Madagascar Water Supply Project: TAC Review Summary May 14, 2013
Feb 23, 2016
Madagascar Water Supply Project: TAC Review
SummaryMay 14, 2013
Ambalona, Madagascar
Population: ~800Households: ~160
~125 m
Project Objective:Domestic Water Supply
Project History
May, 2008: Initial Visit December, 2009: Test Well
Installation March, 2012: Follow-Up Assessment
• Status of test wells• Feasibility of a gravity flow system
Test Wells
May, 2008: Initial Visit December, 2009: Well Installation March, 2012: Follow-Up Assessment
Test Well Status
Village Well Several breaks in
service Low yield/sediment
School Well• Working since
installation• Serves entire village
Gravity Flow
Springs nearby
Technically feasible
High capital cost
Sustainable?
Project Process
October, 2012: Alternatives Analysis Report
December, 2012: Preliminary Design Report
January, 2013: Pre-Implementation Report
February, 2013: TAC Review
Alternatives Analysis
Gravity Flow
Wells, Solar Powered Pumps & Elevated
Water Tanks
Wells & Hand Pumps
BioSand Filters
Preliminary Design
Demand Analysis: For this population, five communal water supply points are required to meet basic water needs – 20 l/capita-day
Four new wells India MK III pumps ≥100-mm casing (allowing
for later installation of solar pumps, if desired)
Preliminary Design
Hydrogeology: Based on test well logs and slug tests, assumed unconfined conditions, Kh = 2-5×10-5 cm/s
Depth-to-water varies seasonally: ~3-7 mbgs
Porosity, anisotropy, etc. estimated
Modeled multiple well scenarios with AQTESOLV
Preliminary Design
TD: 39.5 mbgs Screened Interval: 8 –
38 mbgs Sump: 38 – 39.5 mbgs Casing: 100-mm SCH
80 PVC Borehole: 40 mbgs Cement grout surface
seal: 0 – 6 mbgs Washed sand filter
pack: 6 – 40 mbgs
Preliminary Design
India Mk II/III pumps
Sloping concrete apron
Protective casing
Fenced enclosure
Preliminary Design
Well siting criteria:• Locations decided with community• Provide reasonable access• At least 30 m from human waste disposal• At least 15 m from food/wastewater disposal• At least 30 m from animal housing• Outside areas susceptible to flooding
Solicited bids from three drilling contractors Phased implementation: build two now,
monitor, build remainder next year
TAC ReviewContext
Follows initial technical approval of Pre-Implementation Report by Project Manager
Requires short (20 minute) webinar presentation to one of the regional Technical Advisory Committees (not necessarily home region TAC)
TAC reviews Pre-Implemetation Report, HASP and slides prior to presentation
Q&A session follows presentation More than one project may be on the agenda
TAC Review:Presentation Structure
24 Slides Country Background: 3 Slides (12.5%) Community Background: 3 Slides (12.5%) Project Overview, Including Objectives,
History, stakeholders: 6 Slides (25%) Alternatives Analysis: 1 Slide (4%) Preliminary Design: 11 Slides (46%)
TAC Review:Q&A
12 Questions Country Background: 0 Questions(0%) Community Background: 0 Questions(0%) Project Overview, Including Objectives,
History, stakeholders: 0 Questions(0%) Alternatives Analysis: 0 Questions(0%) Preliminary Design: 12 Questions(100%)
TAC ReviewQuestions/Comments
Why does the well have a sump? What is the minimum/maximum grain size of
the filter pack? Has the depth of the village test well been
measured to determine is it has been filling up with sediment?
Will centralizers be used to keep the casing in the center of the borehole?
TAC ReviewQuestions/Comments
The preliminary design is for 39 metre wells, compared to 18 metres for the test wells. If the driller is unable to go to 39 mbgs, it may be possible to get sufficient yield from a shallower well.
What water quality testing has been done? The pH of well water is in the range 4.7 – 5.4.
How will this be addressed? The Denver wiki shows a high coliform count
for the village well.
TAC ReviewQuestions/Comments
The design is based on demand of 20 l/capita-day. This is too low.
Some wells are telescoped (i.e., borehole diameter is wider near the surface and narrows with depth). Was this considered?
The setbacks specify 15 metres from the wellhead to food/wastewater disposal areas. This should be 30 metres.
TAC ReviewResponse
If TAC questions and comments are not resolved during the Q&A following the presentation, the project may be put on hold until these issues are they are.
Don’t panic! This is perfectly normal. All questions and comments to be resolved are
provided in writing. Responses are submitted in the a Form 809
report – Response to TAC Comments Can be an iterative process
TAC ReviewResponse
All questions and comments must be addressed, but acceptable responses may vary from compliance to dispute, as long as they are technically sound.
Examples:• A more comprehensive water quality monitoring
program will be implemented; 30 metre setbacks will be introduced
• The 20 l/capita-day design basis was retained; telescoped well was not necessary or feasible
TAC ReviewConclusion
The Madagascar project submitted responses two weeks after being put on hold.
The TAC gave techinical approval ten days later
The project will be traveling to Madagascar this June to install two new wells in Ambalona
Final Note
Wiki as a means to preserve and share TAC experiences?