Top Banner
Modul ke: Fakultas Program Studi Manajemen Persediaan 11 FEB Manajemen MRP EOQ
58

Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Apr 03, 2019

Download

Documents

lethuy
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Modul ke:

Fakultas

Program Studi

Manajemen Persediaan

11 FEB

Manajemen

MRP EOQ

Page 2: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Learning Objectives

• Describe the conditions under which MRP is most appropriate.

• Describe the inputs, outputs, and nature of MRP processing.

• Explain how requirements in a master production schedule are translated into material requirements for lower-level items.

• Discuss the benefits and requirements of MRP.

Page 3: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Learning Objectives

• Explain how an MRP system is useful in capacity requirements planning.

• Outline the potential benefits and some of the difficulties users have encountered with MRP.

• Describe MRP II and its benefits.

• Describe ERP, what it provides, and its hidden costs.

Page 4: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

• Material requirements planning (MRP): Computer-based information system that translates master schedule requirements for end items into time-phased requirements for subassemblies, components, and raw materials.

MRP

End products

Time-phase based

• Subassemblies

• Components • Raw materials

MRP

Page 5: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Independent and Dependent Demand Independent Demand

A

B(4) C(2)

D(2) E(1) D(3) F(2)

Dependent Demand

Independent demand is uncertain. Dependent demand is certain.

Page 6: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

• Dependent demand: Demand for items that are subassemblies or component parts to be used in production of finished goods.

• Once the independent demand is known, the dependent demand can be determined.

Dependant Demand

Page 7: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Demand

Time

Time Time

Time

De

man

d

De

man

d

Stable demand “Lumpy” demand

Am

ou

nt

on

han

d

Am

ou

nt

on

han

d

Safety stock

Page 8: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

MRP Inputs MRP Processing MRP Outputs

Master schedule

Bill of materials

Inventory records

MRP computer programs

Changes

Order releases

Planned-order schedules

Exception reports

Planning reports

Performance- control reports

Inventory transaction

Primary reports

Secondary reports

Overview of MRP

Page 9: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

• Master Production Schedule

• Time-phased plan specifying timing and quantity of production for each end item.

• Material Requirement Planning Process

MPR Inputs

Page 10: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Master Schedule

Master schedule: One of three primary inputs in MRP; states which end items are to be produced, when these are needed, and in what quantities.

Cumulative lead time: The sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of final assembly.

Page 11: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Planning Horizon

1 2 3 4 5 6 7 8 9 10

Procurement

Fabrication

Subassembly

Assembly

Time Period (weeks)

Page 12: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Bill-of-Materials

Bill of materials (BOM): One of the three primary inputs of MRP; a listing of all of the raw materials, parts, subassemblies, and assemblies needed to produce one unit of a product.

Product structure tree: Visual depiction of the requirements in a bill of materials, where all components are listed by levels.

Low-level coding: Restructuring the bill of materials so that multiple occurrences of a component all coincide with the lowest level the component occurs

Page 13: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Product Structure Tree Chair

Seat

Legs (2) Cross bar

Side Rails (2)

Cross bar

Back Supports (3)

Leg Assembly

Back Assembly

Level 0

1

2

X

B (2)

D (3) E

C

E (2) F (2)

E (4)

X

B (2)

D (3) E

C

E (2) F (2)

E (4) E E (2)

Level

0

1

2

3

Page 14: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Inventory Records

• One of the three primary inputs in MRP

• Includes information on the status of each item by time period – Gross requirements

– Scheduled receipts

– Amount on hand

– Lead times

– Lot sizes

– And more …

Page 15: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Inventory Requirements

• Net requirements:

• Available Inventory:

Net Requirements = Gross Requirements

– Available Inventory

Available Inventory = Projected on hand

– Safety stock

– Inventory allocated to

other items

Page 16: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Assembly Time Chart

1 2 3 4 5 6 7 8 9 10 11

Procurement of raw material D

Procurement of raw material F

Procurement of part C

Procurement of part H

Procurement of raw material I

Fabrication of part G

Fabrication of part E

Subassembly A

Subassembly B

Final assembly and inspection

Page 17: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Time-Phased Product Structure

| | | | | | | |

1 2 3 4 5 6 7 8 Time in weeks

F (2)

2 weeks

3 weeks

1 week

A

2 weeks

1 week

D (2)

E (2)

2 weeks

D (2)

G (1)

1 week

1 week

2 weeks to produce

B (2)

C (3)

E (2)

Start production of D

Must have D and E completed here so

production can begin on B Lead time

A B C D E F G

1 2 1 1 2 3 2

weeks weeks weeks weeks weeks weeks weeks

Page 18: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Gross Requirements Plan

