P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume XXII, Number 3 2714 Cypress Point, Suite D, Missouri City, Texas 77459 E-mail: [email protected] October 1, 2010 www.pipelineintelligence.com Continued on page 5 MAJOR PROJECTS AND NEWS ITEMS gether so they could work out all the issues related to this special feasibility hole we did in advance.” Design-build is relatively new to the HDD industry, Fluharty said. Design-build offers a subtle but important difference from the typical procedure for HDD projects. In the typical process, a com- pany such as TECO would hire an engineer to develop plans, pro- cure a construction company to implement those plans and then construct the project -- often called design-bid-build. Design-bid- build requires multiple contracts. With design-build, however, a single company is hired to engineer and to build the project, all under a single contract. Susan Hines of the Design-Build Institute of America says utiliz- ing design-bid-build can create contention between the engineer or designer of a project and the company that constructs the pro- ject. She said it creates a disconnect between the two parties which can often turn contentious because of concerns of liability and litigation. For instance, Hines said when the construction company finds changes need to be made to designs during con- struction, it takes paper work and dialogue for the changes to be approved and implemented. “It slows things down a lot,” she said. In the end, design-build projects help to improve two important aspects of any project: money and time. Design build projects cost at least 6% less than design-bid-build projects and are con- structed 12% faster, according to the Design-Build Institute of America. At the same time, the institute reports that design-build projects earned the highest owner satisfaction than other project concepts. “One of the main advantages of design build is the fact that every- one on the design and construction job is on the same side,” Hines said. “They are all sharing in the risks and the rewards of a job well done.” She added: “Owners save money, they save time.” 830-792-5445 www.pipelineskidservice.com THOUSANDS OF HARDWOOD MATS & SKIDS AVAILABLE INDUSTRY NEWS (Rosebush, MI) – Mears Group, Inc. com- pleted in April a 7,400-foot Horizontal Directional Drilling bore in Jacksonville, Florida, a design-build project that allows a re- gional energy producer to expand its natural gas pipeline to serve new facilities. To complete the project, Mears drilled a 7,400-foot pilot hole beneath the St. Johns River at a depth of 130 feet below river bottom to install the 16-inch steel pipe. It is an essential link in a 50-mile pipeline that ends at the Jacksonville Electric Author- ity (JEA’s) Greenland Energy Center. Though just 1.4 miles of the 50 mile pipeline, the section under the St. John’s River proved the most daunting in planning stages. “This was the biggest obstacle to go from one side to the other,” said Mark Haney, director of engineering for TECO Peoples Gas, the company that owns the pipeline. Haney said HDD was virtually the only option to install the pipe- line through that area. “Other than HDD, there were no other good options.” But project officials said the timing of the project was also a major issue. Haney said that the pipeline providing service to the power plant will be operational by Jan. 1, 2011. That means JEA was depend- ent on the pipeline being in place in time to move forward on the operation of the power plant. To help ensure a timely project, TECO hired Mears to complete a design-build project. “If it is not built on time you literally have a billion dollar power plant there with no fuel,” said John Fluharty, project manager for J.R. Giese Operations, Mears’ sub-consultant that handled engi- neering duties. Fluharty says design-build allowed Mears to drill a pilot hole months in advance to pulling product pipe to ensure the project was feasible. “(TECO) wanted to know that early enough in the process so they would know if they needed to go another direc- tion,” Fluharty said. “(TECO) wanted a true partnership put to-
28

MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Aug 22, 2018

Download

Documents

vunhan
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 1

P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume XXII, Number 3 2714 Cypress Point, Suite D, Missouri City, Texas 77459 E-mail: [email protected] October 1, 2010 www.pipelineintelligence.com

Continued on page 5

MAJOR PROJECTS AND NEWS ITEMS gether so they could work out all the issues related to this special feasibility hole we did in advance.” Design-build is relatively new to the HDD industry, Fluharty said. Design-build offers a subtle but important difference from the typical procedure for HDD projects. In the typical process, a com-pany such as TECO would hire an engineer to develop plans, pro-cure a construction company to implement those plans and then construct the project -- often called design-bid-build. Design-bid-build requires multiple contracts. With design-build, however, a single company is hired to engineer and to build the project, all under a single contract. Susan Hines of the Design-Build Institute of America says utiliz-ing design-bid-build can create contention between the engineer or designer of a project and the company that constructs the pro-ject. She said it creates a disconnect between the two parties which can often turn contentious because of concerns of liability and litigation. For instance, Hines said when the construction company finds changes need to be made to designs during con-struction, it takes paper work and dialogue for the changes to be approved and implemented. “It slows things down a lot,” she said. In the end, design-build projects help to improve two important aspects of any project: money and time. Design build projects cost at least 6% less than design-bid-build projects and are con-structed 12% faster, according to the Design-Build Institute of America. At the same time, the institute reports that design-build projects earned the highest owner satisfaction than other project concepts. “One of the main advantages of design build is the fact that every-one on the design and construction job is on the same side,” Hines said. “They are all sharing in the risks and the rewards of a job well done.” She added: “Owners save money, they save time.”

