LEA-COLLIGA LNS (Catania) October 13 - 15 2008 Gianfranco Prete The SPES Project @ LNL Selective Production of Exotic Species
Mar 27, 2015
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
The SPES Project @ LNL
Selective Production of Exotic Species
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
SPES project
SPES is part of the INFN Road Map for the Nuclear Physics.
Main goal: ISOL facility to perform nuclear physics research with neutron-rich re-accelerated beams.
Host laboratory: Laboratori Nazionali di Legnaro
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
The INFN Legnaro LaboratoryThe INFN Legnaro Laboratory(brief introduction)(brief introduction)
Elettrostatic AcceleratorsElettrostatic Accelerators- Tandem XTU (16 MV)- Tandem XTU (16 MV)- Van der Graff (7 MV)- Van der Graff (7 MV)- An 2000 (2 MV)- An 2000 (2 MV)
SCSC Linac Linac- Alpi - Alpi (Veq=40MeV)(Veq=40MeV)
SCSC RFQ RFQ injectorinjector- - PiavePiave
RIB Facility plannedRIB Facility planned- SPES (ISOL)- SPES (ISOL)
SPES re-acc
elerator
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Main SPES project parts
• 2 RIB production stations by ISOL UCx direct target
• Proton driver: cyclotron with 2 exit ports
• RIB handling with 1/20000 HRMS
• RIB re-acceleration by PIAVE-ALPI supercondictive RFQ-LINAC
• Neutron facility by high current Proton RFQ (TRASCO): LENOS and BNCT applications
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
The SPES Project @ LNLThe SPES Project @ LNL
Applied Physics with proton beam
Multi user projectMulti user project
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
SPES SPES scheme scheme : : RIB ISOL RIB ISOL facilityfacility
Similar to HRIBF-EXCYTSimilar to HRIBF-EXCYTschemescheme
proton driver:Cyclotron
UCx ISOL target 30grUCx ISOL target 30gr8kW 108kW 101313 f/s f/s
HV platform (Pre-accleration)
Isobar separator
Charge Breeder
PIAVE-ALPI (re-accelerator)
1+ n+
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
The SPES components
and project status
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
UCx discs Graphite containerTantalum Heather
- - MULTIPLE UCMULTIPLE UCXX SLICES SLICES : increase the surface radiation area: increase the surface radiation area (P= (P= εε··σσ·S· T·S· T44 Stefan-Boltzmann lawStefan-Boltzmann law))
- GRAPHITE DUMP- GRAPHITE DUMP : : send the proton with low fission rate & high stopping power valuesend the proton with low fission rate & high stopping power value
Basic ideas:
Fission efficiency 100p per 1.5 Fission Fragments
Power density in UCx = 70W/gr
Proton Beam
200A 40 MeV
8kWExotic beam: Exotic beam:
1+1+
10101313 fissions/sec fissions/sec
Stopping Power & Fission Cross Section f or p-> UCx
0
0,5
1
1,5
2
2,5
3
3,5
4
4,5
2 6 10 14 18 22 26 30 34 38 42 46 50
Proton Energy (MeV)
Barn
& M
eV/d
g*cm
2.
Fission Cross Section
Stopping PowerDump: graphite
Target: UCx (30gr)Target: UCx (30gr)
Operating temperature: 2000oC
SPES project 2007:
Direct Target
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
SPES Target developments
Material DevelopmentMaterial Development
- Carbide productions
- Carbide characterizations
- New porous material
- New characterization methods
Mechanical DevelopmentMechanical Development
- Thermo-Mechanical Calculation
- Target Handling radiation hard system
- CAD mechanical drawings
- Development of target prototypes
- Front- end & new devices
20 40 60 80 100
0,0
0,2
0,4
0,6
0,8
1,0
§ * **
*
**** *
**
*
*
Inte
nsity
2
*
* UC2 pdf # 84-1344
§
§ Graphite pdf #
1
MNMX
XY
Z
Target SPES
.797E+07.291E+08
.502E+08.714E+08
.925E+08.114E+09
.135E+09.156E+09
.177E+09.198E+09
FEB 11 200723:44:17
NODAL SOLUTION
