182 III.4AnInvestigationintoFactorsAffectingthe
DesignTechniquesUsedtoControl Legionella in Water Systems Paul
AngusBEng (Hons) EngTech, FCIPHE, ACIBSE RPSenior Public Health
Engineer, WSP Ltd. Steven IngleDSc, MSc, I Eng, FCIPHE, ACIBSE,
FSoPHE, LCGI, RP Director, Ingle Project Design Ltd. Derek
KingMPhil BEng (Hons) Cert Ed CEng MCIBSESenior Lecturer, Liverpool
John Moores University John TurnerMSc, CEnv, I Eng, MCIWEM, FIHEEM,
FCIPHE,ACIBSE.Director, Public Health Engineering Direct Ltd.
Abstract
Overthepasttenyearstherehasbeenmuchdevelopmentinvariousandnovel
meansofcontrollingLegionellainwatersystems,whilsttryingtomaintain
compliance with the current water and health & safety
regulations. However, as most large projects now are value
engineering driven, in the current
economicclimatethereisoftenaninsistenceonre-interpretingtheCodesof
Practice to provide designs with cost advantages.In many instances
this saving
maynotprovidethebestoverallcostandlowrisksolutionforaparticular
installation.
183Decisionmakersintheconstructionprocess,drivenbyfinancialconsiderations,
appeartoooftentoinsistonthemostcosteffectivedesignsolutions,aslongasthe
spirit of the design code indicates that such a solution is
acceptable.
Thispapersuggeststhatthisphilosophyencouragesundesirablecompromises.An
environmentisfosteredwheredecisionsmayoftenbemadeonavalueengineering
andprofitbasis,whileleavingrealpublichealthrisksandnon-sustainable,non-maintainable
systems in their wake. Introduction It is intended that this paper
will critically analyse some methods of control of legionella
bacteria in hot and cold water systems.
Thepaperwilladdress,inparticular,butnotbeconfinedto,theimpactofusing
temperature as a sole means of Legionella control in domestic hot
water systems based on value engineering design.Under examination
also are the issues of management and
operationalcostsofutilisingthispractice,and,inthecontextoftheconstantquestfor
CO2reductionandsustainability,whethersuchatechniquecanbeconsidered
environmentally friendly.
Furthermore,thepaperwilldiscusstheuseoftraceheatingwithoutsecondary
circulation pipework, and the associated risks and advantages of
this application, along with the benefits or otherwise of
alternative treatments. When considering cold water systems, the
present Codes of Practice accept the widely
heldviewthatattemperaturesbelow20oC,Legionellabacteriaremaindormant2.Furthermore,itiscommonlyacceptedthatcoldwaterpipeworkwillremainatsafe
temperatureswithouttheneedforanyparticularpracticalsteptoguaranteethis(other
thaninsulatingpipework,whichhaslongbeenstandardprocedure).However,global
warmingisbeginningtocauseappreciablyhigherairandgroundtemperatures.In
addition, changed rainfall patterns may mean that water supplies in
the UK must come
fromalternativesources,evenfromdesalinationprocesses(asintheMiddleEast).Thus
cold water may well be supplied to buildings at temperatures closer
to the higher end of what may be considered safe. 22 HSE. (2000)
Legionnaires Disease: The control of legionella bacteria in water
systems. Approved Code of Practice and Guidance L8, Health and
Safety Executive. 184Bacterial growth in hydrodynamic systems
Research has long shown that the use of heat and chlorine
treatments to control bacterial growth in water pipework has given
rise to certain bacteria developing higher tolerances
tobothheat3andchlorine4.Legionellabacteriahavebeenisolatedfromnatural
environmental locations where temperatures have been as low as 5oC
and as high
63oC3.Isolationinsystemsattemperaturesmaintainedat30oC54oCiscommon,however
legionella bacteria are not found at temperatures above 71oC5.In
addition, it has been shown that thermophilous bacteria,
Pseudomonas aeruginosa and other similar bacteria are becoming
increasingly common and may partner the Legionella bacterium.These
bacteria are believed to cause an increase in health problems,
particularly those related
totheskin6.Free-livingamoebaeareoftenfoundalongsideLegionellaeandother
pathogenicbacteria,amoebaeofthegeneraNaegleriaandAcanthamoebacanbe
pathogenictohumans.Thesecancauserapidfatalmeningoencephalititis,when
introducedthroughthenasalmucosae,aswellasbrain,eye,pulmonaryandkidney
infections7. Itisanacceptedcontroltechnique in hydrodynamic systems
that a temperature should
bemaintainedatwhichbacteriallifecannotbesustained.Suchfactorsaskilltime
(thetimetakenfortemperaturetokillbacteria)andresidencetime(thetimethat
waterstaysinthesystembeforebeingdrawnoff),however,arealsocritical.Ifthe
residence time in a system is shorter than the kill time (and this
can easily be the case at 60oC) then this is clearly
unsatisfactory.At 60oC it takes 32 minutes to kill Legionella
bacteria, while at 55oC this period is increased to 5-6 hours3.
