Top Banner
Land use planning issues near major hazard facilities in Melbourne John O’Meara [email protected] Nov 2009
44

Land use planning issues near major hazard facilities in Melbourne

Jan 16, 2016

Download

Documents

isaura

Land use planning issues near major hazard facilities in Melbourne. John O’Meara [email protected]. Nov 2009. The LUP/MHF project. Risk Engineering Society commissioned project to: explain Victorian planning processes to engineers review MHF situation in Melbourne - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Land use planning issues near major hazard facilities in Melbourne

Land use planning issues near major hazard facilities in

Melbourne

John O’[email protected]

Nov 2009

Page 2: Land use planning issues near major hazard facilities in Melbourne

The LUP/MHF project

• Risk Engineering Society commissioned project to:– explain Victorian planning processes to

engineers– review MHF situation in Melbourne– examine recent planning applications near

MHFs to identify issues– examine UK situation & compare to Vic

Page 3: Land use planning issues near major hazard facilities in Melbourne

Project output

• collection of hyperlinked files• hybrid:

–something like a website–something like a wiki–many links to external resources

• educational tool• information resource• will demonstrate later

Page 4: Land use planning issues near major hazard facilities in Melbourne

Reverse disclaimer

• Responsibility for this presentation is mine alone – all mistakes are proudly mine

• Presenting factual material• This is information, not opinion

Page 5: Land use planning issues near major hazard facilities in Melbourne

Some pragmatism

• Complex areas to study

• Need to:-– use simplified explanations (apologies to

experts)– avoid “tangents”

Page 6: Land use planning issues near major hazard facilities in Melbourne

Tangents

important, but distracting

FlixboroughLUP/MHF issues

Buncefield causes

Cranbourne landfill

Environment Protection Act

Dangerous Goods Act

Coode Island

Other States

OHS lawharmonisation

Page 7: Land use planning issues near major hazard facilities in Melbourne

Introduction

• MHF regs introduced 2000• Direct consequence of Longford incident, 1998• Purpose – to minimise likelihood of major

chemical incidents that could harm community• Minimise harm to community if an incident

occurs• Inwards focus – on control measures within

MHFs• Say nothing on developments & activities

outside MHFs

Page 8: Land use planning issues near major hazard facilities in Melbourne

Intro…

• Planning laws – Planning and Environment Act 1987

• Apply to all land• One general aim – keep industry and societal

uses apart• In place before MHF regs• Reference MHF minimally

Page 9: Land use planning issues near major hazard facilities in Melbourne

Intro…

• Victoria’s safety regulator defines MHFs as a special class of industry requiring its own set of reg’s to protect the community

• Town planning perspective?- sees MHFs as a special class? - or sees them as just “industry”

• Hobsons Bay review of industrial land use strategy, 2006– 8x MHFs in Hobsons Bay (more than any other)– 100 Page report– No mention of “major hazard facilities”

Page 10: Land use planning issues near major hazard facilities in Melbourne

UK / Vic comparison

Regulator: HSE (Health& Safety Executive)

Worksafe

Popn: 60 million 5 million

COMAH regs (Control ofMajor Accident Hazards)

MHF regs - MajorHazard Facility

1100 COMAH sites 45 MHFs

108 bulk fuel sites4 bulk fuel MHFs inMelbourne

Significant researchcapacity

Victoria can use HSEresearch output

UK Victoria

Page 11: Land use planning issues near major hazard facilities in Melbourne

Buncefield fuel depot

Before Dec 11 2005

Page 12: Land use planning issues near major hazard facilities in Melbourne

Buncefield fuel depot

Dec 11 2005 (a Sunday)

Page 13: Land use planning issues near major hazard facilities in Melbourne

The incident• In a very small nutshell:

– a tank overflowed for more than 30 minutes– 300 te petrol escaped– vapour cloud formed (no wind) : 200m radius,

2m deep, 30 te petrol vapour– at 6:00 am the vapour cloud ignited & there

was a massive explosion– no fatalities or serious injuries– significant damage to neighbouring properties

(go back to aerial shots of depot)

Page 14: Land use planning issues near major hazard facilities in Melbourne

Neighbouring building damaged by blast & secondary fire

Page 15: Land use planning issues near major hazard facilities in Melbourne

Crushed car

200 kilopascals overpressures

Page 16: Land use planning issues near major hazard facilities in Melbourne

Video of Buncefield damage

• 3 minute video taken by forensic photographers for investigators

• note damage to “square” building and to vehicles

(run video)

Page 17: Land use planning issues near major hazard facilities in Melbourne

UK government response to Buncefield

• MIIB - Major Incident Investigation Board

• 3 year investigation by Health and Safety Executive (UK safety regulator)

• Many objectives & many reports, including:– “Land use planning and societal risk near

major hazard sites”

Page 18: Land use planning issues near major hazard facilities in Melbourne

Land use planning & societal risk report

• Chair of Investigation Board: the subject was “without a doubt, the most difficult and technically challenging that the Board has addressed”

• The longest of their reports – “because we made a particular effort to make our conclusions and recommendations intelligible beyond the narrow community of practitioners”

Page 19: Land use planning issues near major hazard facilities in Melbourne

Land use planning recommendations

• 18 recommendations, including “review land use planning system around major hazard sites”

• Need for “Societal Risk Assessment” approach”

• So:– ongoing work– forebodes significant changes

Page 20: Land use planning issues near major hazard facilities in Melbourne

recommendations...