STEP=1SUB =1TIME=1SEQV (AVG)DMX =.571E-03SMN =.797E+07SMX =.198E+09
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Alberto Andrighetto 2008
Constraint: U/C ratio = 1/4
Effect of Uranium Oxide precursor Effect of Uranium Oxide precursor on UCon UCxx bulk Density and Porosity bulk Density and Porosity
Effect on grain size and shape
Cold pressing conditions:P= 750 Mpa, 1h
3.0
3.2
3.4
3.6
3.8
4.0
4.2
4.4
g
*cm
-3)
UO2
U3O
8UO
3
Final Bulk Density
P=375 Mpa, 1h
UCx from UO2 UCx from U3O8 UCx from UO3
5m 5m 5m
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
High Temperature Test Bench High Temperature Test Bench
SPES target prototypewith 7 SiC Ф=40 mm. discs
Thermal conductivity
0
5
10
15
20
25
30
35
40
45
50
900 1000 1100 1200 1300 1400 1500 1600 1700
Mean temperature (°C)
Th
erm
al c
on
du
cti
vit
y (
W/m
^2
*K)
DATASHEET
Past work
New experimental apparatus
1000 1200 1400 1600 1800 20000,0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1,0
SiCA (hexagonal, bulk) SiCG (hexagonal, bulk) SiC xycarb (cubic, porous) Al2O3 Graphite (fine) LaCx
T (°C)
Emissivity
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Next actions for target
On line test of target material
ORNL-HRIBF
ISOLDE
Install Test bench at LNS
Aluminum I sotopic Chain
10
100
1000
10000
100000
24.5 25 25.5 26 26.5 27 27.5 28 28.5 29 29.5
Mass (amu)
Cou
nts/
s
2 microA, 1800°C
5 microA, 1800°C
10 microA, 1800°C
12 microA, 1800°C
2 microA, 1600°C
TASK3_Direct Target
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
150
50
64
160
120
100
290
150
100
205
245
132(Distances in cm)
OnLine Test Benchat LNS
Spes front-end
Tape transport system
CS proton beam100nA 30-70MeV
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
The SPES The SPES Ion SourcesIon SourcesIonization schema with a Surface ionizer coupled to a Laser beam
Hot surface
Atom Ion
Surface ionization
Ionization energy< 5-6 eV
Ground state
Ground state
continuum
Conductive bandFermi energy
Hot surfaceWork function
Ion
Laser ionization
Atom
laser
Ionization energy
< 9 - 10 eV
Ground state
continuum
Excited states
Laser beam
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Pavia Laser lab(Piero Benetti INFN Pavia)
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
The PIAVE Superconductive RFQThe PIAVE Superconductive RFQ
ALPI Output with the two Injectors
0
10
20
30
0 50 100 150 200 250A
E/A
[M
eV
/u]
Tandem+ALPI (G-F) (some pnA)
PIAVE+ALPI (some 10 pnA)
PIAVE+ALPI
XTU+ALPI
ECRIS
LEBT 3H-BSRFQs
QWRsB
to ALPI booster
TDB
1.
2. 3. 4.Transmission
1.► 2. 90% 2. ► 3. 68% 3. ► 4. 85%
The PIAVE The PIAVE Superconductive RFQFrom October 2006: Regular Operation
β=0.047
β=0.0089
ALPI injectorALPI injector
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Superconductive linac based on QW resonators.
2003: Up graded to Veq ~ 40 MV
Nb/ Cu spattered
cavitiesor bulk Nb
cavities
The ALPI post acceleratorThe ALPI post accelerator
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Year 2006CR03 0 0 0 6 6 6CR04->CR06 3 3.5 3.5 3.5 6 6CR07->CR20 3.6 3.6 4.2 4.5 4.5 4.5CR21->CR26 5.5
238U28+ 4.96 5.21 5.84 6.2 6.6 9.9132Sn16+ 6.7 7 7.5 10.3132Xe19+ 6.13 6.39 7.15 8 8.9 12.1132Xe26+
9.6 10.8 16.1
Energy [MeV/A] 132Xe 40÷44+ 9.1 10.6 12.8 20
with stripper 132Xe 41÷45+ 13 22.8
2007 2008
Eacc [MV/m]
Energy [MeV/A]
High not installed
The ALPI post acceleratorThe ALPI post accelerator
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Accelerated RIBs from U fissionAccelerated RIBs from U fission
Proton driver: 40-50 MeV, 10 Aupgrade to 20 A
Direct target: UCx
Fission rate: 4x1011 f/s
SPES expected beam SPES expected beam intensities : intensities :
at least 20 times at least 20 times HRIBFHRIBF