830-792-5445 www.pipelineskidservice.com

THOUSANDS OF HARDWOOD MATS & SKIDS AVAILABLE

INDUSTRY NEWS (Rosebush, MI) – Mears Group, Inc. com-pleted in April a 7,400-foot Horizontal Directional Drilling bore in Jacksonville, Florida, a design-build project that allows a re-gional energy producer to expand its natural gas pipeline to serve new facilities. To complete the project, Mears drilled a 7,400-foot pilot hole beneath the St. Johns River at a depth of 130 feet below river bottom to install the 16-inch steel pipe. It is an essential link in a 50-mile pipeline that ends at the Jacksonville Electric Author-ity (JEA’s) Greenland Energy Center. Though just 1.4 miles of the 50 mile pipeline, the section under the St. John’s River proved the most daunting in planning stages. “This was the biggest obstacle to go from one side to the other,” said Mark Haney, director of engineering for TECO Peoples Gas, the company that owns the pipeline. Haney said HDD was virtually the only option to install the pipe-line through that area. “Other than HDD, there were no other good options.” But project officials said the timing of the project was also a major issue. Haney said that the pipeline providing service to the power plant will be operational by Jan. 1, 2011. That means JEA was depend-ent on the pipeline being in place in time to move forward on the operation of the power plant. To help ensure a timely project, TECO hired Mears to complete a design-build project. “If it is not built on time you literally have a billion dollar power plant there with no fuel,” said John Fluharty, project manager for J.R. Giese Operations, Mears’ sub-consultant that handled engi-neering duties. Fluharty says design-build allowed Mears to drill a pilot hole months in advance to pulling product pipe to ensure the project was feasible. “(TECO) wanted to know that early enough in the process so they would know if they needed to go another direc-tion,” Fluharty said. “(TECO) wanted a true partnership put to-

Page 2: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume
Page 3: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 3

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Enterprise Products Houston, TX

17 mi. 20” OD natural gas gathering pipeline located in Dimmit county, TX.

Construction 4th quarter 2010

Gulf South Pipeline Houston, TX

Comp. Station

2,370 HP Add additional compressor unit to the existing Airport compressor station located in Mobile county, AL.

Construction 1st quarter 2011

Gulf South Pipeline Houston, TX

Comp. Station

10,311 HP Add additional compressor unit to the existing Clarence compressor station located in Natchitoches Parish, LA.

Construction 3rd quarter 2011

Iroquois Gas Shelton, CT

135 mi. 36” “NYMarc Penn Option” to be located in PA and NY. Also includes one com-pressor station east of the Millennium Pipeline.

Could be 2014

Tennessee Gas Pipeline Houston, TX

7 mi. 30” Looping project located in Bradford and Tioga counties, PA.

Will file with FERC fall 2010 Construction early 2012

New Listings

Page 4: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 4

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

AES Corp. Arlington, VA

88 mi. 30” Mid Atlantic Express pipeline project is part of the Sparrows Point LNG project. The line would run from the LNG facility to near Eagle, PA.

Delayed

Air Products & Chemicals Allentown, PA

180 mi 16” or 20” Project located in Pennsylvania Construction 2011

Algonquin Gas Transmission Boston, MA

32 mi. 1.7 mi.

36” 30”

Take up 24” line and relay with 36” pipe. Also includes new lay of 1.8 mi. 30”. Pro-ject located near Medway & Canton, MA.

Filed w/FERC 1st quarter 2008 Construction could be mid 2010

Algonquin Gas Transmission Boston, MA

2.5 mi.

36” “East-West Expansion” project will con-nect LNG from its east end to markets in New England, NY & New Jersey.

Could be late 2010

Arizona Natural Gas Storage Westport, CT

27 mi. 12”, 16”, 24”

Project located in Pinal Co, AZ Could be early 2012

Bay State Gas South Hadley, MA

11.7 mi. 12” Project runs from Ganby, MA to near North Hampton, MA.

Project to be done in late 2010

Updated Listings (A bold listing indicates a change)

Page 5: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 5

Mears drilled the feasibilitypilot hole for the project in No-vember 2009. Product pipe was pulled in April 2010. Mike Maxwell, Mears’ project superintendent, said the crew drilled from both sides of the St. Johns River and intersected the two holes under the river -- a waterway lined with stately homes and used mostly for rec-reational purposes. A 330,000-pound rig was used for the pilot hole on one side of the river and a 140,000-pound rig was used to drill from the opposite side. Mears utilized its 500,000-pound rig to per-form the reaming and to pull the product pipe through the hole, Maxwell said. Maxwell said the crews reamed the bore to 24-inch diameter and then swabbed the hole before pull-ing the product pipe. The crew drilled through sandy silt be-fore making it to clay for the drill’s running depth. It was fairly easy going; we were able to use a jetting bit all the way through,” he said. Maxwell said the length of the drill com-bined with the unique aspects of the job, made it a satisfying accomplishment. INDUSTRY NEWS (Houston, TX) – UniversalPegasus Inter-national is proud to announce that Jim Slagle has joined the Business Development Team of the Power Division. Jim brings over 20 years expe-rience in relevant power distri-bution and natural gas pipeline engineering and project mana-gement to the UniversalPegasus Team. His career has included roles as marketing account en-gineer, field engineer, project engineer, construction mana-ger, project manager, Director of Project Management, and General Manager. With a Me-chanical Engineering degree and strong leadership skills, Jim has successfully managed diverse energy projects from

start to finish. Craig Pierrotti, Vice President of Business Development, states “We are very pleased to have Jim join our team. As he works closely with Carl Svard out of the Golden, Colorado office, we are con-fident Jim will be a valuable asset to our company as we continue to build our presence in the Po-wer Industry.”

