manufacturer instructions to further limit respirable silica exposures. During clean-up, use HEPA vacuums or wet methods, never dry sweep. For further information, refer to our installation guides and Material Safety Data Sheet available at www.maxitile.com or by calling (800) 451-2003. FAILURE TO ADHERE TO OUR WARNINGS, MSDS, AND INSTALLATION GUIDES MAY CAUSE SERIOUS PERSONAL INJURY OR DEATH..

CUTTING:

2 MaxiTILE P7TM | www.maxitile.com

Page 3: Maxilite P7 Installation Instructions

PITCH:

3:12 minimum, 21:12 maximum. For pitches below 3:12, MaxiLITE P7TM must be installed over an approved water proof covering (including battens and counter battens) complying with the applicable building code.

ROOF DECK:

MaxiLITE P7TM must be installed over code complying solid wood sheathing. Minimum ½ inch rated plywood decking is recommended for use with standard roof felt underlayment. See ICC Evaluation Report for fire classification.

UNDERLAYMENT:

Class “A” fire rating (New construction): One layer of non-perforated Type II (commonly called No. 30) felt in according with ASTM D 226 and one layer of 72-pound mineral-surfaced non-perforated cap sheet complying with ASTM D 3909.

Class “B” fire rating (New construction): A minimum one layer of non-perforated Type II (commonly called No. 30) felt complying with ASTM D 226 shall be installed.- See ICC Evaluation Report for fire classification.

DECK PREPARATION:

 Felt must be installed in a manner to allow water to run off only at the eave. Underlayment must be installed in accordance with the applicable building code.

 Install the following nailers: - At gables: 2 inches X 2 inches and must be nailed approximately 1 inch from edge. - At hips: 2 inches X 6 inches on edge, holding back 6 inches from eave. - At ridge: 2 inches X 4 inches on edge plus 1 inch X 2 inches.

 Wrap gable, hip and ridge nailers with non-perforated Type II (commonly called No. 30) felt in accordance with ASTM D 226.

 Install base flashing around pipes, vents, chimneys, etc. Skylights should have a 2 inches X 6 inches curb to flash against using same type of flashing as chimneys.

 Check to make sure that the roof is square. Apply horizontal chalk lines. The first chalk line should be 22 inches up from the eave, 23 inches if there are gutters. Maximum spacing for the remaining lines is 20 inches.

www.maxitile.com | MaxiTILE P7TM 3

Page 4: Maxilite P7 Installation Instructions

FASTENERS:

Nails and screws must be corrosion-resistant, preferably hot-dipped galvanized for best results, in accordance with local building codes. MAXITILE is not responsible for corrosion resistance of fasteners.

MAXITILE products can be hand nailed using a smooth faced hammer, never use a waffle hammer, and fastened with pneumatic tools. When hand nailing, first perforate the opening to be used for fastening in order to avoid accidental breakage of the roofing product.

Always drive fasteners perpendicular to roofing and solid deck. Do not over-drive under drive fastener heads and never drive fastener in at an angle. Fastener head must be flush on the surface of the product (no air space). If fastener is countersunk, patch fastener hole and add a fastener. Repair nail-sizes holes by filling with adhesive.  Exposed Fastener: 4-1/2 inches long (114.3 mm), 0.175 inch shank diameter (4.44 mm), corrosion-resistant lag

screw with 0.375 inch diameter heads (9.52 mm) with 1 ½ inches X 1 ½ inches galvanized metal washer with neoprene brushing.

 Hidden Fastener: Ring-shank nails, a minimum of 1-3/4 inches (44.45 mm) long and having 0.130 inch diameter (3.30 mm) shank, with a 1 inch (25.4 mm) X 1 inch (25.4 mm) galvanized cap washer (Cap-n-nail). In lieu of nails, No. 11 gage (3.0 mm) (0.12 inch diameter shank), 1-3/4 inches long (44.45 mm), corrosion-resistant screws having 0.375 inch diameter heads (9.5 mm), with a neoprene-lined washer can be used.

