www.construction.murrob.com KHUSELEKA North-West, Rustenburg PROJECT TYPE: OPENCAST MINING CLIENT: Anglo Platinum Limited VALUE: R109 Million CONSULTANTS: None PROJECT DURATION: 24 Months DATE OF PROJECT: 1 November 2011 PROJECT DESCRIPTION: Opencast Mining of Merensky Reef to a depth of 20m. Approximate volumes mined for the project :- Topsoil 384,428m³ Overburden 1,342,440m³ Ore 169,878m³ Topsoil Rehab 337,189m³ Filling Void 1,039,109m³
1

Kuseleka Opencast

Jul 03, 2015

Download

Business

Gert Buitendach

Opencast Contract Mining, Drill, Blast, Load, Haul, Crushing
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Kuseleka Opencast

www.construction.murrob.com

KHUSELEKA North-West, Rustenburg

PROJECT TYPE: OPENCAST MINING

CLIENT:

Anglo Platinum Limited

VALUE:

R109 Million

CONSULTANTS:

None

PROJECT DURATION:

24 Months

DATE OF PROJECT:

1 November 2011

PROJECT DESCRIPTION:

Opencast Mining of Merensky Reef to a depth of

20m.

Approximate volumes mined for the project :-

• Topsoil 384,428m³

• Overburden 1,342,440m³

• Ore 169,878m³

• Topsoil Rehab 337,189m³

• Filling Void 1,039,109m³