We give our clients a balance of their most important

concerns; quality, safety, price, and schedule. We are a

mainline contractor capable of installing pipeline projects

ranging up to 48” anywhere within the United States.

Contact us for your next pipeline construction project or:

• Anomaly Investigation/Rehabilitation

• Launcher/Receiver & Meter/Regulator Station Construction

• Pipeline Segment Replacement

Welded Construction, L.P.Pipeline Professionals

Since 1966

419.874.3548 Phone

www.welded.com

Value. Welded Construction has built a reputation for providing what our customers want: value.

We’re proud of our reputation – ask those we have worked for.

Page 6: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 6

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Boardwalk Pipeline Houston, TX

99 mi. 36” “The Fayetteville Lateral” will be lo-cated near Coahoma county, MS.

Construction 2011

Boardwalk Pipeline Houston, TX

95 mi. 36” “The Greenville Lateral” will start near Greenville, MS and end near Koscius-kom MS.

Construction 2011

Buckeye Partners Breinigsville, PA

225 or 275 mi.

12” & 16” “The Marcellus Union Pipeline” will run from near Detroit, MI to near the West Virginia & PA border.

Could be 2012 or 2013

Cadeville Gas Storage LLC Houston, TX

1,056’ 7,392’ 13,728’ 4,752’ 33,792’

20” 16” 16” 16” 24”

Project located near Monroe, LA. Construction mid 2011

Calais Pipeline Company Calais, ME

20.7 mi. 36” “Calais Pipeline Project” located near Calasi, ME.

Could be 2012 or 2013

Centerpoint Energy Field Services Shreveport, LA

200 mi. Various diameters

Project to be located in the Hainesville Shale area in Louisiana.

Could be 2011

Centerpoint Energy Field Services Shreveport, LA

Comp. Stations

22,500 HP Project to be located in the Hainesville Shale area in Louisiana.

Could be 2011

Page 7: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 7

Company

Length

Diameter

Location/Description

Approx. Bid Date/Awarded Contractor

Cheniere Energy Partners Houston, TX

330 mi. 42” Project would run from near Dequincy, LA and end near Mobile, AL.

Postponed

Cheniere Pipeline Co. Corpus Christi, TX

24 mi. 48” Corpus Christi Pipeline would connect the proposed Corpus Christi LNG Ter-minal to existing pipelines in San Patri-cio county., TX.

Postponed

Chevron Pipeline Richmond, CA

2.2 mi 16” “Contra Costa Pipeline Project located near Richmond, CA

Awaiting Permits Construction could be 2010-2011

Chevron Pipeline —Richmond, CA Praxair, Inc.—Martinez, CA

7.8 mi 12” “Contra Costa Pipeline Project” Take up and relay . Convert natural gas to hydro-gen line located near Richmond, CA

Awaiting Permits Construction could be 2010-2011

Columbia Gas Transmission Columbia, WV

17 mi. 36” Take up and relay located near Deer-park, NY.

Construction 2011

Crosstex Energy Dallas, TX

15 mi. Undet. Project located in the Barnett Shale area in north Texas. It’s a new gathering system.

Construction 2011

DCP Midstream, LLC Denver, CO M2 Midstream, LLC Houston, TX

150 mi. 20” “Haynesville Connector” will run from western Desoto Parish, LA to several major pipelines that cross in the Delhi, LA area.

Construction 2011

Page 8: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 8

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Dominion Gas Transmission Richmond, VA

25 mi. Undet. “Gathering Enhancement Project” lo-cated in the Marcellus shale area inside Pleasants & Louis counties, WV.

Construction 2012

Dominion Gas Transmission Richmond, VA

9 Comp. Units

7,000 HP Project located in the Marcellus shale area inside Pleasants & Louis counties, WV.

Construction 2012

Dominion Gas Transmission Richmond, VA

54.3 mi. 24” “Appalachian Gateway Project” located in Greene, Washington, Allegheny and West Moreland counties, PA.

Construction late 2011

Dominion Gas Transmission Richmond, WV Williams-Transco Houston, TX

240 mi. Undet. "Keystone Connector" would begin at the terminus of the Rockies Express pipeline in eastern Ohio and end at Williams' Transco Station 195 in southeastern Pennsylvania.

Construction could be 2013

Dominion Gas Transmission Richmond, VA

44 mi. 30” “Appalachian Gateway Project” located in Marshall Co, WV and Greene county, PA.

Construction late 2011

Duke Energy Houston, TX

19 mi. 20” Project to be located in Floyd and Harri-son counties, IN.

Planning stages Will need to be filed w/FERC

Since 1998“An experienced drilling company where standards are continually being set.”

• Successful completion of eight “single-shot” drills over 8,000 feet with the longest being 9,500 feet

• Extensive support with design and constructability issues

• Multi-rigs having pullback capacity ranging from 100,000 lbs. to 660,000 lbs.

• Field Personnel experienced with AutoCAD and capable of making on-site design changes

• One of the most efficient drilling companies in the industry

19319 Highway 101Iowa, LA 70647

Office: (337) 582-3760Fax: (337) 588-4058

www.jancodrilling.com

Janco Directional Drilling

Page 9: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 9

Company

Length

Diameter

Location/Description

Approx. Bid Date/Awarded Contractor

DCP Midstream, LLC Denver, CO

30 mi. 20” Project located in east Texas inside Pa-nola and Rusk counties, TX.

