1 LOWER MEKONG RIVER BASIN LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME DEVELOPMENT PLAN PROGRAMME (2001 (2001 2006): AN INTRODUCTION 2006): AN INTRODUCTION Presenter: Dr. Vu Van Tuan, Associate Professor, Team Leader, Basin Development Programme Mekong River Commission Secretariat
61

LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

Aug 28, 2018

Download

Documents

volien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

1

LOWER MEKONG RIVER BASIN LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME DEVELOPMENT PLAN PROGRAMME

(2001(2001–– 2006): AN INTRODUCTION2006): AN INTRODUCTION

Presenter: Dr. Vu Van Tuan,Associate Professor,

Team Leader,Basin Development Programme

Mekong River Commission Secretariat

Page 2: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

2

TOPICS FOR PRESENTATIONTOPICS FOR PRESENTATIONTOPICS FOR PRESENTATION

1. LMB: INTRODUCTION

2. BDP: ACHIEVEMENTS

Page 3: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

3

1. LMB: INTRODUCTION

11. LMB: . LMB: INTRODUCTIONINTRODUCTION

1.1. WATER RESOURCES IN LMB

1.2. WHAT IS BDP AND WHY DO WE NEED BDP ?

Page 4: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

4

1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB

Abundance:Annual runoff averages

around 475 km3 / year. 8500 m3/person/year –

compared with 2200 for the Nile; 1400 for the Rhine; 2265 for the Yangstze1700-4000 for the Ganges

Page 5: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

5

1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB

Low level of exploitation for extractive uses:

Average annual withdrawals 60,000 million m3 (12% of total annual flows)

The total volume of regulated storage in the basin (including the Upper Basin) is less than 20,000 million m3

(6% of annual flows).

Page 6: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

6

1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB

High dependence on in-stream uses:

The Mekong fishery is the largest inland fishery in the world, ($US 2,000 million annually)

Inland navigation is an important mode of transport for many areas where road access is limited.

There is an urgent need to balance in-stream uses against extractive demands as agricultural production in the LMB is expanding rapidly.

Page 7: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

7

1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB

Extreme seasonality: Flows in the driest three

months is less than 10% of total annual flows;

Flows in the wettest three months is over 50% of total annual flows

Page 8: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

8

1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB

Importance of the floodplain :

During the wet season, between 1 and 4 million hectares of floodplain are submerged, including the TonleSap.

Page 9: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

9

1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB

Dry season water shortages:

As a result of the rainfall seasonality, concentration of extractions in the driest period and drought events during the onset of the wet season.

Page 10: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

10

1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB

Water quality: In general, it is good

and is rarely a constraint to water use.

The exception is saline intrusion, acid sulphate drainage and pollution in areas of the Mekong Delta

Page 11: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

11

1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB

Groundwater: Widely used as a source for domestic and industrial supply. Use for irrigation is limited, but expanding. Groundwater systems in the flood plain are closely coupled to the river.

Page 12: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

12

1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB1.1. WATER RESOURCES IN LMB

Upper basin:Flows from China and

Myanmar constitute around 18% of total Mekong flows.

The proportion is higher in the dry season, when snow melt contributes a significant component of flow

Page 13: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

13

Lower Mekong Lower Mekong water balancewater balance

Total Mekong Basin

475 km3

YunnanComponent

86 km3

Average annual inflow from China into the lower Mekong basin is 86 km3 . . .

. . . . which is around 18% of the total Mekong mean annual flow of 475 km3

The largest proportionof total flow is contributed by the major left bank tributaries in Laos

Page 14: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

14

MAIN IMPACTSMAIN IMPACTS

Major dams in ChinaSmall to medium dams in LMB

Forest cover reductionFreshwater fisheriesBrackish water fisheriesHigh population densities

Irrigation development

Page 15: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

15

…… Change will continueChange will continue

Population pressures

Environmental awareness

Development opportunities

Climate change

Page 16: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

16

Major Gauging Stations

in Lower Mekong

Understanding the Understanding the hydrology of LMBhydrology of LMB

Initial assessment of seven main reaches :1) Chiang Saen to Luang Prabang2) Luang Prabang to Vientiane

3) Vientane to Nakhon Phanom4) Nakhon Phanom to Mukdahan5) Mukdahan to Pakse6) Pakse to Kratie7) The system downstream of Kratie (the Cambodian Floodplain, Tonle Sap and the Delta)

