LARGE SCALE 610-REMEDIATION PROJECTS John A Christiansen, PE.' Clayton R. Page, PhD.' Michael D. Thomas, M.S., E.I.T.' 'Environmental Remediation, Inc., Baton Rouge, Louisiana Bioremediation of hazardous waste and petroleum hydrocarbons and sludges in soils are still described in scientific literature as an "emerging technology". In fact, today there are very large scale applications of bioremediation techniques to contaminated sludges in soils in a variety of regulatory environments. Bioremediation has been accepted for the Superfund program as evidenced by the number of Records of Decisions (ROD) in which bioremediation is named. By the end of 1989 there were twenty five (25) ROD'S which included bioremediation. This amounted to over 15% of ROD'S written to date. In addition to this acceptance by CERCLA programs, bioremediation is being used in a number of RCRA underground storage tank and emergency response sites. The purpose of our paper is to describe two such large scale bioremediation applications. The first is the description of the bioremediation of an abandoned refinery site in the mid-west. This site is being remediated under RCRA using slurry reactor and land treatment techniques. The volume of waste to be treated is more than 150,000 cubic yards of sludge and contaminated soil. The second application is the treatment of crude contaminated beaches in Valdez, Alaska, with emphasis on the development of specialized microbial cultures. Our discussion in this case will center on the isolation, adaption and screening of microorganisms for application at this site. 795
24
Embed
Large Scale Bio-Remediation Projectsinfohouse.p2ric.org/ref/31/30406.pdf · The initial project to be discussed is an abandoned refinery site. It is located in the mid-west, next
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
LARGE SCALE 610-REMEDIATION PROJECTS John A Christiansen, PE.'
Clayton R. Page, PhD.' Michael D. Thomas, M.S., E.I.T.'
Dibenzo (a, h) anthracene Sum of Eight Potentially
Carcinogenic PAHs Total PAHs
Cleanup Level
E.P. Tox Levels 3.2 mg/kg
90 mg/kg
160 mg/kg 300 mg/kg
The bioremedial design of the project involves slurry reactor treatment for the
pumpable sludges and land treatment for the non-pumpable sludges. To achieve this
treatment and remain within the context of RCRA, the existing surface impoundments
would also have to serve as the treatment units. Accordingly, it was decided to store
approximately 50% of the contents of the pond sludges in the pit area, as well as create
a temporary storage area for sludges and soils within the confines of the lagoon. The
remaining lagoon sludges were transferred to this temporary storage area and the lagoon
itself converted into a 6.5 acre land farm and a 1 .O acre storm-water management area.
The units were partitioned as shown in Figure Two.
The basis for this treatment system was extensive laboratory and field treatability
studies conducted during the a 36 month period by several consultants. From these
studies, the ha!f-!ife ya!uns fQr key constitg$nts were idectified as she:"::: i:: Table Three.
Hydraulic retention times for continuous and batch processing were developed. Batch
processing was selected due to variability of the waste, with slurry reactor retention times
of 60 to 135 days identified for the most concentrated constituents. An additional benefit
797
identified during slurry reactor treatment was the destruction of organic solids and the
subsequent volume reduction of sludges. A wastewater treatment system was provided
in order to allow the discharge of free liquid contaminated with degradation metabolites
and salts during the treatment process.
TABLE THREE
Degradation Estimates for Slurry Reactor
Constituents Pond - Pit Lagoon
Oil and Grease, Half-life, Days 69-1 13 20-58 25-65 Total PAHs, Half-life, Days 29-69 1 6-24 NIA Carcinogenic PAHs, Half-life, Days 19-42 44-82 N/A Average Design Hydraulic Retention
Processing, Days 135 90 90 Time Assumed for Sludge
N/A - These sludges were not subjected to bench scale studies
To effect the treatment, a slurry reactor was constructed out of the existing pond.
To maintain a solids concentration of about 10% during slurry treatment, high speed
direct drive mixers were utilized, as shown in Figure Three. These devices used a
polyurethane foam filled float to maintain buoyancy in the reactor. Suction was taken
from the sides of a cone underneath the float and pump through a volute, by high speed
propeller. The pumping action was considered essential to suspend grit, as well as
organic solids. Several of these mixers were placed throughout the slurry reactor, as
shown in Figure Four. !r! order tc! prevent .ncnntm!!ed ccnuring or eresie!? of the pond,
a proprietary mixer frame was designed which acted as a mixer positioning control and
test block. Oxygen transfer was the next requirement. After evaluating the diffused and
mechanical aeration systems, mechanical aeration was selected for several reasons. The
798
primary reason was the recognition that volatilization concerns would be present with
both types of systems. Volatilization of BTEX peaked after the first 48 to 96 hours of
treatment and declined drastically thereafter. With controlled start-up, volatilization would
be effectively controlled. The combination of surface aerators and direct drive mixers
achieved a mixing level of approximately 160 HP per million gallons or about 150% of a
normal activated sludge system. In monitoring during the slurry reactor, treatment was
set so that no detectable carcinogenic constituents would be found outside the exclusion
zone of the treatment unit.