Construction 2010

Dominion Gas Transmission Richmond, VA

6.5 mi. 24” “Appalachian Gateway Project” located in Greene county, PA.

Construction late 2011

Dominion Gas Transmission Richmond, VA

3.5 mi 1160’ 850’

16” 16” 16”

Project to be located at Light burn Plant located in Lewis Co, WV.

Awaiting FERC Approval

Dominion Gas Transmission Richmond, VA

5.2 mi. 20” “Appalachian Gateway Project” located in Kanawha county, WV.

Construction late 2011

Dominion Gas Transmission Richmond, VA

3550 HP 3550 HP

Comp Stat Comp Stat

Light burn Plant will add two compressor units

Awaiting FERC Approval

Dominion Gas Transmission Richmond, VA

Comp. Station

6,130 HP “Appalachian Gateway Project” located at the Burch Ridge Stations in WV.

Construction late 2011

Dominion Gas Transmission Richmond, VA

Comp. Station

3,550 HP “Appalachian Gateway Project” located at The Lewis-Wetzel Station in WV.

Construction late 2011

DCP Midstream, LLC Denver CO

20 mi. 24" Gathering pipeline to be located in the Collbran Valley in western Colorado.

Construction 2010

Page 10: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 10

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Dominion Gas Transmission Richmond, VA

Comp. Station

1,775 HP “Appalachian Gateway Project” located at the Morrison Station in WV.

Construction late 2011

Dominion Gas Transmission Richmond, VA

Comp. Station

4,735 HP “Appalachian Gateway Project” located at the Chelyan Station in WV.

Construction late 2011

Down East Pipeline, LLC Robbinston, ME

30 mi. 30” Project located near Baileyville, ME. Construction 2012

East Cheyenne Gas Storage, LLC Denver, CO

Undet. Dual 24" "The East Cheyenne Storage Project" located near Peetz, CO. Lines will run to Trailblazer & Rockies Express gas lines also includes 19,000 HP of com-pression .

Construction 2011

Eagleford Gathering, LLC (Kinder Morgan & Copano En-ergy Joint Venture) Houston, TX

85 mi. 24” & 30” “Eagle Ford Shale JV” will be located in South Texas within Webb, LaSalle and Dimmit counties.

Construction early to mid 2011

Eastern Shore Natural Gas Dover, DE

8.3 mi. 16” Project located in Lancaster and Chester counties PA.

Waiting on FERC approval Could be 2012

East Tennessee Natural Gas Houston, TX

9.3 mi. 24” “NET Project” “Bristol Discharge” take up & relay located in Washington county, VA and Sullivan county, TN

Will be rebid August 2010 Construction Summer 2011

Page 11: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 11

Company

Length

Diameter

Location/Description

Approx. Bid Date/Awarded Contractor

East Tennessee Natural Gas Houston, TX

8.53 mi. 24” “NET Project” New lay located in Greene and Hawkins counties, TN.

Awards pending

East Tennessee Natural Gas Houston, TX

2.37 mi. 24” “NET Project” “Fordtown Discharge” take up & relay located in Sullivan county, TN

Awards pending

East Tennessee Natural Gas Houston, TX

7.76 mi. 24” “NET Project” “Flatwoods Loop” Loop-ing project located Sullivan, Washing-ton, and Greene counties, TN.

Awards pending

El Paso Energy Colorado Springs, CO

675 mi. 42” “Ruby Pipeline” begins at the Opal Hub in Wyoming and will end at a Malin, Oregon interconnect, near California’s northern border. Construction begins October 2010.

US Pipeline-Houston, TX Rockford Corp.-Hillsboro, OR Precision P/L-Eau Claire, WI Associated Pipeline-Houston, TX

Empire Pipeline (A National Fuel Gas Co.) Williamsville, NY

16 mi 24” “Tioga County Expansion” project runs from Corning, NY to the PA border in Tioga county.

Will file w/FERC August, 2010 Construction April 2011

Enbridge Energy Houston, TX

11 mi. 12” “The Bakken Pipeline” project will be located between Kenaston & Lignite, ND. Take up and relay on the Portal Line. Also includes 2 pump stations.

Construction 2013

Page 12: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 12

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Enbridge Energy Houston, TX

29 mi. 16” “Beaver Lodge Loop” project will be located between the Stanley station & another station near Berthhold, ND.

Could be Spring 2011

Enbridge Energy Houston, TX

330 mi. 36” “East Expansion Project”. Project would run from Southeast TX to MS.

Could be 2011

Enbridge Energy Houston, TX

340 mi. 24” 36” 42”

“The LaCrosse Pipeline” would run from near Carthage, TX to Washington parish, LA.

Construction Phase I—2011 Construction Phase II—2012

Enbridge Energy Houston, TX

36 mi. 24” Project will run from near St. Augustine, TX to Carthage, TX

Construction 2011

Enbridge Energy Houston, TX Exxon/Mobil Houston, TX

768 mi. 30” Project begins near Patoka, IL and runs to near Nederland, TX.

2011

Enbridge Energy Houston, TX

85 mi. 16, 24” Project located near Carthage, TX Construction 2011

Enbridge Energy Houston, TX

26 mi. 12” or 16” “Beaver Lodge Loop” project will be located near Tioga, ND.