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Some expected Beams at SPES
1,00E+00
1,00E+01
1,00E+02
1,00E+03
1,00E+04
1,00E+05
1,00E+06
1,00E+07
1,00E+08
1,00E+09
1,00E+10
70 80 90 100 110 120 130 140 150
inte
ns
ity
(se
c-1
)
mass
Accelerated RIB beams
132Sn
Ga
KrSr
AgIn
Sn Cs
ionization efficiencies: (1+) 30% and (n+) 4%(1+) 90% and (n+) 12% for Kr and Xe,
Transport efficiency 50%
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Neutron rich beams expected at SPES facilityElement Mass Most Intense
isotope(1/s)
IonizationEff (%)
Target SourceSurface IonizationLaser Ionization
R&D (difficulty)
Ni 65-69 10+6 6 UCx LIS **
Cu 66-76 10+6 7 UCx LIS **
Zn 72-79 10+6 5 UCx LIS **
Ga 72-84 10+6 20 UCx LIS **
Ge 75-84 10+7 3 UCx LIS ***
Rb 86-94 10+9 65 UCx SIS *
Sr 89-96 10+8 UCx SIS+LIS ***
Y 90-97 10+7 UCx LIS ****
Pd 111-118 10+7 UCx LIS ****
Ag 110-120 10+8 14 UCx LIS **
Cd 115-124 10+8 10 UCx LIS **
In 116-128 10+8 15 UCx SIS+LIS **
Sn 123-134 10+9 15 UCx LIS **
Sb 124-135 10+8 3 UCx LIS ***
Te 129-138 10+7 UCx LIS ****
Cs 134-144 10+9 85 UCx SIS *
Ba 139-146 10+8 UCx SIS+LIS ***
La 141-145 10+6 UCx SIS+LIS ***
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
The driver cyclotron(Commercial solution chosen)
IBA C70 characteristics: (possible candidate)
• Diameter < 4m
• Weight > 120t
• Magnetic Gap: 30mm• Magnetic field: 1.55T• Extraction Radius: 1.2m• 2 exit ports
SPES designSPES design
• Particles: H- / D- / He2+/ HH+
• Variable Energy : 15 MeV 70 MeV
• extraction Systems: Stripper H- / D-
Deflector He2+/ HH+
• Performances: 750µA H- 70MeV IBA C70 cyclotron: 35µA He2+ 70MeV
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
RIB transport lines
20 m
HRMS
CBMS
Charge Breeder(HVplatform 250kV)
TIS – RF Cooler - WienFilter(60kV extraction + 250kV platform)
8 m15 m
cryopanel
1/15000
1/2500
43 m
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Second stage of the EXCYTisobaric mass separator
Comparison of the main parameters of the EXCYT and the SPES
mass spectrometer.
Project name EXCYT SPES
Number of dipoles 2 2
Bending Angle 90° 110°
Bending radius 2.6 m 2.6 m
Entrance/exit angle 12.8° 32°
Magnetic field range 0.6 - 4.4 kGauss 1.0 - 4.4 kGauss
beam size at analysis slits 0.4 mm 0.4 mm
Teta acceptance 40 mrad 40 mrad
(x,x’) emittance 4 mm.mrad 4 mm.mrad
Y beam size 2 mm 2 mm
Phi acceptance 10 mrad 10 mrad
(y,y’) emittance 4 mm.mrad 5 mm.mrad
Resolving power >15.000 >20.000
Dispersion 16 m 28 m
High Resolution Mass Separator
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Which Charge Breeder?
REXEBIS+REXTRAPPulsed mode
PHOENIX boosterCW mode
Efficiency 15 4% 10 2% broader charge statedistribution
Breeding time From 13 to 500ms depending on A 100 ms to 300ms
A/q 2 – 4.5 4 – 8
A No real limitation Injection difficult A<40
Mode Pulsed Continuous or pulsed
Imax few nA 1 μA
Beam emittance
15-20 mm·mrad (95% geometrical)for 20·q keV – measured
10 mm·mrad at 19.5*q keV (90%)
Background Beside residual gas peaks <0.1pA Usually >2nA
Reliability Cathode is fragile (could be solved with different gun design) and overall system complex
Robust and simple
Eurisol_DS Task9 preliminary report 2008
EBIS or ECR ??
Follo
w and
par
tecip
ate
to th
e
deve
lopm
ent p
rogr
ess.
(CW
ope
ratio
n)
Ope
ratio
n m
ode
fits
to A
LPI r
eque
sts.
App
elin
g re
liabi
lity
and
sim
plic
ity
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
SPESNeutron facility
Measurement of Maxwellian Averaged Cross Section (MACS): Measurement of Maxwellian Averaged Cross Section (MACS): the quantity needed for the calculation of the stellar reaction rate.the quantity needed for the calculation of the stellar reaction rate.