 Adhesive: Polyurethane construction adhesive conforming to AFG-01, ASTM D 557 or ASTM D 3498.

 Wind Clip: Use a wire clip, 1/8 inch diameter conforming to ANSI 1075.

4 MaxiTILE P7TM | www.maxitile.com

Page 5: Maxilite P7 Installation Instructions

INSTALLATION OF FIELD TILE FOR WIND SPEED 60-100 mph

MaxiLITE P7TM roofing tile is applied with the staggered joint installation method

1) On gable roofs, before installing field tile, the trim tile should be installed at the gable.

2) As a general rule, begin by applying field tile at a gable and run toward a valley, hip or wall.

3) Start by installing a full width six corrugation tile at the lower edge of the gable with an overhang of 1 inch at the gable and 2 inches at the eave (1 inch if gutters). Apply the following tiles in the first course by side lapping one full corrugation.

4) You may start at either end of the roof.

5) Place the exposed fastener through the top of each corrugation behind the bird stop or in the eave course (first course only) into the roof deck, a minimum 2 inches from the bottom edge. Then install the hidden fastener through at each valley of corrugation of the each panel located 2 inches from the top edge of the tile panel. Avoid over tightening the fasteners to prevent breakage of the panel. The fasteners should only be tightened moderately. (The exposed fastener can also be applied in last course if desired).

6) Before laying the next course, apply a 1 inch wide dab of adhesive to the side slope of each corrugation (horizontal side lapping), and a thick bead of adhesive on every overlapped corrugation.

7) Cut one full corrugation of field tile and start the second course with this five-corrugation panel (only the first tile panel). Install the tile with a minimum 4 inches head lap over the previous course. Apply adhesive (Review Step 6) and place a full width panel continued until flush the rake edge.

8) The third course should be started with a field tile cut vertically in two full corrugations. Repeat Step 7.

9) The fourth course is installed with a field tile cut vertically in half. Repeat Step 7.

10) The fifth course is installed as the first course. Repeat Step 3 to 9 until reaching the ridge.

11) For all field tile application, install the hidden fastener at each valley of corrugation of the panel located 2 inches from the top edge of the tile panel. Also a wind clip at the lower edge of each overlapping corrugation may be installed.

 Nails: Corrosion-resistant 8d common nails.

Incorrect Correct

www.maxitile.com | MaxiTILE P7TM 5

Page 6: Maxilite P7 Installation Instructions

Exposed Fastener First course only through the top of each corrugation behind the bird stop or

eave course

Rake Tile

Metal bird stop

Wind ClipAt the lower edge of each over-

lapping corrugation

Hidden fastenerAt each valley of corrugation at 2” from the top edge of the tile

Ridge Tile

Apply thick bead of adhesive on every overlapped barrel

Apply a 1” wide by minimum 1/4”

thick dab of adhesive to sides of each

barrel about 2” from the top edge

INSTALLATION OF FIELD TILE FOR WIND SPEED > 110 mph

a) Prior to installing field tiles on gable roofs, the trim tile should be installed at the gable.

b) As a general rule, begin by applying field tile at a gable and run toward a valley, hip or wall.

c) Start by installing a full width six-corrugation panel at the lower edge of the gable with an overhang of 1 inch at the gable and 2 inches at the eave (1 inch if there are gutters). Apply the following tiles in the first course by side lapping one full corrugation.

d) In high wind areas, the field and ridge trim tile should be installed with the laps facing downwind of the prevailing wind direction.

e) Place the exposed fastener through the top of each corrugation either behind the bird stop or in the eave course (first course) into the roof deck, a minimum 2 inches from the bottom edge. Then install the hidden fastener, secured through every other valley of corrugation of the panel located 2 inches from the top edge of the tile panel. Avoid over tightening fasteners to prevent breakage of tile panel. The fasteners should only be tightened moderately. Cover the fastener heads with adhesive.

