Los Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension Regional Connector Crenshaw/LAX Transit Corridor
29

Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Mar 25, 2018

Download

Documents

dangtuyen
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Los Angeles County

Metropolitan Transportation Authority

1

Los Angeles Metro

Upcoming Tunneling Opportunities

Westside Subway

Extension

Regional

Connector

Crenshaw/LAX

Transit Corridor

Page 2: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Westside Subway Extension

2

Page 3: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

8.9 mile Extension of Metro Purple Line

7 New Stations

$5.66 Billion (YOE 2022-30/10) (FTA New Starts Criteria)

78,700 New Daily Project Trips

3

Westside Subway Extension

Page 4: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

4

Westside Subway Extension

Administrative Final EIS/EIR

Status

• August 26th – Second Draft submitted; FTA comments

received October 3rd (initial) and October 7th (complete)

• September 12th – Financial Plans submitted

• October 21st – Third Draft submitted; FTA requested a more

robust discussion on project phasing

• November 30th – Updated Fourth Draft submitted

• December 16th – Approval to Circulate Final EIS/EIR

• Early January 2012 – Release for 45-day Review Period

• February 23, 2012 – Board Certification

• March 2012 – Record of Decision for entire nine-mile Project

Page 5: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Westside Subway Extension

Project Schedule

5

= Milestone Date = FTA Action

Last Revised: 11/29/11 * Note: December 2012 - Early Construction start for VA Parking Structure (D/B Contract)

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022

Entry into Final Design - Jun 2012

FFGA Negotiations

Third Party Coordination

Final Design and Construction *

Revenue Testing

Revenue Operations - Nov 2022

Page 6: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Westside Subway Extension

Possible Construction Contract Packaging

6

Page 7: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Westside Subway Extension

Study Area Fault Locations

7

Page 8: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Westside Subway Extension

Century City Area Fault Zones

8

Page 9: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Station on Santa Monica

Boulevard Shifted east to avoid

active Santa Monica Fault Zone

Westside Subway Extension

Century City Station Locations

9

Page 10: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Westside Subway Extension

Santa Monica and Constellation Blvd Options

10

Santa Monica Boulevard

Fault zone extends sub-parallel

to Santa Monica Boulevard -

area of complex faulting

East station location is within

West Beverly Hills

Lineament/Newport Inglewood

Fault zone

Constellation Boulevard

Location is south and west of

fault zones

No evidence of faulting at

station location

Page 11: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

• Demonstrated on Gold Line Eastside Extension (2006) – Similar: diameter, oil field, gassy soil, seismic area, depth

– Similar soils: dense and suitable for tunnel boring machine (TBM)

• Pressurized closed-face TBM minimizes ground movement – Little to no ground settlement Little to no impact on buildings

Westside Subway Extension Century City Study Area

Tunneling Can Be Accomplished Safely

11

– Gas-and-water-tight final

lining installed within TBM

– Tunnel ventilation

prevents gas buildup

during tunneling and

operations

Page 12: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

• Noise and vibration during tunneling and operations

– Will be specified, monitored, and controlled to existing criteria

– Substantiated complaints will be addressed and mitigated

• Investigation of oil wells

– Conducted investigation on Beverly Hills High School (BHHS) Campus

– Further investigation (magnetic probing) to confirm tunnel area clear of wells

– Proven methods exist to treat oil well casings

• Project requires tunneling through active faults

– Many precedents for successful tunneling through active faults

– Pressurized face TBMs can tunnel through fault zones safely

– Installed lining will be designed to accept fault offsets without collapse

Westside Subway Extension Century City Study Area

Tunneling Can Be Accomplished Safely

12

Page 13: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

• Many alignments evaluated, none

avoided BHHS buildings

– Selected best for BHHS

– Passes only beneath South Wing of

Building B

– Not below gym/pool building

• Depth allows future development

(including deep basements and

underground parking)

Westside Subway Extension Safe Tunneling Beneath Beverly Hills High School

13

• Presence of tunnels

– Does not affect overlying structures during an earthquake

– Does not impact use as emergency evacuation center or shelter

– Will not pose new risks to students, faculty and community

Page 14: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

• Santa Monica Boulevard

– Fault zones at both proposed station sites

– Neither site acceptable for station

• Constellation Boulevard

– No evidence of faulting at station location

– Location is acceptable for station

• Tunnels can be safely constructed under Beverly Hills,

Beverly Hills High School, Century City and Westwood

Conclusions Westside Subway Extension

Century City Area Study Conclusions

14

Page 15: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Advanced Preliminary Engineering

October 27th – Board approved Modification to Parsons Brinckerhoff contract:

Continuation of current PE to support Final EIS/EIR approvals, risk

assessment, contract packaging, constructability, cost estimating,

scheduling, early utility relocation, real estate certification and property

acquisition, early building demolition and third party coordination

Advance:

• Architectural design of station entrances for interface with properties

and major stakeholders

• Electrical, mechanical and fire/life safety design to enhance system

interface with existing Metro Red Line and Purple Line

• Geotechnical analysis, structural design of tunnels and station

excavation support and building protection

Westside Subway Extension

Extended PE Plan Update

15

Page 16: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Regional Connector Transit Corridor

16 16 16

Page 17: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Locally Preferred Alternative

1.9 Miles

3 Stations

90,000 Daily Project Trips

$1.367 Billion (YOE 2019-30/10)

Regional Connector Transit Corridor

17

Page 18: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Regional Connector Transit Corridor

