Large Capital Process – What is it? Archdiocese of Atlanta Office of Planning and Research Archdiocese of Atlanta Archdiocese of Atlanta Large Capital Process – What is it?
8

Large Capital Process – What is it? Archdiocese of Atlanta Office of Planning and Research Archdiocese of Atlanta Large Capital Process – What is it?

Mar 30, 2015

Download

Documents

Juan Gonzales
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Large Capital Process – What is it? Archdiocese of Atlanta Office of Planning and Research Archdiocese of Atlanta Large Capital Process – What is it?

Lar

ge

Cap

ital

Pro

cess

– W

hat

is

it?

Archdiocese of AtlantaOffice of Planning and Research

Archdiocese of AtlantaArchdiocese of Atlanta

Large Capital Process – What is it?

Page 2: Large Capital Process – What is it? Archdiocese of Atlanta Office of Planning and Research Archdiocese of Atlanta Large Capital Process – What is it?

Lar

ge

Cap

ital

Pro

cess

– W

hat

is

it?

Archdiocese of AtlantaOffice of Planning and Research

2

The sixty-nine county area that comprises the Archdiocese of Atlanta continues to experience significant population growth. This growth creates a strain on existing Archdiocesan facilities and also highlights the need for new facilities. Therefore, one of the key challenges facing pastors* is the maintenance, renovation, and expansion of parish facilities. Pastors and parishes need to know what steps they need to take when a parish believes it needs to expand.

The planning and construction of facilities is an exciting but long effort for a parish. We have developed a series of presentations that contain the key information that a pastor and parish will need to begin the process, as well as an overview of the entire process. We hope that by providing information and tools, parishes will be able to more quickly and effectively identify the key projects that are both important and feasible for their future growth and understand how to obtain required approvals for them.

BALDWIN

BANKS

BARROW

BARTOW

CARROLL

CATOOSA

CHATTOOGA

CHEROKEE

CLARKECOBB

COWETA

DADE

DAWSON

DeKALBDOUGLAS

ELBERT

FANNIN

FLOYD FORSYTHFRANKLIN

FULTON

GILMER

GORDON

GREENE

GWINNETT

HABERSHAM

HALL

HANCOCK

HARALSON

HART

HEARD

JACKSON

LINCOLN

LUMPKIN

MCDUFFIE

MADISON

MERIWETHER

MORGAN

MURRAY

OCONEE

OGLETHORPEPAULDING

PICKENS

PIKE

POLK

PUTNAM

RABUN

STEPHENS

TALIAFERRO

TOWNS

TROUP

UNION

UPSON

WALKER

WARREN

WHITE

WHITFIELD

WILKES

NEWTON

SPALDINGJASPER

MONROELAMAR

BUTTS

HENRY

WALTON

CLAYTON

FAYETTE

ROCKDALE

Why do We Need a Large Capital Project Process?

To help and protect Parishes, Schools and other Archdiocesan

entities when they expand, renovate or maintain their

current facilities or properties.

*Anytime the word “Pastor” is used, it is meant to include Pastors, Principals, Administrators, etc.*Anytime the word “Parish” is used, it is meant to include Parishes, Schools, Missions, etc.

Page 3: Large Capital Process – What is it? Archdiocese of Atlanta Office of Planning and Research Archdiocese of Atlanta Large Capital Process – What is it?

Lar

ge

Cap

ital

Pro

cess

– W

hat

is

it?

Archdiocese of AtlantaOffice of Planning and Research

3

Large Capital Projects may involve significant risk for Archdiocesan entities. Therefore, projects that will cost over a certain amount must obtain the Archbishop’s approval before proceeding with major capital improvements to the facilities and properties.

Photo by Michael Alexander, The Georgia Bulletin

Key Thresholds

When should we use the Large Capital Project Process?

What size project requires the sign off of the Archbishop?

If your project cost is equal to or below the value listed above, then you may proceed without obtaining the Archbishop’s approval. If you plan on using volunteer labor for these projects, then please be especially cautious in dealing with legal and liability issues of volunteers doing facility work without meeting proper codes and licensing. Catholic Construction Services, Inc. is available to help you plan and execute these projects.

Page 4: Large Capital Process – What is it? Archdiocese of Atlanta Office of Planning and Research Archdiocese of Atlanta Large Capital Process – What is it?

Lar

ge

Cap

ital

Pro

cess

– W

hat

is

it?

