LHC Ramp Commissioning Mike Lamont Reyes Alemany-Fernandez Thanks to: Stefano, Verena, Walter
Dec 26, 2015
LHC Ramp Commissioning
Mike Lamont
Reyes Alemany-Fernandez
Thanks to: Stefano, Verena, Walter
LHC ramp commissioning 29/5/2007
LHC ramp commissioning Ramp generalities Overall strategy Beam entry conditions and tolerances Entry conditions Procedures Exit conditions What’s in place Upcoming tests
LHC ramp commissioning 39/5/2007
Magnets The basic design of the LHC ramp (parabolic, exponential, linear,
parabolic (PELP)) is designed to: P: Push up the time in which the snapback is resolved. E: Constant Bdot – ramp induced coupling current L: Max dI/dt of MB power converters P: smooth round off at top energy
Start [s] End [s] Start p [GeV] End p [GeV]
Snapback 0 70 450 ~500
Parabolic 0 405 450 ~900
Exponential 405 820 ~920 ~2400
Linear 820 1500 ~2400 ~6800
Parabolic 1500 1600 ~6800 7000
LHC main dipole proposed baseline current ramping - Bottura, Burla and Wolf
LHC ramp commissioning 49/5/2007
Ramp Construction
Construct idealized MB current function (PELP) using standard prescription (defined in terms of current variation during snapback etc.)
From this generate momentum(t) using averaged calibration curve
Use this a scale parameter for settings generation Optics defined as a function of time
Design optics (Note change of IR2 optics)
Circuit currents via FiDeL generated calibration curves
LHC ramp commissioning 59/5/2007
Nominal cycle
0
14000
-3000 -2000 -1000 0 1000 2000 3000
Time [s]
MB
cu
rre
nt
0
1
2
3
4
5
6
7
8
9
B [
T]
RAMP DOWNSTART RAMP
PHYSICS
PREPAREPHYSICS
BEAM DUMP
PREINJECTIONPLATEAU
INJECTION
T0 Tinj
SQUEEZE
PHYSICS
Ramp down 18 Mins
Pre-I njection Plateau 15 Mins
I njection 15 Mins
Ramp 28 MinsSqueeze 5 Mins
Prepare Physics 10 MinsPhysics 10 - 20 Hrs
I ~ t2
I ~ et
I ~ t
Injection plateau 0alpha 5.92105E-06current rate end snapback 0.6current at injection 760current variation during snapback 20parabolic segment duration 405.333current at end exp 4110.000b at end exp 3.000current to field scaling factor 1370.000max current rate 10.000current rate end parablolic 3.648exp time constant inverse 2.433E-03
LHC ramp commissioning 69/5/2007
Possible variations
Skip exponential Ramp induced inter-strand coupling currents small Simplifies ramp structure – easier to stop anywhere Cost – one minute per ramp
Slower snapback Measurements planned to check dependency
Programmed stop in ramp Parabolic – (Linear) - Parabolic
Pre-cycle (as entry condition) Snapback minimization – particularly during commissioning
LHC ramp commissioning 79/5/2007
Stopping with beam in the ramp
Must be programmed before starting the ramp with appropriate round-off behaviour of the functions Might need to handle (much reduced) decay after the stop
Restart with beam is possible in theory. requires a new set of functions to be loaded including corrections for handling the associated snapback during commissioning will be dumping the beam
Used for commissioning of beam dump, beam loss monitors, beam measurements, optics checks, physics...
LHC ramp commissioning 89/5/2007
Settings/Trim
Run to run feed forward Feed forward from feedback system Incorporation of TRIMs into settings before ramping
Ensure and test compatibility with feedbacks and make sure that machine safety cannot be compromised
constant strength, smoothed out etc. as appropriate. This will be configurable depending on the parameters involved. The
appropriate strategy will be decided based on common sense and experience with beam.
Real time knobs on key beam parameters (tune, chromaticity) are planned. To be tested during commissioning.
