7/27/2019 LM1 (1)
1/29
Logistics Management
Overall Industrial/ business
context
7/27/2019 LM1 (1)
2/29
Manufacturer
Distribution centre Distribution centre
Customer Customer Customer Customer
Suppliers
of
materialsand
services
Tier 1
Tier 2
Supply chain for a manufacturing firm
.
.
.
7/27/2019 LM1 (1)
3/29
Following terms are used almost
interchangeably:
Purchasing
Procurement
Materials management Logistics
Supply management
SCM
7/27/2019 LM1 (1)
4/29
Broadly defined, physical
distribution includes:
Transportation
Warehousing
Packaging Order processing
Inventory control
7/27/2019 LM1 (1)
5/29
N
A
B
C
D
E
F
G
H
I23 Km
15
15
22
Stage I Stage II Stage III
7/27/2019 LM1 (1)
6/29
Stage III analysis
Location Alternatives Remaining distance Optimal distance Optimal decision
D Go to G 16+21 37 Go to G
E Go to G 13+21 34 Go to G
H 17+19
F Go to G 23+21 32 Go to H
H 13+19
Stage II analysis
Location Alternatives Remaining distance Optimal distance Optimal decision
A Go to D 15+37 52 Go to D
E 25+34
B Go to D 17+37 49 Go to E
E 15+34
F 18+32
C Go to E 20+34 54 Go to E or F
F 22+32
7/27/2019 LM1 (1)
7/29
Stage I analysis
Location Alternatives Remaining distance Optimal distance Optimal decision
Factory N Go to A 18+52 70 Go to AB 23+49
C 17+54
----------------------------------------------------------------------------------------------------------------
Back tracking through the Tables of stage results, optimal route is:
Factory N-A-D-G-I with the total distance 70 Km.
7/27/2019 LM1 (1)
8/29
Key questions that must be
answered in the design of a
physical distribution system are: The number, location, and size of warehouses
The items to be stocked in each warehouse
Which plants or vendors are to supply which itemsto each warehouse
The customers to be served by each warehouse
The mode of transportation
The degree to which the company will carry out itsown distribution activities
The routing of vehicles
The selection of an inventory control system
7/27/2019 LM1 (1)
9/29
Distribution Requirements Planning
(DRP)
An approach that is characterized by the
planning of shipments out through a
planning horizon. DRP has been extended to DRP II, which
includes the planning of warehouse space,
personnel, and transportation equipment.
7/27/2019 LM1 (1)
10/29
Multi-echelon Distribution Systems
One or more stocking points between the plantand customer
A branch warehouse is frequently called adistribution centre (DC).
A warehouse that serves a group of satellitewarehouses is called a Regional DistributionCentre.
A company may choose this mode of operations
for the following reasons:(i) Faster service in filling customer orders
(ii) Transportation cost may be saved
(iii) Customers tend to feel more confident
7/27/2019 LM1 (1)
11/29
Two-echelon distribution system
Manufacturers plant
Central supply
DCA
DCB
DCN
7/27/2019 LM1 (1)
12/29
Three-echelon distribution system
Manufacturers plant
Central supply
DCA
DCB
DCN
Company
ownedretail
stores
7/27/2019 LM1 (1)
13/29
Design of the distribution system will
be affected by a number of factors:
The bulk, weight, and value of the product
The degree to which it is subject to
obsolescence and physical deterioration
Quantity of the product being distributed
The distances involved
Transportation tariffs The need for rapid delivery to customers
7/27/2019 LM1 (1)
14/29
Order point systems
A pull system can be based on any of theindependent demand inventory system. The DCwould periodically review the inventory of anitem and send an order to central supply if the
inventory were at or below an order point. Central supply supports two DCs A and B. A has
a forecast demand of 15 units of an item. Theinventory is reviewed at the beginning of eachweek. The safety stock is set at 10 units. Leadtime is two weeks, so the order point is(2x15)+10= 40. The order quantity based onEOQ considerations is 50.
7/27/2019 LM1 (1)
15/29
Ordering policy: OP/EOQ LT: 2 weeks Order point: 40
Forecast per period: 15 Safety stock: 10 Order quantity: 50
-----------------------------------------------------------------------------------------------------------------
Week: 1 2 3 4 5 6 7 8 9 10 11 12
Demand: 11 8 17 12 16 15 10 19 11 14 12 18
Receipts: 50 50 50
Available balance: 40 29 71 54 42 26 11 1 32 21 7 45 27
Order release: 50 50
-----------------------------------------------------------------------------------------------------------------
DC B has a forecast of 30 units per Wk., LT of 1 Wk. and a safety stock of 20 units.
The order quantity is 100. Initial available balance is 75.
