HTC 0 Final Thesis Vertical Mills For Raw and Cement Grinding – Inspection and Evaluation From: Josef Koch (Technical Trainee 2009/2010) Supervisor: Gerhard Gudat (Team Leader of Comminution Department) Date of Conduction: 02.2010 – 04.2010
Oct 01, 2014
HTC
0
Final Thesis
Vertical Mills For Raw and Cement Grinding –
Inspection and Evaluation
From: Josef Koch (Technical Trainee 2009/2010)
Supervisor: Gerhard Gudat (Team Leader of Comminution Department)
Date of Conduction: 02.2010 – 04.2010
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc I
Summary
The industrial development of vertical mills started in the beginning of the 20th century in the
USA. Since then many different designs of vertical mills from many different manufacturers
emerged on the market.
Vertical mills are gas-swept-mills. They are used for fine- and finest-grinding and
simultaneous drying of cement-clinker and raw-material. The advantages and disadvantages
of vertical mills will be described in detail. A comparison between vertical mills and ball mills
will be drawn, too.
As in the area CE/CA mainly mills from the manufacturers Gebrüder Pfeiffer, Loesche and
Polysius are in use, the vertical mills of these suppliers as well as the vertical mill from
FLSmidth will be described in detail.
For optimizing a vertical mill there are many different points to consider. The right dam-ring-
height, the proportion of the separator-speed to fan-speed, the amount of water injected into
the mill or the hydraulic pressure of the grinding rollers are just a few parameters with which
it is possible to control the running of a vertical mill. Based on two examples, the
Polysius RM 46/23 in Slite and the MPS 3705 C in Hannover different possibilities of
optimizing a vertical mill will be discussed.
The introduced optimization charts are a tool for optimizing a vertical mill. By displaying the
grinding process as detailed as possible it is possible to find optimization potentials for
grinding on a vertical mill. The so called optimization charts have gathered these important
parameters and linked their interferences. With these optimization charts it is possible to find
the right measures to enable a smooth operation under the given requirements on the
product.
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc II
Zusammenfassung
Die industrielle Entwicklung der Vertikalmühle begann im frühen 20. Jahrhundert in den USA.
Seit dieser Zeit kamen viele verschiedene Auslegungen der Vertikalmühle von
verschiedenen Herstellern auf den Markt.
Vertikalmühlen sind luftdurchströmte Mühlen. Sie werden für die Fein- und
Feinstzerkleinerung mit gleichzeitiger Trocknung von Zementklinker und Rohmaterial
verwendet. Die Vor- und Nachteile der Vertikalmühlen werden im Detail beschrieben. Ein
Vergleich zwischen Vertikalmühlen und Kugelmühlen wird zusätzlich im Detail behandelt.
Da in der Region CE/CA hauptsächlich Mühlen der Hersteller Gebrüder Pfeiffer, Loesche
und Polysius Verwendung finden, werden die Vertikalmühlen dieser Hersteller detailliert
beschrieben. Zusätzlich wird auf die Vertikalmühle der Firma FLSmidth eingegangen.
Um eine Vertikalmühle zu optimieren gilt es, verschiedenste Einflussgrößen zu beachten.
Die richtige Höhe des Staurandes, das Verhältnis von Sichterdrehzahl zu Gebläsedrehzahl,
die Menge an Wasser, das in die Mühle eingedüst wird oder der hydraulische Druck der
Mahlwalzen sind nur ein paar wenige Faktoren, mit denen man das Laufverhalten einer
Vertikalmühle beeinflussen kann. Basierend auf zwei Beispielen, der Polysius RM 46/23 in
Slite und der MPS 3705 C in Hannover werden verschiedene Möglichkeiten der Optimierung
einer Vertikalmühle dargestellt.
Die vorgestellten Optimization charts sind ein Hilfsmittel, um Vertikalmühlen zu optimieren.
Diese haben die wichtigen Einflussgrößen auf die Mahlung mit Vertikalmühlen
zusammengetragen und deren Querbeziehungen dargestellt. Mit diesen ‘Optimization
Charts’ ist es möglich, die richtigen Maßnahmen zu finden, um eine konstante und
gleichmäßige Mahlung unter den gegebenen Bedingungen an das hergestellte Produkt zu
gewährleisten.