LSA
LHC ramp commissioning 99/5/2007
Magnets Transfer functions DC components
Geometric, DC magnetization, Saturation, Residual MB MQ (Decay &) Snapback predictions
b1, b2, b3, b5, a2, a3… Cycling prescriptions – all magnets Corrector Hysteresis
Handled on-line by LSA’s implementation of FiDeL Snapback “on the fly” invocation and incorporation
Import of FiDEL coefficients into LSA database in progress
LHC ramp commissioning 109/5/2007
Power converters
Load I(t) to all 1700 power converters Ramp won’t load if I(0) not within 0.01 of actual reference value 100 µs granularity up to 5000 points, maximum duration 400000 s. Linear interpolation of supplied points FGC runs full table – no stop/re-start Abort running ramp possible - don’t expect to keep the beam There can be no trims after loading the ramp Changes can still be put through the real time channel, however,
the real time TRIMs are not ramped Ramp start on receipt of timing event
LHC ramp commissioning 119/5/2007
RF Use multiplexed FGCs for function generation
The FGC2_RF will generate sixteen 16-bit integer functions at 1 kHz and will use the RFC-500 card to distribute the function values to the relevant nodes on the bus
Will ramp: 2*8*Cavity voltages & phase Coupler positions RF frequency (offset from 400 MHz). Both rings nominally locked
to the same frequency to avoid re-phasing before physics gain of the phase loop gain and time constant of the synchro loop Plus transverse damper etc.
LHC ramp commissioning 129/5/2007
Radial Loop
Fixed radial position, variable frequency Adjusts RF frequency to centre beam at pickup in IR4
measure frequency offset and feed correction forward into functions [LSA]
Choices Single pickup as planned Global orbit average – correct via RT system (robust) Two pick-ups at Pi Feed forward – check mean orbit – implies RT global orbit
acquisition – correct either radial loop reference or frequency
LHC ramp commissioning 139/5/2007
Beam Dump Loaded with the reference energy ramp On-line secure energy monitoring MSD/Q4 – FGC – I(t) locked in MKD, MKB kicker and MSD septum energy tracking
Extract single pilot at pre-defined energies in the ramp (calibrated points)
Check MKD kicker “fine” timing adjustment
Brennan Goddard
Cham 2006
Orbit/aperture
Extraction trajectory
Instrumentation
Kicker timings, retriggering
Post mortem and XPOC
LHC ramp commissioning 149/5/2007
LBDS beam commissioning – pilot beamLBDS beam commissioning activity LHC mode Beam type Energy GeV
Things to do before first pilot extraction
IR6 optics measurements Injection Circulating 1 pilot 450
Commission dedicated LBDS BDI in IR6 Injection Circulating 1 pilot 450
Extraction element aperture measurements Injection Circulating 1 pilot 450
… before first pilot ramp
First extractions: rough timing adjustment Inject & dump Extract 1 pilot 450
TD line BDI commissioning Inject & dump Extract 1 pilot 450
Extraction trajectory and aperture measurements Inject & dump Extract 1 pilot 450
Data diagnostics: IPOC, logging, FDs, PM, XPOC Inject & dump Extract 1 pilot 450
MKD waveform overshoot measurements Inject & dump Extract 1 pilot 450
MKB sweep measurements Inject & dump Extract 1 pilot 450
… with the pilot ramp
Energy tracking measurements Ramp Extract 1 pilot 450-7000
…before moving to operation with potentially “unsafe” beams
Fine timing adjustment Inject & dump Extract 2 pilots 450
Commission SW interlock on beam position at TCDQ Injection Circulating, safe beam 450
Commission IR6 orbit BPM interlock Injection Circulating, safe beam 450
Commission abort gap watchdog Injection Circulating, safe beam 450
TCDQ “injection setting” positioning Injection Circulating, safe beam 450
Fine timing in ramp Ramp Extract 2 pilots 450-7000
TCDQ positioning at 7 TeV Adjust/squeeze Circulating, 1 pilot 7000
= time consuming
LHC ramp commissioning 159/5/2007
Collimators
Motor positions(t) down loaded to controllers Functions triggered with timing event Settings maintained on LSA with full parameter space
defined (position, angle, emittance, Twiss etc.)
High Intensity ramp behaviour defined C. Bracco: Collimator settings during the energy ramping
Low Intensity ramp commissioning Cleaning not an issue, protection. Set TCDQ/TCS at ±10 at 450 GeV, primary at 7-8 Good enough for intermediate energies Provides protection at 7 TeV, but still might want to bring them in
Stefano and Delphine
LHC ramp commissioning 169/5/2007
Timing System
Timing table(s) pre-configured and loaded to the CBCM Start PC ramp Start RF ramp Start collimator ramp BPM – closed orbit/capture BLM – burst Fly Wire Scanner Etc. etc.
