Top Banner

of 30

Material Management 2 (b)

Apr 14, 2018

Download

Documents

asadhot_shot
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/30/2019 Material Management 2 (b)

    1/30

    Aggregate Production Plan

    THREE BASIC PRODUCTION STRATEGIES

    1. Chase Strategy-

    Adjusts capacity to match the demand pattern. Firmhires & lays off workers to match production todemand. Workforce fluctuates but finished goodsinventory remains constant.

    Works well for make-to-order firms as they cannot

    rely on finished goods inventory to satisfy thefluctuating demand pattern and cannot manufactureahead of the order as the actual specifications of thefinished goods are not known.

    1

  • 7/30/2019 Material Management 2 (b)

    2/30

    Aggregate Production Plan

    2. Level Production Strategy- Relies on a constantoutput rate & capacity while varying inventory &backlog levels according to fluctuating demandpattern. Workforce levels stay constant & firmrelies on fluctuating finished goods inventories &backlogs to meet demand. Works well for make-to-stock manufacturing firms.

    3. Mixed Production Strategy- To maintain stableworkforce core while using other short-termmeans, such as overtime, & additionalsubcontracting or part time helpers to manageshort-term demand.

  • 7/30/2019 Material Management 2 (b)

    3/30

    Demand

    No. of Units

    Time

    For Example:

  • 7/30/2019 Material Management 2 (b)

    4/30

    Demand

    ChaseProductionNo. of Units

    Time

    Chase Production:

  • 7/30/2019 Material Management 2 (b)

    5/30

    An Example of Chase Production Strategy

    Capacity (Labor)

    Period Forecast Demand Needed Workers Production Ending Inventory

    January 120 Units 960 Hrs 6 120 Units 100 Units

    February 100 Units 800 Hrs 5 100 Units 100 Units

    March 300 Units 2400 Hrs 15 300 Units 100 Units

    April 460 Units 3680 Hrs 23 460 Units 100 Units

    May 600 Units 4800 Hrs 30 600 Units 100 Units

    June 700 Units 6600 Hrs 35 700 Units 100 Units

    July 760 Units 6080 Hrs 38 760 Units 100 Units

    August 640 Units 5120 Hrs 32 640 Units 100 Units

    September 580 Units 4640 Hrs 29 580 Units 100 Units

    October 400 Units 3200 Hrs 20 400 Units 100 Units

    November 200 Units 1600 Hrs 10 200 Units 100 Units

    December 140 Units 1120 Hrs 9 180 Units 40 Units

    5,000 Units 40000 Hrs 252 5040 Units

  • 7/30/2019 Material Management 2 (b)

    6/30

    Demand

    Level Production

    No. of Units

    Time

    Level Production:

  • 7/30/2019 Material Management 2 (b)

    7/30

    Demand

    Level Production

    No. of Units

    Time

    Level Production:

    CREATE Inventory

    USE Inventory

  • 7/30/2019 Material Management 2 (b)

    8/30

    An Example of Level Production Strategy

    Capacity (Labor)

    Period Forecast Demand Hours Workers Production Ending Inv/backing

    January 120 Units 960 Hrs 21 420 Units 300 Units

    February 100 Units 800 Hrs 21 420 Units 620 Units

    March 300 Units 2400 Hrs 21 420 Units 740 Units

    April 460 Units 3680 Hrs 21 420 Units 700 Units

    May 600 Units 4800 Hrs 21 420 Units 520 Units

    June 700 Units 6600 Hrs 21 420 Units 240 Units

    July 760 Units 6080 Hrs 21 420 Units (100) Units

    August 640 Units 5120 Hrs 21 420 Units (320) Units

    September 580 Units 4640 Hrs 21 420 Units (480) Units

    October 400 Units 3200 Hrs 21 420 Units (460) Units

    November 200 Units 1600 Hrs 21 420 Units (240) Units

    December 140 Units 1120 Hrs 21 420 Units 40 Units

    5,000 Units 40000 Hrs 252 5040 Units

  • 7/30/2019 Material Management 2 (b)

    9/30

    Demand

    Hybrid

    No. of Units

    Time

    Hybrid:

  • 7/30/2019 Material Management 2 (b)

    10/30

    Numerical Example:

    Period 1 2 3 4 5 6 Total

    Forecast (Demand) 150 160 180 175 155 140 960

    Suppose the forecasted demand for a product family looks

    like the table below. Assume the product family is a

    Make-to-Stock family with a starting inventory of 100.

  • 7/30/2019 Material Management 2 (b)

    11/30

    Production Plan using Chase Strategy

    Period 1 2 3 4 5 6 Total

    Forecast (Demand) 150 160 180 175 155 140 960

    Planned

    Production

    150 160 180 175 155 140 960

    Planned Inventory 100 100 100 100 100 100

  • 7/30/2019 Material Management 2 (b)

    12/30

    Production Plan Using a Level Strategy

    Period 1 2 3 4 5 6 Total

    Forecast (Demand) 150 160 180 175 155 140 960

    Planned

    Production

    160 160 160 160 160 160 960

    Planned Inventory 110 110 90 75 80 100

  • 7/30/2019 Material Management 2 (b)

    13/30

    Production Plan using a Hybrid Strategy

    Period 1 2 3 4 5 6 Total

    Forecast

    (Demand)

    150 160 180 175 155 140 960

    Planned

    Production

    140 140 140 175 175 175 945

    Planned Inventory 90 70 30 30 50 85

  • 7/30/2019 Material Management 2 (b)

    14/30

    The Master Production Schedule

    The formal link between production planningand actual production

    The basis for calculation of resources needed The driving force behind the material

    requirements plan

    The primary priority plan for manufacturing

  • 7/30/2019 Material Management 2 (b)

    15/30

    Master Production Scheduling

    A detailed disaggregation of the aggregateproduction plan, listing the exact end items to beproduced by a specific period.

