Making the Right Decision to Rehabilitate: An 1894 Vintage Reservoir
• Annual Fall Conference, Las Vegas, NV• Wednesday, October 28, 2015• Session 16 – Operator• Keeping you Out of Trouble on Capital Projects--Part I• 10:00 a.m. to 11:00 a.m.
11/11/2015 AFC15 Slides 1
AWWA CA/NV Presentation on Forbes Hill Tank
Carl A. Gowan, P.E., MMWDGary Ho, S.E., Beyaz & Patel
Forbes Hill Reservoir (Now known as Forbes Hill Tank)
11/11/2015 10
11/11/2015 11Existing Floating Hypalon Cover
11/11/2015 12
Existing Floating Hypalon Cover
• Water quality risk• 2004-2012 Worker safety & maintenance
issues• Open space in 1960’s era homes and
community• Adjacent pump station
Forbes Hill Tank
11/11/2015 13
• Increase protection for water • Reduce maintenance• Improve worker safety• On-site renewable energy• Minimize community disruption
Project Purpose
11/11/2015 14
Evaluated Options
• Replace liner and cover; $1.7 million• Replace liner and new roof; $3.7 million• New tank; $12.7 million
11/11/2015 15
• Design study; summer/fall 2013; 6 months• Final design; winter/spring 2013/2014; 6 months• Site preparation; summer/fall 2014; 4 months• New roof; winter/spring 2014/2015; 6 months• Solar panels; winter/spring 2015/2016; 6 months
Project Schedule
11/11/2015 16
Public Outreach• Marin Independent Journal
(press release)• Communications with
neighbors
Century-old reservoir slated for overhaul (Marin IJ, Nov. 18, 2014)
Hello Neighbors,
Thanks to the Hepburn Heights residents for allowing access for the concrete pour this past Tuesday. I’ve attached the Contractor’s 3-week Look Ahead Schedule for your view. Just a couple minor items for you to consider:
1. The Contractor will have a small crew onsite tomorrow, Saturday, excavating footings inside the reservoir. This is mostly hand excavation work using shovels and pneumatic spades. This is the first time we’ve had Saturday work on the project, which may bemore increasingly necessary in the coming months. As a reminder, we have a relatively short window to complete this project before next May in order to maintain water service during the dry season. The Contractor is allowed to work Saturdays to accomplish this task. We’ll continue to monitor noise levels and do what we can to mitigate the impact to neighbors.
2. The Contractor may utilize a truck mounted crane next Thursday, 11/20, to remove slabs of concrete from the reservoir. As with the previous concrete pours, we’d ask that Hepburn residents park cars closer to the side of the road to allow adequate access. I will send a reminder email next week if the the crane delivery is to take place.
Thanks for your cooperation and as always, feel free to contact me as needed at (707) 344-8203.
Sincerely,
Clay Kuzma | The Covello Group, Inc. | Cell: (707) 344-8203
11/11/2015 17
Engineering Design Phase
• PDR• Design Phase• Bid Phase• Construction Phase
11/11/2015 18
Objectives
• Evaluate alternative roof systems• Support solar panels• Low profile roof structure• Limit construction to winter months
7b. Constructability: Truck and Vehicle Traffic, Crane, etc. 1.00 0.50 1.00 0.508. Life Cycle Cost (Construction, O&M, Re-Coat)
0.91($3.2M)
0.74 (0.74)($2. 6M)
1.00($3.5M)
0.89 (0.89)($3. 1M)
9. Operation and Maintenance Cost1.00
($1,000K)0.02
($20K)1.00
($1,000K)0.02
($20K)
10. Construction Timeline1.00
(8-10 months)1.00
(8-10 months)0.89
(7-9 months)0.89
(7-9 months)
Totals 6.715.43
(4.90) 7.88 6. 32(5.78)11/11/2015 26
Preliminary Design ReportFindings and Recommendations
• Alternative 2: Aluminum multi-span roofPreferred long-term roof solutionCorrosion resistanceMaintenance freeLowest score/Best alternativeMost effective life cycle costLow rim heightLowest peak profile height from top of shell
11/11/2015 27
Design PhaseMajor Design Components/Elements
• Aluminum multi-span roof• Liner• Underground overhead power line serving
Marin Emergency Radio Authority (MERA)• Overflow pipe modifications• Outlet structure modifications• Strict qualifications for subcontractors and
suppliers
11/11/2015 28
Design Phase
Roof Plan
11/11/2015 29
Design Phase
Longitudinal Section
11/11/2015 30
Design Phase
Exterior Column Support11/11/2015 31
Design PhaseDesign Challenges
• Coordinate preliminary roof design with roof supplier
• Roof support on exterior columns• Columns designed to resist lateral loads (roof
suppliers)• Design schedule
6 months (November 2013 to May 2014)50%, 85% and final submittalsDesign review meetings
11/11/2015 32
Bid PhaseBid and Award
• Six competitive bids• 30% spread between bidders• Low bidder: AZTEC Consultants• Bid price: $3.04 million
11/11/2015 33
Construction PhaseConstruction Challenges
• Reservoir shutdown requirements• Outlet structure revisions• Change orders• Final work on-going, complete in January
11/11/2015 34
Scheduled Activity Date Begin Date End
Construction August 1, 2014 April 30, 2015
MERA Undergrounding
September 2014 October 2014
Tank out-of-service October 15, 2014 April 30, 2015
Liner, roof, and pipe installations
October 2014 April 2015
Clean, disinfect, fill, test
March 2015 April 2015
Construction PhaseConstruction Schedule
11/11/2015 35
Construction Phase
Construction Photos
11/11/2015 36
Existing Floating Hypalon Cover
Crane location
11/11/2015 37Overhead Power Line
11/11/2015 38
MERA Underground Work
11/11/2015 39Reservoir with Floating Cover Removed
11/11/2015 40
Demo Existing Liner
11/11/2015 41
Column Footing Complete
11/11/2015 42
First Column for New Aluminum Roof
11/11/2015 43
New Aluminum Roof
11/11/2015 44
New Aluminum Roof Framing
11/11/2015 45
Tension Ring Strut/Shoe
11/11/2015 46
Existing Outlet Pipes
11/11/2015 47
Tunnel Piping Removal
11/11/2015 48
Outlet Structure Reconstruction
11/11/2015 49
Outlet Pipe
11/11/2015 50
Outlet Tunnel
11/11/2015 51
New Outlet Pipes
11/11/2015 52
Filling Reservoir
11/11/2015 53
Overflow Piping
111th Aerial Photography
11/11/2015 54
New Aluminum Roof
• Repair liner leaks• Touch up paint on overflow box• Install missing blots inside tank• Repair peeling weather stripping• Turn over all project files
Outstanding Punch-List Items
11/11/2015 55
Tank Project Cost
Category Budget Projected Total
Construction, Final* $3,042,200 $3,060,195
Design Services $379,394 $375,863Project and
ConstructionManagement $471,956 $372,058Less: MERA Reimbursement, Final ($93,550) ($93,116)Total $3,800,000 $3,715,000
*Change orders total net cost of $17,995 = 0.6% of original contract
11/11/2015 56
• Install solar panels on new roof– Operate Grove Hill
Pump Station– Estimated Cost
$65,000– Ten-year payback– Completion March
2016
Solar Project
111th Aerial Photography
11/11/2015 57
• Project Management• Construction Management• Design• Construction• Community Outreach
Lessons Learned
11/11/2015 58
Questions?
• Contractor: Aztec Contractors• Construction Manager: The
Covello Group• Design: Beyaz & Patel, Inc.• Liner Design: Hilts Consultants• Civil Works Design: IEC