Week: 1 2 3 4 5 6 7 8 9 10 11 12
Demand: 28 31 24 31 39 22 36 19 40 28 35 31
7/27/2019 LM1 (1)
16/29
DC B
Ordering policy: OP/EOQ LT: 1 week Order point: 50
Forecast per period: 30 Safety stock: 20 Order quantity: 100
-----------------------------------------------------------------------------------------------------------------
Week: 1 2 3 4 5 6 7 8 9 10 11 12Demand: 28 31 24 31 39 22 36 19 40 28 35 31
Receipts: 100 100 100
Available balance: 75 47 16 92 61 22 0 64 45 5 77 42 11
Order release: 100 100 100 100
-----------------------------------------------------------------------------------------------------------------
At central supply, average demand per Wk. is 15+30=45.
LT is 2 weeks. and the safety stock is 30. So the OP is (2X45)+30 = 120.
The order quantity = 200
Initial available balance = 30
Central supply
-----------------------------------------------------------------------------------------------------------------Week: 1 2 3 4 5 6 7 8 9 10 11 12
Demand: 100 150 150 100
Receipts: 200 200 200
Available balance: 30 230 130 130 130 130 -20 -20 -20 30 30 30 130
Order release: 200 200
-----------------------------------------------------------------------------------------------------------------
7/27/2019 LM1 (1)
17/29
In week 6, in spite of the substantial inventory of 130, a shortage of 20 units resulted.
Suppose that only 30 units are sent to DC A immediately and backorder remaining 20.
DC A receives 30 units in Wk. 8 and a shortage of 13 units would have occurred in
Wk. 10.
7/27/2019 LM1 (1)
18/29
Base-stock system
The principal advantage is that the replenishment of centralsupply is based on customer demand at the DCs rather thanon the replenishment orders from the DCs.
The principal features:
(a) Demand and inventory information is sent at frequentintervals from down-stream stocking points to all upstreamstocking points.
(b) A base stock is calculated for each item for each stockingpoint which is based on the inventory to be maintained at thatlocation and all downstream stocking points.
(c) At periodic intervals each stocking point places areplenishment order for a quantity equal to its base stockminus the sum of its own inventory position and the inventorypositions of all downstream locations.
7/27/2019 LM1 (1)
19/29
Consider the previous example.
The base stocks for DC A and B are calculated as the expected demand during an
Order cycle and a lead time, plus the safety stock.
All order quantities must be rounded up to multiples of 10, the number of units which
fit on a pallet.
DC A:
EOQ 50
Weeks in cycle = = = 3.3 ~ 3
Forecast/ period 15
L.T. in weeks = 2Total weeks = 5
Base stock = (5X15)+10 = 85
7/27/2019 LM1 (1)
20/29
DC B:
EOQ 100
Weeks in cycle = = = 3.3 ~ 3
Forecast/ period 30
L.T. in weeks = 1
Total weeks = 4
Base stock = (4X30)+20 = 140
--------------------------------------------------------------------------------
Central supply:
Weeks in cycle = 200/45 = 4.44 ~ 4
L.T. in weeks = 2
Total weeks = 6
Calculation for the base stock:
(6X45) + 30 = 300
Base stock for DC A = 85
Base stock for DC B = 140
Central supply base stock = 525
7/27/2019 LM1 (1)
21/29
DC A:
Ordering policy: Base stock LT: 2 weeks Order cycle: 3 weeks
Base stock: 85
-----------------------------------------------------------------------------------------------------------------
Week: 1 2 3 4 5 6 7 8 9 10 11 12
Demand: 11 8 17 12 16 15 10 19 11 14 12 18Receipts: 50 20 40 50
Available balance: 40 29 71 54 42 46 31 21 42 31 17 55 37
Order release: 20 40 50
Inventory position: 79 71 74 62 46 71 61 42 81 67 55 37
-----------------------------------------------------------------------------------------------------------------
An additional row of inventory position is added. It is the sum of available balance
and on order. As the order cycle is 3 weeks, an order should be released in Wk.3.