Page 17: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

17

1.2. WHAT IS BDP ?AND WHY DO WE NEED BDP ?

1.2. WHAT IS 1.2. WHAT IS BDPBDP ??AND WHY DO WE NEED BDP ?AND WHY DO WE NEED BDP ?

BBASINDDEVELOPMENTPPLAN

Page 18: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

18

Basin Development Plan

BDP : Planning process & tools to identify, categorise & prioritise joint or basin-wide projects and programs

VISION : Contribute to economic growth through a participatory process that encourages investment and sustainable development of the shared resources of the Mekong River

(1995 Agreement)

Page 19: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

19

BASIN DEVELOPMENT PLAN

MRC ProgrammesWUP, EP, FMMP, AIFP, TSD, HRD, Fisheries, Hydropower, WRMP, Navigation, Tourism

National ProgrammesNMCs, Line Agencies, Universities, Research Inst, Bi-lateral, NGOs;Private Sector; Other Stakeholders.

Regional ProgrammesGreater Mekong Sub-region (GMS), ASEAN-Mekong

Page 20: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

20

BDP ORGANISATIONBDP ORGANISATIONBDP ORGANISATION

Programme Coordination

GroupCoordination

Meeting

NMCs

National BDP/Coordination

Unit

Sub-area working groups

BDP Sub-Committee

NMCSecretariat

Line Ministries, Local

Authorities, others

MRC/JC

Secretariat

BDP Team

Office of CEO

ProgrammesManagement

Group

Page 21: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

21

ROLE OF BDP IN MRC(as in MRC Strategic Plan 2006 – 2010)

ROLE OF BDP IN MRCROLE OF BDP IN MRC(as in MRC Strategic Plan 2006 (as in MRC Strategic Plan 2006 –– 2010)2010)

Page 22: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

22

KEY OBJECTIVES

• A participatory planning processestablished and ongoing; and

• A Basin Development Plandrafted and agreed on

... aimed at a balanced mix of social, economic and environmental factors

Page 23: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

23

KEY OUTPUTS

OBJECTIVE 1:

1.1. Planning Process

1.2. Guidelines

1.3. Data System

1.4. Trained Staff

1.5. Reporting

1.6. Workshops

OBJECTIVE 2:

2.1. Sub – area Studies

2.2. 20 – year Scenarios

2.3. Sub – area Strategies

2.4. Basin – wide Strategy

2.5. Project Long-list

2.6. Project Short-list

2.7. Implementation Plan

Page 24: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

24

2. BDP: ACHIEVEMENTS

2.2. BDP: BDP: ACHIEVEMENTSACHIEVEMENTS

2.1. OBJECTIVE 1: A participatory basin planning process established and ongoing;

2.2. OBJECTIVE 2: A BDP aiming at a balance mix of social, economic and environmental factors drafted and agreed on

Page 25: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

25

OUTPUT 1.1. PLANNING PROCESSAchievements:

In CAMBODIA: 13 ministries and equivalents, in which:

BDP Sub – committee: 16 members

BDP Coordination Unit: 16 members

BDP / CNMC Unit: 04 members

SA Working Group: 90 members

WG-1 (6C&8C): 17 (3 provinces)

WG-2 (7C): 18 (3 provinces)

WG-3 (9C): 26 (9 provinces)

WG-4 (10C): 29 (9 provinces)

Indicator 1.1.2:

A network of institutional stakeholders established under each NMC

Page 26: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

26

OUTPUT 1.1. PLANNING PROCESSAchievements:

In LAO PDR: 06 ministries and equivalents, in which:

BDP Sub – committee: 09 members

BDP National W. Group: 12 members

BDP / LNMC Unit: 04 members

SA Working Group: 18 members

WG-1 (1L): 08 (8 provinces)

WG-2 (4L): 06 (6 provinces)

WG-3 (6L & 7L)): 04 (4 provinces)

Indicator 1.1.2:

A network of institutional stakeholders established under each NMC

Page 27: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

27

OUTPUT 1.1. PLANNING PROCESSAchievements:

In THAILAND: 05 ministries and equivalents, in which:

BDP National W.G: 23 members

BDP / TNMC Unit: 09 members

SA Working Group: 67 members

WG-1 (2T): 15 (3 provinces)

