Top Banner
Lockout/Tagout Training Division of Facilities Construction and Management 2001
35

Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Dec 26, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Lockout/Tagout Training

Division of Facilities Construction and Management

2001

Page 2: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Energy Control Program

Page 3: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Training Review At the end of this training you will be

required to complete an on-line quiz. Please review the information until

you feel comfortable with it.

Page 4: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Every year hundreds of people are injured or killed when the equipment they are working on accidentally turns

on.

Page 5: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

These injuries and deaths could have been prevented by using a lockout/tagout.

Page 6: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

The purpose of DFCM’s Lockout/Tagout Program is to protect you.

Page 7: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

At the completion of this training you will be able to:

Be aware of different types of energy.

Recognize energy sources in the workplace.

Conduct a lockout/tagout. Know the limitations of tags.

Page 8: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

There are many types of energy present in facilities managed by DFCM

Hydraulic Electrical Chemical Mechanical Thermal Pneumatic

Page 9: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Each of these types of energy poses hazards if adequate precautions are not taken.

Page 10: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Lockout/Tagout Procedures

Page 11: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Every time equipment that relies on energy to operate is worked on it MUST be locked or tagged out.

Page 12: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

An exception to this rule is when you are working on a piece of equipment that can only receive energy through a plug.

If you have continuous control of the cord and plug, no

lockout/tagout is necessary.

Page 13: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Work Request

You should be able to tell from your work request if a lockout/tagout will be necessary.

If you are unsure about whether a lockout/tagout is required, check with your supervisor

Page 14: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Begin a Lockout/Tagout Log

Lockout/Tagout Logs are available at each facility. If a Lockout/Tagout is necessary for your work order, get a Log and complete the necessary information such as equipment number, name, etc.

Sometimes you may not have access to a Log before you work on equipment. In this case, complete your assignment and then fill out a Lockout/Tagout Log after you are done.

Page 15: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Gather necessary equipment

Every person has a lock assigned to them for locking out equipment. This equipment protects you!

A variety of additional lockout/tagout devices are available. Choose one that is appropriate to your needs.

Page 16: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Notify affected employees

Tell co-workers and other people who are effected by the shutdown of equipment that you are beginning a lockout/tagout. Complete a tag with the necessary information

Page 17: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Prepare the equipment for shutdown

Page 18: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Isolate energy sources

Page 19: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Place the lock and tag

Equipment that can receive a lock, must be locked out. Tags are not substitutes for locks.

Page 20: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Test and make sure the equipment you are working on is not energized.

Page 21: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Complete repairs or maintenance and remove the lockout/tagout

Page 22: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Re-energize and test the equipment

Page 23: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Remove tools and equipment from the work area.

Page 24: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Notify affected employees

Let employees affected by the lockout/tagout know that it has been completed and removed.

Page 25: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Complete the Lockout/Tagout Log

Page 26: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Different types of machinery may need different types of equipment to lock it out.

Make sure that you have the right equipment to perform the lockout/tagout.

Page 27: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Review of Lockout/Tagout Obtain work order Begin Lockout/Tagout Log Gather equipment Notify affected employees Prepare equipment for shutdown Isolate energy sources Place the locks and tags Test equipment and make sure the equipment is not

energized Complete repairs or maintenance Remove lockout/tagout Re-energize and test the equipment Remove tools and equipment from the work area Notify affected employees Complete a Lockout/Tagout Log

Page 28: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

This is a photograph taken of an electrical panel that was not locked out. Instead of a proper lockout/tagout, red tape was placed over the breakers.

Page 29: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

You must use DFCM’s Lockout/Tagout policy when working on equipment.

Corrective action may be taken when required safety procedures are not followed.

Page 30: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Group Lockout/TagoutFrequently more than one person will work on a piece of equipment. In such cases each person should attach his or her lock to the equipment. Hasps, which are available at all facilities, can hold several locks at a time.

This protects everyone working on the equipment since the equipment can’t be energized until every lock has been removed.

Page 31: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

ContractorsAt times contractors will also work on equipment. They must use a lockout/tagout program that protects them, as well as you. If you have questions about a contractor’s lockout/tagout process, check with your supervisor.

Page 32: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

TagsIf equipment can’t be locked out, tags must be used.

Page 33: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

WARNING Tags don’t provide the physical

restrain provided by a lock. Tags are not to be lifted. Tags must be legible. Tags must be securely fixed in an

obvious location. Tags can’t be reused.

Page 34: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Review Energy can be deadly. Following the Lockout/Tagout

Program can protect you from injury. Correct lockout/tagouts include the

actions which have been described. Tags do not provide the same level

of protection that locks do.

Page 35: Lockout/Tagout Training Division of Facilities Construction and Management 2001.

Congratulations! You have now completed the

Lockout/Tagout Training. Click to take the On-line Quiz when

you are ready.