Order release = Base stockInv. Position
= 8571
= 14~ 20
7/27/2019 LM1 (1)
22/29
DC B
Ordering policy: Base stock LT: 1 week Order cycle: 3 weeks
Base stock: 140
-----------------------------------------------------------------------------------------------------------------Week: 1 2 3 4 5 6 7 8 9 10 11 12
Demand: 28 31 24 31 39 22 36 19 40 28 35 31
Receipts: 100 80 100 90
Available balance: 75 47 16 92 61 22 80 44 25 85 57 22 81
Order release: 100 80 100 90
Inventory position: 47 116 92 61 102 80 44 125 85 57 112 81
-----------------------------------------------------------------------------------------------------------------
7/27/2019 LM1 (1)
23/29
Central supply
Ordering policy: Base stock LT: 2 weeks Order cycle: 4 weeks
Base stock: 525
-----------------------------------------------------------------------------------------------------------------Week: 1 2 3 4 5 6 7 8 9 10 11 12
Demand: 100 20 80 40 100 50 90
Receipts: 200 210 180
Available balance: 30 230 130 110 110 240 200 200 100 230 230 140 140
Order release: 210 180 180
Inventory position:
DC A 79 71 74 62 46 71 61 42 81 67 55 37
DC B 47 116 92 61 102 80 44 125 85 57 112 81
Central supply 230 130 320 320 240 200 380 280 230 230 320 320
Total 356 317 486 443 388 351 485 447 396 354 487 438
-----------------------------------------------------------------------------------------------------------------
Order quantity released at the beginning of period 3 = 525317
= 208
~ 210
7/27/2019 LM1 (1)
24/29
Distribution Requirements Planning
Push system
Decisions on shipments are made at theupstream locations.
Rather than reacting to current conditions,orders are scheduled in advance based ondemand forecasts.
Generally a schedule of orders planned inthis way is frozen through a certainnumber of weeks.
7/27/2019 LM1 (1)
25/29
Planned replenishment of a two-echelon distribution system using DRP:
DC A
Ordering policy: DRP (EOQ/ time-phased O.P.) LT: 2 weeks
Forecast per period: 15 Safety stock: 10 Order quantity: 50-----------------------------------------------------------------------------------------------------------------
Week: 1 2 3 4 5 6 7 8 9 10 11 12
Forecast Demand: 15 15 15 15 15 15 15 15 15 15 15 15
Receipts: 50 50 50
Available balance: 40 25 60 45 30 15 50 35 20 55 40 25 10
Order release: 50 50
-----------------------------------------------------------------------------------------------------------------
DC B has a forecast of 30 units per Wk., LT of 1 Wk. and a safety stock of 20 units.
The order quantity is 100. Initial available balance is 75.
7/27/2019 LM1 (1)
26/29
DC B
LT: 1 week Forecast per period: 30 Safety stock: 20
Order quantity: 100
-----------------------------------------------------------------------------------------------------------------
Week: 1 2 3 4 5 6 7 8 9 10 11 12Forecast: 30 30 30 30 30 30 30 30 30 30 30 30
Receipts: 100 100 100 100
Available balance: 75 45 115 85 55 25 95 65 35 105 75 45 115
Order release: 100 100 100 100
-----------------------------------------------------------------------------------------------------------------
Central supply
Ordering policy: Lot for Lot LT: 2 weeks Safety stock: 0
-----------------------------------------------------------------------------------------------------------------
Week: 1 2 3 4 5 6 7 8 9 10 11 12
Gross Reqmt.: 100 50 100 50 100 100
Receipts: 200 20 50 100 100
Available balance: 30 130 130 130 80 0 0 0 0 0 0 0 0
Order release: 20 50 100 100
-----------------------------------------------------------------------------------------------------------------
7/27/2019 LM1 (1)
27/29
Actual inventory performance at the DCs
DC A
-----------------------------------------------------------------------------------------------------------------
Week: 1 2 3 4 5 6 7 8 9 10 11 12
Demand: 11 8 17 12 16 15 10 19 11 14 12 18Receipts: 50 50 50
Available balance: 40 29 71 54 42 26 61 51 32 71 57 45 27
Order release: 50 50
-----------------------------------------------------------------------------------------------------------------
DC B has a forecast of 30 units per Wk. Following are the actual demands:
Week: 1 2 3 4 5 6 7 8 9 10 11 12
Demand: 28 31 24 31 39 22 36 19 40 28 35 31
7/27/2019 LM1 (1)
28/29
DC B
-----------------------------------------------------------------------------------------------------------------
Week: 1 2 3 4 5 6 7 8 9 10 11 12
Demand: 28 31 24 31 39 22 36 19 40 28 35 31
Receipts: 100 100 100 100Available balance: 75 47 116 92 61 22 100 64 45 105 77 42 111
Order release: 100 100 100 100
-----------------------------------------------------------------------------------------------------------------
As the schedule of orders is frozen for 12 weeks, the actual performance at central
supply will be the same as the planned performance.
7/27/2019 LM1 (1)
29/29
Comparison:
Pull Push
OP Base stock DRP
DC replenishment orders 6 7 6
Central supply replenishment orders 2 3 4
Shortages Yes No No
Inventory in part/Wks. 1818 3168 1918
(Lowest) (78% increase (6% increase
as compared over OP/OQto OP) system)