KTH - SCOPE OF WO
KTH - 5055 Highway 6 North
Houston, TX 77084
CSI DESCRIPTION: SCOPE OF WORK QTY
1 Division 01 - General Requirements:
Side walks XContractor to power wash all exterior concrete after project is
complete
Siding XContractor to clean with either degreaser of 50/50 bleach and
water mixture.
Pavement Markings XContractor to re-stripe all spaces and paint all previously painted
parking and sidewalk areas
Curbs X Replace missing or broken speed bumps
Subtotal Division 01:
2 Division 02 - Site Work
Demolition
Guestroom X
Contractor to remove all items not being reused and place in
contractor provided container or dumpster. All other items are to
be placed in the center of the room and wrapped in visqueen to
keep safe and free of debris.
Contractor to ensure all sprinkler heads are protected during
renovation. Any heads with overspray will be the responsibility ofthe contractor to replace, at the contractors cost.
EVAC Signage XRemove, repair door , paint door Intown specs. Manager will
reinstall after painting
Floor Door Stops X Remove and dispose of existing floor mounted stops
Old Paint X Remove any old paint from window and window lock.
Drapery XExisting drapes and drape rods to be reused. Owner to remove and
store drapes. Owner to reinstall drapes, contractor to install rods.
Bathroom X
Contractor to supply all labor to remove and dispose of vinyl
flooring, lighting, mirrors, hardware, vinyl base, etc. Contractor to
place carpet in tub with fibers down to store toilet and otherhardware to remain. Contractor to tape and visqueen entire tub
area during renovation.
Bath Tub Caulk / Paint XRemove existing caulk and old paint from perimeter of shower /
tub unit
Water Closet X Remove and place in tub during renovation
Phones X Property to remove, store and reinstall existing phones and cords.
Fridge X Protect during painting
Subtotal Division 02:
OS
O
I
OS
C
I
CS
C
I
1
Page 2
7/31/2019 KTH Bid Scope New Format
http://slidepdf.com/reader/full/kth-bid-scope-new-format 2/7
KTH - SCOPE OF WO
CSI DESCRIPTION: SCOPE OF WORK QTY
O
S
O
I
O
S
C
I
C
S
C
I
3 Division 03 - Concrete
Gypcrete Repair
Subtotal Division 03:
4 Division 04 - Masonry
Subtotal Division 04:
5 Division 05 - Metals
Subtotal Division 05:
6 Division 06 - Wood & Plastics
Window Sill X Furnish and install new window sill
Counter / End Splash / P'lam Backsplash X
OSCI:
Contractor to cut 2 back splashes OR 5 (24") side splashes per
sheet. Fully adhere side and bask splashes to kitchen walls.
Contractor to cut out top for sink and burner installation.
Wire Shelving - Vinyl Coated X
Contractor to install 16" deep wire shelf with side and back
supports under cook top. Height is established with existing
garbage cans plus 2".
Cabinet Doors X
OSCI first floor only , reuse all other doors on second and third
floor. Place as directed any doors on the 2nd and 3rd floors with
the 1st floor doors as directed by the ITS PM.
Kitchen Counter Skirts & Drawer Fronts X OSCI first floor only.
Registration Desk X
Contractor to furnish and install new wider opening at registration
counter for ADA counter top to match existing. Replace trim,
drywall and texture to match adjacent walls.
Subtotal Division 06:
7 Division 07 - Thermal & Moisture Protection
Entry Threshold X
Remove during flooring installation. Re-install with new White
Lightning 3006 Elastomeric Caulking, Color: Gray. Install at
underside of threshold prior to setting. Caulk both sides where it
meets door frame at exterior.
Caulking X Perimeter of window
X Base of interior entry, closet and bath door frame
2
Page 3
7/31/2019 KTH Bid Scope New Format
http://slidepdf.com/reader/full/kth-bid-scope-new-format 3/7
KTH - SCOPE OF WO
CSI DESCRIPTION: SCOPE OF WORK QTY
O
S
O
I
O
S
C
I
C
S
C
I
X Perimeter of shower / tub surround
X Shower diverter and / or tub spout
Counter / End Splash / P'lam Backsplash XCaulk ends and joints with DAP 35 year White Silicone and side
splash to countertop DAP 35 Year Aluminum Gray
Kitchen Sink & Cook Top XReuse existing, Contractor to caulk perimeter of sink with clear
silicone.
Subtotal Division 07:
8 Division 08 - Doors, Windows & Hardware
Weather Stripping X OSCI weather-strippingSecurity Latch X Remove, store and re-install after entry door is painted.
Door Sweeps X
Remove existing and install owner supplied door sweeps on entry
door only. Ensure there is not light showing under door when
closed.
Drapery Rods XContractor to reinstall drapery supports, rod and Wall bracket
hook. Supports are to receive 3 hex head screws each.