3WadowskyRMetal.(1985)EffectofTemperature,pH,andOxygenlevelsonthemultiplicationofnaturallyoccurringLegionellapneumophilainPotableWater.Applied&EnvironmentalMicrobiologyMay1985p119712054RidgwayHF.OlsonBH.(1982)Chlorineresistancepatternsofbacteriafromtwodrinkingwaterdistributionsystems.Applied&EnvironmentalMicrobiology44(4)972987.5WadowskyRMetal.(1982)HotwatersystemsassourcesofLegionellapneumophilainhospitalandnonhospitalplumbingfixtures.Applied&EnvironmentalMicrobiology43;110411106OvesenK,SchmidtJorgensenF,&BaghL.(1993)Bacteriagrowthinhotwatersystems.DanishNationalBuildingResearchInstitute7TyndallRL,DomingueEL.(1982)CocultivationofLegionellapneumophilaandfreelivingAmoebae.Applied&EnvironmentalMicrobiology44;954959185It
is also known that dead bacterial cells can provide a food source
for living bacteria5,
andthatbacteriacansurviveinanaerobicconditions(althoughtheydonotgrowor
multiply readily in such conditions3).Mutant strains have also been
shown to develop,
dependinguponthequalityofthesourcesupply,andmaterialsutilisedinthesystem
installation, galvanised steel, copper and plastics being the most
common.Corrosion in galvanised steel in particular isaccelerated at
temperatures above 60oC, as is the build up of debris from the
killed bacteria in all materials at these elevated temperatures.The
unevensurfacesofcorrodedpipeworkandsettleddetritusthenprovidenutritionand
breedinggroundsforbacteria.Plasticshavebeenshowntoactivelyincreasebacterial
growth rates across all temperature ranges6.
Inmanycases,legionellabacteriaarefoundinthesedimentincoolingtowers,
calorifiers or pipework systems even at 65oC high colony counts
have been found in sludge in calorifiers8.In cooling towers, where
water is treated using biocides, it is not
unusualforthebiocidestohavetobealternatedtoensurethatthebacteriadonot
become tolerant.
Standingwaterisknowntobeundesirableinhydrodynamicsystems:longerresidence
timesleadtostagnationandthisisknowntoincreasethegrowthrateofbacteriaas
morenutrientsbecomeavailable.Heattransferbetweenhotandcoldwaterservices
pipeworkincloseproximityisalsoinevitableifwaterisleftstandinginthepipework
forlongperiods,nomatterhowwellpipesareinsulated,andthisisevenmore
unhelpful.Stagnant water in a system is considered to represent a
fluid category 3 risk under the current water regulations9.
Ifengineerscouldinterpretsuchmicro-biologicalresearchlanguageandrelatethisto
practicalandeffectiveengineeringdesignreality,theycouldpossiblymakedesign
recommendations with confidence and rebut the constant arguments in
favour ofvalue
engineeredsolutionsandcostcutting,whichmaywellcompromisepublichealthand
sustainability. Influences on design techniquesHot water supply
accounts for as much as 30% of all energy consumption in buildings
such as hotels, hospitals and residential homes.It is estimated
that 65-70% of hydrodynamic systems in public buildings utilise
heat as ameansofpreferredcontrol of contamination10 and this
approach is seen to comply
8SchmidtJorgensenF.(1991)Danishinvestigationsonbacterialcontaminationinhotwatersystems.DanishNationalBuildingResearchInstitute.BuildingServicesDivision.9
HMSO. (1999) The Water Supply (Water Fittings) Regulations 1999 10
Arrowsmith, M. (2006) Legionnaires Disease Risk Minimisation, IHEEM
Journal, August 2006.
186withalldesignguidanceandlegislation.Inpractice,however,particularlyinlarge
systems, it is difficult to ensure that balancing achieves the
required temperatures at all
drawofflocations,orallowsthewholesystemtobeproperlypasteurisedintheheat
cycle.Itisdifficulttobecertainthatfrequentstagnationdoesnotoccuratlocations
with low water usage (e.g. washbasins in hospitals).In addition,
designers seldom fully
addresstheimportanceoftemperaturemaintenanceofthecoldwaterdistribution
network, and the consequences should cold supply temperature be
allowed deviate.