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc
Contents Summary..................................................................................................................... I
Zusammenfassung ................................................................................................... II
1 Introduction........................................................................................................ 1
2 Vertical Mills....................................................................................................... 2
2.1 Overall description ..................................................................................................2 2.2 Grinding principle....................................................................................................4 2.3 Vertical mills in CE/CA............................................................................................6 2.4 Vertical mills vs. ball mills .......................................................................................8
3 Comparison of different vertical mill types ................................................... 10
3.1 Gebrüder Pfeiffer MPS mill ...................................................................................10 3.2 Loesche LM mill....................................................................................................11 3.3 Polysius mill ..........................................................................................................12 3.4 FLSmidth OK mill..................................................................................................14
4 Comparison...................................................................................................... 16
4.1 Active Grinding Area per time ...............................................................................16 4.2 Top view ...............................................................................................................18
5 Ideas of Optimization....................................................................................... 21
5.1 Polysius Mill RM 46/23 in Slite ..............................................................................21 5.2 Gebrüder Pfeiffer mill MPS 3750 C in Hannover...................................................26
6 Optimization charts ......................................................................................... 29
6.1 Optimization chart: Fineness.................................................................................29 6.2 Optimization chart: Temperature behind mill.........................................................33 6.3 Optimization chart: Vibration.................................................................................35 6.4 Optimization chart: Output ....................................................................................40 6.5 Optimization chart: Mill power...............................................................................42 6.6 Optimization chart: pressure drop .........................................................................44 6.7 Comments on the optimization charts ...................................................................45
7 Conclusion ....................................................................................................... 47
8 Bibliography..................................................................................................... 48
9 Annex................................................................................................................ 49
9.1 Cost calculation between vertical mill and ball mill ................................................49 9.2 Calculating the active grinding area per time ........................................................50 9.3 Pictures of Raw mill 8 in Slite................................................................................51 9.4 Pictures of Cement mill 11 in Hannover ................................................................53
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc
Figure index Figure 1: schematic drawing of a vertical mill .........................................................................3 Figure 2: schematic drawing of a vertical mill with material & gas flow ...................................4 Figure 3: grinding principle of a vertical mill............................................................................5 Figure 4: Picture, drawing and flow-sheet of a Gebrüder Pfeiffer vertical mill .......................11 Figure 5: design of the Loesche grinding rollers ...................................................................11 Figure 6: Picture, drawing and flow-sheet of a Loesche LM vertical mill ...............................12 Figure 7: design of the Polysius grinding roller .....................................................................13 Figure 8: Picture, drawing and flow-sheet of a Polysius vertical mill .....................................13 Figure 9: Design of the FLSmidth grinding roller...................................................................14 Figure 10: Picture, drawing and flow-sheet of an FLSmidth OK vertical mill .........................15 Figure 11: Top view on the grinding table of a Polysius vertical mill .....................................18 Figure 12: Top view on the grinding table of a Loesche vertical mill .....................................19 Figure 13: Material inlet of a Loesche mill ............................................................................19 Figure 14: Top view on the grinding table of a Pfeiffer vertical mill .......................................20 Figure 15: Material inlet of a Gebr. Pfeiffer mill in Hannover.................................................20 Figure 16: Different shapes of a dam ring.............................................................................24 Figure 17: schematic drawing of the gas flow outside of a vertical mill .................................34 Figure 18: changes in mill design for higher output ..............................................................51 Figure 19: mill internals ........................................................................................................51 Figure 20: critical wear spots................................................................................................51 Figure 21: constructive modifications of the mill ...................................................................52 Figure 22: Bad condition of the vertical mill ..........................................................................52 Figure 23: changes of the mill design for a smoother grinding process ................................53
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc
Table index Table 1: Overview of manufacturers of vertical mills in CE/CA ...............................................7 Table 2: general comparison between vertical roller mill and ball mill systems.......................9 Table 3: Calculating the active grinding area per time ..........................................................17 Table 4: basic information of vertical mill in Slite, Sweden....................................................21 Table 5: Blaine and Output for different cement types in Hannover 2009 .............................26 Table 6: side effects of changing parameters of grinding process of a vertical mill ...............46 Table 7: cost comparison between vertical mill and ball mill (Gorazdze) ..............................49
Diagram index Diagram 1: ground material structured into countries in CE/CA..............................................7 Diagram 2: Throughput as function of hydraulic pressure and dam ring height.....................23 Diagram 3: records of the ZM 11 from the control room in Hannover ...................................27 Diagram 4: Optimization Chart: Influence on the fineness....................................................32 Diagram 5: Optimization chart: Influence on the temperature...............................................35 Diagram 6: Vibrations of a VRM due to false grinding bed height (Hannover) ......................36 Diagram 7: Optimization chart: Influence on mill-vibration I ..................................................38 Diagram 8: Optimization chart: Influence on mill-vibration II .................................................39 Diagram 9: Optimization chart: Influence on mill-output........................................................41 Diagram 10: Optimization chart: Influence on mill power......................................................43 Diagram 11: Optimization chart: Influence on the pressure drop ..........................................45
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 1
1 Introduction
Vertical mills have gained an increasing percentage of the raw-meal-production in cement-
plants over the last decade. The mills are used more and more in new cement-plants due to
their cost-effectiveness and their good controllability. The possibility to handle the full hot gas
amount, produced by even the biggest kilns for usage as transport gas as well as drying-gas,
increased the output of vertical mills from 100 t/h to nowadays over 500 t/h in the last
decade. At the same time the mill-drive-power increased from approximately 800 kW to over
3.400 kW.
