Magma Construction Company Capital Budgeting Project
14
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Magma Construction Company

Magma Construction CompanyCapital Budgeting Project

Page 2: Magma Construction Company

ProjectProject:MODERN TOWNSHIPMODERN TOWNSHIP

•LOCATION – GANDHINAGARLOCATION – GANDHINAGAR• 500 acre of space.500 acre of space.

• Education and medical facilities at a small Education and medical facilities at a small distance .distance .

•Eco friendly atmosphere.Eco friendly atmosphere.

Page 3: Magma Construction Company
Page 4: Magma Construction Company

Capital (source)

•50 % of the capital is sourced through bank loan at an interest of 10% p.a.•The rest of the capital is sourced in the following manner – 1)25% - unsecured loans 2)25% - personal wealth

Page 5: Magma Construction Company

Construction Cost Estimation

The construction process is outsourced through a company named PMC . All of the projects are sub projects of the township project and are carried out simultaneously . The following is the estimate of construction costs incurred in these sub projects.

Page 6: Magma Construction Company

Township project

Project A Project B Project C

Page 7: Magma Construction Company

Project A (Flats)(25crore*5)Project A (Flats)(25crore*5)

•Construction cost – Construction cost – 1) Raw material costs – 10 crore1) Raw material costs – 10 crore 2) Labor costs – 1 crore 2) Labor costs – 1 crore -skilled -skilled -unskilled-unskilled 3) Employee costs – 10 crore3) Employee costs – 10 crore -Civil Engineers-Civil Engineers -Architectural engineers(1%)-Architectural engineers(1%) -Structural engineers(1%)-Structural engineers(1%)•Profit share of 5% - 1.25 croreProfit share of 5% - 1.25 crore•Provision for Accidental damage and loss – 2.75 croreProvision for Accidental damage and loss – 2.75 crore

Page 8: Magma Construction Company

Project B (Hospital)(80 crore)Project B (Hospital)(80 crore)

•Construction cost – 1) Raw material costs – 30 crore 2) Labor costs – 5 crore -skilled -unskilled 3) Employee costs – 30 crore -Civil Engineers -Architectural engineers(1%) -Structural engineers(1%)•Profit share of 10% - 8 crore •Provision for Accidental damage and loss – 7 crore

Page 9: Magma Construction Company

Project C (School)(60 crore)Project C (School)(60 crore)

•Construction cost – 1) Raw material costs – 20 crore 2) Labor costs – 10 crore -skilled -unskilled 3) Employee costs – 20 crore -Civil Engineers -Architectural engineers(1%) -Structural engineers(1%)•Profit share of 10% - 6 crore •Provision for Accidental damage and loss – 4 crore

Page 10: Magma Construction Company

Project D(Garden Museum) ( 4 crore)Project D(Garden Museum) ( 4 crore)

•Construction cost – 1) Raw material costs – 25 lacs 2) Labor costs – 50 lacs -skilled -unskilled 3) Employee costs – 2 crores -Civil Engineers -Architectural engineers(1%) -Structural engineers(1%)•Profit share of 25 lacs •Provision for Accidental damage and loss – 1 crore

Page 11: Magma Construction Company

Project Planning period

Township project

12 months

Construction planning

(2 months)

Execution and Finishing Plan

(2 months)

Approvals and Permissions(8 months)

Page 12: Magma Construction Company

Debt Repayment Target

Repayment of Secured loan (Total Interest after 3 years = 31.1%)

Repayment of Unsecured loan

Increase cash flows to reduce the period of time of repayment.

Page 13: Magma Construction Company

Revenue estimation

Revenue from sale of school = 50 crore.

Revenue from sale of Hospital = 100 crore.

Revenue from sale of museum tickets = 2 crore

Revenue from sale of high rise apartments = R.s. 125 crore (25*5)

Page 14: Magma Construction Company

Repayment cycle•Total project cost = R.s 277 crore •Total insurance = R.s. 150 crore•Sum total = R.s. 427 crore•Sum total debt = R.s. 450 (50% secured, 25% unsecured, 25% personal wealth )•Gross Income = 150 crore p.a.•Total amount of secured loan = R.s. 225 crore.•Total interest on loan after execution time of 3 years = 31.1% = R.s. 299.48 crore•Repayment period = Project Cost /Gross income = 277+299.48/150 = 3.84 years (round off to 4)