Overrecentyearstherehavebeensignificantchangestohowwestore,heatand
distribute water around buildings.These changes are mainly
influenced by the ongoing
pressurestoreducespacetakenupbymechanicalservicesequipmentandvalue
engineeredsolutionstoreducecosts.Thuscentralisedplantroomshavetendedto
becomethenorm,coupledwithboostedorpressurisedunventedhotandcoldwater
networkswithextensivedistributionsystems.Off-siteprefabricationofpipeworkhas
alsobeenintroduced,oftenwithlittleconsiderationofpossibleheattransferbetween
services,coupledwiththemoveawayfromcopperandothermetallicpipework
materials (common in the UK) to plastics.Strangely enough, there
are many examples of where strainers or filters are added to a
system to protect equipment, but these are not considered as a
necessity to help reduce system contamination and protect public
health on incoming water mains. Selection of pipework sizes is
another factor which should be examined when looking at
establisheddesignpractices:Currentpracticeistousetheloadingunitsmethod
describedinBS6700,andintheCIPHEandCIBSEDesignGuides.Inthismethod
pipeworksizesareselectedbasedontheinter-relationshipsbetweenseveraldynamic
properties of water and the pipework material, though flow velocity
and its relationship to pipework generated noise is used as the
main limiting factor.Normal practice when using this method is to
maintain velocities below 1 m/s, or exceptionally 1.5 m/s.It is,
however, some time since any study was carried out as to the extent
that noise generated
inpipeworkisactuallylikelytobeproblematicinmodernbuildings,giventhat
installationpracticeisconstantlyevolving.Forinstance,pipesaremorelikelytobe
located centrally and in ducts, remote from working areas of
buildings, and all pipework is routinely thermally
insulated.Furthermore, at larger pipe sizes, there is evidence that
the loading unit method becomes unreliable and over-sizing is
routine.This, as well as being non-sustainable, is likely to
increase the chance of stagnation and precipitation of
debris.Itmaythusbepossibletorelaxtherequirementtokeepnoiseatlowlevelsso
thatflowvelocitiescanbeincreased,andthiswouldpromoteausefulscouringaction
within pipes.Consequently there would be less likelihood of debris
and detritus settling
andprovidingnutritionorbreedingplacesforbacteria.Thewelcomeby-productof
suchatechniquewouldreducepipeworksizesandthuscontributefurtherto
sustainability. 187More recently, the pressure to reduce carbon
footprints and make savings of energy and water have moved
designers into new areas of risk and managing that risk.For example
intheUK,BREEAMpointscanbeearnedbyutilisingsolenoidvalvescontrolledby
Passive infrared detectors (PIRs) to isolate infrequently used hot
and cold water supplies
tosanitaryfittings11.Thereisnoguidancetoinsistthatthegreatestofcareshouldbe
takeninlocationofthesevalveswhilethereisquiteclearlyariskthatpipeworkdead
legsandpossiblestagnationmayinadvertentlybetheresultofusingthismethod.It
could certainly be argued here that public health is potentially
compromised for the sake of sustainability! There is also a
constant paradoxical question for engineers as to how it can be
possible to reduce the fuel costs of producing hot water, when
increasingly elevated temperatures are advised (in preference to
biocides to which bacteria grow immune) in an attempt to
controlbacterialcontaminationofsupplies.Howmuchbenefitistherethen,fromthe
emergence of condensing boilers, which perform at their highest
efficiency with return temperatures of 40-45oC?
Whenquestioned,manypracticingdesignengineersandfacilitiesormaintenance
managers will not know exactly the quality of the water entering
their building, though
mostwillaffirmthatitcomplieswiththeRegulatoryDrinkingWaterStandards12.Giventhecurrentfinancialclimateanddrivetowardssustainability,thechancesof
reducing resultant levels of settled suspended matter, scale
formation and corrosion, all contributors to fouling and
microbiological activity, seem minimal. From a water conservation
perspective it is noted that rainwater harvesting and re-use of
greyandevenblackwaterisgatheringpace,certainlyasagainitattractsBREEAM
points.Fromapublichealthviewpoint,however,howsensibleisitthatwateris
broughtintobuildingsthatcouldpotentiallycontainhighnumbersofpathogenic
bacteriaforpossibleaerosoldispersionwithinconfinedspacessuchastoiletcubicles?Thefutureriskoferroneouscross-connectionbetweenre-cycledwaterpipeworkand
potable water pipework is also often not considered in the design
of such systems. Legionella in cold water systems
Legionellaisoftenconsideredasbeingaproblemassociatedonlywithhotwater
installations.As previously stated however, it is necessary to
ensure that temperatures
incoldwatersystemsaremaintainedideallybelow20oC2,althoughthecurrentUK
waterregulationspermitutilitiescompaniestosupplyattemperaturesupto25oC9.11
BREEAM. (2008) The Code for Sustainable Homes
12ProceedingsofLegionellaSeminar.(2009)OldTraffordCricketGround,OldTrafford,
Manchester, 05/11/2009 188Cold water piped installation systems are
required to be insulated and kept as far away as possible, from
sources of heat such as hot water pipe-work, warm air ductwork and
electrical services.Practically, this is difficult to achieve since
service risers and ducts
areoftenofrestrictedsizeandareusuallyexpectedtoaccommodateallservices,thus
muchmaydependupontheskillandingenuityoftheinstaller.Suchconcernsmay
easilybeoverlookedonsite,especiallywherecoldwaterpipeworkisinstalledwithin
ceiling voids or plant rooms.
Itisofupmostimportancetoconsidercarefullythelocationofthecoldwaterstorage
cistern.TheinstallationitselfshouldcomplywiththeWaterSupply(Waterfittings)
Regulations 19999 and Water Byelaws 2000 in Scotland13.It is the
responsibility of the design engineer to ensure the cistern is
located in a cool, dry place, being protected from extremes of
temperature by thermal insulation.The cold water storage
requirement for
everydaypurposessuchasdrinking,washingandcooking,isnormallydeterminedon
thebasisofcompensatingfora24hourinterruptionofsupply,asindicatedbythe
appropriate British and European Standards14.Where a larger storage
volume is needed for particular requirements such as catering, this
may require additional treatment such
asregularorcontinuouschlorinedosing,chlorinedioxidedosingorothermeansof
disinfection such as ionisation. Figure 1: Cold Water Storage and
system distribution temperatures (Source: Copper Development
Association) 13 HMSO. (2000) Water Bye Laws (Scotland). 14 BSI
(2006) BS6700 Design, installation, testing and maintenance of
services supplying water for domestic use within buildings and
their curtilages. 189In countries where high ambient temperatures
are usual, such as in the Middle East, the
incomingcoldwatermainssupplytothebuildingcanoftenbecharacteristicallyin
excess of 20C.As discussed earlier within this paper, such
temperatures provide ideal conditions for Legionella bacteria to
breed within pipework and components like
tanks.Inordertocombatthisproblem,thewatermustroutinelybedisinfected,usually
chemically or by ionisation treatment, before distribution.In
addition storage tanks are
oftenlocatedinthebasementsofbuildings,takingadvantageofconstantcooler
temperaturesunderground.As global warming takes effect, such
techniques are likely to be required in parts of the world where
the problem of cold supply temperatures were previously seldom
considered, such as in northern Europe and North America.