WG-2 (3T-1): 17 (4 provinces)

WG-3 (3T-2): 16 (5 provinces)

WG-4 (5T): 19 (5 provinces)

Indicator 1.1.2:

A network of institutional stakeholders established under each NMC

Page 28: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

28

OUTPUT 1.1. PLANNING PROCESSAchievements:

In VIETNAM: 05 ministries and equivalents, in which:

BDP Sub – committee: 08 members

BDP National W.Group: 21 members

BDP / CNMC Unit: 03 members

SA Working Group: 32 members

WG-1 (7V): 14 (3 provinces)

WG-2 (10V): 18 (8 provinces)

Indicator 1.1.2:

A network of institutional stakeholders established under each NMC

Page 29: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

29

OUTPUT 1.1. PLANNING PROCESSAchievements:

The document “ The BDP Planning Cycle following principles of Integrated Water Resources Management” was endorsed by the Joint Committee in March 2005

The format of PIN were proposed and developed in this document

The document “The process from long-listing to short-listing and the prioritization process of projects” was endorsed in August 2005 by the JC and approved in November 2005 by Council

Indicator 1.1.3:

An agreed planning cycle endorsed by the JC

Page 30: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

30

Analysis1: Sub-area studies2: Sub-area scenarios

3: Basin-wide strategy

4: Project identificationLong-listing (database)

5: Project Short-listing

Project PreparationImplementation

Learning Monitoring & Evaluation

Impact Assessment Tools (DSF, RAM, SIA, SEA)

PLANNING CYCLEPLANNING CYCLEPLANNING CYCLE

Page 31: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

31

PROJECT IDEAS DATABASE SHORTLIST PROMOTION ACTION

JCNMCs

FROM IDEA TO IMPLEMENTATION

JUSTIFICATION

Page 32: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

32

Classification criteriaClassification criteriaClassification criteria

(Details are given in Volume 1 – Planning Process)A - E5. Implementation aspects A - E4. Completeness of decision basis

A - E3. Potential value, costs, side effects, risks, uncertainties

A - E2. National priority and support from member countries

A - E1. Harmony with IWRM strategy RatingCriterion

Page 33: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

33

PRIORITIZATION OF PROJECTPRIORITIZATION OFPRIORITIZATION OF PROJECTPROJECT

1. Update Projects Database / Long-list2. Negotiation through transboundary meetings 3. The Regional Working Sessions are convened regularly to

agree the list of projects need to be screened4. Screening projects by applying 5 criteria in Planning Cycle, by

using the Screening Toolkits5. Classification of these projects leads to the draft Short-lists

prepared by BDP MRCS 6. Review by NMCs, readjustments by BDP MRCS7. Submission of the draft Short-lists to JC 8. JC decision on the Short-lists and follow up decisions of JC

Page 34: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

34

OUTPUT 1.1. PLANNING PROCESSAchievements:

The Guideline 'BDP quality plan'was prepared in September 2003 & revised in February 2004. It was submitted to NMCs in May 2005.

See the List of Core Library in Output 1.2. Guidelines

Indicator 1.1.4:

Quality management procedures

Page 35: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

35

OUTPUT 1.2. GUIDELINESAchievements:

BDP 005 Sep. 2002 Sub-area analysis

BDP 026 Nov. 2003 (Rev) Sub-area reporting (draft format – indicative), September 2003

BDP 001 Mar. 2004 (Rev) Identification of Sub-area of the LMB for the BDP, December 2001

Dec. 2004 - Report on Sub-area Transboundary Meetings

13 Sub – area reports was completed

Indicator 1.2.1:

Sub – area guideline was prepared and implemented

Page 36: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

36

OUTPUT 1.2. GUIDELINESAchievements:

• More than 100 technical reports and papers

• 08 six- monthly progress reports

• 19 Coordination meeting records

• BDP Archive, version 3 (May 2005) contains 281 documents

• BDP Core Library

• BDP Planning atlas (10 SAs)

Indicator 1.2.2:

Full set up documentations in the BDP final document

Page 37: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

37

OUTPUT 1.3. DATA SYSTEM & KNOWLEDGE BASE

Achievements:

CNMC, LNMC, TNMC and VNMC have established national BDP data management systems

BDP / MRCS have established and updated Project Database (new activity) with more than 400 projects