    More detailed than APP & easier to plan under stabledemand. Planning horizon is shorter than APP, butlonger than the lead time to produce the item.

    The sum of the Master Production Schedule ( MPS) isequal to the total of the Aggregate Production Plan(APP).

    15

  • 7/30/2019 Material Management 2 (b)

    16/30

    Information Needed to Develop an MPS

    Production Plan data

    Forecasts

    Actual customer orders Inventory levels

    Capacity constraints

  • 7/30/2019 Material Management 2 (b)

    17/30

    Master Schedule Focal Points

    Make-to-Stock Limited end products, manycomponents

    Make-to-Order Many end products, fewercomponents

    Assemble-to-Order Many end products,combination of components and

    subassemblies

  • 7/30/2019 Material Management 2 (b)

    18/30

    Example MPS Environments

    Figure 3.3 Different MPS environments

  • 7/30/2019 Material Management 2 (b)

    19/30

    Master Production Scheduling

    The MPS is the production quantity to meetdemand from all sources & is used forcomputing the requirements of all time-

    phased end items.

    Frequent changes to the MPS may createsystem nervousnessa situation where a

    small change in the upper-level-productionplan causes a major change in the lower-levelproduction plan.

    19

  • 7/30/2019 Material Management 2 (b)

    20/30

    ATVs Master Production Schedule for January and February

    Period Model A Model B Model C

    January week 1 10 10 10

    January week 2 10 10 10

    January week 3 20 0 10

    January week 4 0 20 10

    February Week 1 20 0 0

    February Week 2 0 20 0

    February Week 3 0 0 20

    February Week 4 20 20 0

    Total 80 80 60

  • 7/30/2019 Material Management 2 (b)

    21/30

    Master Production Scheduling

    Many firms use a time fence system to deal withsystem nervousness. A time fence separates theplanning horizon into two segments

    Firmed Segment (demand time fence), fromcurrent period to several weeks into future. Canonly be altered by senior management.

    Tentative segment (planning time fence), fromend of the firmed segment to several weeksfarther into the future.

  • 7/30/2019 Material Management 2 (b)

    22/30

    Time Fences

    The flexibility allowed in the MPS Frozen Zone (closest to current date)

    Capacity and materials committed to customerorders, forecast generally ignored

    Senior management approval for changes Slushy Zone

    Less commitment of materials and capacity Tradeoffs negotiated between marketing and

    manufacturing Liquid Zone All changes allowed within limits of the Production

    Plan

  • 7/30/2019 Material Management 2 (b)

    23/30

    Master Production Scheduling

    Available-to-Promise (ATP) Quantities-

    The MPS decides whether additional orders can be acceptedfor difference between confirmed customer orders & the

    quantity the firm planned to produce.

    Three methods to calculate available-to-promise quantities:

    1. Discrete available-to-promise

    2. Cumulative available-to-promise without look ahead, &

    3. Cumulative available-to-promise with look ahead.

    23

  • 7/30/2019 Material Management 2 (b)

    24/30

    Discrete ATP Calculations for January and February

    Week 1 2 3 4 5 6 7 8

    Model A-0. 4-liter EngineMPS BI=30Committed Customer Order

    ATP:D

    1010

    20

    100

    0

    2030

    0

    010

    0

    200

    0

    020

    0

    00

    0

    2010

    10Model B-0.5-liter EngineMPS BI=40Committed Customer OrderATP:D

    102010

    10100

    0100

    2000

    000

    20200

    0200

    200

    20

    Model C-o0.6-liter EngineMPS BI=40Committed Customer OrderATP:D

    102020

    10100

    10200

    1000

    000

    0100

    2005

    0150

  • 7/30/2019 Material Management 2 (b)

    25/30

    Master Production Scheduling

    Discrete Available-to-Promise

    1. Add the beginning Inventory to the MPS for Period

    1, and subtract the Committed Customer Orders.

    2. For the next period, subtract the CommittedCustomer Orders from MPS. If quantity is positive,this becomes the Period 2 ATP. If negative, subtractenough from the previous periods ATP to make thecurrent periodsATP zero.

    3. For subsequent periods, follow Step 2

    25

  • 7/30/2019 Material Management 2 (b)

    26/30

    Materials Requirement Planning

    A computer-based materials managementsystem. The materials requirement plan

    calculates the exact quantities, need dates, &planned order releases for sub-assemblies &materials required to manufacture the finalproducts listed on .

    26

  • 7/30/2019 Material Management 2 (b)

    27/30

    Independent versus Dependent demand

    Independent Demand

    Not related to demand for other assemblies orproducts, instead from outside sources

    Generally forecasted demand

    Dependent Demand

    Generally related to production of an end product

    (as defined on the MPS) Can be calculated instead of forecasted

  • 7/30/2019 Material Management 2 (b)

    28/30

    Dependent Demand Approach

    Materials Requirement Planning (MRP)

    Major objectives of MRP

    Determine requirements calculated to meet

    product requirements defined in the MPS

    What to order

    How much to order

    When to order When to schedule delivery

    Keep priorities current

  • 7/30/2019 Material Management 2 (b)

    29/30

    Materials Requirement Planning

    MRP requires: The independent demand information. Parent-component relationships from the bill

    of materials. Inventory status of the final product & all of

    the components. Planned order releases (output of the MRP

    system)

    Advantage of MRP- provides planning information

    Disadvantage of MRP- loss of visibility, especiallyacute for products with a deep bill of materials, & ignorecapacity & shop floor conditions.

  • 7/30/2019 Material Management 2 (b)

    30/30

    Links To Other MPC Functions

    Figure 4.2 Manufacturing planning and control systems