Legionella in hot water systems In practice it is known that around
half of the reported cases of Legionnaires disease are associated
with contaminated hot water, though these outbreaks are not
normally widely
reportedbecausethenumberofcasesinvolvedisrelativelysmall.Itishelpfulto
examine the situation in homes and commercial buildings separately.
Housing
Therehavebeenonlyoccasionallinksbetweenthehotwaterservicesinhousingand
Legionnairesdisease,despitesurveysofdomesticsystemsshowingthereareindeed
traces of legionella.The main reasons for this are:
1.Itisdifficulttolinkpersonstoanyonesource:householdsareunlikelytocontain
more than one susceptible occupant, and since an epidemic would not
be recognized
unlesstwoormorecasesaroseinthesamehousehold,GeneralPractionersand
epidemiologists do not search for a common link.2.There is rapid
turnover of hot water in domestic systems, with residence time in
the
pipeworkandcomponentstendingtobeveryshort.Inadditionthereisanever
increasinguseofinstantaneouswaterheatersorcombinationboilers.Themodest
size of a five person British house (around 80 m) also means that
there tend not to be long dead legs of piping.
3.Domestichotwatersystemstendtocompriseofpredominantlycopperpipework
andstoragevessels(thoughplasticshavebeenintroducedincreasinglyinrecent
years).Ithasbeenshownthatmicro-organisms find it difficult to
colonize copper
pipeworkandcomponents:microbiologicalcolonizationinpipeworkalwaysstarts
atthewallsurfaces,andcopperanaturalbiocidewhennewinitiallyinhibitsthis
190initiallyuntilthesurfacebecomesoxidised15,16.(Itis,however,worthmakingthe
pointthatinhardwaterareas,thisprotectionquicklydisappearswhenmineral
deposits coat the wall surfaces.) Once such a storage cylinder is
heated and at steady state, stratification becomes evident and a
temperature gradient exists, which is shown in Figure 217. Figure
2: Temperature profiles in an indirectly heated water cylinder
(Source: Whiteside, 1990)
Thepotentialproblemareainsuchhotwatercylindersliesinthebase.Debrisfrom
killedbacteriawilldroptothebaseduringtimeofnondrawoffandwillcollectthere
overtime,thusprovidingnutritionforbacteria,and,duetothecoldfeedwaterbeing
suppliedinthisregionofthecylinder,temperaturesatthebasecanbelukewarm
(around30oC)forlongperiodsoftime.Ifthebaseofthecylinderdoesheatuptoan
acceptabletemperature,suchatemperaturemaynotbemaintainedforasufficiently
long period to kill the bacteria.The UK Health & Safety
Executive (HSE) recommends
15RidealS.andBainesE.(1904)Thesuggesteduseofcopperdrinkingvesselsasaprophylactic
against water borne typhoid. Royal Sanitation lnstitute Journal
(London), 25 591-595 16 Place, F.E. (1905) Water cleansing by
copper. Journal of Preventive Medicine, (London), 13, 379 17
Whiteside, D. (1990) DHW: heat loss from tanks. Building Services
Journal 12 (l), 57
191thatinlargerstoragevesselsade-stratificationpumpbefittedtocirculatewaterfrom
the top of the cylinder to the bottom via the cold
feed2.Inatypicaldomestichotwaterdistributionsystemthermalinsulationisusually
sufficienttominimizeheatlossesandmaximizeoutlettemperaturesatthetaps.Self-regulatingtraceheating,whichisarelativelynewtechnique,claimedbymanytobe
costeffective,mayalsobeconsideredinconjunctionwiththethermalinsulation,
particularlyifdeadlegsexceedregulations.Thistechniqueoffersinstanthotwaterat
the outlets, at some energy cost, but with less wastage of water
since when users operate the taps they do not need to let the tap
run while waiting for hot water.
Instantaneouselectricwaterheatersareusedfordomesticshowers.Theseare
connecteddirectlytothemainscoldwatersupplyandsupplywaterisdirectedovera
powerful (up to 12 kW) immersion heater, emerging hot and at
pressure.Such units are also available as spray taps for hand
washing.
