Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011
12

Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

Dec 21, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

Luminosity Monitor MWPC status report

A.Kiselev OLYMPUS Collaboration Meeting

DESY, Hamburg, 09.09.2011

Page 2: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

Layout of the talk

Installation in the experiment Survey and alignment Performance in the august test run ToDo list

Page 3: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

Installation at DORIS July 2011

Missing part of equipment delivered to DESY and tested on time Installation in the experiment went smoothly No apparent conflicts with other subdetectors seen Cabling work done Installation in the EH is complete

Page 4: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

Installation at DORIS July 2011

Page 5: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

Installation at DORIS July 2011

Page 6: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

Installation at DORIS July 2011

Page 7: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

Survey and alignment

3-6 target nests per chamber ~150um per point matching accuracy in XY-directions

-> quite some work and effort from the MEA team!

Page 8: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

Survey and alignment

X,[mm] Y, [mm] Z, [mm] rX, [deg] rY,[deg] rZ, [deg]

MWPC-L1 8.88 +/- 0.08

-4.52 +/- 0.09 1993.0 +/- 0.4

-0.47 +/- 0.10 0.17 +/- 0.10 1.21 +/- 0.05

MWPC-L2 11.38 +/- 0.08

-1.46 +/- 0.09 2329.6 +/- 0.4

-0.29 +/- 0.10 0.10 +/- 0.10 0.21 +/- 0.05

MWPC-L3 13.39 +/- 0.06

-0.31 +/- 0.06 2690.2 +/- 0.3

-0.02 +/- 0.07 0.07 +/- 0.07 0.49 +/- 0.04

MWPC-R1 -5.21 +/- 0.08

-8.15 +/- 0.09 1987.6 +/- 0.4

-0.28 +/- 0.10 0.26 +/- 0.10 -1.17 +/- 0.05

MWPC-R2 -5.14 +/- 0.25

-5.66 +/- 0.28 2324.1 +/- 0.4

-0.20 +/- 0.35 0.09 +/- 0.30 -0.71 +/- 0.05

MWPC-R3 -5.77 +-/ 0.09

-3.53 +/- 0.09 2686.4 +/- 0.4

-0.57 +/- 0.11 0.00 +/- 0.10 -0.61 +/- 0.05

chambers are more or less in place ~100um positioning accuracy (stat. errors only)

-> NB: data quoted in 12-degree rotated system!

Page 9: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

August 2011 test run at DORIS

Small leakage currents (typically below 100nA per plane) Low hit occupancy (typically 1 hit per plane for “track

candidate events”) No issues with the readout No trips, even during injection

-> in general: very reasonable performance!

Page 10: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

Test run wire maps (left arm)

Page 11: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

Test run wire maps (right arm)

Page 12: Luminosity Monitor MWPC status report A.Kiselev OLYMPUS Collaboration Meeting DESY, Hamburg, 09.09.2011.

MWPC ToDo list till Feb’2012

Replace few preamplifier cards Arrange temperature measurement (+ respective Slow Control) Design/manufacture/install/test SiPM-based trigger scintillators Consider CROS3 2.5ns-slice firmware upgrade

Manufacture/ship/test a spare MWPC

Install CAEN multichannel TDC Tune DAQ driver

Finalize survey/alignment Verify efficiencies; select working conditions

Finalize software integration