Vertical mills are gas-swept-mills. They are used for fine- and finest-grinding and
simultaneous drying of cement-clinker and raw-material. With the DIN 24 100, Teil 2
“Mechanische Zerkleinerung; Maschinenbegriffe” there exists a standardized description
“Roller Mill“. The definition describes as follows:
„Machine; in which the grinding table is formed circular. Grinding elements are rolling onto it.
The grinding elements are pressed onto the grinding table either by its self-weight, by
centrifugal force, by springs, by hydraulic- or pneumatic-systems. Both, the grinding table
and the grinding elements are able to be driven.”
By the, in the cement industry commonly used mill-designs, the geometric design of the
grinding elements range from cylindrical rollers to truncated cones, to balls and the
transmission of the pressure range from self-weight to centrifugal force and spring-pressure
to hydro-pneumatic-pressure-systems. [Brundiek 1989]
Objective of this final-trainee-thesis was to gather theoretical basic knowledge about vertical
mills. On the basis of two particular vertical mills ideas for optimizing vertical mills have been
worked out.
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 2
2 Vertical Mills
The industrial development of vertical mills started in the beginning of the 20th century in the
USA. Since then many different designs of vertical mills from many different manufacturers
emerged on the market. The theoretical basics as well as information of vertical mills used in
HeidelbergCement Group will be described in this chapter.
2.1 Overall description
At least two fixed grinding rollers (cylindrical or conical shape) are rolling on a horizontal
grinding table. The contact pressure is transferred by weight and hydro-pneumatically. The
grinding table is driven by a gearbox, which also takes up the roller-pressure. By installing an
additional cascade gearbox or a frequency controlled drive it is possible to adjust the
circumferential speed of the table. The material feed is usually carried out in the middle of the
grinding table. The grinding material is transported by centrifugal force to the rim of the
grinding table. On the way to the rim of the grinding table, the material is drawn underneath
the grinding rollers. By self weight of the grinding rollers as well as by additional grinding
force the material is ground (see Figure 3). After grinding and passing the rollers the material
is transported further to the rim of the grinding table. Along the rim of the grinding table a
dam ring is placed (see Figure 19). The height of the dam ring is an important adjustment. By
the height, as well as by the circumferential speed of the grinding table it is possible to adjust
the height of the grinding bed. The higher the dam ring and the lower the circumferential
speed, the higher the grinding bed and vice versa. Between grinding table and mill housing,
a fixed nozzle ring is placed. The ground material passes over the dam ring and falls on the
nozzle ring (Figure 19). Through this nozzle ring, hot gas, produced either by an additional
hot gas burner or coming from the kiln, enters the mill below the grinding table. From there it
passes guiding blades which guide and accelerate the gas. By the area of the nozzle ring,
the speed of the gas flow can be adjusted. Coarse material, which is falling onto the nozzle
ring but can’t be lifted up by the gas flow is falling through the nozzle ring and is transported
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 3
out of the mill. It is also possible to build a vertical mill as circuit mill, which means, that the
coarse particles are transported back into the mill. Material which passes the dam ring and is
fine enough is lifted up. The, from guiding blades guided and accelerated lifting (hot-) gas lifts
the dust in a kind of fluidized bed to the upper part of the mill. Due to an increasing diameter,
the velocity of the gas reduces above the grinding rollers. Coarse particles are falling back
onto the grinding table. The other, finer material is lifted further to the top of the mill. Here,
either a static or a stage-less adjustable dynamic separator separates the coarse material
from the fines. The fineness of the ground material can either be adjusted by the grinding
force of the grinding rollers, by the velocity of the gas flow or by the speed of the dynamic
separator. The higher the grinding force, the lower the speed of the gas flow and the higher
the speed of the separator, the finer the ground material and vice versa. The rejected
particles are falling back onto the grinding table for additional grinding. The fine particles are
passing the separator and are conveyed by the hot gas out of the mill into cyclones or filters.
So, generally speaking, a vertical mill can be divided roughly into three different unit
operations: drive, grinding and separation (see Figure 2).