Ithasbeenshownandiswellknownthatlimedepositionratesinhardwaterareas
increasedramaticallyabove60C,whereasinsoftwaterareasthereisnodeposition
problem. However, corrosion is accelerated at the higher
temperatures18. Commercial buildings The hot water system in
commercial buildings starts with a large storage vessel known
asacalorifier.Inlargebuildingsthiscontainsaheatingcoilthroughwhichhotwater
from the boiler plant flows.Some plant contains both LPHW and
steam.Fourfactorsaredesirableinthedesignofacalorifiertominimizetheriskof
contamination with legionella:
1.Thebulkstoragetemperatureshouldbereasonablyuniformthroughoutthevessel
whenfullyheated.Inoldersystemsitiscommonforthelowest100mminthe
vicinityofthecoldinletfeedtobelukewarm.Thispotentiallylukewarmzonein
the base, with the debris mentioned above, can provide a most
suitable environment
forthemultiplicationoflegionella.Atechniqueofpreventingthisistoincludea
de-stratification pump (as recommended by the HSE in Approved Code
of Practice L82) which continually circulates water from the top to
the bottom of the
calorifier.Alternatively,thesecondaryreturnpipeofthehotwatersystemcanbeconnected
intothecoldfeedpipeatthebottomofthecalorifierinsteadofitsnormal
connection point two-thirds of the distance from the bottom.
18ASHRAE(1987)HVACHandbookAmericanSocietyofHeatingRefrigerationandAir
Conditioning Engineers, Atlanta, USA
1922.Thecalorifierandentiredistributionsystemshouldbecapableofbeingheatedto
70Cforpasteurisationpurposes,andmustbecapableofmaintainingthis
temperature for some hours if necessary.
3.Calorifiersmusthaveeasyaccessfordraining,dismantlingandcleaning2.All
calorifierswhichareheatedbypressurisedhightemperaturewatermustbe
inspected by law to ensure that the heating coil is able to
withstand the pressure and
somustbefittedwithanaccesshatch.Thishatchcanalsobeusedforcleaning
purposes when the calorifier is drained down ready for
inspection.Some engineers,
however,specifynohatchwherethereisnoheatingcoil,whichistechnically
permissible, but is seen as bad practice.
4.Volumetricsizingiscloselylinkedwiththeheatrecoverytimeoftheheat
exchanger in the calorifier and therefore calorifier should be
adequately sized for its duty.A two hour recovery period is usual
but the storage volume can be reduced if
ashorterrecoverytimeisdesired,dependantontheenergyinputavailable.Ifthe
unitisunder-sizedinvolume,thenattimesofhighhotwaterflowdemand,the
outlettemperaturewillfallandwaterattemperatureslowerthanthedesign
temperature will pass through the system, carrying with it
initially dormant bacteria
fromthemainssupply.Subsequentlyifthewaterinthebaseofthecalorifieris
contaminatedthenthecontaminationwillbespreaddownstreamthroughthe
distribution network.This passing of live bacteria into the
distribution network will of course allow the bacteria to colonise
in dead legs and areas of low velocity. In practice the current
design guides are over generous in their sizing and there is little
riskofunder-sizinginnewinstallations19.Ithasbeenfoundthatthehighest
dischargetemperatureduringdrawoffisachievedbyuseofvesselswithaheight
fourtimestheirwidth,thesedimensionsprovidingoptimumstratification
characteristics during discharge20. 5.On pressurised unvented hot
water systems care must be taken to allow maintenance of the
expansion vessel.The expansion vessel should maintain a temperature
below 20oC and be constructed of a material that does not support
bacterial growth. For buildings in continuous use (such as
hospitals, hotels etc.) it is usual to provide two calorifiers to
allow for maintenance: a service and standby calorifier both sized
at 100% capacity may be provided, or alternatively, two calorifiers
sized at two-thirds capacity.This latter option is preferable since
the standby unit will come online more frequently
19CorlessDK.(1990)Hotwaterservicesforamodernhospitalwardunit.BuildingServices
Engineering Research and Technology 11 (2), 57-63
20Cole,RL.andBellingerF.O.(1982)Thermallystratifiedtanks.ASHRAETransactions,88(2)
1005-1017
193attimesofhighdemandandthiswillensurethatwaterisnotallowedtostagnate.In
systems where the standby unit is offline for considerable periods,
it will remain full of water and may be heated slightly by leakage
at the valves controlling flow to the heating
coil.Thus,suchstandbycalorifiersmustbeconsideredcontaminatedandshouldbe
pasteurisedbeforebeingbroughtbackintoservice.Pasteurisationisachievedby
bringingthewatertemperatureuptoaminimumof60Candmaintainingthis
temperatureforatleast2hours.Duringpasteurisationhotwatermustbecirculated
fromthecalorifiertothevariousoutletpointsaroundthebuildingandbacktothe
calorifier via a return pipework loop.The loop takes the water from
the hottest part of the calorifier, the top, and returns it to the
calorifier cold feed pipe.A small water pump is provided to
circulate the water gently but sufficiently fast for the heat
losses to permit the water return temperature to be 50C or more
when the water leaves the calorifier at 70C.
Commercialkitchensalsodeservespecialmentionbecausetheyrequirewaterat82C
for dish washing rinsing.This can be achieved by controlling the
calorifier at 82C for the dish washer and blending cold water to
provide temperatures around 40C at normal
outletstopreventscalding,orbymaintainingthecalorifierat60Candproviding
specialistlocalheatingforthedishwashers.Bothsystemsarelikelytobelegionella-free
at these temperatures. A particular problem with high temperature
calorifier operation is the increase in water volume with
temperature, and this relationship is illustrated in Figure
321.This increase
involumemayforcethewateratthebottomofthecalorifierbackintothecoldfeed
supplyaswellasthroughtheopenventpipe.Sincethewateratthebaseofthe
calorifier is likely to be the most contaminated then this
expansion can contaminate the
feedpipe.Thiscouldsubsequentlyleadtorapidrecontaminationaftercalorifier
cleaning.Non-return valves (NRVs) are recommended by the HSE
(Approved Code of
PracticeL8)atthecoldfeedinlettocalorifiers2,however,carefulthoughtisneeded
whenpositioningthese,sinceanincorrectlocationcouldresultinwastageofheat
energyinthewaterandwateritself.Inpressurisedsystemstheexpansionvesselwill
containwateratidealtemperaturesforbacterialcolonisation,thuscarefulthoughtis
neededtoincorporatethispieceofequipmentsuchthatbacteriacannotenterthe
distribution pipework.