Could be Spring 2011

Page 13: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 13

Company

Length

Diameter

Location/Description

Approx. Bid Date/Awarded Contractor

Encore Acquisition Company Fort Worth TX

230 miles 8", 10" CO2 line to be built. Project will begin at the Lost Cabin Plant in WY and ends at the Bear Creek Field in southeastern Montana.

CH2M Hill Denver, CO (Engr) Construction late 2010 or early 2011.

Energy Transfer Dallas, TX

80 mi. 20” Project located in South Texas. Awards pending

Energy Transfer Dallas, TX

80 mi. 30” Project located in East Texas. Out for bids early 2011

Energy Transfer Dallas, TX

10 mi. 16” Project located in the Haynesville area Driver Pipeline Pearland, TX

Energy Transfer Dallas, TX

51 mi. 24” Project located in south TX. Troy Construction Houston, TX

Energy Transfer Dallas, TX

63 mi 20” & 24” Project will run from Shelby Co to Nacog-doches Co, TX

Construction Fall 2010

Enterprise Products Houston, TX

249 mi Undet. The Haynesville extension will begin near the Haynesville shale and end at the Cypress gas pipeline

Construction 2011

Page 14: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 14

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Enterprise Products Houston, TX

270 mi 36” & 42” Project runs from Bosier City, LA to Baton Rouge, LA

Construction 2011

Enterprise Products Houston, TX

80 mi 30” Project located in South Texas Construction 2011

Enterprise Products Houston, TX

26 mi 24” Phase I. Eagle Ford Shale far western reaches.

Construction could be late 2011 or early 2012

Enterpise Products Houston, TX

142 mi. 30” & 36” Phase II. Eagle Ford Shale on the east-ern portion.

Construction could be late 2011 or early 2012

Enterprise Products Houston, TX

64 mi. 30” “Wilson Natural Gas Storage” Project located in Wharton county, TX

Construction could be late 2011 or early 2012

Enterprise Product Houston, TX

127 mi. 12” NGL pipeline located near Mont Bel-vieu.

Construction could be late 2011 or early 2012

Exxon Mobil Houston, TX

88 mi. 24” Project would originate near Nederland and end near Houston, TX.

2011

Page 15: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 15

Company

Length

Diameter

Location/Description

Approx. Bid Date/Awarded Contractor

Florida Gas Transmission Houston, TX

8.9 mi. 24” “Mobile Bay Lateral Expansion Project” in Mobile County, Alabama.

Awards pending Construction early 2011

Florida Power & Light Co. Juno Beach, FL

300 mi. 30” Project will run from Palm Beach county, FL to Bradford county, FL.

Postponed

Holly Energy Partners Dallas, TX Sinclair Transportation Salt Lake City, UT

400 mi. 12” Petroleum products line to run from Salt Lake City and Las Vegas, NV. Construc-tion to be done in 2011.

Quanta Services Houston, TX

Inergy Midstream, LLC Kansas City, MO

43 mi. 36” "The MARC I Hub Line Project" is to move gas bi-directionally between the South Lateral of Inergy's Stagecoach Gas Storage Facility, Tennessee Gas Pipeline Company's 300 Line near its compressor station 319, and Transco's Leidy Line near its compressor station 517. Also includes compression and interconnect facilities.

Construction Summer 2011

Iroquois Gas Shelton, CT

21.5 mi. 24” “Brookhaven Lateral” project to run from Commack, NY to Yaphank, NY.

Fall 2010

Iriquois Gas Transmission Shelton, CT

66 mi. 36” NYMARC Pipeline to be located in the New York and New England areas.

Could be 2014

Page 16: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 16

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Kern River Gas Transmission Salt Lake City, UT

28 mi. 36” "Apex Expansion". Wasatch Looping project located in Morgan, Davis and Salt Lake counties, UT. Project also includes construction of a new compres-sor station near Mildford, UT and modifications to existing stations in southeast WY, Elberta & Fillmore, UT & northeast of Las Vegas.

Construction early 2011 Barnard Construction Bozeman, MT

Kern River Gas Transmission Slat Lake City, UT

Comp Station

HP Undet. Muddy Creek compressor station upgrade located in Lincoln Co., WY also includes meter station construction.

Construction 2010

Kinder Hawk Houston, TX

10 mi. 16” Project located in the Haynesville area. Driver Pipeline Pearland, TX

Kinder Morgan Houston, TX

230 mi. 16” “Marcellus Lateral Pipeline” would run from the Marcellus Shale Basin in WV to near Toledo, OH.

Construction summer 2011

Laser Northeast Gas Gathering Houston, TX

30 mi. 16” Project will run through Susquehanna and Windsor counties PA also runs into Broome county, NY Will tie into the Millennium pipeline in NY.

Construction 2012

Page 17: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 17

Company

Length

Diameter

Location/Description

Approx. Bid Date/Awarded Contractor

Magnum Gas Storage, LLC Salt lake City, UT

61.5 mi 36” Project to be located in Millard, Juab and Utah counties, UT

Could be 2012

Magnum Gas Storage, LLC Salt lake City, UT

18,800 HP Comp Stat Project included with the 61.5 mi 36” in Utah.

Could be 2012

Marathon Pipe Line Co., LLC Findlay, OH

29 mi. 24” "The Detroit Heavy Oil Upgrade Pro-ject" will be located in Monroe and Wayne Counties, MI.

