Learning Curve A presentation by Ahmad Tariq Bhatti FCMA, FPA, MA (Economics), BSc
Jan 17, 2015
Learning Curve
A presentation by
Ahmad Tariq BhattiFCMA, FPA, MA (Economics), BSc
04/10/2023 Learning Curve Phenomenon 2
OriginIt was found at Boeing, the aircraft manufacturing company, during WW-II period, that the time
taken to assemble an individual aircraft declined as the number of aircrafts assembled increased. It was noted that the rate of
improvement (known as rate of learning) was so regular that it was presented in the form of a mathematical formula. Thus, the labor hours required for the assembly of aircrafts could be predicted with reasonable precision. The name given to this effect of increased efficiency was
Learning Curve (LC) phenomenon. The phenomenon was tested in a number of
manufacturing setups across the industries and it was found invariably everywhere. However, the
learning rate of laborers differed from one industry to another.
04/10/2023 Learning Curve Phenomenon 3
Defi nitionThe mathematical expression of the phenomenon
that, when complex and labor–intensive procedures are repeated, unit labor time tend to decrease at a constant
rate. LC models mathematically this reduction in unit
production time.
– Cima Official TerminologyThe LC is based on the idea that labor hours decrease
in a definite pattern as labor operations are repeated. More specifically, it is derived from statistical
findings that as cumulative production doubles, cumulative average time required per unit will be reduced by some constant percentage, say 10% to
20%.
04/10/2023 Learning Curve Phenomenon 4
The ConceptIt was found that the cumulative average time per unit
decreased by a fixed percentage each time the cumulative production doubled.
In aircraft industry, the percentage by which cumulative average time per unit decreased was typically 80%. Similarly different
learning rates were noted for different industries.Let us examine an example of production where learning rate is
noted at 90%:Units
Avg. time/unit (hrs.)
Cumulative production time (hrs.)
1 100.00 100.00
2 90.00 (100x90%) 190.00
4 81.00 (90x90%) 271.00
8 72.90 (81x90%) 343.90
16 65.61 (72.90x90%) 409.51
32 59.05 (65.61x90%) 568.56
04/10/2023 Learning Curve Phenomenon 5
An I l lustrat ive Model
Order #
No. of UnitsTotal Time
@LR of 80%
Per order
Cumulative
Production
Per Unit(Hours)
All Units
(Hours)
1 2 3 4 5 = 3 x 4
1 1 1 2,000 2,000
2 1 2 1,600 (2,000 x 80%) 3,200
3 2 4 1,280 (1,600 x 80%) 5,120
4 4 8 1,024 (1,280 x 80%) 8,192
5 8 16 819 (1,024 x 80%) 13,104
6 16 32 655 (819 x 80%) 20,960
04/10/2023 Learning Curve Phenomenon 6
The Shape of LC
1 2 3 4 5 60
500
1000
1500
2000
2500
1 2 4 8 16 32
2,000
1,600
1,280
1,024
819655
Learning Curve W. 80% LR
Cumulative Quantity in Units (Col. 3)Avge. Hrs./Unit of Cumulative Production (Col. 4)
(Data used from table given at slide 5)
04/10/2023 Learning Curve Phenomenon 7
The Formula
𝑌 𝑥=𝑎 𝑋 𝑏
Where,Y = the cumulative average time required to produce X
unitsa = the time required to produce the first unit of output
b = the learning /improvement rate/index of learning X = number of units to be produced
Important Note ,This formula calculates only direct labor time against given number of units. The direct labor cost shall be calculated,
thereafter, by multiplying the time calculated by this formula with standard labor rate.
04/10/2023 Learning Curve Phenomenon 8
CalculationThe cumulative average time taken to produce 10
and 20 units is calculated as follows:
Y= 2000x0.476431
Y= 953 hours
Y = 2000 x 0.381126
Y = 762 hours(Data used from table given at slide 5)
𝒀 𝟐𝟎=𝟐𝟎𝟎𝟎 𝐱𝟐𝟎−𝟎 .𝟑𝟐𝟐
04/10/2023 Learning Curve Phenomenon 9
Calculating Incremental HoursTo calculate incremental hours, we need to examine the
differences between total hours for various combinations of cumulative hours. For instance, in our foregoing illustrative model , the company has completed
an order for 4 units and an enquiry has been received for 6 units later.
The calculation for the time required for the production of additional 6 units shall proceed in the manner given as
below:
Total hours if an additional 6 units are produced (10 x 953) = 9530 …..(a)
Total hours for the first four units (4 x 1280) = 5120…..(b)
Hours required for 6 units after completion of 4 units = 4410 ……(a-b)
(Data used from table given at slide 5)
04/10/2023 Learning Curve Phenomenon 10
Calculating LR by Using LogsIllustration 1
Data relating to the production of first 12 batches of Product X are given as follows:
Time taken to produce the first unit = 15 hoursCumulative time taken to produce first 12 batches 81
hours.Requirement: Calculate the learning rate???
