Top Banner
LIGO-G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004
20

LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

Dec 18, 2015

Download

Documents

Bryan Ross
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LIGO-G040332-00-M

State of the LIGO Lab

Stan Whitcomb

LSC meeting Hanford

17 August 2004

Page 2: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 2LIGO-G040332-00-M

LIGO Science Runs

S22nd Science Run

Feb - Apr 03(59 days)

S11st Science Run

Sept 02(17 days)

S33rd Science RunNov 03 – Jan 04

(70 days)

LIGO Target Sensitivity

S3 Duty Cycle

Hanford 4km

69%

Hanford 2km

63%

Livingston 4 km

22%*

Page 3: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 3LIGO-G040332-00-M

Summary Science Run Metrics

RUN S1 S2 S3

IFO

BNS RANGE

(kpc)

DUTY FACTOR

(%)

BNS RANGE

(kpc)

DUTY FACTOR

(%)

BNS RANGE

(kpc)

DUTY FACTOR

(%)

L1 ~150 43% 900 37%800-1500

22%

H1 ~30 59% 350 74%1500-5000

69%

H2 ~40 73% 200 58%600-1100

63%

3-way 24% 22% 16%

Page 4: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 4LIGO-G040332-00-M

Shot Noise Improvements at LHO

• Coordinated improvements in several areas

» Increase laser power (refurbish lasers after years of service)

» Thermal compensation system for ITMs

» Added photodiodes to share power

» Develop sequencing to get to high power operation

Page 5: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 5LIGO-G040332-00-M

Noise Improvements at LHO

Page 6: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 6LIGO-G040332-00-M

EMC/acoustic mitigation retrofit at LLO

• EMC & acoustics retrofit in progress, end stations complete & working (also in commissioning)

Page 7: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 7LIGO-G040332-00-M

HAM

BSC

External Pre-Isolators

Seismic Remediation at LLO

Page 8: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 8LIGO-G040332-00-M

HEPI Installation

Page 9: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 9LIGO-G040332-00-M

HEPI Performance—One Arm Test

Success

Page 10: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 10LIGO-G040332-00-M

LDAS -- Software Infrastructure

• LDAS project integrated into DASWG activities » 1.2.0 release of LDAS in late August - early September

• ITR2003 task -- TCL/Globus Integration Project» Continuing to work with LBNL on combined SWIG/Globus Project

which unifies TCL and Python steering language extensions

» http://tclglobus.ligo.caltech.edu

• S4 Preparation» Enhance RDS generation code to support longer file sizes

» Upgrade to newest DB2 database server

» Support for faster commercial compilers

» Support for file types other than .gwf (frame files) in diskCacheAPI

Page 11: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 11LIGO-G040332-00-M

Data archive/Computing

• All 4 Lab clusters: CIT, LHO, LLO, and MIT are now running Grid as well as LDAS jobs. » 2.2THz of CPU cycles

» Current usage can be monitored from the LSC Data Grid web page along with the LSC clusters: http://www.lsc-group.phys.uwm.edu/lscdatagrid/

» Allows users to make decisions on where to run their jobs

• All Science and Engineering run data has been migrated from HPSS to SAM-QFS for easier access and long-term archiving..» ~ 20,000,000 frame files managed in archive

» Some old trend frames from between runs still remains to be migrated over the next 1-2 Months

Page 12: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LIGO-G040332-00-M

•Measured mirror phasemaps being used with FFT model

•Allows:» Evaluation/modeling of large BS curvature effect on SB imbalance

»Realistic beam profile simulation

–phase camera image and error signal

Interferometer Modeling--FFT simulation

LHO4k BS ROC:200km SB imbalance : ITMx cold, ITMy hot

Flat BS Curved BS

Page 13: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 13LIGO-G040332-00-M

Advanced LIGO R&D Highlights

• Seismic Isolation» Successful implementation of

HEPI

» Further commissioning of platform at Stanford

• Suspensions» Installation of Mode Cleaner triple

suspension at LASTI

• ISC/40m» Completed installation, locked

lots of bits

» Found problem with locking scheme (sidebands on sidebands)….probably found solution (Mach-Zehnder)

Page 14: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 14LIGO-G040332-00-M

Advanced LIGO R&D Highlights

• Pre-stabilized laser » Power Stage injection locked» 170 W, single frequency laser!

• Input Optics» Thermal focusing/matching

approach successfully prototyped

• Auxiliary Optics/Thermal compensation» Successful application to initial LIGO» Analysis includes inhomogeneity of coating absorption – important for

substrate selection

Master Slave IISlave I

Page 15: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 15LIGO-G040332-00-M

Advanced LIGO R&D Highlights

• Coatings» Reductions in absorption with

increasing dopant in Titania (LMA)

» Need another factor 2-3 reduction…

• Core Optics» Focus on substrate selection

» Many factors – astrophysics, implementation, risks

» Important to get LSC input at this meeting

Page 16: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 16LIGO-G040332-00-M

AdvLIGO Status as a Project

Advanced LIGO proposal submitted in early 2003 and was reviewed in June 2003

• Reviews very favorable

• Next step is NSB discussion/approval and scheduling in MREF account

• Should be considered later this year (October?)

• Earliest MREF funding start FY 2007 (Oct 2006)• Depends critically on future funding levels for NSF

• Developing detailed project management data (cost, schedule, technical work packages)

• Advanced LIGO organization interacts with up-coming Lab operations renewal, evolving relation between Lab and LSC

Page 17: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 17LIGO-G040332-00-M

LIGO Outreach Activities

• New outreach coordinators at both observatories» Dale Ingram at LHO

» John Thacker at LLO

National Astronomy Day at LHO

School Group Tour at LLO

Page 18: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 18LIGO-G040332-00-M

LIGO Outreach Collaboration

• Newly funded collaborative effort focused on Louisiana» LIGO provides scientific motivation and constructs/operates

visitor center

» Exploratorium provides hands-on exhibits, experience with interactive learning, teacher workshops

» Southern University brings LIGO science to science education, training for pre-service teachers

» Louisiana Board of Regents extends our program through public education, provides links to schools and teachers

• Other Lab-LSC collaborative efforts welcome» Example: Steve Penn and Greg Baker

Page 19: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 19LIGO-G040332-00-M

Challenges

• Commissioning progress will be harder as we near the design goal

• Need more fire in the belly to find GWs

• Need to change our mode of operation, to accommodate longer runs

• New LIGO Lab operations contract has triggered discussions on the relationship between LSC and LIGO Lab

Page 20: LIGO- G040332-00-M State of the LIGO Lab Stan Whitcomb LSC meeting Hanford 17 August 2004.

LSC Meeting -- August 2004 20LIGO-G040332-00-M

Plan for S4

• Goal to have more flexibility to react to conditions as we approach and initiate the run

• Peter Fritschel chairs run planning committee » Representatives from commissioning, GEO, LSC, Lab, …» Recommends timing, duration, goals for run» Ability to delay or modify run if conditions warrant

• Tentative plan» S4 to be held starting in January 2005, ~ 4 weeks duration» Engineering run(s) approximately 1 month in advance» Sensitivity goals: H1 7.5 Mpc, L1 4Mpc, H2, 2 Mpc» Duty cycle goal: All Individuals 70%, triple 40%» “Science content” ~ 5-10 times S3

• ~6 month commissioning interval, followed by long S5 (latter half of 2005)