Week

1 2 3 4 5 6 7 8 Lead Time

A. Required date 50 Order release date 50 1 week

B. Required date 100 Order release date 100 2 weeks

C. Required date 150 Order release date 150 1 week

E. Required date 200 300 Order release date 200 300 2 week

F. Required date 300 Order release date 300 3 weeks

D. Required date 600 200 Order release date 600 200 1 week

G. Required date 300 Order release date 300 2 week

Page 19: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

MRP Structure

Figure 14.5

Output Reports

MRP by period report

MRP by date report

Planned order report

Purchase advice

Exception reports

Order early or late or not needed

Order quantity too small or too large

Data Files

Purchasing data

BOM

Lead times

(Item master file)

Inventory data

Master production schedule

Material requirement

planning programs (computer and

software)

Page 20: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Determining Gross Requirements

Starts with a production schedule for the end item – 50 units of Item A in week 8

Using the lead time for the item, determine the week in which the order should be released – a 1 week lead time means the order for 50 units should be released in week 7

This step is often called “lead time offset” or “time phasing”

Page 21: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Determining Gross Requirements

From the BOM, every Item A requires 2 Item Bs – 100 Item Bs are required in week 7 to satisfy the order release for Item A

The lead time for the Item B is 2 weeks – release an order for 100 units of Item B in week 5

The timing and quantity for component requirements are determined by the order release of the parent(s)

Page 22: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Determining Gross Requirements

The process continues through the entire BOM one level at a time – often called “explosion”

By processing the BOM by level, items with multiple parents are only processed once, saving time and resources and reducing confusion

Low-level coding ensures that each item appears at only one level in the BOM

Page 23: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Net Requirements Plan

Page 24: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Net Requirements Plan

Page 25: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

MRP Processing

• Gross requirements

• Schedule receipts

• Projected on hand

• Net requirements

• Planned-order receipts

• Planned-order releases

Page 26: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

MPR Processing

• Gross requirements

– Total expected demand

• Scheduled receipts

– Open orders scheduled to arrive

• Projected on hand

– Expected inventory on hand at the beginning of each time period

Page 27: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

MPR Processing

• Net requirements

– Actual amount needed in each time period

• Planned-order receipts

– Quantity expected to be received at the beginning of the period

– Offset by lead time

• Planned-order releases

– Planned amount to order in each time period

Page 28: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Lot-Sizing Techniques

Lot-for-lot techniques order just what is required for production based on net requirements

May not always be feasible

If setup costs are high, costs may be high as well

Economic order quantity (EOQ)

EOQ expects a known constant demand and MRP systems often deal with unknown and variable demand

Page 29: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Lot-Sizing Techniques

Part Period Balancing (PPB) looks at future orders to determine most economic lot size

EPP = setup cost / holding cost

Programming technique

Assumes a finite time horizon

Effective, but computationally burdensome

Page 30: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Lot-for-Lot Example

Week 1 2 3 4 5 6 7 8 9 10

Gross

requirements 35 30 40 0 10 40 30 0 30 55

Scheduled

receipts

Projected on

hand 35 35 0 0 0 0 0 0 0 0 0

Net

requirements 0 30 40 0 10 40 30 0 30 55

Planned order

receipts 30 40 10 40 30 30 55

Planned order

releases 30 40 10 40 30 30 55

Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week

Page 31: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Lot-for-Lot Example

1 2 3 4 5 6 7 8 9 10

Gross

requirements 35 30 40 0 10 40 30 0 30 55

Scheduled

receipts

Projected on

hand 35 35 0 0 0 0 0 0 0 0 0

Net

requirements 0 30 40 0 10 40 30 0 30 55

Planned order

receipts 30 40 10 40 30 30 55

Planned order

releases 30 40 10 40 30 30 55

No on-hand inventory is carried through the system Total holding cost = $0 There are seven setups for this item in this plan Total setup cost = 7 x $100 = $700

Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week

Page 32: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

EOQ Lot Size Example

Week 1 2 3 4 5 6 7 8 9 10

Gross

requirements 35 30 40 0 10 40 30 0 30 55

Scheduled

receipts

Projected on

hand 35 35 0 43 3 3 66 26 69 69 39

Net

requirements 0 30 0 0 7 0 4 0 0 16

Planned order

receipts 73 73 73 73

Planned order

releases 73 73 73 73

Average weekly gross requirements = 27; EOQ = 73 units

Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week

Page 33: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

EOQ Lot Size Example

1 2 3 4 5 6 7 8 9 10

Gross

requirements 35 30 40 0 10 40 30 0 30 55

Scheduled

receipts

Projected on

hand 35 35 0 0 0 0 0 0 0 0 0

Net

requirements 0 30 0 0 7 0 4 0 0 16

Planned order

receipts 73 73 73 73

Planned order

releases 73 73 73 73

Annual demand = 1,404 Total cost = setup cost + holding cost Total cost = (1,404/73) x $100 + (73/2) x ($1 x 52 weeks) Total cost = $3,798 /year Cost for 10 weeks = $3,798 x (10/52) = $730 Or Total cost = setup cost + holding cost Total cost = 4 x $100 + 318 x ($1 /weeks) Total cost = $718

Average weekly gross requirements = 27; EOQ = 73 units

Holding cost = $1/week; Setup cost = $100/times; Lead time = 1 week

Page 34: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

PPB Example

1 2 3 4 5 6 7 8 9 10

Gross

requirements 35 30 40 0 10 40 30 0 30 55

Scheduled

receipts

Projected on

hand 35 35 0 50 10 10 0 60 30 30 0

Net

requirements 0 30 0 0 0 40 0 0 0 55

Planned order

receipts 80 100 55

Planned order

releases 80 100 55

Holding cost = $1/week; Setup cost = $100; Lead time = 1 week ; EPP = 100 units

Page 35: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

PPB Example

1 2 3 4 5 6 7 8 9 10

Gross

requirements 35 30 40 0 10 40 30 0 30 55

Scheduled

receipts

Projected on

hand 35

Net

requirements

Planned order

receipts

Planned order

releases

Holding cost = $1/week; Setup cost = $100; EPP = 100 units

2 30 0 2, 3 70 40 = 40 x 1 2, 3, 4 70 40 = 40 x 1 2, 3, 4, 5 80 70 = 50 x 1 + 10 x 2 100 70 170 2, 3, 4, 5, 6 120 230 = 90 x 1 + 50 x 2 + 40 x 1

+ =

Combine periods 2 - 5 as this results in the Part Period closest to the EPP

Combine periods 6 - 9 as this results in the Part Period closest to the EPP

6 40 0 6, 7 70 30 = 30 x 1 6, 7, 8 70 30 = 30 x 1 6, 7, 8, 9 100 120 = 60 x 1 + 30 x 2 100 120 220 + =

10 55 0 100 0 100 Total cost 300 190 490

+ =

+ =

Trial Lot Size Periods (cumulative net Costs Combined requirements) Part Periods Setup Holding Total

Page 36: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Lot-Sizing Summary

For these three examples

Lot-for-lot $700 EOQ $730 PPB $490

Wagner-Whitin would have yielded a plan with a total cost of $455 for this example

Page 37: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Example

1 2 3 4 5 6 7 8 9 10

Gross

requirements 35 30 40 0 10 40 30 0 30 55

Scheduled

receipts

Projected on

hand 35 35 0 50 10 10 0 30 0 0 55

Net

requirements 0 30 0 0 0 40 0 0 30 0

Planned order

receipts 80 70 85

Planned order

releases 80 70 85

Holding cost = $1/week; Setup cost = $100; Lead time = 1 week ; EPP = 100 units

Page 38: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Lot-Sizing Summary

In theory, lot sizes should be recomputed whenever there is a lot size or order quantity change

In practice, this results in system nervousness and instability

Lot-for-lot should be used whenever economical

Lot sizes can be modified to allow for scrap, process constraints, and purchase lots

Page 39: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Lot-Sizing Summary

Use lot-sizing with care as it can cause considerable distortion of requirements at lower levels of the BOM

When setup costs are significant and demand is reasonably smooth, PPB, Wagner-Whitin, or EOQ should give reasonable results

Page 40: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Updating the System

• Regenerative system

– Updates MRP records periodically

• Net-change system

– Updates MPR records continuously

Page 41: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

MRP Primary Reports

• Planned orders - schedule indicating the amount and timing of future orders.

• Order releases - Authorization for the execution of planned orders.

• Changes - revisions of due dates or order quantities, or cancellations of orders.