Executed on request by timing system
LHC ramp commissioning 179/5/2007
Measurements on ramp
Periodic BCT/Lifetime Synchrotron light monitors Beam Loss Monitors Schottky WCM
Continuous Tune PLL – clear priority Chromaticity
RF modulation (Synch with orbit -> dispersion) Ramp – different frf
“Slow” orbit acquisition ~ 1 Hz RT orbit acquisition ~10 Hz
LHC ramp commissioning 189/5/2007
Measurements at intermediate energies
Tunes, Chromaticity, Orbit, Coupling Tracking between sectors Transfer functions Beta beating
LHC ramp commissioning 199/5/2007
Feedback using the PLL tune system Tune feedback requirements
Stable PLL tune measurement system Knowledge of correction quad transfer functions
already known from initial tune corrections Implementation of feedback controller
Coupling feedback requirements Stable PLL tune measurement system Knowledge of skew quad transfer functions Implementation of feedback controller
Chromaticity feedback requirements Stable PLL tune measurement system RF frequency modulation
All of these will require dedicated beam time for testing the control loop response and the final closing of the loop.
Rhodri Jones
LHC ramp commissioning 209/5/2007
Machine Protection
Single beam through snapback
Switch to nominal cycle
Ramp – single beam
Single beam to physics energy
Two beams to physics energy
Start
End
Low intensity, single bunch, low energy... same as at 450 GeV BLMs: acquisition – no dump,
check losses against thresholds collimators & TDCQ coarse
settings
Critical machine protection systems must be in place minimum subset of BLMs
connected to beam interlock system
collimators interlocked in place local orbit stabilisation around
beam cleaning insertions and dump region
further commissioning of beam dump & BLMs
BEM & SBF
Overall strategy
LHC ramp commissioning 229/5/2007
Initial Ramp Commissioning
Baseline 450 GeV commissioning Snapback light pre-cycle Pilot beam Wait it out at injection Snapback using FiDeL predictions Ramp to reduced energy Recycle full machine Thus in seven steps with seven ramps to seven TeV Repeat for beam 2
Procedures
LHC ramp commissioning 249/5/2007
LHC Stage A: Commissioning phasesPhase Description
A.1 Injection and first turn: injection commissioning; threading, commissioning beam instrumentation.
A.2 Circulating pilot: establish circulating beam, closed orbit, tunes, RF capture
A.3 450 GeV initial commissioning: initial commissioning of beam instrumentation, beam dump
A.4 450 GeV optics: beta beating, dispersion, coupling, non-linear field quality, aperture
A.8 Snap-back and ramp: single beam
A.9 Top energy checks: single beam
A.6 450 GeV Two beam operation
A8.b Ramp two beams
A.10 Top energy checks: two beams
A.5 450 GeV Increasing intensity: prepare the LHC for unsafe beam
A.11 Top energy: collisions
A.12 Squeeze: commissioning the betatron squeeze in all IP's
Commission snap-back corrections Commission the RF up to top energy Commission beam dump and machine protection (MPS) at different
intermediate energies Commission BI acquisition in the ramp
Snap-back & Ramp with single pilot beam – Basic Objectives
LHC ramp commissioning 259/5/2007
Overview of Steps Involved
Step Activity Priority
A.8.1 Prepare ramp:Prepare ramp: Correction of snap-back and TRIM incorporation; beam 1
1
A.8.2 Ramp Ramp beam 1 up to pre-defined energy steps (E=1TeVE=1TeV); commission the RF systemRF system
1
A.8.3 CheckCheck the key instrumentationinstrumentation and control key beam beam parametersparameters: orbit, tune, coupling, chromaticity
1
A.8.4StopStop in the ramp and commission beam dumpcommission beam dump and machine machine protection systemsprotection systems at intermediate energies. Perform beam based checks at intermediate energies
1
A.8.5 Ramp to 7 TeVRamp to 7 TeV, beam 1 1
A.8.6 Repeat A.8.1 to A.8.5 for beam 2 1
LHC ramp commissioning 269/5/2007
Beam Entry Conditions
Beam Entry conditions: One bunch, Ib = 5x109 p to 3x1010 p Separate commissioning for beam 1 and beam 2 Nominal beam emittance (value agreed for ramping)
Beam tolerances: 450 GeV tolerances should also apply for the ramp as
the available beam aperture stays constant Need to allocate budgets for static and dynamic
tolerances Relaxed tolerances on key beam parameters
LHC ramp commissioning 279/5/2007
Entry conditionsEntry Description
E.A.8.1 First optimization of the machine at 450 GeV done
.01Tune, chromaticity, orbit, coupling measured and corrected beta beating at least measured. Aperture reasonably well established
.02 All circuits up to b3 commissioned – polarities check with beam, etc
.03 Collimators providing basic protection
.04PC OFF: Skew sextupoles; octupoles spool pieces; decapoles spool pieces; crossing angle; spectrometer magnets; experiments solenoids and separation bumps
E.A.8.2 Settings generation
.01LSA parameter space fully defined. Settings generation available and debugged. Ramps to pre-defined intermediate energies.