BDP / MRCS have established the Hydropower Database (new activity) with 90 projects

Indicator 1.3.1:

Database established, continuously expanded and updated

Page 38: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

38

OUTPUT 1. 3. DATA SYSTEM & KNOWLEDGE BASE

Achievements:

Applied DSF for 5 scenarios: Baseline, Upper dams, Irrigation, Low and High developments

Applied RAM for 4 scenarios: Baseline, Irrigation, Low and High developments

Prepared the Project Screening Toolkit by using Economic, Social and Environmental factors

Applied for prepare short-list

Training for using Toolkits in MRCS for 4 riparian countries (October 2005)

Indicator 1.3.2:

Impact Assessment Tools were applied in BDP process

Page 39: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

39

OUTPUT 1.4. TRAINED STAFFAchievements:

6 students have completed their MSc studies (1 female)

TNA made in all four countries(2002 – 2004)

Formal training programmes have been conducted in all riparian countries

Indicator 1.4.1:

M.Sc. Study

Indicator 1.4.2:

Training Needs Assesments

Page 40: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

40

OUTPUT 1.4. TRAINED STAFFAchievements:

The MDBC training completed included four modules + an additional study tour to TonleSap.

12 regional workshops have been conducted

IRBP training curriculum (8 training modules) tested and training conducted based on curriculum (November 2005)

Indicator 1.4.3:

Regional Training Programme

Page 41: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

41

OUTPUT 1.5. REPORTINGAchievements:

Eight semi-annual BDP Progress Reports have been produced integrating NMC national progress reports (From PR No1: April – Sep. 2002 to PR No8: Oct. 2005 – Mar. 2006)

Reporting prepared for the CPMG, PMM, JC, Council meetings; donors’ missions

Indicator 1.5.1:

Scheduled reporting

0%

10%

20%

30%

40%

50%

60%

70%

80%

Cambodia Lao PDR Thailand Viet Nam

Area harvested % increase 1990-2000Total production % increase 1990-2000

Page 42: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

42

OUTPUT 1.6. WORKSHOPS / MEETINGS

Achievements:

REGIONAL MEETINGS: 46

Coordination Meetings: 19

Others (Cons. TB …) 27

NATIONAL MEETINGS: 119

SAs MEETINGS / FORUMS: 120

Indicator 1.6.1:

Coordination and planning meetings conducted

Page 43: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

43

OUTPUT 2.1. SUB-AREA STUDIESAchievements:

Cambodia, Lao PDR and Viet Nam have BDP Sub-area Working Groups. In Thailand, sub-groups of RBCs are responsible for BDP implementation in collaboration with TNMC

Forum 1 & 2 have been conducted.

Indicator 2.1.1:

Public Participation and Stakeholder Forums

date:06/02/05 tim e:18:10:10.94

Luang Prabang Baseline v Chinese Dams scenario

01/01/1985 to 31/12/2000

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

m3/

s

Y ears

1986

1988

1990

1992

1994

1996

1998

2000

Page 44: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

44

OUTPUT 2.1. SUB-AREA STUDIESAchievements:

13 Sub – area Reports were completed

10 Sub – area for Planning Atlas were completed in 2 CDs

There are 14 sections in each SA:1. Introduction2. Population and socio-economic conditions3. Water resources4. Physical features and environment5. Planning and the BDP6. Major water related sectors (7 sectors)

Indicator 2.1.2:

Sub – area study and analysis

Page 45: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

45

OUTPUT 2.1. SUB-AREA STUDIESAchievements:

7. Watershed management

8. Strengths, weaknesses, opportunities and threats

9. Identified transboundary issues

10. Scenarios for development

11. Sub-area development strategies

12. Proposed projects

13. Case study

14. Information sources

Indicator 2.1.2:

Sub – area study and analysis

Page 46: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

46

OUTPUT 2.2. 20 YEARS SCENARIOSAchievements:

Five scenarios have been tested in conjunction with the World Bank under the heading “ModelledImpacts of Scoping Development Scenarios in the LMB”.

Four initially development-planning scenarios (baseline, irrigation, low and high) have been run using the RAM.