Irradiation facility: production of nuclear data (neutron capture cross section) Irradiation facility: production of nuclear data (neutron capture cross section) for nuclear energy, new technologies, international agencies (NEA,IAEA)for nuclear energy, new technologies, international agencies (NEA,IAEA)
Radiation hardness studies on electronics and detectors for Radiation hardness studies on electronics and detectors for High Energy Physics, Space and Avionic applicationsHigh Energy Physics, Space and Avionic applications
Radiobiology application: cell irradiation facility complementary to Radiobiology application: cell irradiation facility complementary to actual radiobiology facility at ALPI and CNactual radiobiology facility at ALPI and CN
Nuclear medicine research: Boron Neutron Capture Therapy. Nuclear medicine research: Boron Neutron Capture Therapy.
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
• 6/6 modules machined• RFQ1 and RFQ2 brazed and accepted• RFQ3 first brazing performed• All modules brazed within 2008
RFQ construction: status
5MeV 30-50mA5MeV 30-50mA
TRASCOHIGH CURRENT proton linac
TRIPS Ion Source TRIPS Ion Source (developed by LNS and (developed by LNS and
operated at LNL)operated at LNL)
Brazing process performed at CERN
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Neutron Beam
Neutron Flux = 51010 n cm2 s-1
Lithium target
Berillium target
Thermal neutron beam at exit port of moderator:
109 n cm-2 s-1
Irradiation facility: Irradiation facility: 2 experimental halls2 experimental halls
BNCT
Astrophysics and irradiation
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Radiation safety issues
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Target radioactivity
Radius of the
sphere(cm)
Average neutron
flux(cm-2 s-1)
Average neutron ambient dose
equivalent H*(10) (Sv/h)
15.5 1.9101
0
2.5104
100 3.9108 5.4102
Target inventory evaluated by ENEAIrradiation = 30 daysProduced actinides: U236 (0.34 mg), Np 237 (0.52 mg), Pu236 (0.10 mg), Pu239 (5 mg)
Neutron doses.
cooling days
source s-1
Max dose on the anticorodal sphere
surface
3 1.6·1012 6 Sv/h
365 3.7·109 13 mSv/h
Calculated dose. The radius of the anticorodal sphere is r=15.5cm.
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco PreteSPES TARGET GROUP
At ISOLDE ‘ .. monitor BLM at 2.3 m from target indicates 12
Gy/h for U-runs ..’
From ‘RADIATION PROTECTION ISSUES
WITH ACTINIDE TARGETS AT ISOLDE’
Talk: A. DORSIVAL, CERN-SC-RP
First Workshop on Actinide Target Development
April 27-29, 2006
At SPES : Total Dose at 2.3 m from the target forseen 100 Sv/h for UCx -> ~ 10 Gy/h
-> Same dose as ISOLDE
From ‘The SPES target – Power deposition and preliminary radiation
protections analyses’
C. Petrovich ENEA Report FPN-P815-007
Target Target ActivationActivation
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Preliminary project of
safety systems
• Detailed Shielding analisys
• Vacuum pumps Exaust System
• Nuclear Ventilation System
• Cooling and Drainage of controlled area
• Radiation and access Control Systems
RISK EVALUATIONSAFETY REPORT
Expertise and PeopleExpertise and People
D.Zafiropoulos (Qualified Expert)L.Sarchiapone (FLUKA)
G.Bassato (ControlSystemDesign)S.Canella (ControlSystemDesign)
M.Giacchini (EPICS)
Palermo University (Nuclear Ingeneering)Padova Univ. (Nuclear WasteBuilding)
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
LNL Director: G.Puglierin
LNS Director: M.Lattuada
Advisory Committee
SPES Working Group
Steering Committee
Project Leader: G.Prete
Technical Coordinator: A.PisentScientific Coordinator: A.CovelloQualified Espert: D.Zafiropoulos
Task LeadersProject manager
Management board
SPES project organization
La Rana, Pirrone, Colonna, Million, Bruno, Lunardi, Corradi, Casini, Cuttone, Alba
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
SPES Working Group
task responsible
1 Safety, Radiation protectionControl system
F.Gramegna
2 Infrastructure P.Favaron
3 Direct TargetRIB Sources, Beam Test
A. Andrighetto
4 RIB manipulationCharge Breeder, Spectrometer
L.Calabretta (interim)
5 High Intensity Proton DriverNeutron Facility and BNCT
A.Pisent
6 Re-accelerator G.Bisoffi
7 High Energy Proton Driver A. Lombardi
8 Scientific support A. Covello
0 Project Management
Project Leader: G.Prete
Technical CoordinatorA.Pisent
Scientific Coordinator A.Covello
Radiation protection Procedures D.Zafiropoulos
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
Ingegneria Meccanica (Sezione Materiali) – Univ. di PadovaIngegneria Meccanica (Sezione Materiali) – Univ. di Padova