Bath Wall Door Stop X
Contractor to remove existing stop and reinstall with anchor after
painting is complete. Contractor to ensure all paint (old or new) is
removed from hardware.
Vanity Mirror X OSCI, install 5" above vanity / splash and centered above faucet.
Closet Door Roller Stop XOSCI roller door stop with contractor provided screws, lock
washers and nuts. Install per ITS specifications.
Subtotal Division 08:
9 Division 09 - Finishes
Drywall Prep X Prep and patch all surfaces to receive new paint/texture.
Painting - Guest Room, Bath
Guest Laundry, Front Office, Lobby, Back Hall & RR
Walls & Ceilings X
Contractor to prime all walls and ceiling prior to application of
paint.
Walls: Soft Off-White #A0082
Walls 1416-0110
#44YY 76/094
Ceiling: White High-Hiding RM #A0113
Ceilings 1412-0100
Interior Doors & Frames
Lobby Accent: ICI Special Formula Blue 1403-0500V
Smoke Detector X Protect during renovation
Sprinkler Heads X Protect during renovation
3
Page 4
7/31/2019 KTH Bid Scope New Format
http://slidepdf.com/reader/full/kth-bid-scope-new-format 4/7
KTH - SCOPE OF WO
CSI DESCRIPTION: SCOPE OF WORK QTY
O
S
O
I
O
S
C
I
C
S
C
I
Interior Doors & Frames X
Contractor to remove all hardware, sand prime and finish with two
coats of ITS specified paint:
Semi Gloss Paint on interior door and frame:
ICI White High-Hiding #A0113
Contractor to paint hinges if previously painted. Contractor to
remove any old paint from all hardware
Exterior Doors & Frames X
Contractor to remove all hardware, sand prime and finish with two
coats of ITS Specified
Frame: ICI White High-Hiding #A0113 Semi Gloss
Door: ICI Colonial Red #A0299 Semi Gloss.
Auxiliary Doors: ICI Obelisk #A1797
Stair Treads, Risers & Stringers XContractor to sand, prep, prime and apply two coats of ITS
Specified ICI Colonial Red #A0299 Semi Gloss.
Belly Bands XContractor to paint per Intown specs the colored bans at the
walkway perimeter
Exterior Fire Extinguisher Cabinets XContractor to prep, prime and paint face of FE Cabinet to match
exterior frames
Window Sills X
Contractor to sand, prime and finish with two coats of ITS
Specified ICI White High-Hiding #A0113 Semi Gloss Paint. Any
cracks in wood sill are to be floated to a smooth finish.
Bath Exhaust Fan Cover X
Contractor to remove, clean and paint all metal covers. Remove,
clean and re-install plastics covers.
A/C Wall Sleeves XContractor to paint PTAC Sleeves with Krylon Appliance Paint,
color is white.
Hood Vent XContractor to remove, clean and paint all sides of hood vent. Re-
install after painting
Switches, Outlets, Coax, Phone, Cat 5, GFI XClean all outlets (new and existing) after painting; Remove and
install new jumbo cover place
Flooring
Carpet - Guestrooms & Front Office X
Contractor to prep floor to accept new OSCI direct glued
carpeting. Contractor to install OS transition strips where carpet
meet vinyl flooring. Contractor to ensure all miters are tight andinstalled after base. Do not trim base around transition strip.
Pad - Front Office XContractor to furnish and install two layers of mildew resistant
padding.
Vinyl Flooring (Entry, Closet, Kitchen, Bathroom) X
Contractor to prep floors and install Mapei Primer L; float floors
with a self-leveling compound and install OS vinyl sheet goods.
Trim all edges to walls.
VCT - Guest Laundry X 12" x 12" Vinyl Composite Tile
Base
4
Page 5
7/31/2019 KTH Bid Scope New Format
http://slidepdf.com/reader/full/kth-bid-scope-new-format 5/7
KTH - SCOPE OF WO
CSI DESCRIPTION: SCOPE OF WORK QTY
O
S
O
I
O
S
C
I
C
S
C
I
Carpet Base X
Contractor to prep wall to receive new OSCI carpet base. Base is
to be glued to walls minimizing the use of staples. Corner are to
be turned so that binding wraps the edge. Clip seam as to ensure
piles are even.
Vinyl Cove Base:
Entry, Closet, Kitchen, BathroomX
OSCI 4" vinyl base. Ensure all inside and outside corners are
tight. Caulk any gaps along top of base.
Vinyl Cove Base:
Guest LaundryX
OSCI 4" vinyl base. Ensure all inside and outside corners are
tight. Caulk any gaps along top of base.
Tub Strips XContractor to install OS 60" vinyl tub strips. Tub strips are to
receive additional adhesive caulking prior to installation.
Subtotal Division 09:
10 Division 10 - Specialties
Room Number Signage X
Owner supplied and contractor to install (number will go on wall,
install on latch side of door). Install signage 4" from edge of
frame and 60" AFF.
