1 – Management At Program Level
1
– Management At
Program Level
Monitoring multiple projects at program level
Sharing resources between multiple projects
Multiple projects monitoring through critical
milestone
2
3
Consolidation Of
Projects
Steps :
Open new Microsoft project file
Project – sub project
4
To consolidate works from different sources of files
(e.g: Stadium file & Padang Hoki file)
1
2
Steps : From dialog box – select files to be consolidate - insert
5
Result : Multiple project with different ID
6
Steps : Save file
7
Steps : To insert level 0 project
8
File – option – advance – select “show project summary task” - ok
9
Monitoring multiple projects at program level
10
Consolidation Of
Sub Projects Into
Master Project File
Steps :
Open Master Project file (eg. Velodrom) & sub project file (eg.
Badminton)
View – arrange all
11
To consolidate works into same sources of files
12
Master Project file
Sub Project file
13
Highlight tasks which need
to consolidate into master
project file
14
Drag tasks into master project file
Result : Continuity of ID & WBS
nos. with new tasks
15
Master Project file with new tasks
16
Sharing Resources
Between Multiple
Projects
17
To share resources between multiple projects
Steps : Open file 1 (eg. Padang Hoki file ) with resources loaded
18
Resources sheet …
Steps :
Open file 2 (eg. Lapang Sasar file ) without resources
19
?
Steps : Use Lapang sasar file : Resource – Resource Pool – Share Resources
20
To share resources in Padang Hoki into Lapang Sasar
21
From dialog box, select :
1
23
22
Result : Lapang Sasar with resources (same as Padang Hoki)
23
Assign resources
Lapang Sasar file
24
Result 1 : Padang Hoki files after sharing resources with Lapang Sasar
25
Result 2 : Padang Hoki files after sharing resources with Lapang Sasar
Resources become overallocated
26
Multiple Projects
Monitoring Through
Critical Milestone
Tracking (CMT)
27
Category (milestone) Identification
1 Mandatory (contractual) 1. Site possession (conventional)2. CPC (conventional)3. CCC (Design & Build)4. sectional site possession5. Sectional completion
2 Deliverables - BQ items 1. preliminaries2. site clearance earthwork3. Structure sub-station
3 Project Mgt Practices 1. Planning2. Monitoring
4 JKR Project Life Cycle 1. Planning2. Design3. Procurement4. Construction5. Operation
28
Category (milestone) Identification
5 Construction practices 1. For Bridge- sub-structure & superstructure2. For building- beam / column / slab
6 Change Request EOT, VO, VOP
7 External Dependencies e.g. land issues, local authority approval
8 Clients organisation process 1. Payment2. Reporting3. Audit4. Site meeting5. Provisional sum …..NSC
9 Client's Authority
29
Category (milestone) Identification
10 Process interfacee.g. special equipmentcoordination works
1. Test material 2. procurement3. purchase4. delivery5. installation6. testing
11 Earned Value Techniques 1. Resources2. Fixed Formula3. Weighted milestone
12 Interim milestone 1. Work
29
30
To monitor multiple projects through critical
milestone tracking
31
Get standard JKR Project work programs
Establish standard pattern.
Come out with milestone schedule.
Decide critical milestone to be used in
monitoring.
Perform CMT at the high level (project –
program level)
31
32
33
Identify the pattern :
a. Show as Milestone Schedule
b. Set duration = 0
c. Insert start date or finish date
34
Refer steps in slide no. 4 – 9
35
36
Steps : Highlight all activities - view – outline – all sub tasks
37
Steps : View – filter – milestones
38
File 1
File 2
39
Result : Show only critical milestone activities
0 duration
milestone
symbolmultiple
projects
40
41
42
42
43