Mission Statement: Reduce the effect of fixture leakage on leakage data Leakage Test Stand Improvement Marie Rohrbaugh
18

Leakage Test Stand Improvement Marie Rohrbaugh

Feb 23, 2016

Download

Documents

Hope..!

Leakage Test Stand Improvement Marie Rohrbaugh. Mission Statement: Reduce the effect of fixture leakage on leakage data. Background. Situation: External Leakage Testing Important Test Should be very near zero Goal: Reduce the effect of fixture leakage on test data. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Leakage Test Stand Improvement Marie  Rohrbaugh

Mission Statement: Reduce the effect of fixture leakage on leakage data

Leakage Test Stand ImprovementMarie Rohrbaugh

Page 2: Leakage Test Stand Improvement Marie  Rohrbaugh

BackgroundSituation: External Leakage Testing Important Test Should be very near zeroGoal: Reduce the effect of fixture leakage

on test data

Page 3: Leakage Test Stand Improvement Marie  Rohrbaugh

Highly Concentrated Area

Vent Between O-rings to eliminate pressure build-up

Pulse Purge

Page 4: Leakage Test Stand Improvement Marie  Rohrbaugh

Large o-ring seals 2 holes 180 degrees apart

Pressurize one side with Nitrogen

Large Surface Area

Vacuum Chamber

Nitrogen In

Page 5: Leakage Test Stand Improvement Marie  Rohrbaugh

Function Tree

Page 6: Leakage Test Stand Improvement Marie  Rohrbaugh

Block Diagram

Page 7: Leakage Test Stand Improvement Marie  Rohrbaugh

Voice of the Engineer

Page 8: Leakage Test Stand Improvement Marie  Rohrbaugh
Page 9: Leakage Test Stand Improvement Marie  Rohrbaugh

Constraints Use of Nitrogen Gas 1 psi Vacuum 24V signal power supply Class10,000 Clean Room SAFE USERS

Page 10: Leakage Test Stand Improvement Marie  Rohrbaugh

Necessary Tasks Change Plug Design (Interface with the

can) Pneumatics Design/Layout FMEA Software Controls Moog will provide Manufacturing Testing Maintenance and Training Plans

Page 11: Leakage Test Stand Improvement Marie  Rohrbaugh

Benchmarks

Vented

Page 12: Leakage Test Stand Improvement Marie  Rohrbaugh

Brainstorming Pulse with Nitrogen to both Large O-rings release to ambient on

opposite side Vent hole toggles between Nitrogen and

Vacuum

Page 13: Leakage Test Stand Improvement Marie  Rohrbaugh

Brainstorming Always a Constant flow of Nitrogen to

Large Orings Vent hole Toggles between Vacuum and

Nitrogen

Page 14: Leakage Test Stand Improvement Marie  Rohrbaugh

Brainstorming Constant Flow to large O-ring Vent hole Toggles between pressurized

Nitrogen and Ambient

Page 15: Leakage Test Stand Improvement Marie  Rohrbaugh

Brainstorming Constant flow of Nitrogen to Large O-

rings Vent Hole has a constant Vacuum

Page 16: Leakage Test Stand Improvement Marie  Rohrbaugh

Staffing

Page 17: Leakage Test Stand Improvement Marie  Rohrbaugh

Feedback Improve Block Diagram to include a detailed

interface with the AGT and the two systems Team Must Understand functionality

Constraints vs. Functions If team believes another way is better, “ OK”

Timeline IP considerations: We will work it all out over

summer Drawings Test Specifications

Page 18: Leakage Test Stand Improvement Marie  Rohrbaugh

Questions??