Top Banner

of 16

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 5/20/2018 Lec-5 Fundamentals of AGC

    1/16

    1

    Fundamentals of

    Load Frequency Control (LFC)and

    Automatic Generation Control(AGC)

  • 5/20/2018 Lec-5 Fundamentals of AGC

    2/16

    The system frequency reaches steady-state at a value

    that causes the sum of the on-line generator output

    MW to be equal to the system load MW.

    With this type of governor Control (Primary Control),when the system load increases, the system

    frequency decreases and visa versa.

    How do we control frequency to 50HZ, no matter whatthe load is?

    We need Secondary Control also

    Limitation of Governor Control (Pr. Control)

    2

  • 5/20/2018 Lec-5 Fundamentals of AGC

    3/16

    Governor with

    Speed-droop

    Feedback Loop

    3

    (Ref. W&W p. 337)

    By changing the load

    reference set pointThe generators governor

    characteristics

    can be set to give

    reference frequency fo

    at any desired unitoutput.

    The bas ic con tro l input to th e

    generat ing un it as far as generat ion

    contro l is co ncerned is the load

    reference set po int (Raise/Lower).By adjusting this set point on each

    unit, a desired unit dispatch can be

    maitained while holding system

    frequency close to the desiredvalue

  • 5/20/2018 Lec-5 Fundamentals of AGC

    4/16

    Speed-Changer Settings

    4

  • 5/20/2018 Lec-5 Fundamentals of AGC

    5/16

    Steady-state speed characteristic

    with speed changer

    50

    5

  • 5/20/2018 Lec-5 Fundamentals of AGC

    6/16

    Power output as a function of frequency

    6

  • 5/20/2018 Lec-5 Fundamentals of AGC

    7/16

    7

  • 5/20/2018 Lec-5 Fundamentals of AGC

    8/16

    Primary Control

    Secondary Control

    8

  • 5/20/2018 Lec-5 Fundamentals of AGC

    9/16

    How does the addition of the Raise/Lower Speed

    Changer( Sec. Control) to the Governor Control (Pr.Control) facilitate the control of frequency?

    Hint: It causes the sum of the on-line generator

    output MW to be equal to the system load MWexactly at desired value of steady-state system

    frequency.

    Governor alone can not eliminate frequency errorcaused by load changes. Advantage of governor is its

    quick response and reasonable frequency correction

    9

    Primary Control and Secondary Control

  • 5/20/2018 Lec-5 Fundamentals of AGC

    10/16

    From a central control site, you increase or decrease

    the no-load frequency set-points of generating unitsuntil the sum of the generated power is equal to the

    present system load, then the frequency will stabilize

    at 50HZ.

    This form of supplemental control is called Automatic

    Generation Control (AGC) and more specifically, Load

    Frequency Control (LFC).

    AGC, and LFC

    10

  • 5/20/2018 Lec-5 Fundamentals of AGC

    11/16

    Automatic Generation Control, AGC

    AGC is usually implemented in EnergyManagement System(EMS) of Energy

    Control Centers(ECC).

    The components of AGC in modern powersystem are:

    Load Frequency Control(LFC)

    Economic Dispatch(ED)

    Interchange Scheduling(IS)

    11

  • 5/20/2018 Lec-5 Fundamentals of AGC

    12/16

  • 5/20/2018 Lec-5 Fundamentals of AGC

    13/16

    13

    To

    50 Hz

  • 5/20/2018 Lec-5 Fundamentals of AGC

    14/16

    14

    ACE Calculation

  • 5/20/2018 Lec-5 Fundamentals of AGC

    15/16

    15

    Generation Allocation

  • 5/20/2018 Lec-5 Fundamentals of AGC

    16/16

    Losses, Loads, Export PowerGenerated, Import

    50 Hz, in ourcountry

    16