Out for bids late 2011

Meritage Midstream Houston, TX Laredo Energy Houston, TX

48 mi. 16” High pressure gathering system in Webb county, Texas. This is located in the Eagle Ford Shale.

Construction 2011 or 2012

National Fuel Gas Supply Williamsville, NY

32 mi. 30” Phase I. Project to run through Elk, Cameron, & Clinton counties, PA

Construction 2011

National Fuel Gas Company Williamsville, NY

50 mi 30” Phase II. Project will run through Clearfield, Jefferson, & Elk counties PA.

Construction 2012

National Fuel Supply Buffalo, NY

19 mi. 20” Take up and relay located in Greene & Washington counties, PA.

Filed w/FERC April, 2010 Awaiting FERC approval

National Fuel Gas Co. Buffalo, NY

324 mi. 42” “West to East Project” would run from Southeastern Ohio to Corning.

Delayed Could be 2011 or 2012

SPECIALTY POLYMER COATINGS, INC.INNOVATION IS OUR SPECIALTY

CHECK OUT OUR WEB PAGE AT: WWW.SPC-NET.COMCANADA: (604) 514-9711 USA: (281) 332-6948 UK: (44) 208-337-4953

On site and mill applied epoxy and urethane coatings for:

Girthwelds

Horizontal Directional Drills

Rehabilitation of existing pipelines

High Temperature Pipelines

Specialty Coatings Available For:High Temperature Applications For InserviceApplications up to 150°C (302°F)

Damp Substrate Applications

Cold Weather Cure Applications

General Purpose Epoxies (No Abrasive Blast Requirement)

Page 18: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 18

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

National Fuel Supply Buffalo, NY

2 mi. 20” Take up and relay located near Buffalo Township, PA.

Filed w/FERC April, 2010 Construction April, 2011

National Fuel Supply Buffalo, NY

Comp. Station

5,000 HP Project to be located near Buffalo Town-ship, PA.

Filed w/FERC April, 2010 Construction April, 2011

Natural Gas Pipeline Company of America Houston, TX

226 mi. 42” "The NGPL Express" will run from Harper, IA to the Joliet hub area.

Construction 2011

Nisource Gas Transmission Houston, TX

82 mi. Undet. “New Penn Pipeline” would begin at the Leidy Storage facility in PA and interconnect with Millennium Pipeline in Steuben Co., NY.

Could be late 2011 or early 2012

Northern Border Houston, TX

8.9 mi 16” The Princeton Lateral Project is located in Bureau Co, IL

Filed Environmental Assessment With FERC in Early 2010

Northwest Pipeline Group Salt Lake City, UT

157 mi. 30” or 36” “Blue Bridge Pipeline Project” will run from Washington into Oregon.

Construction could be Spring 2012

Oneok Partners Tulsa, OK

525 mi. 12” “Bakken Pipeliine” will start at the Bakken Shale in North Dakota and tie into the Overland Pass Pi;peline near the Wyoming and Colorado border.

Construction will begin mid 2012

Page 19: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 19

Company

Length

Diameter

Location/Description

Approx. Bid Date/Awarded Contractor

Oneok Partners Tulsa, OK

7 Pump Stations

— Project located on existing Sterling I natural gas liquids line. Line runs from Medford, OK to Mont Belvieu, TX

Construction late 2010 or early 2011

Orbit Gas Storage, Inc. Henderson, KY

22 mi. Undet. Project located near Madisonville, KY. On-hold

Orbit Gas Storage, Inc. Henderson, KY

Comp. Station

5,400 HP New compressor station to be built near Rabbit Ridge, KY.

On-hold

Ozark Gas Transmission, LLC Tulsa, OK

160 mi. 36” “Tenark P/L Project” to begin in White Co, AR & end near Dyersburg, TN.

Construction could be 4th Quarter 2010

Pacific Gas & Electric Portland, OR Northwest Pipeline Salt Lake City, UT

231 mi. 36” “The Pacific Connector” project starts near Jordan Cove, OR and runs to Ma-lin, OR, southeast of Klamath Falls, OR

Delayed Construction 2011

Palomar Gas Transmission, LLC Portland, OR

110 mi. 110 mi.

36” 36”

Phase 1 & 2 will start at the existing GTN line in north-central OR near Molallu, OR. Phase II may be cancelled.

Construction could be 2011

Perryville Gas Storage, LLC Houston, TX

2.7 mi 11.7 mi

24” 36”

Crownville Salt Dome Storage Project located near Delhi, LA

Construction could be late 2011

Page 20: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 20

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Perryville Gas Storage, LLC Houston, TX

9500 HP Comp Stat Crownville Lateral Project located near Delhi, LA

Construction could be late 2011

Piedmont Natural Gas Charlotte, NC

38 mi 20” Project located in Wayne County, NC. Construction could be 2012

Piedmont Natural Gas Charlotte NC

105 mi. 24” Cardinal Pipeline located near Raleigh, NC.

Construction could be Spring 2011

Piedmont Natural Gas Charlotte, NC

133 mi 20” Project located near Wilmington, NC also includes compressor station work.

Out for bids late 2010 Construction 2011

Point Comfort Pipeline Point Comfort, TX

27.1 mi. 36” Project starts near Point Comfort, TX and ends near Edna, TX

Pending approval of LNG Facility - On-hold

Praxair Martinez, CA

13.5 mi. 12" Project located near Martinez and Rich-mond, CA.