Figure 1: schematic drawing of a vertical mill
Mill stand
Gear box
Rocker arm
Grinding roller
Separator
Mill outlet
Mill feed inlet
Grinding table
Hydraulic system
Separator drive
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 4
Figure 2: schematic drawing of a vertical mill with material & gas flow
2.2 Grinding principle
Grinding in vertical roller mills is carried out by rolling loaded grinding rollers on a grinding
table. Coarse material is broken by the rollers like in a roller crusher. The comminution of the
fine material happens by bruising of the loaded material among each other. After leaving the
grinding table, the partly opened material is exposed to a gas stream with a high velocity and
is torn apart. The ground material is lead to the separator, coarse material back to the
grinding table. Due to the small residence time in the area of grinding (compared to ball mills)
the material bed is freed from finished good, which strains the grinding process
unnecessarily and tends to build agglomerates. Next to a good tapering of the grinding
rollers, the built-up of a stable grinding bed as well as the, for the grinding sufficient, pressure
Drive
Grinding
Separation
Energy
Drying
Hot gas
Material
Waste gases &
Grinding product
Transport
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 5
of the grinding rollers is required for grinding in a vertical mill (see Figure 3). [Kohlhaas,
1982]
Figure 3: grinding principle of a vertical mill
As described above, the grinding process follows two different actions:
Feeding of the grinding material between grinding roller and table
The coarser material, which acts as support-grain in the material bed is ground after the
grinding force exceeds the material-specific compressive strength. The comminution of these
parts is supported by the fact, that between the material and the grinding rollers usually point
contact occurs and so the peak stress is many times higher than the compressive strength.
After the breaking of the coarse material, the partly impulsive acting compressive force is
grinding further material. This event continues to the narrowest point between grinding roller
and grinding table. The continuous reduction of the grinding slot up to the zenith of the
grinding rollers causes a proportional increase of the specific grinding pressure. Thus the, by
comminution increased amount of support-grains, are facing increased specific grinding
forces for further grinding.
Compression of the grinding bed
The compression of the grinding bed by simultaneous reduction of the size of the support
grains causes an intensive spatial rearrangement of the different compressed particles. The
so occurring compressive- and shearing forces lead to a further comminution. Grinding by
shear-force is the main reason for finest comminution in vertical roller mills. The shear-force
is supported by the relative movement of the grinding rollers and the grinding table. This
FGrinding Grinding rollers
Grinding table
Side-view: Top-view:
Dam ring
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 6
relative movement can also prevent the material to stick onto the grinding table, if the
moisture of the material is too high. [Kohlhaas 1982]
Influences on the grinding process
To enable a smooth and constant grinding process with a high productivity and good quality
it is mandatory to have a constant and good material bed. To gain a good grinding
performance, even with difficult material, regarding the grind-ability, there are several ways to
take an influence on the grinding process.
It is possible to adjust the height of the grinding bed by changing the shape and the height of
the dam ring. The height of the dam ring depends on the flow characteristics of the material
to be ground. Does the material tend to stick, a lower height would be better for the material
flow characteristics on the grinding table. Is the material very fluent, a high dam ring and
sharp corners of the dam ring would be beneficial.
Is the material too fine or too dry, it is possible to insert water into the mill to stabilize the
grinding bed. It has been shown, that for grinding cement on a vertical mill it is necessary to
use grinding aids to achieve the most efficient operation with a stable grinding bed and a low
level of vibrations. As experiences show, water has an effect similar to that of a grinding aid.
[Jorgensen, 2005]
If the material is too soft, it can be advantageous to add coarse, extreme hard material. By
rolling over the grinding material, this coarse material leads to a higher resistance and so the
grinding rollers are lifted slightly up. Due to the hydro pneumatically pre-stressing of the
grinding rollers the rollers are falling back onto the grinding bed and so are leading to a
higher grinding force.
2.3 Vertical mills in CE/CA
In the area central Europe/Central Asia (CE/CA), 26 vertical mills are in use for grinding
different material like raw-material, slag, cement and coal. At the same time approximately
151 ball mills are used in the same area. Table 1 shows an overview of the vertical mills
used in CE/CA in the HeidelbergCement Group.
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 7
amount fraction [%]
Gebr. Pfeiffer 15 58
Loesche 6 23
Polysius 2 8
others 3 11
Sum 26 100
Table 1: Overview of manufacturers of vertical mills in CE/CA
As it can be seen, with a fraction of nearly 60 %, mainly mills from the manufacturer
Gebrüder Pfeiffer in Kaiserslautern, Germany are in use. Loesche and Polysius are the two
other important manufacturers for vertical mills in CE/CA. In this table, not all manufacturers
of vertical mills used in the whole group are listed. Raymond mills for example are commonly
used in NAM-area. FLSmidth (cement mill in Union Bridge e.g.) and Claudius Peters (coal
mill in Kakanj e.g.) are two other common vertical-mill manufacturers. There are also vertical
mills from Chinese manufacturers in use (coal mills in Georgia).
