LOI – Next Steps?. John Thomason. ISIS Schedule. All still provisional!. Possible Workplan. Contractors lay in cables ready for break-out box in outer synchrotron. ISIS staff will be busy with routine maintenance work during this short shutdown period. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: LOI – Next Steps?

LOI – Next Steps?

John Thomason

Page 2: LOI – Next Steps?

ISIS Schedule

All still provisional!

Page 3: LOI – Next Steps?

Possible Workplan

Contractors lay in cables ready for break-out box in outer synchrotron

ISIS staff will be busy with routine maintenance work during this short shutdown period

ISIS staff to cable SP8 bias regulator to LOI cavity in R5.4 plus other preparatory work for January

Experiments in R5.4 to showfull operation of system with integration of ISIS LPRF, cure for oscillations in IA,

etc.

ISIS staff complete break-out box in synchrotronand prepare LOI HPD and water manifold for move to synchrotron SP6

Page 4: LOI – Next Steps?

May/June 2008