LANDWARNET 2011 UNCLASSIFIED UNCLASSIFIED LandWarNet 2011 LWN Track 2 Session 3 Updated 22 Aug 2011 1
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED LandWarNet 2011 LWN Track 2 Session 3 Updated 22 Aug 2011 1
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED LandWarNet 2011 2
• Enterprise Initiatives Overview & Army Baseline IT Services (ABITS) • COL Gary Langston, CIO/G-6
• I3MP Processes • Ms. Kendra Acord, NETCOM
• I3MP – Program Overview • LTC David Thompson, Product Manager – I3MP
• Wrap-up • COL Gary Langston, CIO/G-6
LWN Track 2 Session 3 Updated 22 Aug 2011
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED 3 LandWarNet 2011
The Network of 2020 Imperatives are A Single, Secure, Standards-Based
Environment; Enable Global Collaboration; Ensure Access at the Point of
Need; and Most Importantly the Network is Capable, Reliable and Trusted
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED LandWarNet 2011 4 2011-08-11T14:45:00Z 4
HTTP:CIOG6.ARMY.MIL
Network
Imperatives
FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 Fiscal
Year
Capability Sets
19-20 15-16 17-18 13-14 11-12
Access at
the Point
of Need
Classroom
2020 Wireless TOCs
Thin Client/Virtual Desktop Environment
COTM A4A (Digital Apps to the Soldiers)
Army Data Center Consolidation Phase I A Single,
Secure,
Standards-
Based
Network
COE
Infrastructure E2E Architecture
COE Implementation (Tech Stds)
Security
EoIP
Compliance with IT Acquisition Policy
Unified Communications (VoIP/VSoIP, chat, presence and awareness, SIP voice and video
(VoIP/VSoIP +), desktop sharing, & replacement of TDM voice switches)
Army Data Center Consolidation Phase II ?
Enable
Global
Collaboration Share Point
Enterprise
Unified Comms and Collaboration/I3MP
Capable,
Reliable,
and
Trusted
Bandwidth Available
Spectrum Allocation
ITAM
Network Management (ESMS/Remedy)
NetOps Tools (REM/Retina, Spectrum, SCCM, Arcsight)
HBSS
Self Monitoring,
Self Healing Network
"Big data" and Extreme Information
Processing and Management
Cyber Resiliency
Speech & Gesture Recognition
3-D Printing
Predictive & Social Analytics
Context-Enriched
Services
Thick Client/ Hosted Virtual Desktops
?????
N E T W
O R K
2 0 2 0
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
1. Long Haul Communications provides Installation connect ion to the network through the Global Information Grid (GIG)
2. DISA Points of Presence (PoP) provide GIG connectivity to Army Installations
3. Information Assurance provides Intrusion Protection Systems at these POPs to protect the Installation networks
4. The Installation Information Infrastructure Modernization Program (I3MP) extends bandwidth/services via Campus Area Network (CAN)
5. Military Construction funds the connectivity of new facilities to the CAN
6. C4IM Services are provided by Network Enterprise Centers (NECs) who plan for and execute operations and maintenance of the Campus Area Network and IT within buildings
7. Tenants provide end user building infrastructure, end user devices and mission specific capabilities
•BASECOM (Service 15) •INFORMATION ASSURANCE (Service 18) •AUTOMATION (Service 19)
End User Buildings
RESERVE GUARD
Campus Area Network
1
3 POP 2
6
5
4
Operating Forces
7
Installation Infrastructure (I3MP)
Global Info Grid/Defense
Information Systems Network (DISN)
Data Center
Data Center
Data Center
Long Haul Communications
Information Assurance POP
2
C4IM Services
5
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Army C4IM Services List v3.0 for FY12
6
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
C4IM Services List signed memo CIO/G-6 and ACSIM 28 July 2011
7
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Army LWN Services Catalog
8
https://www.itmetrics.hua.army.mil/lwncatalog4/
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
“Transforming How we Deliver and Manage IT Services”
Army Baseline IT Services (ABITS)
9 LandWarNet 2011
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Problem Statement:
Currently there are multiple service providers across the Army supporting common IT services which includes communications systems and systems support (15), information assurance (18) and automation (19). The quality and timeliness of the services provided varies considerably from one location, command or activity to the next without apparent consideration for mission.
Objective:
• Gain an agreement from the Army on the cost to deliver a C4IM service (seat cost) to enable resource transfers IAW implementation plan and comparison with other delivery alternatives. • Identify changes to C4IM services baseline (3.0) that enable “plug and play” capability and/or enhance network defense.