21OughtonD.(2008)Faber&Kell'sHeating&Air-conditioningofBuildings,Butterworth
Heinemann. 194 Figure 3: Expansion volume of heated water (inlet
4oC) (Source: Oughton, 2008)
InpublicbuildingstemperaturechecksunderHSEL8requirements2arenormally
carried out at as part of the maintenance regime at tap outlets to
ensure that hot water is delivered within a reasonable time, and
that the delivery temperature is not below 46C.In hospitals special
guidance defines reasonable time as within 1 minute of opening the
tap the water is expected to reach 50C, although if a blending
device is used to lower the outlet temperature to prevent scalding
of vulnerable users, then 50C at the hot inlet to the blending
valve is recommended22.
Maintenanceforpublicbuildingsmustincluderegularinspectionofshowerheadsto
check that they are clean and, if dirty, they should be cleaned
immediately to avoid the colonisation of the debris with
micro-organisms.Taps or showers which are rarely used
shouldberemovedalongwiththeassociatedpipeworktominimizethedangerof
lukewarm water remaining stagnant for long periods. It is seen as
good design practice that the tap or outlet most frequently used
should be at the end of any dead leg to ensure regular flow through
the length of the supply pipe.It has long been standard practice to
insulate both hot and cold pipework and ensure that the hot pipe is
located above the cold so that convection heat loss from the hot
pipe will not readily affect the cold supply.
Earlyguidelineswereconcernedwiththesmallvolumeofwarmwaterleftinshower
hoses after use.There were proposals that self-draining showers
were inherently safer
thanconventionalshowers.Experimentsonshowerswithaself-drainingvalveand
conventional showers without such a valve showed little difference
to re-colonisation by
22DHSS(1990)ControlofLegionellaeandsafehotwatertemperatures.HealthNoticeHM
(90)12, HN (EP) (90) 195bacteria after sterilization.After 10 days
the re-colonisation was stable and very similar
forbothtypesofshower23.Ithasbeenfound,however,thatremovalofdeadlegs,
regular changing of the mixing valve components, and regular
flushing of shower hoses and heads produces significant reductions
in legionella24.Secondary return systems and trace heating The
conventional approach to the design of hot water services in
commercial buildings
recirculateshotwaterthroughasecondaryreturnsystemasdepictedinfigure4.This
approachensuresthatwaterflowsconstantlythroughthepipeworkanddoesnot
stagnate even if a tap is not used for some time.It ensures that
water is maintained at design temperature around the network, and
it allows the designer to keep supply dead legs to outlets as short
as possible.These systems prevent the inconvenience of waiting
forhotwatertoarriveaswellaspreventingbacterial
contaminationinlengthsofpipe
containingtepidwater.Continuouscirculationisnormallyachievedbypumping,
although in some cases this is programmed to switch off at night.
Figure 4: Representative sketch of secondary return type hot water
distribution An alternative method of maintaining temperature
around the network is to provide
self-regulatingelectricaltraceheatingalongasingledeliverypipe.Theoperating
temperatureofthepipeisdeterminedfromtheknowledgeoftheheatingtape
characteristicswithrespecttotemperature,andknowledgeoftheheatloss
characteristicsofthepipematerial.Thepoweroutputofthetapefallswithhigher
23 Humphrey TJ. (1989) Microbial contamination of hospital showers
and shower water: the effect of an automatic drain valve. Journal
of Hospital Infection, 13, 55-61 24 Makin T. and Hart CA. (1991)
The effect of a self-regulating trace heating element on legionella
within a shower. Journal of Applied Bacteriology, 70, 258-264
ControlHotstoragevesselCirculatingpumpSecondaryflowpipeSecondaryreturnOpenventpipeDrawoffpoints196temperaturesandtheheatlossfromthethermallyinsulatedpipeincreaseswithhigher
pipetemperatures.Thesetwocharacteristiccurvescanbeplottedandtheintersection
betweenthesedeterminestheequilibriumtemperatureofthetraceheatedpipe.This
procedure is illustrated in Figure 5. Figure 5: Determination of
operating temperature of trace heated pipework The installed piping
scheme is much simpler than the conventional one and, on the face
ofit,appearstobemoreeconomicallyappealing.However,theenergycostsof
electricalpumpingandpipeheatlossesoftheconventionalsystemmustbecompared
with the energy costs of running the single pipe trace heated
system.The capital costs of single pipe with trace heating and the
re-circulating system should also be
compared.Theeconomiccaseisoftenstrongestwhenthehotwaterserviceisalongandnarrow
building where the return pipe simply returns the water.It is less
attractive in a square
buildingwherethehotwatercircuitmaybeonepiperunninginalooparoundthe
building.