The residuals from slurry reactor treatment, along with non-pumpable sludges,
would be treated in a land treatment unit. The land treatment unit was approximately 150
feet wide by 1,720 feet long. In order to insure adequate removal of water, prevention
of constituent migration and operation under variable loads of sludge, a double liner leak
detection system was used. The first liner consisted of not less than two feet of
compacted soil on which was placed a 200 mil geo-textile drainage weave. On top of this
was placed an 80 mil HDPE liner. On top of the liner was placed more than 24 inches
of porous fill soil containing a drain system. The drain system was designed to remove
the maximum hydraulic load to the land treatment cell within the 24 hour period. During
the construction phase of this project, the lagoon had to be emptied of sludge. After the
construction of the storage cell, approximately 50,000 cubic yards of sludge and 10,000
cubic yards of sludge from the pond were moved in a period of 40 days using hydraulic
dredge and pumping techniques. Free liquid was maintained on top of the lagoon during
this time in order to minimize air admissions. An air emissions control curtain was
constructed around the operating portions of the site to allow admissions monitoring and
799
to isolate areas of high admissions from areas of site operating personnel. During
excavation, operators were often found in Level B personnel protective equipment though
operating environments were reduced to Levels C and D as soon as air monitoring
indicated no threat to human health and environment existed.
Operations consisted of batch treatment of more than 19,000 cubic yards of waste
in the slurry reactor for approximately 60 to 75 days. During this time, monitoring was
conducted for control parameters and target hydrocarbon parameters. Control
parameters consisted of microbial measures, such as Adenosine Triphosphate (ATP) to
estimate total microbial population, and nutrient parameters, such as nitrogen and
phosphorus. In addition, operating parameters such as dissolved oxygen uptake, pH
alkalinity and other activated sludge functions were observed. Target hydrocarbons were
observed monthly in order to accurately access the degradation of target hydrocarbons.
The slurry reactor was de-energized and a sampling crew collected grab samples from
more than 40 sampling locations. These locations were then composited on-site to
provide a target hydrocarbon sample. Mass balances were calculated for both mixed
liquor (suspended organic matter) and settled sludge in order to assess target
hydrocarbon degradation.
During the first year of operation, more than 3.8 million pounds of oil and grease
were loaded into the slurry reactor and processed until at least 67% degradation was
achieved. At this point, the reaction was stopped and the residuals applied to the land
treatment unit. As shown in Table Four, the oil and grease mass balance indicates more
than 74% degradation in the first batch. Subsequently, in the Spring of 1991, the land
treatment unit was sampled and passed the cleanup standards shown in Table Two. A
800
new batch of sludge was loaded into the reactor for treatment. Thus, a large scale
bioremediation unit was used to successfully treat refinery sludges in the batch slurry
reactor followed by land treatment of residuals. More than 19,000 cubic yards of sludge
were treated in the first batch.
TABLE FOUR
Reduction of Mass Oil and Grease Expressed in Pounds
2. Selected Data On Innovative Treatment Technolorries, U.S.E.P.A. - O.R.D., EPA/600/9-90/041 , December 1990.
3. "Bioremediation In The Field", U.S.E.P.A. - O.S.W.E.R., No. 1 , EPA 540/2-90/004, November, 1990.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
"Operating Plan for the Closure of the Sludge Pond, Sludge P. 4, and Wastewater Treatment Lagoon As a Single Waste Management Unit", Submitted to Missouri Department of Natural Resources and U.S.E.P.A. Region VI1 by Amoco Oil Co., July, 1989.
"Sampling and Analyses Program in Connection with RCRA Closure/Lagoon Cleanup", submitted to Missouri Department of Natural Resources by Amoco Oil Co., November, 1988.
"Biological Treatment Demonstration, Biological Treatment of Petroleum Refinery Sludges From the Sugar Creek Facility Tank - Scale Study", Remediation Technologies, Inc., Ft. Collins, Colorado, December, 1988.
Bioremediation For Marine Oil Stills, U.S. Congress, Off ice of Technology Assessment, OTA-BP-0-70, May 1991.