Indicator 2.2.1:

Scenario analysis prepared

Mean water level difference v Baseline (1985-2000) for Mekong River at Luang Prabang

-1.50

-1.00

-0.50

0.00

0.50

1.00

1.50

Jun Jul Aug Sep Oct Nov

(m)

Chinese dams Low developmentIrrigation High development

Page 47: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

47

Development Development scenariosscenarios

#

##

#

#

#

#

#

##

#

#

#

##

#

#

#

#

#

#

#

#

#

Crop area

Dam

Diversion

Crop area

Dam

Diversion

Crop area

Dam

Diversion

Crop area

Dam

Diversion

Crop area

Dam

Diversion

Crop area

Dam

Diversion

Baseline

Upper dams

Low development

Irrigation

High development

T

L

V

C

Page 48: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

48

Baseline

Chinese Dams

Low Development

Irrigation

High Development

Dam volume (km3)

Irrigation area (‘000 ha)

5

7,400

22

8,200

28

10,400

48

5 DEVELOPMENT SCENARIOS5 DEVELOPMENT SCENARIOS5 DEVELOPMENT SCENARIOS

Page 49: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

49

Scenario detailsScenario detailsScenario details

3,2622,20022,70026,77811,3494,194HighDevelopment

3,2622,20010,30012,44311,3494,194Agriculture

0010,30012,4438,3163,109Low Development

0022,7006,1857,4221,620Upper dams

0006,1857,4221,620Baseline InterIntraChinaLMB

Basindiversions

(mcm)

Hydropower active storage

(mcm)Irrigated

Areas(‘000 ha)

Domesticand

industrialdemand(mcm)

Scenario

Page 50: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

50

Active storage (mcm)$T 0 - 500$T 501 - 5000

$T 5001 - 15000

$T$T

$T$T

$T

$T$T

$T$T

$T

$T

$T

$T

$T

$T

$T

$T$T

$T$T$T

#

Xe Kong 5

#

Xiaowan

#

Manwan

#

Dachaoshan

#

Nuozhadu

#

Nam Ngum 2

#

Nam Ngum 3

#

Nam Ngum 1

#

Nam Leuk

#

Theun Hinboun

#

Nam Theun 3

#

Nam Theun 2

#

Houay Ho

#

Xe Kaman 3

#

Xe Kaman 1

#

Plei Krong#

Kontum# Yali#

Se San 4#

Lower Se San 2

#

Lower Sre Pok 2

200 0 200 400 Kilometers

N Location and relative active storage of hydropower dams modelledfor scenarios(Upper damsand High developmentscenarios)

Location and relative active storage of hydropower dams modelledfor scenarios(Upper damsand High developmentscenarios)

Page 51: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

51

COMPARATIVE TOTAL VALUE ADDED BY WATER TO THE LMB ECONOMY BY 4

SCENARIO

COMPARATIVE TOTAL VALUE ADDED BY COMPARATIVE TOTAL VALUE ADDED BY WATER TO THE LMB ECONOMY BY 4 WATER TO THE LMB ECONOMY BY 4

SCENARIOSCENARIO

Comparative total value added by water to the LMB economy, by scenario

0

500

1,000

1,500

2,000

2,500

3,000

Baseline Low Development Irrigation High Development

US$

(mill

ions

)

Page 52: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

52

VALUE ADDED BY WATERVALUE ADDED BY WATERVALUE ADDED BY WATER

6.0212,5702,5402,4582,107TOTAL

4.110993932930904Viet Nam

1.16602648596569Thailand

39.0104584561551279Laos

2.110391399381356Cambod

US$ per

capita

Value added %

High Develop

mentIrrigationLow

DevelopmentBaselineCountry

Change (Baseline to

High)Value added by water (US$ millions)

Page 53: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

53

OUTPUT 2.3 – 2.4. STRATEGYAchievements:

A series of national and regional consultations were carried out on the revised document (June and August 2005)

The document “Strategic Direction for Integrated Water Resources Management in the LMB” was endorsed by JC (August 2005) and approved by Council (November 2005)

Indicator :

Basinwidestrategy agreed

SWAT and IQQM models

ISIS models

Page 54: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

54

OUTPUT 2.5. PROJECT LONG - LISTAchievements:

P.I.N. format was accepted through the document “The BDP Planning cycle following principle of IWRM” after it was improved by MRCS~ Task Force (P.I.N)

Identification and collection of projects / programmes were carried out.