Decide on prioritization of operational gaps to support CBA objectives
10 LandWarNet 2011
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
NEC
STAFFING
MODEL
NEC
SOFTWARE
AND
EQUIPMENT
SUSTAINMENT
MODEL
NEC SERVICES
MODEL
DATA
Enterprise Services
“Army Seat
Management Model”
(Executive Users and
Non-Executive Users)
with supporting
analytics developed
thru the CBA Process
11
Output will be POM14-18 Requirements supported
by approved CBAs and defendable to Army
Leadership and the II PEG
Cost Benefit Analysis Scope
11 LandWarNet 2011
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED 12 LandWarNet 2011
• IT Metrics Working Group (ongoing this week)
• I3MP Operational Planning Team (next briefer)
• Enterprise Guidance Board, Engineering Review Board, Operations Oversight Board – the Army’s most senior IT Governance Forums
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
COL Gary Langston Chief, Info Infrastructure Integration (SAIS-AOI)
703-545-1385
DSN 312-865-1385
Ms Victoria Strom Deputy, Info Infrastructure Integration (SAIS-AOI)
571-256-8960
DSN 312-260-8960
13
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Installation Information Infrastructure
Modernization Program Processes
Ms. Kendra Acord
14
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Overview of I3MP
Dependencies to Other Enterprise Efforts
Past, Present, and Future of the Requirements Process
On-going Initiatives
Way Ahead
15
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
I3MP modernizes the information infrastructure at Army installations (CONUS/Pacific/Europe/SWA) worldwide
I3MP Scope: • Installation Campus Area Network (ICAN)
NIPR/SIPR Outside Plant Data Network (Core, Distribution, and Access Layers)
• Top Level Architecture (TLA) T-NOSC managed security stack located between DISN POP and ICAN Includes Army Security Router, Data Firewall, and Network Intrusion Prevention System Will include Voice/Video Security stack as VoIP is proliferated throughout Army
• Voice Traditional Time Division Multiplex Defense Red Switch Network Unified Communication and Collaboration (UC&C) infrastructure Voice over Secure Internet Protocol (VoSIP)
$2B in funding executed over the past 10 years Current funding supports less than 20% of known and validated
requirements to modernize information infrastructure through fiscal year 2016 • Validated requirements does not include the additional funding required to O&M
equipment after the provided 2-year warranty expires
16
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
• Enterprise Email
• Army Baseline IT Services (ABITS)
• Army Data Center Consolidation
• Unified Communications and Collaboration
17
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
CIO/G6 published the Installation Sequence List (ISL)
I3MP negotiated requirements with individual NECs (DOIMs)
Based upon requirements identified by the NEC, I3MP developed an Engineering Plan
Unanticipated mission changes or unknown site conditions frequently led to Engineering Change Proposals that can cost 2x as much had the work been identified upfront
18
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
NETCOM,CIO/G6, and PM roles in the I3MP Requirements Process are established in March, 2010 •NETCOM – establish requirements and priorities for I3MP
execution • PM – Interact with NETCOM and CIO/G6 to align I3MP efforts
with Enterprise Initiatives •CIO/G6 – Maintain MDEP and ensure requirements and priorities
established by NETCOM are consistent with overarching Army initiatives
Roles and responsibilities are being formalized •CIO/G6 has incorporated verbiage into Draft AR 25-1, DA PAM
25-1-1, and AR 25-XX • Further refinement may be needed as Army Cyber roles and
responsibilities evolve.
19
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Execution of roles and processes needs further refinement •Effort must extend beyond NETCOM, CIO/G6, and PM I3MP
to include all stakeholders
Additional challenges include: •Lack of institutional knowledge •Cultural shift associated with new process •Communication of expectations, timelines, etc.
I3MP OPT is established •Order to establish OPT was released 15 June 2011 •Goal is to institute a process to identify, prioritize, and
execute I3MP efforts, aligning the program with Enterprise Initiatives
20
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Codified in the update to AR 25-1, DA PAM 25-1-1, and AR 25-XX
Pri
ori
tize
d
Req
uir
emen
tsP
rio
riti
zed
R
equ
irem
ents
Pri
ori
tize
d
Req
uir
emen
ts
Pri
ori
tize
d
Req
uir
emen
ts
Pri
ori
tize
d
Req
uir
emen
tsP
rio
riti
zed
R
equ
irem
ents
Iden
tifi
edR
equ
irem
ents
I3MP Requirements Generation
NECs
ProponentArmy
CYBER/NETCOM
HQDA I.O.CIO/G-6
Mat. Dev.PM Office
ValidatedRequirements
(IRL + $)
Constant ProgramLiaison/Coord./Synch
IntegrationInd. Part.
