LLC «Severstal-Gonvarri-Kaluga». SEVERSTAL–GONVARRI–KALUGA PLANNING First cut 23.06 First cut 18.10 First pack 19.07.

Mar 29, 2015

Download

Documents

Josef Rue
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: LLC «Severstal-Gonvarri-Kaluga». SEVERSTAL–GONVARRI–KALUGA PLANNING First cut 23.06 First cut 18.10 First pack 19.07.

LLC «Severstal-Gonvarri-Kaluga»

Page 2: LLC «Severstal-Gonvarri-Kaluga». SEVERSTAL–GONVARRI–KALUGA PLANNING First cut 23.06 First cut 18.10 First pack 19.07.

SEVERSTAL–GONVARRI–KALUGA PLANNING

First cut 23.06

First cut 18.10

First pack 19.07

Page 3: LLC «Severstal-Gonvarri-Kaluga». SEVERSTAL–GONVARRI–KALUGA PLANNING First cut 23.06 First cut 18.10 First pack 19.07.

GENERAL INFORMATION

Start of the project 2 quarter 2009

Put in the operation 3 quarter 2010

Investment in the non-current assets 30 million Euros

Production capacity is about 170 000 tons per year

Quantity of job positions: 50

Page 4: LLC «Severstal-Gonvarri-Kaluga». SEVERSTAL–GONVARRI–KALUGA PLANNING First cut 23.06 First cut 18.10 First pack 19.07.

LAYOUT STEEL SERVICE CENTER SGK

Page 5: LLC «Severstal-Gonvarri-Kaluga». SEVERSTAL–GONVARRI–KALUGA PLANNING First cut 23.06 First cut 18.10 First pack 19.07.

5

1 Blanking Line

2

Cut to length

3

Slitting Line

ITINERARY FOR FACTORY TOUR

Entry from GSK

Page 6: LLC «Severstal-Gonvarri-Kaluga». SEVERSTAL–GONVARRI–KALUGA PLANNING First cut 23.06 First cut 18.10 First pack 19.07.

EQUIPMENT

1 Blanking Line

1 Cut to Length Line

1 Slitting Line

Page 7: LLC «Severstal-Gonvarri-Kaluga». SEVERSTAL–GONVARRI–KALUGA PLANNING First cut 23.06 First cut 18.10 First pack 19.07.

BLANKING LINE

It’s a cutting line that process irregular shapes. Using a specific tool, forms can be adapted to the final shape of the part.

Technical capabilities

Input coil:

The thickness of the rolled metal: 0,6 - 3 mmCoil width: 200 - 1855 mmInternal diameter of the coil: 508 - 610 mmOuter diameter of the coil: 1000 - 2100 mm Maximum coil weight: 30 tons

Output blanks:

Maximum size of formats: 850x4000 mm The minimum size of formats : 200x200 mm

Uncoiling maximum speed 90 m/minFeeding maximum speed 120 m/minAbility to provide accuracy along the length of ± 0,1 mm

Page 8: LLC «Severstal-Gonvarri-Kaluga». SEVERSTAL–GONVARRI–KALUGA PLANNING First cut 23.06 First cut 18.10 First pack 19.07.

SLITTING LINE

Technical capabilities

Input coil: The thickness of the rolled metal: 0,8 – 6 mm Coil width: 600 - 1850 mm Internal diameter of the coil: 508 -610 mm Outer diameter of the coil l: 900 – 2100 mm Maximum coil weight: 32 tons

Output coil:

Internal diameter: 508 -610 mmMaximum outer diameter: 2100 mmMaximum weight: 32 tonsMinimum strip width 30 mm (depending on the

thickness of rolled metal)

Maximum processing speed 300 m/min Ability to provide accuracy along the width of ± 0,5 mm

Page 9: LLC «Severstal-Gonvarri-Kaluga». SEVERSTAL–GONVARRI–KALUGA PLANNING First cut 23.06 First cut 18.10 First pack 19.07.

CUT TO LENGTH LINE

Technical capabilities

Input coil:

The thickness of the rolled metal: 0,5 – 3 ммCoil width: 200-1850 mm Internal diameter of the coil: 508-610 mm Outer diameter of coil: 900–2100 mm Maximum coil weight: 30 tons

Output parameters of sheets:

Maximum sheet length: 4000 mm Minimum sheet length: 200 mm Maximum weight stack: 10 tons

Maximum processing speed 90 m/minAbility to provide accuracy along the length of ± 0,5 mm