At the end of Phase 1, there are more than 400 projects / programmes in MRC / BDP Project Directory

Indicator :

First long-list agreed

dat e:23 /11/04 tim e:15:43:2 8.97

A verage observed dai l y f low s f or per iod 1969-2000

01/01/2000 to 31/12/2000

0

5000

10000

15000

20000

25000

30000

35000

40000

m3/

s

MonthsJan Feb Mar Apr May Jun Jul Aug Sep Oct N ov D ec

Chiang Saen N ong K hai Pakse K rat ie

Page 55: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

55

OUTPUT 2.5. PROJECT LONG - LISTAchievements:

Joint Projects: 69

National Projects: 250

• Cambodia: 115

• Lao PDR: 91

• Thailand: 9

• Vietnam: 35

MRCS projects: 65

Notified projects: 24

Group projects: 07

Indicator :

First long-list agreed

0

2000

4000

6000

8000

J F M A M J J A S O N D

u/s KratieKratie to Delta

Mekong Delta

Page 56: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

56

OUTPUT 2.6. PROJECT SHORT - LISTAchievements:

The 22nd JC meeting (August 2005) endorsed the 1st batch of screened projects / programmes to be placed on the BDP shortlist.

The BDP’s Process of Prioritization of Joint Projects to be placed on the BDP shortlist

Agreed : the same procedure should be applied to national projects

The 23rd JC meeting (April 2006) took note the 2nd batch of projects to be placed into the BDP shortlist.

Indicator :

First short-list agreed

Page 57: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

57

PRIORITIZATION PROCESS(Cycle to be repeated)

PRIORITIZATION PROCESSPRIORITIZATION PROCESS(Cycle to be repeated)(Cycle to be repeated)

1. Projects / Programmes Data Base / Long-list which will be continuously updated, and gradually contain all projects in LMB and initial checking within MRCS.

2. (Optional) Negotiation through transboundary meetings

3. Regional Working Sessions are convened regularly to agree on the list of projects / programmes that need to be screened / maintained in the Short List.

4. Screening of projects / programmes by applying 5 criteria of the Planning Cycle by using the Screening Toolkits (social, environmental and economic checklists) by BDP MRCS, together with sector experts (in MRCS, NMCs, other organizations)

Page 58: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

58

PRIORITIZATION PROCESS (cont)(Cycle to be repeated)

PRIORITIZATION PROCESS PRIORITIZATION PROCESS (cont)(cont)(Cycle to be repeated)(Cycle to be repeated)

5. Classification of these projects / programmes leads to the draft Short-lists prepared by BDP MRCS (considering recommendations of the Regional Working Sessions)

6. Review by NMCs, readjustments by BDP MRCS; agreement by NMCs

7. Submission of the draft Short-lists to JC for decision – making

8. JC decision on the Short-lists and follow up of decisions made by JC

Page 59: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

59

OUTPUT 2.7. IMPLEMENTATION PLANAchievements:

One example was prepared “Capacity Building in Integrated River Basin Planning and Management”

1. The full P.I.N.

2. The draft P.I.P.

3. Based on:

• The short P.I.N.

• The added information

• The screening results

Indicator :

Implementation plan for priority initiative short-listed

Page 60: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

60

BDP 1 was Implemented in a particularly active collaboration with the NMCs, line

agencies and the MRC Programmes

Financial support and contributions in kind to BDP Phase 1 has kindly been

granted by Australia, Denmark, Japan, Sweden and Switzerland

BDP 1 was Implemented in a particularly BDP 1 was Implemented in a particularly active collaboration with active collaboration with the the NMCsNMCs, line , line

agencies and the MRC agencies and the MRC ProgrammesProgrammes

Financial support and contributions in Financial support and contributions in kind to BDP Phase 1 has kindly been kind to BDP Phase 1 has kindly been

granted by granted by Australia, Denmark, Japan, Australia, Denmark, Japan, Sweden and SwitzerlandSweden and Switzerland

Page 61: LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME … · LOWER MEKONG RIVER BASIN DEVELOPMENT PLAN PROGRAMME ... Training for using Toolkits in MRCS for 4 riparian countries ...

61

Thank you very much

for your attentionDr. Vu Van Tuan,

Associate Professor,Team Leader,

Basin Development ProgrammeM.R.C.S.