Solution
Where:Y = Average time/batch = 81/12 = 6.75 hours
a= 15 hoursX = 12
b = Rate of learning = Log of learning rate/ Log2 ……(a)
𝒀 𝒙=𝒂𝑿𝒃
04/10/2023 Learning Curve Phenomenon 11
CalculationTo calculate b:6.75 = 15 x
= 6.75/15 = 0.45b log12 = log 0.45
b = Log 0.45/Log 12 = (- 0.3468/1.0792) = - 0.3213
Now putting value of b in formula (a) at slide10
b = Log of learning rate/Log2
-0.3213= Log of learning rate / 0.3010Log of learning rate = 0.3010 x (-0.3213) = -
0.09671Log of learning rate = -0.09671
Find the value (-0.09671) in anti-log table. The value -0.09671 converts to 80% i.e.
the learning rate.
04/10/2023 Learning Curve Phenomenon 12
Calculating Total Time - Tabular MethodIllustration 2
XYZ Ltd is calculating the time taken for product Y and found that a 90% LC applies to the behavior of labor working on its production.
The time taken for the first unit produced is 4 hours. Requirement: Calculate total time taken for 8 units to be
produced of product Y???
Solution
# of units Average Time/ Unit Cumulative Time
Hours Hours
1 4.000 4
2 3.600 (4.00 x 90%) 7.2
4 3.240 (3.60 x 90%) 12.960
8 2.916 (3.24 x 90%) 23.328
04/10/2023 Learning Curve Phenomenon 13
Calculating Total Time by Using Formula
Illustration 3Sigma company has noted a learning rate of 85% while launching test for its product ET. It takes 100 hours to
produce the first unit in a batch. Requirement: Calculate total time for 14 unit batch???
SolutionY = average time per unit
a = time taken for the first unitb = 85% = - 0.2345
Y = 100 x = 53.856
Average time per unit for a batch containing 14 units = 53.856 hours
Total time for a batch containing 14 units = 14 x 53.856 = 753.984 hours
04/10/2023 Learning Curve Phenomenon 14
Pricing a Contract by Using LCIllustration 4
ABC Company, finds that product M has 80% learning effect. The company has just produced 50 units at 100 hours per
unit. Detail of cost incurred is given in the table given below.The company has just received a contract calling for another 50 units. The company has decided to have a 50% markup
on the cost. Requirement: Determine price for the contract for the
50 units????
Description Amount in AED.
Materials (50 units @ AED. 20 each)
1,000
Labor & related cost:
-- Direct Labor (100 hours @ AED.8 each)
800
-- Variable Overheads (100 hours @ AED. 2 each)
200
Total cost of 1st 50 units 2,000
04/10/2023 Learning Curve Phenomenon 15
Calculation
Quantity Total Time Average Time /Unit
Units Hours Hours
50 100 2
100 160 (1.6 x 2 x 100) 1.6 (2hrs x 80%)
Solution
Calculation of Contract Price:
Amount
D e s c r i p t i o n o f C o s t & P r i c e C o m p o n e n t s :
AED.
Materials (50 units @ AED. 20 each) 1,000
Direct labor (60 hours @ AED. 8 each) 480
Variable Overhead (60 hours @ AED. 2 each) 120
To t a l c o s t f o r a d d i t i o n a l 5 0 u n i t s 1,600
A d d : M a r k u p 5 0 % 800
Contract Pr ice for 50 un i ts 2,400
04/10/2023 Learning Curve Phenomenon 16
Important NoteThe LC formula is used to estimate direct labor
time for a given number of units and thus is helpful in the calculation of direct labor cost estimates.
Further, the learning effect is applied to those variables also that are dependent upon direct labor time for their time and cost estimation.
The concept of LC is not applied to direct material costs or overhead costs relating to production.
The concept of LC is applicable where operations are complex and carried out manually by labor. Where
operations are so simple that apply very low level of intelligence, there shall be little scope for learning
effect. Hence, there shall be no LC.
04/10/2023 Learning Curve Phenomenon 17
Applications Pr ic ing Dec is ionsIt requires the ability of the management to use the learning effect to forecast and make the cost reductions and obtain a considerable lead over the competitors by giving better prices.
Work Schedul ingUseful in the management of delivery orders and related schedules. Scheduling labor work requirements.
Standard Sett ing & Budget ingPlays meaningful role in standard costing and applying budgetary controls. Standard costs should reflect the point that has been reached on LC.
Pr ic ing ContractsThe LC has been quite useful in determining the likely costs relating to various contracts. It provides a rational basis for price negotiation and cost control.
Sett ing Incent ive Wage RatesThe LC concept is applied in determining incentive wage rates across the industries.
Inventory ManagementThe LC concept can be used in the planning, budgeting and purchasing of inventory.
04/10/2023 Learning Curve Phenomenon 18
Abbreviat ions Used#
Abbrev iation Descr ipt ion
1 AED Emirati Dirham
2 LC Learning Curve
3 LR Learning Rate
4 WW-II World War Two
04/10/2023 Learning Curve Phenomenon 19
References
Management & Cost Accounting by Colin Drury 5/e Cima Official Terminology Business Finance by Joel G. Siegel, Jae K. Shim, Stephan
W. Hartman
04/10/2023 Learning Curve Phenomenon 20
The End.
A presentation by
Ahmad Tariq BhattiFCMA, FPA, MA (Economics), BSc
Dubai, United Arab Emirates.Contact:
T h a n k y o u !