Top Banner
LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB SAN FRANCISCO PUBLIC LIBRARY PROGRAM STATUS UPDATE DECEMBER 4, 2014
13

LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

Jun 09, 2018

Download

Documents

trinhthu
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

LIBRARY CAPITAL PROGRAMS:

BLIP & THE TEEN DIGITAL MEDIA LAB

SAN FRANCISCO PUBLIC LIBRARY

PROGRAM STATUS UPDATE

DECEMBER 4, 2014

Page 2: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

BRANCH LIBRARY IMPROVEMENT PROGRAM

Page 3: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

BLIP BUDGET & EXPENDITURES TO DATE

SAN FRANCISCO PUBLIC LIBRARY

3

Approved Budget - $196,259,350 as of 2/16/12

Revenue - $196,259,350 as of 2/16/12

Appropriations - $196,259,350 as of 2/16/12

Expended and encumbered - $183,020,146 as of 10/31/14

Page 4: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

STATUS OF BLIP

SAN FRANCISCO PUBLIC LIBRARY

4

7 Property Acquisitions complete

Support Services Facility in operation

24 branches Complete and Open:

Excelsior, Mission Bay, West Portal, Sunset, Marina,

Glen Park, Western Addition, Noe Valley, Portola,

Richmond, Ingleside, Eureka Valley, Bernal Heights,

Potrero, Parkside, Park , Presidio, Merced, Anza,

Visitacion Valley, Ortega, Golden Gate Valley,

Bayview, and North Beach.

Old North Beach Library – Demolition complete

Fiscal Closeout – in progress

Page 5: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

TEEN DIGITAL MEDIA LAB CAPITAL PROGRAM

Page 6: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

TEEN DIGITAL MEDIA LAB

CAPITAL PROGRAM EXPENDITURES TO DATE

PHASE DESCRIPTION

OCT 2014

EST. BUDGET

ACTUALS AS

OF 10.31.14

ENC. AS OF

10.31.14

BAL AS OF

10.31.14

Phase 1: Tenant Improvements for

Administrative Space

(Lower Level, 4th & 6th Floors)

Construction $716,830 $627,986 $48,752 $40,092

Furniture, Fixtures & Equipment (FF&E) $219,757 $197,412 $22,298 $47

Architectural & Engineering (A&E) Fees $179,017 $176,683 $0 $2,333

Permits $15,905 $15,905 $0 $0

Contingency $0 $0 $0 $0

DPW Construction Management $32,445 $30,012 $1,011 $1,422

Phase 1: Tenant Improvement Total $1,163,954 $1,047,998 $72,061 $43,895

Phase 2: Literacy & Learning Center

The Bridge at the Main

Construction $1,143,005 $795,710 $243,884 $103,411

FF&E $187,399 $28,580 $155,824 $2,995

A&E Fees $273,117 $273,117 $0 $0

Permits $13,259 $13,259 $0 $0

Contingency $0 $0 $0 $0

DPW Construction Management $66,427 $61,190 $0 $5,237

Phase 2: Literacy & Learning Center Total $1,683,206 $1,171,856 $399,708 $111,642

Phase 3: Teen Digital Media Lab

The Mix at SFPL

Construction $2,083,705 $0 $2,057,612 $26,093

FF&E $330,500 $0 $0 $330,500

A&E Fees $886,932 $728,343 $57,088 $101,501

Permits $27,000 $25,776 $0 $1,224

Contingency $391,142 $0 $0 $391,142

DPW Construction Management $233,561 $108,045 $7,748 $117,768

Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164 $2,122,448 $968,228

Capital Project Phases 1-3 Grand Total $6,800,000 $3,082,018 $2,594,217 $1,123,765

Capital Program Reserve $0 $0 $0 $0

CAPITAL PROGRAM GRAND TOTAL $6,800,000 $3,082,018 $2,594,217 $1,123,765

6

Page 7: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

TEEN DIGITAL MEDIA LAB CAPITAL PROGRAM STATUS

Phase 1 Administrative Office Relocations & Tenant Improvements:

• Tenant improvement completed in Summer 2014

Phase 2 Literacy & Learning Center:

• Literacy & Learning Center - The Bridge

o Construction completed in Fall 2014

• 1st floor bathroom ADA renovations:

o Renovations in progress

Phase 3 Teen Digital Media Lab:

• Demolition completed in Fall 2014

• Construction in progress

• Project completion anticipated in Spring 2015

SAN FRANCISCO PUBLIC LIBRARY

7

Page 8: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

PHASE 1 TENANT IMPROVEMENTS: Information Technology

SAN FRANCISCO PUBLIC LIBRARY

8

Page 9: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

PHASE 1 TENANT IMPROVEMENTS: Chief of Main &

Chief of Community Programs & Partnerships

SAN FRANCISCO PUBLIC LIBRARY

9

Page 10: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

PHASE 1 TENANT IMPROVEMENTS: Human Resources

SAN FRANCISCO PUBLIC LIBRARY

10

Page 11: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

PHASE 2: LITERACY & LEARNING CENTER

- THE BRIDGE AT THE MAIN

SAN FRANCISCO PUBLIC LIBRARY

11

Page 12: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

TEEN DIGITAL MEDIA LAB:

CONCEPTUAL DESIGN

Page 13: LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA LAB · LIBRARY CAPITAL PROGRAMS: BLIP & THE TEEN DIGITAL MEDIA ... Phase 3 Teen Digital Media Lab Total $3,952,840 $862,164

PHASE 3: TEEN DIGITAL MEDIA LAB

SAN FRANCISCO PUBLIC LIBRARY

13