ABO/OCLL/ G-8/ G-4/G-3/etc.
NECs
NECs
NECs
NECs
NECs
NECs
NECs
NECs
NECs
106SignalBDE
93rdSignalBDE
TheaterSignal
Command
Theater
PD coord
Region
TheaterSignal
Command
Installation
TheaterSignal
Command
Iden
tifi
edR
equ
irem
ents
Iden
tifi
edR
equ
irem
ents
IntegratedRequirement
List (IRL)
POMCost
Estimate
ValidatedRequirements
(IRL + $)
HQDA Integration Office
DOTML-PFanalysis
material solution
GNEC
(GlobalRequirementsIdentification
and Prioritization)
Bridge theCapability Gap
SignalBDE
SignalBDE
SignalBDE
SignalBDE
21
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Transitioning to UC&C is not optional •VoIP is DoD policy • TDM products begin to drop off of the UC APL as soon as July 2012 •Vendors are withdrawing support for TDM
Implementation and Operational Viewpoint •Only one network to implement and maintain • Provides a foundation for implementing unified capabilities
(presence, instant messaging, video, user-initiated conferencing)
On-going efforts include: • Participation in DoD Unified Capabilities Spiral
Four Army participants confirmed: 311th, 5th, ALTESS and Ft. Huachuca
•Draft UC CONOPS • Proposed UC Strategy developed by PM I3MP
22
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
TDM Moratorium impacts several CONUS sites with End-Of-Life equipment as early as FY11
Health and safety issues must be addressed • UCR 2008 Change 2 does not require backup power for users that
cannot initiate precedence calls • The VVoIP STIG recommends only 15-30 minutes back up power be
provided to non-C2 users for emergency/safety reasons • Army needs a policy
Additional analysis of Proposed Regional VoIP construct is required • Several technical and operational issues must be addressed • Only basic interoperability is required between vendors today • Unique mission requirements must be identified • Additional policy and guidance required
I3MP POM 13-17 Submission did not go as anticipated, funding for UC will be limited
23
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Working to realign TLA efforts with Senior Leadership’s strategic vision
Recognize the need to standardize the TLA across the Enterprise •Solutions will be designed in accordance with the threat
Looking to leverage JOINT initiatives
Per MG Napper’s guidance, focus is on SIPR first, NIPR next
24
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Develop strategy for identifying our current baseline infrastructure across the Enterprise in FY12
Collaborate with CIO/G6 on CBA for POM 14-18 submission • CBA to support POM 14-18 submission must be completed by November,
2011 • Establish short-term and long-term requirements and priorities to develop
submission
Crosswalk Enterprise Initiatives with planned I3MP efforts to ensure synchronized approach • Identify FY12 & FY13 efforts to support
Refine UC Strategy • Define bridging strategy to meet short-term requirements • Conduct in-depth analysis of Theater VoIP Designs • Identify Army-unique requirements and codify in Functional Requirements
Document and CONOPS • Establish plan to transition Spiral efforts to I3MP for lifecycle sustainment
Establish an Enterprise TLA Design for NIPR Continue to refine processes through OPT
25
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Questions?
26
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Ms. Kendra N. Acord 520-538-8133
DSN 312-879-8133
27
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
LTC David Thompson
28
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Enable the Warfighter with emerging information technology and infrastructure systems, through lifecycle
management, supporting Army Enterprise and joint networks.