0123456789
10
Bosnia-H
erzegovin
a
Czech Republic
Georgia
Germany
Hungaria
Poland
Romania
Ukraine
Am
ount
of V
RM
[-]
CoalRawmaterialCementSlag
Diagram 1: ground material structured into countries in CE/CA As it can be seen in Diagram 1 vertical mills are used in Germany mainly for Raw-material
grinding. In the eastern countries (as well as in plants in NAM-area, not listed here) vertical
mills are commonly used for coal-grinding.
The only vertical mill for cement-grinding in CE/CA is situated in Hannover.
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 8
2.4 Vertical mills vs. ball mills
Over the last decades, the vertical roller mill has become the preferred mill for grinding of raw
materials. The grinding efficiency of the vertical roller mill combined with an ability to dry,
grind and classify within a single unit gives the vertical roller mill a decided advantage over
ball mill systems. However, despite these benefits, applications of the vertical roller mill for
cement grinding are less prevalent. The two-compartment ball mill, which operate in a closed
circuit with a high efficiency separator, is thus still the most preferred arrangement for new
cement grinding installations although the vertical roller mill now has emerged as a viable
alternative to the ball mill system and has increased its share of the market for cement mills
over the last decade. There are a number of explanations to this situation which relate to
issues like cost of installation, cost and ease of operation, cost and ease of maintenance,
product quality range, versatility, etc [Jorgensen, 2005].
Comparing vertical mills with ball mills rough overall-assumptions can be made (see Table
2). These assumptions are a general overview but, as the following example shows (see
Annex Table 7) it is necessary to investigate exactly for each installation of a new mill
whether a vertical mill or a ball mill suits best.
The investment cost of the two alternative grinding systems depend on a number of factors
such as the application, whether a separate drying facility is required for the ball mill, system
capacity, requirements with respect to country of origin of the equipment and a number of
other factors. The costs for civil works and erecting show also large regional variations.
Furthermore, the specific details of building requirements vary from plant to plant.
Predominant climatic and weather conditions will have a significant impact on the final
building design, and a ball mill and vertical roller mill installations have significantly different
foundations and layout requirements. Nevertheless, it can be said, that the total costs of
installation is in most cases higher for a vertical roller mill system than for a ball mill system.
The most significant advantage of a vertical roller mill compared to a ball mill system is
related to the specific consumption of electrical energy of the two systems. As examples
have shown [Jorgensen, 2005] the specific energy consumption can be up to 40 % lower for
a vertical mill system than for a ball mill system. The same assumptions can be made for the
operating costs.
As an example shows (see Table 7), the maintenance costs for a vertical mill are much
higher than for a ball mill. Work for remedying progressive wear of the grinding parts of a
vertical mill may involve reversal of roller segments, hard-facing of roller and table segments
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 9
and/or eventually replacement of worn out parts. This work is more complicated than just
adding more balls into a ball mill. The wear rate measured in grams per ton is much higher
for a ball mill than for a vertical roller mill. However, the unit costs for wear parts for a ball mill
are much lower than for a vertical roller mill.
The drying capacity of a vertical mill is much higher than for a ball mill system. Based on
manufacturer’s data, vertical mills can dry and grind material with a moisture-content of up to
20 w.-%. Ball mills can grind and dry feed material with a moisture-content of only 2 w.-%.
Another advantage of the vertical roller mill system is, that grinding, drying and separation of
the material takes place in only one unit (see Figure 1). On the one hand, no additional
installation of a dryer is necessary, leading to a significant reduction of the investment costs.
On the other hand, the size of this grinding unit is much more compact than the size for a ball
mill system, leading to a lower required space for installation.
Vertical mill Ball mill
Investment-costs û ü operating-costs ü û Wear û ü Spec. Energy consumption ü û Drying-capacity ü û Size ü û Table 2: general comparison between vertical roller mill and ball mill systems
It appears that quite a number of factors should be taken into consideration when making a
comparative evaluation of a vertical roller mill system and a ball mill system for grinding,
although the cost of electrical energy and total installation costs may be the most significant.
The significance of those factors may vary substantially depending on the location of the
installation, so it is not possible to make a ranking order for the two grinding systems that is
globally applicable. Such an evaluation must be made for the specific project while taking
into consideration the fact that the effects of the various factors depend on local conditions
and specific demands.
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 10
3 Comparison of different vertical mill types
As it can be seen in Table 1 there are three main suppliers for vertical mills in the area
CE/CA, Gebrüder Pfeiffer, Loesche and Polysius. In this chapter, the vertical mills of these
suppliers as well as the vertical mill from FLSmidth will be described in detail. Due to the
multitude of different manufacturers and mill types it is not possible to cover all vertical mills.
This is an assumption to classify and introduce the nowadays commonly used mill designs,
whereas this should not be considered as a valuation.