Status of Administrative Final EIS/EIR

Status

• September 6th – Comment period concluded for Supplemental

Environmental Assessment/Re-circulated Sections of Draft EIS

- Received over 250 comments

• September 12th – Financial Plan submitted

• September 15th – SHPO executed MOA

• September 26th – Submitted Revised Volume 1 (Third Draft)

• October 11th – Submitted Volumes 2-4 Comments/Responses

• November 7th – Submitted Fourth Draft

- November 18th - Received FTA comments

• December 1st - Submit Fifth Draft

• December 9th – Approval to Circulate Final EIS/EIR (open)

• December/January – Release for 30-day Review Period (open)

• January 26, 2012 – Board Certification

• February 2012 – Record of Decision

18

Page 19: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Regional Connector Transit Corridor

Project Schedule

19

= Milestone Date = FTA Action

Last Revised: 11/29/11

2012 2013 2014 2015 2016 2017 2018 2019

FFGA Negotiations

Third Party Coordination

Construction

Revenue Testing

Revenue Operations - Nov 2022

Entry into Final Design - Oct 2012

Page 20: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Regional Connector Transit Corridor

PE Design Progress Update

20

• September 29th & October 20th – submitted Pre-Final PE packages

• Incorporated Final Value Engineering recommendations in the

design

• Continued comprehensive project constructability review

• Updating construction schedule and cost estimate for design

development

Civil/Track

• Continued potholing utility and relocation design

• October 13th – submitted 85% 1st Street sanitary sewer design

• Performed evaluation of traffic design at 2nd/Hope Streets

• Further developed raised decking drawings on Flower Street and

1st/Alameda

Page 21: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Regional Connector Transit Corridor

PE Design Progress Update

21

Stations • Developed entrance pavilions at three stations

• Continued:

- Station configuration design development

- Space allocation and adjacencies development

Tunnels/Cut and Cover • October 20th – Submitted Draft Geotechnical Baseline Report

• October 21st – Submitted Draft Geotechnical Data Report

• Mid-November – Two additional Environmental Borings

• Advancing design for traction power, OCS, signals and

communications

• Revised RAILSIM model to reflect current track profile and

configuration

Page 22: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Crenshaw/LAX Transit Corridor

22

Page 23: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Crenshaw/LAX

Transit Corridor

8.5 miles Light Rail

6-8 Stations

$1.749 Billion (Board approved LOP)

24,400 Project Trips (2035)

23

Page 24: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Crenshaw/LAX Transit Corridor

Project Schedule

24

= Milestone Date = FTA Action

Last Revised: 11/15/11

2012 2013 2014 2015 2016 2017 2018 2019

Third Party Utility Relocations

Final Design & Construction

Revenue Testing

Revenue Operations – Dec 2018

Design Build Contract Procurements

Right-of-Way

Page 25: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

Crenshaw/LAX Transit Corridor

Current Major Project Issues

25

• FAA / LAWA / LAX RPZ Design Negotiations

– Issued Form 7460 application for guideway configuration

– Regular standing meetings with the local office commenced

October 2011

– FAA Utility Relocation – Design standards provided and

design concepts under discussion; Decision on civil

infrastructure built by Metro and fiber installation by FAA still

required

• Progressing constructability approach with FAA/LAWA to identify

construction windows along south runways and defining

requirements for procurement documents; Will be covered as a

separate 7460 process

Page 26: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

26

Crenshaw/LAX Transit Corridor

Current Major Project Issues

• BNSF Abandonment Negotiations

– November 17th – Term sheet to Metro Construction Committee

– December 15th – Board Action

– Anticipate BNSF Board meeting in December

– Preparation of agreement in progress

– Winter/Spring 2012 (target) - BNSF to file with the Surface

Transportation Board a petition for exemption to abandon rail

freight service

– Summer 2012 (target) – Approval by Surface Transportation

Board

• Leimert Park Station – developing best way to include as bid option

• Westchester Station – Metro Board approved motion to include as

bid option December 15, 2011

Page 27: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

27

Crenshaw/LAX Transit Corridor

PE Design Progress Update

• BNSF Abandonment

– Incorporated into baseline design

– Revising CPUC exhibits

– Revised and reissued the PSR/PR for I-105 and I-405 to Caltrans

• Preparing final PE plans and procurement documents

• Continuing Advanced Utility relocation design for early utility

relocation contract

• Tunnel Advisory Panel reviewing updated Draft Geotechnical

Baseline Report

• Initiated appraisals for full take properties including Southwestern

Yard; progressed legals and plats for partial takes and temporary

construction easements

Page 28: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

• Progressing the Southwestern Yard design

‒ Confirmed the Yard’s programming requirements and preferred

vehicle flows (excluding buildings)

‒ Integrated the Mainline Alignment with yard access tracks

• Completed

– Station ventilation analysis, evaluating supplemental fire

protection with additional sprinklers over guideway to address

accelerated fire growth rate; reissued associated design

deviation request to FSLC for approval

– August 23rd – Rail Fleet Management Plan

– October 10th – Real Estate Acquisition Management Plan

28

Crenshaw/LAX Transit Corridor

PE Design Progress Update

Page 29: Los Angeles Metro Upcoming Tunneling · PDF fileLos Angeles County Metropolitan Transportation Authority 1 Los Angeles Metro Upcoming Tunneling Opportunities Westside Subway Extension

• Continue Monthly Updates

• November 17th – Complete Base Project PE design

– BNSF Abandonment incorporated

• November 21st – Issue Step 1 RFQ

• January 5, 2012 – Industry Review ends

• January 30, 2012 – Issue Step 2 RFP

29

Crenshaw/LAX Transit Corridor

Next Steps