.02Decay/snapback effects will be handled by LSA’s implementation of FiDEL. Pre-cycles defined.
.03 RF functions (frequency & voltage etc.) available
.04Collimator ramp settings (not used initially but there with all functionality tested)
LHC ramp commissioning 289/5/2007
Entry conditions
Entry Description
E.A.8.3 Power Converters
.01 All operational functionality tested.
E.A.8.4 BI
.01 BCT commissioned
.02 Closed orbit acquisition
.03 PLL commissioned
.04 BCT & lifetime commissioned
.05 Synchrotron light monitors commissioned (not critical)
E.A.8.5 Feedbacks
.01 Orbit (1) and tune (2) feedbacks are the priority.
LHC ramp commissioning 299/5/2007
Entry conditions
Entry Description
E.A.8.6 Machine protection
.01 Critical BLMs commissioned and connected to the BIS
.02 Collimators interlocked in place
.03Local orbit stabilization around beam cleaning insertions and dump region
.04 Further commissioning of beam dump(*) and BLMs
.05 Intensity versus energy logic in SBF tested
E.A.8.7 Controls
.01 Timing system fully commissioned/input to equipment
.02 Ramp timing table populated
03 Logging & data acquisition criteria established
LHC ramp commissioning 309/5/2007
Stage A.8.1 – Prepare ramp
Step Activity Group Priority
A.8.1 Prepare ramp, single beam, ring 1
.01Snap –back prediction, incorporation into functions, decay at stop point to be anticipated
MA/OP 1
.02 450 GeV trim incorporation OP 1
.03 Prepare RF: RF/OP 1 Load RF functions Radial loop on – to be done after last injection and before start ramp
LHC ramp commissioning 319/5/2007
Stage A.8.1 – Prepare ramp
Step Activity Group Priority
A.8.1 Prepare ramp, single beam, ring 1 (cont.) 1.04 Transverse feedback not needed in the first instance.05 Load Power Converters (Table) OP
.06Collimators (not ramped during first attempts to lower energy)
OP
.07 Timing table configured and loaded OP
.08 BLM thresholds up the ramp - check BI
.09 TDI, TCT, TCLI out. Kickers off.0.10 Check BLMs threshold table (energy dependence)
LHC ramp commissioning 329/5/2007
Stage A.8.2 – Ramp single beam
Step Activity Group Priority
A.8.2 Ramp single beam; ring 1
.01 Send timing event: Start Ramp
.02Monitor: Lifetime, tunes, orbit, energy, beam losses, beam sizes (synchrotron light)
OP
.03 Measure: Capture losses (flash loss of out-of-bucket beam at start of ramp) Continuous measurements of frequency response of loops during ramp
RF Parasitic
Bunch length (emittance growth), RF noise RF Parasitic
.04Feed-forward of measured frequency offset for eventual switch to synchro-loop operation
RF 2 Parasitic
LHC ramp commissioning 339/5/2007
Stage A.8.2 – Ramp single beamStep Activity Group Priority
A.8.2 Ramp single beam; ring 1 (Cont.).06 Feedbacks:
Orbit feedback: Synchronized acquisition and feed-forward Global orbit feedback a.s.a.p.