3.1 Gebrüder Pfeiffer MPS mill
Basically, the design of this mill is the same as described in chapter 2.1: yet the three bent
grinding rollers are in a convex shape and are rolling in an accordantly designed grinding
table. According to this design, the material inlet happens from the side onto the grinding
table. The, for grinding the material, required grinding pressure is generated by the self-
weight of the grinding rollers as well as by a hydro-pneumatically pre-stressed spring-system
which is arranged inside of the mill body.
After leaving the grinding table, the ground material passes onto the fixed nozzle-ring and is
loosened and pre-separated by the guided and accelerated lifting gas. By adjusting the
inclination of the nozzles, the ground material is driven in the same direction as the rotational
direction of the grinding rollers. Coarse particles are falling, as well as the by the stage-less
adjustable separator rejected particles, back onto the grinding table for additional grinding.
The fine particles are passing the separator and are conveyed by the hot gas out of the mill
into cyclones or filters (see Figure 4).
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 11
Figure 4: Picture, drawing and flow-sheet of a Gebrüder Pfeiffer vertical mill
3.2 Loesche LM mill
The feed material is discharged into the mill via an airlock and a downpipe to the centre of
the rotating grinding table. The material to be ground moves on the grinding track towards
the edge of the grinding table under the effect of centrifugal force and in this way passes
under the hydro pneumatically spring-loaded grinding Master rollers (M-rollers). These
comminute the material while the smaller S-rollers, which each operate between the M-
rollers, support preparation of the grinding bed by de-aeration, crabbing and pre-compaction
(see Figure 5). The rollers are forced upwards as they roll on the material bed.
Figure 5: design of the Loesche grinding rollers
At the same time the functional unit, consisting of M-roller, rocker-arm, spring rod and the
piston of the hydraulic cylinder are deflected. Rotation of the grinding table causes the
ground material from the M-rollers to be thrown outwards over the edge of the table. In the
area of the louver dam ring, which surrounds the grinding table the upwards directed hot gas
Grinding table
S-Roller M-Roller
Packing Grinding Expansion
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 12
stream captures the mixture of ground material and material still to be ground and conveys
this to the classifier.
Depending on the classifier settings coarse material is rejected. This falls into the internal grit
return cone and from there is returned to the grinding table for re-grinding under the rollers.
Final product material passes the classifier and is conveyed from the mill with the gas
stream. The mill is driven by an electric motor via a vertical gearbox. A segmented thrust
bearing in the top of the gearbox absorbs the roller forces. Before starting the grinding
process the M-rollers are lifted hydraulically from the grinding track. The support rollers are
also lifted when starting the mill [Loesche].
Figure 6: Picture, drawing and flow-sheet of a Loesche LM vertical mill
3.3 Polysius mill
The essential components of a Polysius Roller mill are the motor, the gear unit (for instance
a planetary bevel unit), the grinding table carried in tilting pad thrust bearings, the two roller
pairs, the housing and the static separator equipped with adjustable guide vanes. A dynamic
separator incorporating a deflector rotor can be used instead of the static separator.
The grinding principle and the basic description of the Polysius mill is the same as described
in chapter 2.1 and 2.2.
The design of the grinding rollers as well as the grinding table in a Polysius mill is special.
The grinding rollers of a Polysius mill are performed as twin rollers. If the inner roller is lifted
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 13
up by the material flow and thus the outer roller is pressing all the more onto the material bed
(see Figure 7). This design should lead to a constant output and energy consumption.
Figure 7: design of the Polysius grinding roller
The shape of the grinding table follows the shape of the grinding rollers. Thus the double
groove grinding track increases the retention time of the material on the grinding table. This
is a particular advantage in the case of material with unfavorable grinding properties and a
tendency not to form a stable bed. The double groove grinding track also ensures that the
bed of material is not too deep and minimizes the amount of material passing ungrounded
between the rollers and the grinding table. The basic idea behind this design is to reduce the
specific power requirement [Polysius].
Figure 8: Picture, drawing and flow-sheet of a Polysius vertical mill
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 14
3.4 FLSmidth OK mill
Basically, the design of this mill is the same as the ones described before.
The specialness of the FLSmidth mill is the roller and grinding table designs. As shown in
Figure 9, the rollers of the OK mill are spherical in shape with a groove in the middle. The
table is also curved forming a wedge-shaped compression and grinding zone between the
rollers and the table. This dual-lobed design is optimum for clinker grinding because it
supplies two distinct grinding zones – a low pressure zone and a high pressure zone. The
low-pressure area under the inner lobe de-aerates and consolidates the material to be
ground.