29
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Unified Messaging
Voice
RSS
Fax
Rich Presence
Calendar
Web
Conferencing
& IM/Chat
App
Sharing
Display
Sharing
File
Sharing White-
board
Mobile
Tele-
phone
Voice
& Video
VoIP
VTC
Video
oIP
•Fixed Mobile Tactical
•PEDs, Phones, PCs
•Service Mgmt
•Identity
•IA
IM /
Chat
30
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
TDM
UC
31
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Core
Infrastructure
Systems Main communications
Node (MCN)
Area Distribution
Node (AND)
Distribution Infrastructure
System
(CAT 6 Cable or WLAN)
Wired
Wireless
PSTN
Outside Plant
and Ethernet
Switches
Security Infrastructure
System
(TLA)
DISN &
Commercially Provided Services
UC Infrastructure System
(Voice Call Processor (VoIP))
Tech Control
Facility
NIPRNet
SIPRNet
JWICS
Gateway (GW)
UC End Points
Facilities
Infrastructure
Systems
DISN- Defense Information Systems Network
TLA- Top Level Architecture
CAT- Category
LAN- Local Area Network
WLAN- Wireless LAN
GW- Gateway
UC- Unified Capabilities
PSTN- Public Switched Telephone Network
Analog GW
Analog
VoIP
Analog
VoIP
Data
Data
Analog GW
Terrestrial Transmissions
(PAC & Europe)
32
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
InterSwitch Connectivity
High Availability (5-9s) (down time <5 min/yr)
Medium Availability (4-9s) (down time <52 min/yr)
DoD Unified Capabilities Requirements
UC APL Listed Equipment
DIACAP/IA Core Backup Power
33
Core Switches (MCNs & ADNs)
MCN- Main Communication Node ADN- Area Distribution Node DoD- Department of Defense UC APL- Unified Capabilities Approved Products List DIACAP- DoD Information Assurance Certification and Accreditation Process IA- Information Assurance
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Physical connectivity is most intrusive and is the longest portion of the fielding schedule
MCN/ADN/Access Layer Connectivity
Access Switches / Backup Power/ IA
MCN- Main Communication Node ADN- Area Distribution Node IA- Information Assurance
34
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
End User Building (EUB) Telecommunications Room (TR)
End User Building (EUB) Equipment Backup Power
EUB Wiring: TR to Desktop
EUB TR HVAC
HVAC- Heating Ventilation and Air Conditioning TR- Telecommunications Room; EUB- End User Building
35
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
SIPRNet
Defense Red Switch Network (DRSN)
NIPR/SIPR Top Layer Architecture
/ VoSIP
Terrestrial Transmission
Systems
Edge Boundary Controller (EBC)
NIPR- Non–Classified IP Router Network SIPR- Secret IP Router Network VoSIP- Voice over Secure IP IP- Internet Protocol
36
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Enterprise Services
Enterprise Systems Management Command & Control Facilities and Systems Visual Information Systems &
Video Communications
Audio and Visual Command and Control Facilities
EUCOM HQ
Command Center Upgrades (CCU)
37
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
PSTNNetworx
Soft phone
MCN
ADN
EUB
ASLAN/Non-ASLAN
Data Firewall
Edge Boundary Controller (Voice Firewall)
Parent CallProcessor
TLAGateway
Integrated Access Device
PSTNNetworx
Soft phone
MCN
ADN
EUB
ASLAN/Non-ASLAN
Data Firewall
Edge Boundary Controller (Voice Firewall)
Standby CallProcessor
TLAGateway
Integrated Access Device
PSTNNetworx
Soft phone
MCN
ADN
EUB
ASLAN/Non-ASLAN
Data Firewall
Edge Boundary Controller (Voice Firewall)
Standby CallProcessor
TLAGateway
Integrated Access Device
DISN Parent Location
Child Location #1
Child Location #2
TDM- Time Division Multiplexing ASLAN- Assured Service LAN LAN- Local Area Network TLA-Top Level Architecture
P
P P
P
P
P
P P
P P
P
P
P
P P
P P P P
P
Child Location
TDM
IP
Parent Location
38
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
UC Endpoints: IP Phones, Video Phones, Soft Phones
IP- Internet Protocol UC- Unified Communications
39
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
RDT&E- Research Development Test & Evaluation, VoIP- Voice over Internet Protocol I3MP- Installation Information Infrastructure Modernization Program JITC- Joint Interoperability Test Command, UC- Unified Capabilities DoD- Department of Defense, APL- Approved Products list C2- Command & control TBD- To Be Defined
Terrestria
Transmiss
DISN
Bandwidt
Core
Syste
Distribu
Systems
Facilities
System
Secure
System
UC
Infrastructure
Systems
UC
Endpoints
C2
Command & Control
Infrastructure Systems
UC
VoIP
TBD
JITC Certification Sponsorship
& APL Placement
Candidate Technology
I3MP Fielding
System Integration Capability
Demonstration
40
Integration
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Sustainment
Unplanned Required
Improvements
Legacy
TDM
Pre Planned Product
Improvement
Leverage the remaining useful life of existing equipment as the UC infrastructure is prepared and extended
Where there is an urgent need and where economically practical, implement line side VoIP while Regional infrastructure is built out
FY 12 Initiate planned sustainment efforts
FY 13-17 Programmed sustainment of fielded systems 41
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
• Requirements
• Project / Site Concurrence
FCM
• Survey
• Design Reviews
• Technical Requirement Document
Engineering • RFP
• Evaluation
• Award
Contracting
• Implement
• Migrate
• Closeout
Fielding
42
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
Questions?
LANDWARNET 2011 UNCLASSIFIED
UNCLASSIFIED
WRAP-UP