Page 42: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

MRP Secondary Reports

• Performance-control reports

system evaluation, deviation, late delivery, stockouts

• Planning reports

useful for forecasting future inventory, assess future material requirement

• Exception reports

late or overdue orders, excessive scrap rate, requirement of non-existing parts

Page 43: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Material Checking & Balancing

Use for monitoring of amount of part and product during processes

Needs information to balance materials

Accumulative production planning or target plan

BOM or Assembly diagram

Normally periodic checked

Page 44: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Material Checking & Balancing

9 8 7 6 5 4 3 2 1 0 Week

A

B C

D

E

F

G

H I J K

Assembly diagram

D N O S A J J M A M F J

Target Plan

Acc

um

ula

tive

pro

du

ctio

n

K J I H G F E D C B A

Balancing chart

Page 45: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Resource Requirements Profile

Lot 1

Lot 2

Lot 4

Lot 7

Lot 8 Lot

3 Lot 5

Lot 10 Lot

13

Lot 9 Lot

12

Lot 14 Lot

16

Lot 6

Lot 15

Lot 11

Available capacity

Capacity exceeded in periods 4 & 6

Lot 1

Lot 2

Lot 4

Lot 7

Lot 8 Lot

3 Lot 5

Lot 10 Lot

13

Lot 9 Lot

12

Lot 14 Lot

16

Lot 6

Lot 15

Lot 11

Available capacity

Lot 6 “split” Lot 11 moved

200 –

150 –

100 –

50 –

1 2 3 4 5 6 7 8

Period (a)

Sta

nd

ard

la

bo

r h

ou

rs

200 –

150 –

100 –

50 –

1 2 3 4 5 6 7 8

Period (b)

Sta

nd

ard

la

bo

r h

ou

rs

Page 46: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Smoothing Tactics

1. Overlapping

Sends part of the work to following operations before the entire lot is complete

Reduces lead time

2. Operations splitting

Sends the lot to two different machines for the same operation

Shorter throughput time but increased setup costs

3. Lot splitting

Breaking up the order into smaller lots and running part ahead of schedule

Page 47: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Other Considerations

• Safety Stock

• Lot sizing

– Lot-for-lot ordering

– Economic order quantity

– Fixed-period ordering

Page 48: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

• Food catering service

– End item => catered food

– Dependent demand => ingredients for each recipe, i.e. bill of materials

MRP in Services

Page 49: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Benefits of MRP

• Low levels of in-process inventories

• Ability to track material requirements

• Ability to evaluate capacity requirements

• Means of allocating production time

• Ability to easily determine inventory usage by backflushing

• Backflushing: Exploding an end item’s bill of materials to determine the quantities of the components that were used to make the item.

Page 50: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Requirements of MRP

• Computer and necessary software

• Accurate and up-to-date

– Master schedules

– Bills of materials

– Inventory records

• Integrity of data

Page 51: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

• Expanded MRP with emphasis placed on integration

– Financial planning

– Marketing

– Engineering

– Purchasing

– Manufacturing

MRP II

Page 52: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Market Demand

Production plan

Problems?

Rough-cut capacity planning

Yes No Yes No

Finance

Marketing

Manufacturing

Adjust production plan

Master production schedule

MRP

Capacity planning

Problems? Requirements

schedules

Ad

just

mas

ter

sch

ed

ule

MRP II

Page 53: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

• Enterprise resource planning (ERP):

– Next step in an evolution that began with MPR and evolved into MRPII

– Integration of financial, manufacturing, and human resources on a single computer system.

ERP

Page 54: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

ERP Software

– ERP software provides a system to capture and make data available in real time to decision makers and other users in the organization

– Provides tools for planning and monitoring various business processes

– Includes

• Production planning and scheduling

• Inventory management

• Product costing

• Distribution

Page 55: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

MRP in Services

• Service applications such as:

– Professional services

– Postal services

– Retail

– Banking

– Healthcare

– Higher education

– Engineering

– Logistical services

– Real estate

Page 56: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

ERP Strategy Considerations

• High initial cost

• High cost to maintain

• Future upgrades

• Training

Page 57: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Daftar Pustaka

• Richardus Eko Indrajit, (2005), Manajemen Persediaan, Grasindo, Jakarta

• Heizer Jay, B.Rander, (206), Manajemen Operasi, Salemba Empat, Jakarta

• Hani handoko, (2002), Manajemen Produksi dan Operasi, BPFE, Yogyakarta

• Siswanto, (2005), Riset Operasi, Erlangga, Jakarta

• M. Syamsul Ma’arif, (2003), Manajemen Operasi, Grasindo, Jakarta

• Sofyan Assauri, (2001), Manajemen Operasi, BPFE, Jakarta

• Martinich, (2003), Operation Manaement, Prenice hall, New Yory

Page 58: Manajemen Persediaan Modul ke: 11Wardhana+... · Manajemen Persediaan 11 FEB Manajemen MRP EOQ . ... • Describe ERP, what it provides, ... MPR Inputs. Master Schedule

Terima Kasih