Berkey, E., et al. "Evaluation Process for the Selection of Bioremediation Technologies", Environmental Biotechnolonv for Waste Treatment, Plenum Press, New York, New York, 1991.
Vanosa, A., et al. "Tests to Screen Bioremediation Products for Efficacy Against Weathered Crude Oil Using Respirometer and Shaker Flask Microcosms", U.S.E.P.A. - Risk Reduction Engineering Laboratory, Cincinnati, Ohio, March 23, 1990.
"Special Notice", U.S. Commerce Business Daily, February 12, 1990, No. 1953N.
R.M. Atlas, 1984. Petroleum Microbiolonv, MacMillan Publishing Company, New YOTK, Xew -fork. \ I - .I
M.R. Overcash, et all 1979. Desicln of Land Treatment Svstems for Industrial Wastes - Theow & Practice, Ann Arbor Science, Ann Arbor, Michigan.
U.S. Environmental Protection Agency (EPA), 1986. Test Methods for Evaluatinq Solid Waste: Phvsical/Chemical Methods. SW-846, 3rd Edition.
807
14. APHA, 1985. Standard Methods for the Examination of Water and Wastewater, 15th Edition.
15. EPA, 1083. Methods for Chemical Analvsis of Water and Wastes. EPA-600/r-79- 020.
II
808
PRODUCT G
i o g
I O 8
i o 7
105 0 z
i o 4
i o 3 0 10
Non-Sterile
Sterile Product
Sterile Background
No Oil
20 30
TIME, DAYS
40 50
FIGURE 6
809
-L 0
0 0
O I
tn 0
CUMULATIVE 0 2 UPTAKE, mg/l h)
si: 0 0 0 Q Q 8
0
I
810
PRODUCT G 16000
2000
0
UNSTERILE
STERILE PRODUCT
STERILE BACKGROUND
-0- NO NUTRIENTS
ALKANES FIGURE 8
81 1
1
0 0
t
E W
(D
I
y! m
a,
3 W
a,
n
812
DRAWING NOT TO SCALE
FIGURE 3 SLURRY MIXER
I
815
Top o f dike
Bottom of reactor Water line
. .
i Sludge ; Storage ; Cell
....................................... .
\ L u,,.,.,, - ., .. - - Y - Y - ,. ,. ,. Y - ..
llsolation Curtain i FIGURE 4
SLURRY REACTOR LAYOUT \
c3 031 0
4000
3500
3000
2500
2000
1500
lo00
500
0
0 28
Time (Days) 70 91
REDUCTION OF MASS OF OIL AND GREASE EXPRESSED IN POUNDS
817 FIGURE 5
OIL & GREASE MASS BALANCE BATCH ONE
ESTIMATING ENVIRONMENTAL RESTORATION COSTS I N THE DOE COMPLEX
Marc Zocher Environmental Restoration Technical Support Office
LOS Alamos National Laboratory Los Alamos, New Mexico 87545
Introduction
The United States Department of Energy (DOE) is embarking on one of the largest environmental restoration undertakings of this century. The diversity of locations, site conditions, nature and extent of contaminants, and regulatory environments make this an exceedingly complex, and therefore costly, program. The planned budget for fiscal year 1992 alone exceeds 5.9 billion dollars for DOE environmental restoration and waste management activities'. minimize costs and maximize returns (lower risk to human health and the environment), good cost estimating tools and techniques must be employed.
Traditional Cost Estimating
The DOE has been estimating the costs of construction successfully for years. Typical construction projects within the DOE are laboratory and process buildings, offices, support facilities, and infrastructure (roads, utilities). Most of these projects and project components follow typical construction practices and are built by a contracted work force.
The in-house estimating staff that prepares government estimates follow policies and guidelines that cover the development of the base estimate, the application of contingency, and the use of escalation factors. Many sources of data exist to assist the estimators.
In order to
They include:
0 Commercially available estimating handbooks (e.g. R . S . Means). These books compile actual productivity , equipment, and material costs from many sources across the United States. By developing this large of a database, the actual cost history of the included project components can be used as good reference material.
0 Site specific actual costs. Estimators rely on data from projects completed at their installations for cost elements. past, this data is invaluable for determining site specific cost drivers.
Computer models and estimating tools. general shell to develop internal databases, or specific models that contain their own cost elements to use and mndify.
If similar projects have been completed in the recent
0 These computer software packages are either a
' DOE Five-Year Plan (1990). This figure includes both validated and unvalidated estimates and will be updated in the September, 1991 release of the five-year plan.