Therearetwootherapplicationsoftraceheatingforhotwaterpipes.Thefirstisto
remedy deficiencies in existing equipment or systems.If there are
long dead legs in the
distributionsystemthenelectricaltraceheatingcanbeincorporatedsimplyalongthis
particularlengthofdeadleg.Experimentsusingthetechniquetomaintainthe
temperature in the dead legs in a shower to 50C were very
successful provided that the
circulatinghotwaterwasgreaterthan45C.Thetemperaturewasmaintainedvery
closely ( 1.5C) and legionella were eradicated or severely reduced
by the technique25. 25 Makin T. and Hart C.A. (1990) The efficiency
of control measures for eradicating Legionellae in showers. Journal
of Hospital Infection, 16, 1-7
197Thesecondisforplaintraceheatingusedforpasteurisation.Thereisagrowing
practice to recommend regular elevation of hot water pipes to 77C
for 15 minutes and to draw this water from each tap or shower head
to disinfect the components18,26.Care
mustbetakenifthispracticeisfollowedtoensurethatthedepositionofcalcium
carbonatewillnotbeexcessiveorthatthecorrosionratewillnotbecomehighinsoft
waterareas.Insomenaturalwaterswherezincisusedasanaturalprotectivecoating
on steel a reversal of polarity occurs around 60-65 C.The zinc then
becomes cathodic to steel stimulating attack which results in
localised pitting corrosion27,28. A suggestion This paper suggests
that general design good practice for public buildings is often
being
compromisedbytoomuchfocusonprojecteconomics.Furthermoretheclientoften
does not seem to benefit from any cost savings realised, and the
end user is left to pick
upthecostsfortheongoingfailureorpoorperformanceofsystemsafterhandover
(although it must be said that in speculative design and build
projects, clients are more
likelytoseesomeofthesavings).Currently,projectmanagersareheedingmany
manufacturersclaimsofmoreinexpensiveinstallationcostsandthusareconstantly
requestingdesignerstocarryoutvalueengineeringofprojects.Capitalcostsmay
subsequently be reduced but life cycle costs seem to be ignored
altogether. One such aspect which raises concern in the context of
this paper is the recent tendency to introduce trace heating as a
means of temperature control, and this technique is now
beingpromotedasaneconomicalternativetotraditionalsecondaryreturntypehot
waterdistributionsystems.Thereareanumberofissuesthatareraisedbythe
introduction of this type of system: Maintenance of design
temperatures throughout distribution networks;
Scalebuildup,stagnationandallowingsuspendedmattertosettleoutthus
creating corrosion spots and bacterial breeding grounds; Energy use
and life cycle costs; Carbon footprint and sustainability. 26
Fliermans CB. and Nygren JA. (1987) Maintaining industrial cooling
systems free of Legionella pneumophila. ASHRAE Transactions, 93 (2)
1405-1415 27 BRE. (1968) Durability of metals in natural waters.
Building Research Station Digest 98 Second Series
28InstituteofPlumbing(1988)PlumbingEngineeringServicesDesignGuide,Instituteof
Plumbing, Hornchurch
198Theinstallationofcentralwaterheatingplantwithdistributionpipeworkrunning
throughout the building is generally considered by engineers as the
most cost effective, efficient and reliable solution to providing
hot water supplies in public buildings.The cost effectiveness and
reliability of this tried and tested system is borne out by the
long life (usually 30 or more years) of low stress components such
as traditional calorifiers, tube bundles, boilers and so on.The
question of cost effective and reliable methods of maintaining
temperatures in the distribution pipe networks at safe levels is
where there may be some disagreement.
Itisclaimedthattemperaturemaintenancetapewillcutbothinstallationandrunning
costs in comparison to a re-circulating hot water distribution
system, whilst maintaining
temperaturewithindeadlegs,andwillthuspreventLegionellagrowthandallowfull
compliance with current legislation.The main cost argument is
clearly the removal of
thetraditionalinsulateddomestichotwatersecondaryreturnline,withitsassociated
balancing valves and circulator pump.The function of the return
pipe is to maintain the
temperaturewithinthesystemsuchthatwaterisavailableatthepointofusequickly,
avoidingwastageoflargequantitiesofwaterwhilstwaitingforhotwatertoarrive
traceheatedsystemscouldmakethesameclaim.Toensuremaintenanceofsafe
temperaturesthroughoutsystems,thesamequantityofheatmustbedeliveredasthat
whichislostduetonaturalcoolingtotheambientsurroundings.Inthetraditional
system standing losses in primary energy are claimed to be
considerably higher than in systems using trace heating; in
addition, installation costs for trace heating systems are lower
and thus the overall capital costs for a traditional system are
usually far higher. Engineers have a duty to their client and to
the environment and should consider wider aspects in relation to
the installation.In fulfilling these responsibilities it is only
proper
thatdetailedcomparisonsbetweenthetwosystemsoftemperaturemaintenancebe
made.
Theenvironmentalimpactandsustainabilityofthesystemshouldbefully
considered:unlessthetraceheatinginstallationistobepoweredbyelectricity
generated from renewable sources, then heating water using
electricity instead of gas is inherently non-sustainable and energy
inefficient.
Thechoiceofprimaryfuelisanimportantdecidingfactor:withintheUK
purchasing costs of fuels generally place the use of natural gas in
front of others
inanurbanenvironment.Ifanalternativefuelmustbeused,orelectricityis
generated on-site, this may radically change the dynamic of the
decision making process.