Figure 9: Design of the FLSmidth grinding roller
The proper grinding takes place in the high-pressure zone under the outer lobe. The groove
in the middle of the roller facilitates de-aeration of the material without fluidizing it. In order to
further ensure a stable operation with low vibrations the OK mill is provided with a high
efficiency separator. This results in a reduced internal circulation of fine material and a
correspondingly higher feed rate. The material on the grinding track will thus become coarser
and therefore less prone to fluidization [FLSmidth]
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 15
Figure 10: Picture, drawing and flow-sheet of an FLSmidth OK vertical mill
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 16
4 Comparison
The comparison of the different types of vertical mills can’t be done at first sight. There is not
such a thing like easily accessible operating figures or mill specific dimensions like table
diameter or number of grinding rollers, with which it is possible to make a direct comparison.
So a new calculated, specific figure has to be found with which it is possible to compare all
different vertical mill types.
Due to different designs of the mill interior by the different manufacturers it is also adjuvant to
take a look from the top onto the grinding table to compare the advantages or disadvantages
of the design and arrangement of the rollers, the table and other internals like ploughs or
material inlet chute for example for each mill.
4.1 Active Grinding Area per time
It is not possible to compare different types of vertical mill by figures like installed motor
power, table diameter or roller diameter for example. The interior of vertical mills is so
different and the application of force is conducted in such different ways, that a direct
comparison will not be able to reflect the grinding process in total. For finding a characteristic
figure, with which you can compare vertical mills from different manufacturers it is necessary
to look more into detail. The active grinding area per time for example is a calculated,
specific, characteristic figure with which it is possible to compare different types of vertical
mills. For the installation of a new vertical-slag-mill in Mokra, Czech Republic, such a detailed
consideration has been conducted. The constraints for this mill were a production of 80 t/h at
a fineness of 4.000 Blaine with a grindability of the material of 35 kWh/t. The figures,
gathered from the different manufacturers, as well as the calculated figures are listed in
Table 3. Four different mills from four different manufacturers have been contemplated: a
MPS 4250 B(C) from Gebr. Pfeiffer, a LM 46.2+2 from Loesche, a 38/19 from Polysius and
an OK 30 from FLSmidth.
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 17
Vendor
Pfeiffer Loesche Polysius FLS
Mill-type MPS4250 B(C) LM 46.2+2S 38/19 OK 30
Grinding Table
Diameter [m] 4,250 4,600 3,800 4,000
Dia. center line of the track [m] 3,400 3,884 3,170 3,000
Active grinding area [m2] 5,661 8,175 5,278 5,212
Number of revolutions [Rpm] 22,5 24,3 23,5 26,3
Circumferential speed [m/s] 5,01 5,85 4,68 5,50
Circumferential speed out [m/s] 4,01 4,94 3,90 4,13
grinding Area per time of table
[m2/h]
7643
(64,1 %)
11920
(100 %)
7442
(62,4 %)
8215
(68,9 %)
Rollers
Diameter [m] 2,300 2,360 1,900 1,770
With [m] 0,530 0,670 0,530 0,553
Number of Rollers [-] 3 2 4 4
Active grinding area [m²] 11,489 9,935 12,654 12,300
Number of revolutions out [Rpm] 33,26 39,99 39,21 44,53
Grinding Area per time of
rollers [m2/h] 22928 23839 14884 16430
Total active grinding area per
time
[m2/h]
30570
(85,5 %)
35759
(100 %)
22327
(62,4 %)
24645
(68,9 %)
Table 3: Calculating the active grinding area per time
The formulas for calculating the grinding area per time can be found in the Annex chapter
9.2.
The active grinding area per time relating to the grinding table gives information about the
area of the grinding table per unit of time which is rolled over by the grinding rollers. The
higher the active grinding area per time, the better, because more grinding-table-area and so
linked more material is rolled over per time unit. It is not possible to use the active grinding
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 18
area per time calculated by the geometric figures from the rollers because there can be
slippage between the rollers and the table. So, a more reliable figure needs to be considered.
The total active grinding area per time can also not been taken into account, because it is
calculated by the active grinding area per time from the grinding-table and the grinding
rollers. Thus the active grinding are per time from the grinding-table remains as
characteristic, specific figure for comparison.
4.2 Top view
Another possibility to compare the different mill-types can be done by a top view onto the
grinding table. The different arrangements of the grinding rollers or additional internals can
have an impact on the grinding process.
Top view on a Polysius mill
In Figure 11 the internal alignment of the mill internals of a Polysius mill can be seen. The
two twin rollers running parallel, the double grooved grinding track, the two material plows
leading the material back onto the grinding table and the material inlet from the side of the
mill housing are the most important internals of a Polysius mill. As it can be seen in Figure 11
the material inlet of a Polysius mill is usually carried out from the side via a chute (see Figure
18). The material is falling onto the centre of the grinding table between the two roller pairs. If
the material is too dry or it has bad inner material support characteristics, it can fall off the
table on the opposite side of the material inlet. It is possible to avoid this by installing material
plows for retention.