Also a 1 inch wide by minimum ¼ inch thick dab of adhesive may be applied to the sides of each barrel and a thick bead on every overlapped barrel, before laying the next course.

6 MaxiTILE P7TM | www.maxitile.com

Page 7: Maxilite P7 Installation Instructions

f ) Cut one full barrel of a field tile and start the second course with this five corrugations tile (only the first tile panel). Install the tile with a minimum 4 inches head lap over the previous course and place an exposed fastener on the first barrel at 2 inches from the lower edge. You can apply adhesive (Review Step “e”) and place a full width tile continued until flush the rake edge.

g) The third course should be started with a field tile cut vertically in two full corrugations. Repeat Step “f ”.

h) The fourth course is installed with a field tile cut vertically in half. Repeat Step “f ”.

i) The fifth course is installed the same as the first course. Repeat Step “c” to “h” until reaching the ridge.

j) For all field tiles, install the hidden fastener at every other valley of corrugation of the panel located 2 inches from the top edge of the tile panel. Also can install an exposed fastener at the top of every crown corrugation. A wind clip must be installed at the lower edge of each overlapping corrugation.

Exposed Fastener For all field tile at the top of every crown corrugation

Rake Tile

Metal bird stop

Hidden fastenerFor all field tile at every other

valley of corrugation at 2” from the top edge of the tile.

Ridge Tile

Apply thick bead of adhesive on every overlapped barrel

Apply a 1” wide by minimum 1/4” thick

dab of adhesive to sides of each barrel

about 2” from the top edge

www.maxitile.com | MaxiTILE P7TM 7

Page 8: Maxilite P7 Installation Instructions

The following is only a suggestion and is not intended to be a set of instructions. Each flashing situation will be slightly different. Review IBC or

Section 1507.3.9; IRC Section R905.3.8 for additional details for valley and flashing.

VALLEY:

Valley metal should extend 12 inches on each side of the valley. The metal should be of proper gauge (minimum No. 26). Valley metal should have at least a 1 inch rise in the middle and be crimped back at the outer edges. It should have a minimum 6 inches head lap. No fasteners should penetrate the metal. Where debris may be a factor, tiles should be held back from the center of the valley to sufficiently to allow run off.

RAKE INSTALLATION:

Nail 2 inches X 2 inches approximately 1 inch from edge of roof. The nailer must be covered with non-perforated Type II (commonly called No. 30) felt in accordance with ASTM D 226. Install rake tile using two corrosion-resistant 8d common nails (top and bottom). Starting from the eave, apply the field tile over previously installed rake tiles. In most cases, a double gable trim system will be needed at one end of a gable roof. For an esthetic match, plan for double rake tile at both ends. For flared gables, use a tile pan type metal flashing under the field tile next to the 2 inches X 2 inches nailer. For high wind areas, fasten externally through the rake tile into place utilizing three nails (one centered) or three screws and washers at each head lap, then cover the fastener with adhesive.

Tile

ValleyValleyMortar

Bird stop

Felt wrapped

Hidden with rake tile Exposed with rake tile Exposed double with trim tile

8 MaxiTILE P7TM | www.maxitile.com

Page 9: Maxilite P7 Installation Instructions

HIP INSTALLATION:

To enail a 2 inches X 6 inches nailer on the top of the hip rafter after the installation of the field tile. Hold 6 inches back from edge. Field tile should be cut as close to the nailer as possible. The hip must be covered with non-perforated Type II (commonly called No. 30) felt in accordance with ASTM D 226. Apply mortar to the valley corrugation or use a plastic hip seal (for pitches 4:12 to 7:12). The hip tile must be fastened to the nailer, starting at the eave, with minimum 4 inches tile head laps, using corrosion-resistant 8d common nail. Apply a thick bead of adhesive along each vertical head lap. Complete hips before starting the ridge. The lower hip tiles can be closed with mortar, a cutout of a bird stop or a stack of cutoffs of ridge tiles with mortar between each piece. For high wind areas, fasten externally through the hip tile into the place utilizing two nails (one centered) or two screws and washers at each head lap and then cover the fastener with adhesive.