Dipartimento Scienze Chimiche – Univ. di PadovaDipartimento Scienze Chimiche – Univ. di Padova
Ingegneria Meccanica (Sezione Progettazione) – Univ. di PadovaIngegneria Meccanica (Sezione Progettazione) – Univ. di Padova
Ingegneria Meccanica (Sezione Meccatronica) – Univ. di TrentoIngegneria Meccanica (Sezione Meccatronica) – Univ. di Trento
Ingegneria Informatica – Univ. di PadovaIngegneria Informatica – Univ. di Padova
ENEA Bologna ENEA FaenzaENEA Bologna ENEA Faenza
Ingegneria Nucleare-Univ. di PalermoIngegneria Nucleare-Univ. di Palermo
(Ing. Energetica Politecnico di Torino)(Ing. Energetica Politecnico di Torino)
SPES CollaborationsSPES Collaborations
International collaborations:International collaborations:
ISOLDE-CERN, HRIBF-ORNLISOLDE-CERN, HRIBF-ORNL
SPIRAL2- Ganil (LEA), ISAC-TRIUMF SPIRAL2- Ganil (LEA), ISAC-TRIUMF
Laboratori Nazionali di Legnaro – Laboratori Nazionali del SudLaboratori Nazionali di Legnaro – Laboratori Nazionali del Sud
Sez INFN: Padova, Milano, Bologna, Catania, Firenze, Napoli, BariSez INFN: Padova, Milano, Bologna, Catania, Firenze, Napoli, Bari
Target development
Nuclear safety and radioprotection
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
RIB production targets - R&D program on Uranium Carbide targets;- design of the target/ion source systems;- targets test experiments and analysis of results with the objectives to quantify the target efficiency in its final geometry.- definition of the industrial fabrication method of the SPIRAL2 high density target.Neutron converter- design, construction and tests of neutron converter for SPIRAL2;- definition of the nuclear constraints for the converter of SPIRAL2;- design of the remote handling system for SPIRAL2.Safety and radioprotection
-evaluation of the risks due to the operation of the ISOL facilities SPIRAL2 and SPES based on UCx targets;-study and design of the safety and radioprotection system according to national laws; exchange of qualified personnel competence, access to documentation, technical drawings and codes for safety and radioprotection;-design and construction of the cryogenic radioactive gas trapping system for SPES and SPIRAL2;
Accelerator technology-Beam control system-high intensity beam diagnostic -low intensity RIB diagnostic systems
High resolution Mass Separator-Beam optics study for isotope selection-Design study for 1/20000 mass spectrometer
Charge Breeder (CB)-collaboration on the development and construction of CB systems-project of SPES CB on the basis of the developed SPIRAL2 ECR CB
Memorandum of Understanding INFN – Ganilon common technical developments of ISOL facilities
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
SPES – ISOLDE MoUTarget development:
material studycharacterizationtest
Laser source for RIB:participation to RILIS development
Radiation safety:safety reportspecial services for RIBrisk evaluation
Charge Breeder and Beam Transport:technical discussions system design definition
Superconductive Linac cavity development:Sputtering of Quarter Wave cavities
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
PlanningPlanning
2006-2008: - Prototype study of the Target
- Facility design
2009: - Authorization requests: safety and radioprotection
2009-2013: - Facility construction
SPES Project at LNL:
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
SPES SCHEDULESPES SCHEDULE2007 2008 2009 2010 2011 2012 2013
Facility design
Target and source prototypes
Authorization to operate
Building construction
Target installation and commissioning
Completion of RFQ for Neutron Facility
Installation and commissioning Neutron Facility
Cyclotron construction
Cyclotron Installation and commissioning
Alpi preparation for post acceleration
Installation of RIBs transfer lines and spectrometer
Complete commissioning
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
SPES Economic plan kEuro
infrastructures 14840
Target (2 stations) 5900
Beam Transfer 7650
safetyRadioprotection 6000
Cyclotron 8400
Re-accelerator 7000
High Intensity Linac 3600
Neutron Facility BNCT - LENOS 3300
56690
MINIMUM for RIB production only (1 target): 41 MeuroMINIMUM for RIB production only (1 target): 41 Meuro
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
SPES projectstatus
• Waiting for final SPES approval by INFN (November 2008) Waiting for final SPES approval by INFN (November 2008)
• Preliminary Project in progress (infrastructure and buildings)Preliminary Project in progress (infrastructure and buildings)
• Project ready for construction phaseProject ready for construction phase
LEA-COLLIGA LNS (Catania) October 13 - 15 2008
Gianfranco Prete
• End presentation