1 Management At Program Level
43

Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Oct 31, 2019

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

1

– Management At

Program Level

Page 2: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Monitoring multiple projects at program level

Sharing resources between multiple projects

Multiple projects monitoring through critical

milestone

2

Page 3: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

3

Consolidation Of

Projects

Page 4: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Steps :

Open new Microsoft project file

Project – sub project

4

To consolidate works from different sources of files

(e.g: Stadium file & Padang Hoki file)

1

2

Page 5: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Steps : From dialog box – select files to be consolidate - insert

5

Page 6: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Result : Multiple project with different ID

6

Page 7: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Steps : Save file

7

Page 8: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Steps : To insert level 0 project

8

File – option – advance – select “show project summary task” - ok

Page 9: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

9

Monitoring multiple projects at program level

Page 10: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

10

Consolidation Of

Sub Projects Into

Master Project File

Page 11: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Steps :

Open Master Project file (eg. Velodrom) & sub project file (eg.

Badminton)

View – arrange all

11

To consolidate works into same sources of files

Page 12: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

12

Master Project file

Sub Project file

Page 13: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

13

Highlight tasks which need

to consolidate into master

project file

Page 14: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

14

Drag tasks into master project file

Result : Continuity of ID & WBS

nos. with new tasks

Page 15: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

15

Master Project file with new tasks

Page 16: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

16

Sharing Resources

Between Multiple

Projects

Page 17: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

17

To share resources between multiple projects

Steps : Open file 1 (eg. Padang Hoki file ) with resources loaded

Page 18: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

18

Resources sheet …

Page 19: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Steps :

Open file 2 (eg. Lapang Sasar file ) without resources

19

?

Page 20: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Steps : Use Lapang sasar file : Resource – Resource Pool – Share Resources

20

To share resources in Padang Hoki into Lapang Sasar

Page 21: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

21

From dialog box, select :

1

23

Page 22: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

22

Result : Lapang Sasar with resources (same as Padang Hoki)

Page 23: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

23

Assign resources

Lapang Sasar file

Page 24: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

24

Result 1 : Padang Hoki files after sharing resources with Lapang Sasar

Page 25: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

25

Result 2 : Padang Hoki files after sharing resources with Lapang Sasar

Resources become overallocated

Page 26: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

26

Multiple Projects

Monitoring Through

Critical Milestone

Tracking (CMT)

Page 27: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

27

Category (milestone) Identification

1 Mandatory (contractual) 1. Site possession (conventional)2. CPC (conventional)3. CCC (Design & Build)4. sectional site possession5. Sectional completion

2 Deliverables - BQ items 1. preliminaries2. site clearance earthwork3. Structure sub-station

3 Project Mgt Practices 1. Planning2. Monitoring

4 JKR Project Life Cycle 1. Planning2. Design3. Procurement4. Construction5. Operation

Page 28: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

28

Category (milestone) Identification

5 Construction practices 1. For Bridge- sub-structure & superstructure2. For building- beam / column / slab

6 Change Request EOT, VO, VOP

7 External Dependencies e.g. land issues, local authority approval

8 Clients organisation process 1. Payment2. Reporting3. Audit4. Site meeting5. Provisional sum …..NSC

9 Client's Authority

Page 29: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

29

Category (milestone) Identification

10 Process interfacee.g. special equipmentcoordination works

1. Test material 2. procurement3. purchase4. delivery5. installation6. testing

11 Earned Value Techniques 1. Resources2. Fixed Formula3. Weighted milestone

12 Interim milestone 1. Work

29

Page 30: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

30

To monitor multiple projects through critical

milestone tracking

Page 31: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

31

Get standard JKR Project work programs

Establish standard pattern.

Come out with milestone schedule.

Decide critical milestone to be used in

monitoring.

Perform CMT at the high level (project –

program level)

31

Page 32: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

32

Page 33: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

33

Identify the pattern :

a. Show as Milestone Schedule

b. Set duration = 0

c. Insert start date or finish date

Page 34: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

34

Page 35: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Refer steps in slide no. 4 – 9

35

Page 36: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

36

Page 37: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Steps : Highlight all activities - view – outline – all sub tasks

37

Page 38: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

Steps : View – filter – milestones

38

File 1

File 2

Page 39: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

39

Result : Show only critical milestone activities

0 duration

milestone

symbolmultiple

projects

Page 40: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

40

Page 41: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

41

Page 42: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

42

42

Page 43: Management At Program Level - epsmg.jkr.gov.myepsmg.jkr.gov.my/images/4/45/Folder11_Multiple_Project_Modul2r2_21Jan...Fixed Formula 3. Weighted milestone 12 Interim milestone 1. Work

43