• Does not follow that a revised planning system will prohibit developments near MH sites – may allow developments not currently allowed

• 90 page report worth studying

(no more about Buncefield)

Page 21: Land use planning issues near major hazard facilities in Melbourne

UK - current planning practice

• HSE defines three consultation distances around each MH site

• inner, middle and outer CDs

• not arbitrary distances, such as 100/200/300m

• CDs calculated on a case by case basis

• Any planning application within a CD MUST be referred to HSE for their advice

Page 22: Land use planning issues near major hazard facilities in Melbourne

CDs - consultation distances

HSE will “advise against” or “not advise against”

Page 23: Land use planning issues near major hazard facilities in Melbourne

Decision matrix

Page 24: Land use planning issues near major hazard facilities in Melbourne

The Oval, London

photo: Jamie Goode, Wine Anorak

Page 25: Land use planning issues near major hazard facilities in Melbourne

Planning application

• Gas holders (top tier COMAH site, ie a MHF)

• Proposal to develop new stand & hotel at cricket ground

• Planning application to Council

• Council referred it to HSE because within consultation distance of gas holders site

• HSE formal response: “advise against”

Page 26: Land use planning issues near major hazard facilities in Melbourne

Approved against HSE advice

• Council approved application

• HSE asked Minister to call in the application

• Minister held inquiry

• Minister supported Council’s decision

• Development will proceed

Page 27: Land use planning issues near major hazard facilities in Melbourne

Melbourne

Page 28: Land use planning issues near major hazard facilities in Melbourne

Yarraville

Page 29: Land use planning issues near major hazard facilities in Melbourne

Development proposal

• Application to Maribyrnong Council

• For 66 dwellings on vacant land

• ~250m from fuel terminal (MHF)

• No consultation distances in Victoria

• Council NOT required to refer this application to Worksafe

• Council sought Worksafe’s view

Page 30: Land use planning issues near major hazard facilities in Melbourne

Worksafe’s comment

• Worksafe commented: “undesirable”

• Comment not binding on Council

• Council decision not yet made public

• possibly to be determined at VCAT

Page 31: Land use planning issues near major hazard facilities in Melbourne

Victoria - planning controls

• How does Victoria control societal risks from industry?– Zones– Threshold distances– Referral to Worksafe

Page 32: Land use planning issues near major hazard facilities in Melbourne

Victoria - zones

• all Victorian land is within a defined planning zone that specifies what the land can be used for & what it cannot be used for

• Look at two opposites– Dandenong & Newport– planned vs historical legacy

Page 33: Land use planning issues near major hazard facilities in Melbourne

Planned - Dandenong

Page 34: Land use planning issues near major hazard facilities in Melbourne

Dandenong - zones

Page 35: Land use planning issues near major hazard facilities in Melbourne

Historical legacy - Newport

Page 36: Land use planning issues near major hazard facilities in Melbourne

Newport - zones

Page 37: Land use planning issues near major hazard facilities in Melbourne

Table of threshold distances

• To define those industries that may cause offence or unacceptable risk to the neighbourhood

• Minimum distance from the land of the proposed use to any residential zone

• seems to apply in one direction only - from industry use to residential, but not other way

Page 38: Land use planning issues near major hazard facilities in Melbourne

Threshold distances - examples

Abattoir 500 m

Milk depot 100 m

Petroleum refinery 2,000 m

Petrol storage 100 m floating roof300 m fixed roof

Organic chemicalsmanufacture 1,000 mInorganic chemicalsmanufacture 1,000 m

Page 39: Land use planning issues near major hazard facilities in Melbourne

Deficiencies with threshold distances

• Seems more concerned with protection of community amenity than safety

• Figures seem arbitrary

• not risk based on a case by case basis

Page 40: Land use planning issues near major hazard facilities in Melbourne

Referral to Worksafe

• Worksafe is a referral authority

• If a referral authority objects to an planning application, Council must refuse the application

• Some industrial developments must be referred to Worksafe

• Residential developments are not referred to Worksafe

Page 41: Land use planning issues near major hazard facilities in Melbourne

Some issues

• Communications - technical jargon, communication with community difficult

• Legacy of unplanned development - co-proximity of residential zones & industrial zones

• high density residential proposals near MHFs likely to continue - what risk assessment process exists?

Page 42: Land use planning issues near major hazard facilities in Melbourne

Issues...

• How is Victoria using the Buncefield experience?

• How will Victoria use the research output from the UK HSE?

• Is there a strategy for preserving land for future MHFs?

• Threshold distances - are they a suitable tool management of societal risk management re MHFs?

Page 43: Land use planning issues near major hazard facilities in Melbourne

Issues...

• Threshold distances - suitable tool management of societal risk management near MHFs?

• Rules for statutory referral to Worksafe - extend?

• Will residential development cause MHFs to increase their hazard controls? Should costs be shared by industry & developer?

Page 44: Land use planning issues near major hazard facilities in Melbourne

The end

(for now)

Thankyou

(show Puerto Rico pix)

(demonstrate project)