RIDGE INSTALLATION:

2 inches X 4 inches ridge nailer with 1 inch X 2 inches nailer on top wrapped with non-perforated Type II (commonly called No. 30) felt in accordance with ASTM D 226. The top course of field tile should be snug with the ridge nailer.

The void between the pans of the field tile and the ridge tile must be water proofed before installing the ridge tile. Use mortar (in accordance with IBC section 2103.7 or IRC section R607.1 as applicable) or a plastic ridge seal (for pitches 4:12 to 7:12).

A strip of chicken wire or fiberglass webbing can be installed along the length of the ridge and contoured into the mortar to keep it in place. The ridge tile must be installed with minimum 4 inches head lap and using a nail.

The fastener must penetrate minimum 1 inch into the nailer. For high wind areas, fasten externally through the ridge tile into place utilizing two nails or two screws and washer (one centered) at each head lap and then cover the fastener with adhesive.

2” x 6” Ridge nailer held back 6” from edge

Bird stop

Mortar

Adhesive over fastener

4 “ min. Headlap

Face fastener first piece

Ridge Tile

Felt wrapped

Hidden Fastener

4” min. headlap

Tile

www.maxitile.com | MaxiTILE P7TM 9

Page 10: Maxilite P7 Installation Instructions

Approvals: “In accordance with ICC-ES Legacy report ESR-2058, MaxiLITE P7TM is in compliance with the following codes: 2006 International Building Code (IBC) and 2006 International Residential Code (IRC).

MaxiLITE P7TM is also recognized for application in the following: Texas Department of Insurance Product Evaluation RC-205. These documents should also be consulted for additional information concerning the

suitability of this product for specific applications.

Additional Installation Information, Warranties, and Warnings are available at www.maxitile.com

ROOF MAINTENANCE:

Normal maintenance tasks will be determined by the geographical area and the exposure of the roofing; (before beginning refer to your paint manufacturer for washing and recoating requirements related to paint performance); the tasks shall include but not be limited to: In very humid climates, MAXILITE is subject to the growth of algae or fungus. Such growth, which is more of

an aesthetic problem rather than one of damage to the integrity of the material, can be eliminated with the application of certain fungicides. Check with the fungicide manufacturers.

 Clean out and repair gutters, flashing around pipes, chimneys, walls and protrusions, blocked pipes or flashing as required.

 In order to maintain the integrity of your roof, it is advisable to periodically clean off debris, such as leaves and pine needles. Wash down the roofing surfaces every 6 to 12 months with a garden hose or low pressure water spray to remove dirt and debris, or a medium bristle (nonmetal) brush that is suitable for cleaning fiber-cement products.

 Do not clean up with high pressure water blasts or sand blasting because it may damage the surface and/or fiber-cement product.

Avoid using steam cleaners or using pressurized cleaning equipment on field tile roofing.

 Do not apply directly acid or soda on fiber-cement surface. Acid solution for washing can be use to clean primer or painted fiber-cement surfaces. If it is necessary, add 1 part of muriatic acid to 5 parts water. Always saturate MAXILITE surfaces with water before applying cleaning agent particularly when using an acid solution.

 A mild detergent and soft brush may be used for stubborn dirt or stains. When reapplying exterior finishes, refer to your paint manufacturer. Patch damaged areas with a good quality spackling compound. Brush or wipe surface to remove loose fibers, dirt or efflorescence. Remove oil and grease spots.  Ensure that surface is thoroughly clean and dry. Then either brush or spray a coating of top quality 100% acrylic

latex exterior paint.

MAXITILE, INC. 12950 Country Parkway Suite 180, San Antonio, Texas 78216. (800) 451-2003 Phone - (210) 545-7315 Fax

www.maxitile.com

Vers

ion:

S-M

P7-E

1-27

0510

10 MaxiTILE P7TM | www.maxitile.com