OP 1
PLL: Continuous tune, coupling High priority: feed forward
OP/BI 1
Tune and coupling: First ramps can be attempted w/o these feedbacks, however, in our interest to commission them a.s.a.p. Critical will be measurements to monitor variations during snap-back and in the ramp
OP/BI 3
.07
Tracking: the real time orbit acquisition allows us to check the relative tracking during the ramp with similar or better accuracy in delta (use difference w.r.t. injection) as compared to injection
OP
LHC ramp commissioning 349/5/2007
Stage A.8.2 – Ramp single beam
Step Activity Group Priority
A.8.2 Ramp single beam; ring 1 (Cont.)
.08 Transfer functions (may be difficult). MA
.09 Chromaticity OP/BI 1 RF modulation synchronized with orbit/dispersion 1
.10Beta beating measurement at intermediate energies – local orbit checks
OPABP
LHC ramp commissioning 359/5/2007
Stage A.8.3 – Post Ramp analysis
Step Activity Group Priority
A.8.3 Post Ramp analysis
.01Feed-forward of measured frequency offset for eventual switch to synchro-loop operation
RF/OP
.02 Feed-forward of tune measurements ABP/OP 1
.03Analysis of orbit and feed-forwarded of orbit corrections (if GOFB not operational)
ABP/OP 1
.04Analysis of GOFB correction and feed-forward if operational
ABP/OP 2
.05 Beta beating ABP/OP
LHC ramp commissioning 369/5/2007
Stage A.8.4 – Beam at Intermediate EnergyStep Activity Group Priority
A.8.4 Beam at Intermediate Energy.01 Follow decay of tune, chromaticity and orbit OP/ABP 1
.02Measure tune, coupling, orbit – only correct if really required
OP/ABP 1
.03 Check optics OP/ABP 1
.04 Monitor beta beating OP/ABP.05 Beam dump commissioning AB/BT 1
Check energy tracking calibration (MKD, MSD, MKB) Orbit/aperture Extraction trajectory Instrumentation Kicker timings, retriggering Post mortem and XPOC
LHC ramp commissioning 379/5/2007
Stages A.8.5 – A.8.7A.8.5 Iterate:
• Dump at progressively higher energies: proposal: 7 steps from 450 GeV to 7 TeV
• Repeat previous stages at each benchmark energy• The full procedure will have to be repeated for beam 2
A.8.6 Commission Collimators in the ramp (Group Coll)
• Procedure should have essentially been commissioned without beam• Watch closed orbit at collimators and related beam losses • No cleaning issue for pilot.. Primary needs to be defined• 10 sigma TCDQ at 450 GeV, primary closer – could leave for first attempts • based on findings during 450 GeV optimization
A.8.7 Commission Feedback using PLL (Group BI)
• If at first you don’t succeed
LHC ramp commissioning 389/5/2007
Exit Conditions Reasonable transmission of pilot through snap-back (first
minute of the ramp) Single pilot at 7 TeV – ramp transmission good enough to
get pilot intensity up Beam dumps commissioned up to 7 TeV Machine Protection good for these intensities to 7 TeV
At the end of this phase:- we can proceed with top energy checks with single beam
What have we got?
LHC ramp commissioning 409/5/2007
Settings Generation
Optics & Twiss import Ramp & squeeze – all circuits Fully integration of LHC power converters Ramp and squeeze tests performed.
Driven by proto-sequencer
Collimators Inc. parameter space – Twiss parameters as functions
RF Incoming
BLMs Just started wrestling with the threshold tables
LHC ramp commissioning 419/5/2007
Collimators Stefano Redaelli
LHC ramp commissioning 429/5/2007
Ramping – IR8
LHC ramp commissioning 439/5/2007
FiDeL Marek
LHC ramp commissioning 449/5/2007
Timing Delphine Jacquet
LHC ramp commissioning 459/5/2007
Sequencer
Requirements specification Mike, Reyes & Fermilab
First prototype in place Tasks, sub-sequences, sequences, external conditions defined
on database
Demo
Vito Baggiolini
Roman Gorbonosov
Reyes Alemany
Greg Kruk
Mike Lamont
LHC ramp commissioning 469/5/2007
Upcoming tests
Ramp and squeeze tests during HWC Ongoing
Ramp tests in SM18 Hit instrumented MBs, MQ Effects of different pre-cycles etc. etc. Stephane Sanfilippo et al.
Dry magnet sector test
Other systems Hardware tests during HWC
LHC ramp commissioning 479/5/2007
Conclusions
Principles and mechanics understood
Procedures for initial commissioning pretty well established
Implementation of tools in progress
Tests planned