LHC Machine Advisory Committee, 6 December 2007 Current status of the LHC project Lyn Evans
12

LHC Machine Advisory Committee , 6 December 2007

Jan 12, 2016

Download

Documents

ben ammar

Lyn Evans. Current status of the LHC project. LHC Machine Advisory Committee , 6 December 2007. Q1.R8. Q3-Q2.8L interconnect after in situ repair. RF bellows in the 1700 interconnections. Transmitter prototype. LHC transfer lines and injections - overview. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: LHC Machine Advisory Committee , 6 December 2007

LHC Machine Advisory Committee, 6 December 2007

Current status of the LHC project Lyn Evans

Page 2: LHC Machine Advisory Committee , 6 December 2007

L. Evans – EDMS Document 884713

Q1.R8

Page 3: LHC Machine Advisory Committee , 6 December 2007

L. Evans – EDMS Document 884713

Q3-Q2.8L interconnect after in situ repair

Page 4: LHC Machine Advisory Committee , 6 December 2007

L. Evans – EDMS Document 884713

RF bellows in the 1700 interconnections

Page 5: LHC Machine Advisory Committee , 6 December 2007

L. Evans – EDMS Document 884713

Transmitter prototype

Page 6: LHC Machine Advisory Committee , 6 December 2007

L. Evans – EDMS Document 884713

23.10.2004, 13:39 first beam at end of TI 8

TI 8 beam tests 23./24.10.04

6./7.11.04

TI 2

TI 8TT40

beam tests 8.9.03

SPS LHC

IR2

IR8

TI 2 upstream part installed and HW commissioned by 2005.

LHC transfer lines and injections - overview

• combined length 5.6 km

• over 700 magnets

• ca. 2/3 of SPS

TI 2 beam test 28./29.10.07

PMI2

28.10.2007, 12:03

first beam at end of TI 2

Courtesy of V. Mertens

Page 7: LHC Machine Advisory Committee , 6 December 2007

L. Evans – EDMS Document 884713

BTVI26706

This BTV screen is the last in the part of TI2 which could be explored with beam on 28 October. It is located some 70 m after the lowest point in TI2, and some 700 m away from the temporary dump, which in turn is placed at some 50 m from the end of the TI2 tunnel, to avoid irradiating the LHC area.

First shot straight down the line at 12:03:47 on 28 October

Courtesy of V. Mertens

Page 8: LHC Machine Advisory Committee , 6 December 2007

L. Evans – EDMS Document 884713

Magnet interconnections

Page 9: LHC Machine Advisory Committee , 6 December 2007

L. Evans – EDMS Document 884713

Closure of continuous cryostat

Page 10: LHC Machine Advisory Committee , 6 December 2007

L. Evans – EDMS Document 884713

Master Schedule – 08.10.07

.

.

2007

2008

2007

2008

Mar.

Apr.

May

Jun.

Jul.

Aug.

Oct.

Sep.

Nov.

Dec.

Jan.

Apr.

Feb.

Mar.

May

Jun.

Jul.

Aug.

Sep.

Nov.

Dec.

Oct.

Mar.

Apr.

May

Jun.

Jul.

Aug.

Oct.

Sep.

Nov.

Dec.

Jan.

Apr.

Feb.

Mar.

May

Jun.

Jul.

Aug.

Sep.

Nov.

Dec.

Oct.

12 23 34 45 56 67 78 81

Machine Checkout

Beam Commissioning to 7 TeV

Consolidation

1011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

5051520102030405

0706

08091011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

505152

1011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

5051520102030405

0706

08091011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

505152

1011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

5051520102030405

0706

08091011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

505152

Interconnection of the continuous cryostat

Leak tests of the last sub-sectors

Inner Triplets repairs & interconnections

Global pressure test &Consolidation

Flushing

Cool-down

Warm up

Powering Tests

Global pressure test &Consolidation

Cool-down

Powering Tests

General schedule Baseline rev. 4.0

Page 11: LHC Machine Advisory Committee , 6 December 2007

L. Evans – EDMS Document 884713 11

Dipole-dipole interconnect

Page 12: LHC Machine Advisory Committee , 6 December 2007

L. Evans – EDMS Document 884713 12

Sector status

1-2 Pressure test end week 49.

2-3 Repair of 2 leaks then flushing.

3-4 Connection of DSL then flushing.

4-5 At 2K. Problem with Y-line in one cell. ELQA and powering of main circuits. RF cavities filled and power tests started.

5-6 Cooling down.

6-7 Flushing.

7-8 Repair leaking bellows on inner triplet then flushing.

8-1 Prepare for cooldown.