Archdiocese of AtlantaOffice of Planning and Research

4

If your project cost exceeds the limits on the preceding slide, then you will need to follow the steps in the Archdiocesan Large Capital Process:

1. Define and review project2. Request First Approval (Initial Conceptual Approval) from the Archbishop3. Develop preliminary design4. Request Second Approval (for capital campaign and detailed drawings)5. Secure funding (includes capital campaign)6. Finalize design7. Request Final Approval (to begin construction)8. Begin Construction management9. Accept and dedicate

You will need to follow this process whether your project involves new construction, renovation, maintenance of facilities or land acquisition.

Key Steps in the Large Capital Project Process

Please note: these presentations are not inclusive of all project exceptions. The process presented is a general overview and may not account for every experience possible while undergoing construction. Rather, these websites will give you the language and background needed to confidently embark on your large capital project under CCSI’s guidance.

Page 5: Large Capital Process – What is it? Archdiocese of Atlanta Office of Planning and Research Archdiocese of Atlanta Large Capital Process – What is it?

Lar

ge

Cap

ital

Pro

cess

– W

hat

is

it?

Archdiocese of AtlantaOffice of Planning and Research

5

PLEASE NOTE: Before being approved for any Large Capital Project, you will need to ensure that your parish is in compliance with Archdiocesan Procedures

• Accounts current (e.g. loans, assessments, etc.)? If not, contact the Controller, Finance Office• Using the LOGOS system? If not, contact the Parish Systems Manager, Finance Office• Using ParishSoft system? If not, contact the Training Coordinator, Finance Office• Using the HR portal? If not, contact the Parish Systems Manager, Finance Office• Safe Environment compliance is current? If not, contact the Director of Safe Environment• Parish facilities master plan in place? If not, contact the Director of Planning and Research

For current contact information, please open our contacts page.

If you suspect you are not in compliance, please go ahead through the initial steps of the process to request First Approval and, concurrently, work with the appropriate Chancery contact to be in compliance before requesting Second Approval.

Page 6: Large Capital Process – What is it? Archdiocese of Atlanta Office of Planning and Research Archdiocese of Atlanta Large Capital Process – What is it?

Lar

ge

Cap

ital

Pro

cess

– W

hat

is

it?

Archdiocese of AtlantaOffice of Planning and Research 6

• Capital Campaign Guidance

• Offertory Best Practices

• Master Planning• Overview of Large

Capital Project process• Steps 1 and 2 of LCP

• Review current financial capacity

• Capital campaign exemption from assessment

• Loan terms and rate• Review final application with

Project Review Committee of Finance Council

• Provides a preliminary budget and monitors cost estimates and change order proposals

• Oversight of design• Contract administration and risk

protection• Inspections throughout construction

Customer Centric View of the Large Capital Process

Please note that through the entire Large Capital

Process, Chancery departments are here to serve you and help you

through your construction projects!

Page 7: Large Capital Process – What is it? Archdiocese of Atlanta Office of Planning and Research Archdiocese of Atlanta Large Capital Process – What is it?

Lar

ge

Cap

ital

Pro

cess

– W

hat

is

it?

Archdiocese of AtlantaOffice of Planning and Research

Acceptance and Dedication

Overview of Large Capital Project Process Overview of Large Capital Project Process

Define and Review Project Request First Approval: Initial Conceptual Approval

• Review letter and forms• Grant initial conceptual approval to

engage design professionals and/or a capital campaign consultant

Develop Preliminary DesignRequest Second Approval: Approval for Capital Campaign andDetailed Drawings

• Review letter and forms• Grant approval to:

• Kick-off capital campaign• Obtain detailed drawings and

cost estimate

Request Final Approval: Build Approval

• Review letter and forms• Grant approval to begin construction

Construction Management

Step 1 Step 2

Step 3

Step 5

Step 6

Step 7

Step 8

Step 9

Step 4

• CCSI to present Preliminary Drawings to the Archbishop

Secure Financing

Finalize Design

Page 8: Large Capital Process – What is it? Archdiocese of Atlanta Office of Planning and Research Archdiocese of Atlanta Large Capital Process – What is it?

Lar

ge

Cap

ital

Pro

cess

– W

hat

is

it?

Archdiocese of AtlantaOffice of Planning and Research

8

Who Do You Call?

• Peter Faletti, Director of Planning and Facilities• Work phone

o (680): 404-885-7279 o (Lake Park): 404-920-7855

• Cell phone: 404-915-3785• Email: [email protected]

• Jenny Scheb, Planning Analyst• Work phone:

o (680): 404-885-7410 o (Lake Park): 404-920-7852

• Email: [email protected]

• http://www.archatl.com/offices/construction/