Delayed

Questar Pipeline Salt Lake City

23 mi. 24" Expansion project to extend Main Line 104 from the Green River Block Valve to Fidlar Comp. Stat. Also includes addi-tional compression at existing station.

Could be 2011

Page 21: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 21

Company

Length

Diameter

Location/Description

Approx. Bid Date/Awarded Contractor

Questar Pipeline Salt Lake City, UT

71 mi. 24” “Bonanza Pipeline” to run from Fidleur to the White River Hub at Meeker.

Could be mid 2010 Construction

Questar Overthrust Pipeline Co. Salt Lake City, UT Alliance Pipeline- Calgary, AL

800 mi. 42” “Rockies Alliance Pipeline” would run from near Wamsutter, WY to the Emer-son trading hub on the Minnesota-Canada border.

Could be late 2011 or early 2012

Regency Energy Dallas, TX

15 mi. 12” Project located near Cotulla, TX Awards pending

Rockies Express, LLC Houston, TX

375 mi. 42” “Northeast Express Project” will begin near Clarington, OH and end near Princeton, NJ.

2011

Seacoast Gas Transmission (TECO Energy) Tampa, FL

50 mi. Undet. “Seacoast Project” would connect Florida Gas Transmission & Southern Natural Gas Transmission pipelines to Jackson Electric Authority’s proposed power plant located near Jacksonville, FL.

Could be 2011

Sempra Energy Houston, TX

70 mi. 36” or 42” Port Arthur Pipeline project to connect LNG terminals to the interstate p/l system in LA.

Postponed

Page 22: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 22

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Sempra Energy Houston, TX

12 mi. 24” Project located near Hattisburg, MS. Pro-ject start delayed until April, 2010.

Delayed

Sonat Birmingham, AL

20 mi. 36” Phase II. SSE III project locted in Lauderdale, MS.

Awards pending Construction 2011

Southern Star Central Gas Owensboro, KY

346 mi. 36” “Highland Trails Pipeline” project would connect the developing Fayette-ville Shale production Basin in Central Arkansasas to Kinder Morgan’s Rockies Express pipeline in Audrain Co, MO.

Could be 2012

Spectra Energy Houston, TX

16 mi 5 mi.

30” or 36” 30” or 36”

Take up and relay 5 miles and add 16 miles of new pipe located near Linden, NJ and Jersey City, NJ.

Construction 2013

St. Lawrence Gas Massena, NY ( An Enbridge Co.)

48 mi 24” Project will run from Stockholm, NY to Chateaugay, NY

Construction 2011 or 2012

Tennessee Gas Pipeline Houston, TX

128 mi. 30” Project will be located in Bradford, Pike, Potter, and Susquehanna counties PA as well as Passaie and Sussex Ctys NJ.

Under FERC Environmental Re-view Could be 2011

Spectra Energy Houston, TX

525’ 24” Take-up & Relay located in Gibson county, IN.

Awards Pending

Page 23: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 23

Company

Length

Diameter

Location/Description

Approx. Bid Date/Awarded Contractor

Tennessee Gas Pipeline Co. Houston, TX

40 mi. 30” “Northeast Expansion Project” located in PA and MA.

Construction 2011

Tennessee Gas Pipeline Company Houston, TX

Comp Station

46,000 HP “300 Line Expansion” will upgrade 4 existing stations in PA. & NJ & build 2 new stations in northwestern PA.

File w/FERC May 2009 Could be 2010/11 Construction

Tennessee Gas Pipeline Co. Houston, TX Equitable Resources Houston, TX

471 mi. 36” “The Northeast Passage Project” will begin at Clarington, OH and end near Pleasant Valley, NY

Delayed Could be 2012-2013

Texas Eastern Transmission Houston, TX

1.8 mi. 4.7 mi. 11.7 mi. 4 mi.

36” 36” 36” 36”

“Team 2012 Project” will be located in Greene, Fayette, Franklin & Adams county PA. Also includes 26,000 HP upgrades at existing compressor sta-tions.

Construction 2012

Texas Eastern Transmission Houston, TX

8.4 mi. 16” “Hot Springs Lateral” located near Mal-vern, AR.

Construction mid 2011

Texas Eastern Transmission Houston, TX

11 mi. 30” “Logan Lateral” project located in Dela-ware Co. PA and Gloucester Co. NJ.

Construction mid 2011

Page 24: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 24

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

TransCanada Calgary, Alberta Conoco Phillips Houston, TX

50 mi. 36” Keystone XL Pipeline Project will split at Liberty TX and run to Houston, TX part of the 478mi project.

Awards pending - Delayed Construction July 2011

TransCanada Calgary, Alberta Conoco Phillips-Houston, TX

478 mi. 36” Keystone XL Pipeline Project will start near Cushing and end near Port Ar-thur, TX. To be done in 6 Spds.

Awards pending - Delayed Construction July 2011

Trunkline Gas Co. Houston, TX

16 mi. 36” or 42” “The Vector Connector Project” will run from Elkhart, IN to St. Joseph Co., MI. Will also include a new Comp. Station.

Postponed

Ultra Resources, Inc. Houston, TX

42 mi. 6” Project located near LaBarge, WY. Could be 2010 or 2011

Venoco, Inc. Carpinteria, CA

8.5 mi. Undet. Project would run from Venoco's proc-essing facility near Goleta, CA to Las Flores Canyon tying into the existing into All American Pipeline.