Ongoingoperationalcostsmustbedeterminedbycarryingoutaseriesof
detailedcalculationsandforecasts,detailingexactlyhowtheoperatingcostsof
the options compare;Detailed knowledge of the relative life cycle
costs for all components is required
toenabletheengineertomakedesign decisions with confidence for
example
199thelikelyongoingmaintenance,repairandreplacementrequirementsandcosts
must be considered;
Inanincreasinglylitigiousworldtheengineerneedstobeconfidentwhen
specifyingeithersystem,thatsafetemperaturesaremaintainedandthe
requirements of legislation and design codes are met. Conclusions
Traceheatinginstallationsonthe
largerscalehavelittlerecordedhistory.Itisknown that they can be
effective in treating relatively short dead legs such as shower
runs and
remoteappliances;thereis,however,scantevidencetosuggestthistechniquecanbe
effectively scaled up to meet all criteria required for public
health.For instance, it is not
knownexactlywhathappensinatraceheatedpipewhenpositionedverticallywhen
waterisnotmoving:doesstratificationanditsassociatedproblemsoccurasitdoesin
storage cylinders?
Furtherresearchisessentialifengineersaretohaveconfidenceinutilisingthetrace
heating technique as a reliable solution.There are at present too
many unknown factors
relatingtothepointsmadeearlier:maintainingdesigntemperaturesthroughout
distribution networks, scale build up, stagnation, settlement of
suspended matter, energy use, life cycle costs, carbon footprint
and sustainability. In addition to all the likely technical
problems engineers face when employing the trace heating tape
technique in large scale centralised systems, other matters must
also be the borne in mind: Any outbreak of Legionnaires disease is
normally sensationalised by the media, and in
todayssocietyscultureofblame,engineerscouldwellfindthemselvesculpable
(corporate manslaughter is a constant
fear).ThepublicaregenerallyunawarethatLegionellaisacommoninhabitantofwater
distributionsystems.Theincorrect,generallyheldassumptionisthatLegionellaisan
unwelcome invader of poorly maintained water systems and that
negligence plays a role in its presence29.This is of course a half
truth, borne out by the fact that most outbreaks
ofLegionnairesdiseaseareindeedrelatedtooccasionswherebasicmaintenanceand
health and safety procedures have been
neglected.Thisisironic,becausetoofewpublicbuildingshaveanydiagnostictestingregimeor
results available to alert staff that there is a problem.Diagnostic
tests, because of their high cost and alleged complexity, are not
recommended in the present Health and Safety
29StoutJE,YuVL.(2001)Legionellainthehospitalwatersupply;Apleafordecisionmaking
based on Evidence-Based Medicine. Infection Control Hospital
Epidmiol. (22) 670-72
200advice,unlessaparticularproblemissuspected.Manywouldarguethatinmany
instancesLegionellosisgoesundiagnosed,andmortalityisincorrectlyattributedto
other causes29. The key issue here is the question of whether the
presence and colonisation of legionella leads to Legionellosis.
Shouldengineersperhapsbeconcentratingtheireffortsonthesourceoftheproblem?
Should they seek to understand the true status of the incoming
water supply, and what implications this has on the particulars of
any installation and how it is to be
operated?Thefitandforgetapproachtowatersupplies,whichmanymightargueisthenorm
today,hasimmeasurableconsequences.Therefore,shouldengineers,asstandard
practice,attempttoreducetheamountofsuspendedmatter,organicloadingsandthe
potentialforscalingthroughadditionalon-sitefiltrationandassociatedtreatment
regimes?Shouldmaintenanceregimesencouragethecheckinganddrainingdownof
sludge from the bottom of calorifiers more regularly than at six
month intervals?Rather than relying on heat treatment in isolation
to offer protection at a cost, should engineers
alternativelyadoptanendofpipesolutionapproach,whereeffortsareconcentrated
on control and reduction, localised to areas perceived as high
risk?TheuseofUV,ultra-filtration,copper-silverionisation,silver-hydrogenperoxideand
so on offer many capital and operational cost advantages, yet are
least often utilised as a preferred method. There may well be an
argument for localised hot water generation, with the acceptance of
plateheatexchangers(orsimilar)delivering almost instantaneous hot
water.These
takeuplittlespace,reducestorageproblemsandcangreatlyreduceandsimplifythe
requirementforsecondarypipeworkinstallationandmaintenance.Thecostofthe
primarypipeworkisalsolowersincecheapermaterialsmaybeused,andthe
distributiontemperaturecouldbemaintainednetworkwidewithmoreconfidence.In
additionturnoverofwatersupplywouldbeguaranteed,thusreducingstagnationand
associatedproblems.Thesupplycouldutiliseasinglemains(pressurised)coldwater
supply, which could be routed externally, therefore limiting heat
gains and maintaining the quality again by guaranteeing the
turnover. Finally, until environmental cultures are performed
routinely, hospitals in particular will
continuetoexperienceLegionnairesdiseasewithitsattendanthighmortality.The
disease will remain under-diagnosed and undetected unless
diagnostic testing is carried
outmorefrequently.Onlyifitisknownwithconfidencethatcolonisationlevelshave
increasedcantrulyappropriateandcosteffective,reliabledisinfectionmeasuresbe
recommended29.