Misc. Exterior Signage X OSCI misc signage, 12 pieces.
ITS Logo X OSCI front office logo
Toilet Paper Holder XOSCI - 18" AFF centered between toilet tank and vanity/vanity
support.
24" Towel Bar XOSCI, install on wall behind bath door, 48" AFF and centered on
wall.
Vanity Sink Supports X
OSCI, Contractor to supply any spacers necessary to make up for
gap between support bracket and under side of vanity. Attach
base of support to sill plate of wall on top of vinyl wall base
Metal Shelf X OSCI; Install 48" AFF to top of shelf and centered above toilet
Shower Rod and Ends X OSCI
Subtotal Division 10:
11 Division 11 - Equipment
Miscellaneous Equipment (Shelving in Storage Rooms)
Subtotal Division 11:
12 Division 12 - Furnishings
Headboards (1st Floor & Double/Double's) XOSCI - install headboard 1" below top of new bed set and
centered on carpeted area.
Nightstands (1st Floor and Double Double's) X OSCI
Chest of Drawers (1st Floor and Double/Double's) X OSCI
5
Page 6
7/31/2019 KTH Bid Scope New Format
http://slidepdf.com/reader/full/kth-bid-scope-new-format 6/7
KTH - SCOPE OF WO
CSI DESCRIPTION: SCOPE OF WORK QTY
O
S
O
I
O
S
C
I
C
S
C
I
Closet Wire Closet Rack X Remove, clean and re-install after painting
Metal Lounge Chair X OSCI - contractor to receive, store and install.
Artwork XRemove and store existing artwork during renovation. Reinstall
existing artwork 20" from ceiling to top of art.
Beds & Frames-----Fulls XOwner supplied and contractor to install new beds and frames.
Contractor to adjust feet so the frame is 11" AFF.
Platform Sofa X OSCI
Televisions (Guestrooms & Lobby) X
Existing television to be reused. Bundle cord and coax, place in a
heavy duty trash bag and place with other salvaged items in
center of room. Upon completion of renovation unbag television,
plug power cord and coax into jacks and clean for punch.
Television Remote X Give remote to manager
TV Mount X OSCI TV mounts
Kitchen Table XOSCI, contractor to install OS adjustable feet on base of each
table (4 each).
Kitchen Chairs X OSCI - Two (2) per room
Faux Wood Blinds XContractor to furnish and install new 2" white faux wood blinds at
the entry door and window.
Subtotal Division 12:
13 Division 13 - Special Construction
Subtotal Division 13:
14 Division 14 - Conveying Systems
Subtotal Division 14:
15 Division 15 - Mechanical Systems
Individual A/C Unit XContractor to remove existing PTACs and place in Owner storage
container. Contractor to receive, store and install new PTACs.
A/C Grills - Exterior X N/AA/C Interior Covers X Contractor to install new OS covers
Water Closet XContractor to reinstall toilet with new bolts and wax rings.
Contractor to replace bolts, washers and rubber seal at tank.
Toilet Seat XProtect during painting. If broken, contractor to notify
operations for a replacement to install.
Angle Stops & Supply Lines X
Contractor to install new 1/4 turn angle stops and metal braided
supply lines. Contractor to ensure all tags are removed from supply
lines.
6
Page 7
7/31/2019 KTH Bid Scope New Format
http://slidepdf.com/reader/full/kth-bid-scope-new-format 7/7
KTH - SCOPE OF WO
CSI DESCRIPTION: SCOPE OF WORK QTY
O
S
O
I
O
S
C
I
C
S
C
I
Escutcheon Plates X
Contractor to install plastic split ring at toilet, bath sink and
kitchen sink. Contractor to install new escutcheon plates at bath
and kitchen sink waste lines.
Permits / Fees
Subtotal Division 15:
16 Division 16 - Electrical Systems
Ceiling Lights X Contractor to install new owner supplied ceiling fixture and lamps.
Bullet Lights XContractor to install new owner supplied wall mounted bullet lights
and lamps
Microwave XOwner supplied and contractor to install. Location is determined
based on Intown specs
Switch & Outlet Cover plates X Install new jumbo cover plates
6 gang outlets X OSCI behind nightstand
Round Cover plate XInstall new contoured round (TayMac SKU: 419-265)ceiling blank
cover plate over bed.
Recessed Ceiling Lights - Lobby/Front Office XContractor to relocate one (1) existing spot light to center of new
opening.
Subtotal Division 16:
Subtotal
17 General Conditions
Project management
Supervision
Supervision # 2
Equip. rental -forklift
Dumpster
Housing - Apt.
Warehousing
Trailer Rental
Misc. Exp.
Postage & office suppliesFederal Express
Permit / Licenses
GC Fee
Subtotal General Conditions
Grand