Could be 2012

Williams Gas P/L - Houston, TX Pugent Sound - Bellevue, WA

119 mi. 30” Blue Bridge Pipeline project will begin in Oregon and end near Chehalis, WA.

Construction 2011

Page 25: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 25

Company

Length

Diameter

Location/Description

Approx. Bid Date/Awarded Contractor

Williams Northwest Salt Lake City, UT

145 mi. 24” “Opal Market Link” project would be-gin at Utah’s Uinta Basin and end at the Opal Hub in Wyoming.

Open season process Construction could be 2013

Williams-Northwest Houston, TX

33 mi. 16”, 24” “Greasewood Lateral” located near San Springs, CO.

Bids 2011

Williams-Northwest Houston, TX

16 mi. 30” “Sundance Trail Expansion” will begin near Green River, WY and end near Muddy Creek, WY.

Price/Gregory Houston, TX

Williams Pipeline Tulsa, OK

28 mi. 20” Project located in Luzerne county, PA. Construction could be summer 2010

Williams-Transco Houston, TX

15.5 mi. 26” “Pascagoula Expansion Project” located in Mobile County, AL.

Construction April 2011

Williams-Transco Houston, TX

Comp. Station

3,025 HP Project located in Coweta county, PA. This is a compressor upgrade.

Construction 2011

Williams-Transco Houston, TX

250 mi. 30” “NE Supply Project” would run from York county, PA to Monroe county, OH.

Could be 2012

Page 26: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 26

Company

Length

Diameter

Location/Description

Approx. Bid Date/ Awarded Contractor

Williams-Transco Houston, TX

19 mi. 42” “The Sentinel Expansion.” Looping project located in Luzerne, Monroe, North Hampton & Chester counties, PA. & also in Summerset Co., NJ.

Construction 2011

Williams-Transco Houston, TX

40 mi. 36” The Pascagoula Expansion Project lo-cated in Butler County, AL.

Construction early 2011

Williams-Transco Houston, TX TransCanada Corp. Calgary, AB

601 mi. 42” “Sunstone Pipeline” to run from the Opal Hub in WY to areas near North-ern NV, Northern CA and parts of OR.

Could be 2011 or 2012

Williams-Transco Houston, TX

Comp Station

8180 HP Mobile Bay South II Expansion Project located at station 85 near Butler, AL also includes facility modifications at station 83

Could be early 2011

Williams-Transco Houston, TX

12.5 mi. 36” Project located near LaGrange, GA. Construction 2011

Williams-Transco Houston, TX

1.4 mi. 1.3 mi.

42” 42”

Mid Atlantic Connection located in Virginia will also include compressor station upgrades.

Will file w/FERC Could be late 2011 or 2012

Page 27: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Pipeline Intelligence Report, October 1, 2010 – 27

Company

Length

Diameter

Location/Description

Approx. Bid Date/Awarded Contractor

Williams-Transco Houston, TX

3.4 mi 42” “Mid South Expansion" looping project to be located in Rockford Co, AL.

Will file w/FERC in Oct 2010 Out For bids early 2011 Construction Spring 2011

Williams Transco Houston, TX

6.9 mi 42” "Mid South Expansion" looping project to be located in Randolph Co, AL.

Will file w/FERC in Oct 2010 Out For bids early 2011 Construction Spring 2011

Williams Transco Houston, TX

3.35 mi 42” "Mid South Expansion" looping project to be located in Davidson Co, NC.

Will file w/FERC in Oct 2010 Out For bids early 2011 Construction Spring 2011

Williams Transco Houston, TX

5.94 mi 42" “Mid South Expansion" looping project to be located in Gastonia Co, NC.

Will file w/FERC in Oct 2010 Out For bids early 2011 Construction Spring 2011

Williams Transco Houston, TX

2.91 mi 42" “Mid South Expansion" looping project to be located in Rowan Co, NC.

Will file w/FERC in Oct 2010 Out For bids early 2011 Construction Spring 2011

Williston Basin Interstate P/L Co. Bismark, ND

100 mi. 16” “The Bakken Pipeline Project starts at existing system near Tioga, ND & ends near Antler, ND.

Could be Spring 2011

Yankee Gas Services Company Berlin, CT

16 mi. 16” Project located near Cheshire and Wal-lingford, CT.

Awards pending

Page 28: MAJOR PROJECTS AND NEWS ITEMS - Pipeline … · Pipeline Intelligence Report, October 1, 2010 – 1 P.O. Box 2726 Sugar Land, Texas 77487-2726 (281) 499-3131 FAX (281) 499-3223 Volume

Order Form

Pipeline Intelligence Report – Master subscription $300 per year for 24 issues. Additional subscriptions for same Company available to any address $150 per year for 24 issues. 2010 Pipeline Intelligence Directory $75 plus S & H $60 for each additional copy. 2010 Pipeline Intelligence Directory CD in Excel format: Pipeline Company, Contractor or Supplier Section – $150 per section or $400 for all three. ** Tax: All orders in Texas are subject to 8.25 % state sales tax. Method of payment: A check for the total amount is enclosed. Charge to my: MasterCard Visa Card Number Exp. Date: Mo. Yr.

Signature

Bill me. Purchase Order No: (if required)

Name Title

Company

Address

City State Zip Phone number ( )

-----------------------------------------------------------------------------------------------------------------------------------------------------------------

FIRST CLASS