Lost Creek Drive Road Rebuild Project Fall 2018 Public Works – Street Division
18

Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Oct 09, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

WWW.Columbia.SC.Gov/Engineering

Lost Creek Drive Road Rebuild

Project

Fall 2018

Public Works – Street Division

Page 2: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Public Works – Street Division

Page 3: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Overview

● Why Road Work is Needed

● Reclamation Method

● Project Schedule

● Lane Closures & Delays

● Things to Consider

● Resources Available to You

Public Works – Street Division

Page 4: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Why Road Work is Needed

● Road is in need of repairs due to major base failures

● Normal method is pothole repair

● Soil under Lost Creek Drive is currently not stable

enough for long term pothole patching or standard

overlay

Public Works – Street Division

Page 5: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Method for Reclamation

Public Works – Street Division

Page 6: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Method for Reclamation

● Full depth reclamation with cement

○ Recycle existing roadway

○ Added cement stabilizes road base

● Steps in process

○ Pulverize existing base

○ Mix in-place with water & cement

○ Grade & Compact Base

○ Wet Cure – Strength & Dust

○ Pave

Public Works – Street Division

Page 7: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Project Schedule

● Bid Contract – Complete

○ – Awarded to Armstrong Contractors, LLC

● Construction Schedule

○ – Construction Phases

● Will Take Approximately 15 weeks

● Milling Phase

● Cement (CMRB) Phase

● Paving Phase

Public Works – Street Division

Page 8: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Milling Phase

Public Works – Street Division

Page 9: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Cement Phases

Public Works – Street Division

Page 10: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Paving Phases

Public Works – Street Division

Page 11: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Traffic by Hour in Chestnut Hill

Public Works – Street Division

Page 12: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Lane Closures & Delays

○ The Contractor will enforce traffic control

○ Access to entrances

○ Efforts to control dust

○ Cure period of CMRB “Reclaimed” roadway (Wet Cure)

○ Construction will take place between the hours of 7:30 a.m.-5:30 p.m.,

Monday morning to Friday evening

Public Works – Street Division

Page 13: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Stationary Construction Signs 500’ from Intersections

Page 14: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Flagger and Pilot Cars

● Flaggers and possibly a pilot car will be used during

construction operations to assist with guiding residents

through the construction zone

● Please forgive the delays for these measures/procedures

are in place to provide continuous safe travel to

Chestnut Hill residents within the construction zone

Public Works – Street Division

Page 15: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Public Works – Street Division

Is It Ok To Pave In The Rain?

Page 16: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Considerations

● Weather Restrictions

● Rain

● If Temperature < 55 °F – cannot pave

● Utilities

○ Although utilities are supposed to be marked there is a high probability that

something is underground that is unknown.

○ Not uncommon to have depths above expected levels

● Other Considerations

○ Murphy’s Law

Public Works – Street Division

Page 17: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

Social Media

● Posts Will be each Friday at 7:30 p.m.● Facebook

○ Construction status reports weekly

○ Updates on lane shifts and progress

● www.facebook.com/COCPublicWorks● Twitter

○ Construction status reports weekly

○ Updates on lane shifts and progress

● www.twitter.com/COCPublicWorks

Public Works – Street Division

#LostCreekPaving

Page 18: Lost Creek Drive Road Rebuild Project - City of Columbia SC Creek... · Why Road Work is Needed Road is in need of repairs due to major base failures Normal method is pothole repair

WWW.Columbia.SC.Gov/Engineering

Questions

Public Works – Street Division

Fall 2018