Figure 11: Top view on the grinding table of a Polysius vertical mill
Material inlet
Grinding Table twin rollers
plow
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 19
Top view on a Loesche Mill
In Figure 12 a Loesche mill Type 3+3 can bee seen meaning it is a mill with 3 Main- (M)
Rollers and 3 Support- (S) Rollers. Between two M-Rollers there is an S-Roller for preparing
a smooth and constant grinding bed. In a Loesche-mill the material inlet is usually conducted
from the top onto the centre of the grinding table. This is carried out via a chute that is
welded onto the separator-grit-cone (see Figure 13). So the material is entering onto the
centre of the grinding table and from there is transported by centrifugal force under each
roller by the same amount. Compared to the Polysius mill, no additional mill-inlets such as
material-retention-plows are needed.
Figure 12: Top view on the grinding table of a Loesche vertical mill
Figure 13: Material inlet of a Loesche mill
Top view on a Gebrüder Pfeiffer mill
In Figure 14 the internal alignment of the mill internals of a Gebrüder Pfeiffer mill can be
seen: the three statically defined grinding rollers, the hydraulic pressure frame, the grinding
table and the guidance for the pressure frame. The material inlet can’t be seen here, but as
mills in Leimen or in Hannover show, the material inlet is conducted in front of one of the
Separator grits
Material inlet S-Roller
M-Roller
Material inlet
S-Roller
M-Roller
Grinding table
Nozzle ring
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 20
grinding rollers (see Figure 15). By doing so, it might be possible that not every grinding roller
gets the same amount of material. If the material is ground fine enough by the first roller, the
second and third roller gets less material. This can lead to an uneven grinding process. In
some cases it is also necessary to install stripper plates to create an even and smooth
grinding bed.
Figure 14: Top view on the grinding table of a Pfeiffer vertical mill
Figure 15: Material inlet of a Gebr. Pfeiffer mill in Hannover
Material inlet
Pressure frame
Grinding roller
Grinding table
Material inlet
Grinding roller
Grinding table Nozzle ring
Guidanc
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 21
5 Ideas of Optimization
There are many different points to consider according to the optimization of vertical mills. The
right dam-ring-height, the proportion of the separator-speed to fan-speed, the amount of
water injected into the mill or the hydraulic pressure of the grinding rollers are just a few
parameters with which it is possible to control the running of a vertical mill. Based on two
examples, the Polysius RM 46/23 in Slite and the MPS 3705 C in Hannover different
possibilities of optimizing a vertical mill will be discussed in the next chapter.
5.1 Polysius Mill RM 46/23 in Slite
The Raw mill 8 in Slite, Sweden was erected in 1978. Since then there have many different
modifications been done to optimize the running of the mill regarding the output, fineness,
wear and energy consumption. Pictures of the modifications can be found in Chapter 9.3,
page 51 ff. Some basic data of the mill and nowadays production are listed in Table 4.
Manufacturer/Type Polysius RM 46/23
Mill power 2.400 kW
Throughput 395 t/h
Table-/Roller-diameter 4.600 / 2.300 mm
Roller widths 650 mm
Circumferential speed table 25 Rpm
Spec. grinding energy consumption 20 kWh/t
Δp mill 100 mbar
Gas volume-flow 1.060.506 m³/h
Hydraulic pressure of rollers 140 bar
Table 4: basic information of vertical mill in Slite, Sweden
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 22
Optimization of output
The first step to optimize the output of the vertical mill was to install two material-ploughs
between the two twin rollers. These internals prevent material to fall directly off the grinding-
table without any grinding by entering the mill too quick. Additionally these ploughs create a
grinding bed of constant height, so that the grinding procedure can go on smoothly (see
Figure 18).
The attempt to increase the output by increasing the table speed didn’t bring much effort.
The table-speed was too high, so the material left the table too quick without any grinding.
This change was undone.
The vertical mill was originally built with a static separator. Thus the second step for
optimizing the output of the mill was to change the static separator to a dynamic separator
with guiding blades and a rotary cage. This was carried out in November 1999. So it was
possible to increase the output of the mill by keeping the same values for the fineness of the
raw-material.
With the new separator it was also possible to install a bigger motor for the fan to increase
the gas-volume-flow. By increasing the volume flow, more material can be put into the mill.
The material, being lifted by the faster gas-stream is coarser than it would be with a slower
gas-flow. But with the new dynamic separator this effect can be reversed and the same
fineness can be kept even with the higher gas-velocity.
Another big issue until nowadays is to find the optimal height of the dam ring. The raw
material from the quarry in Slite reacts very sensitive on changes of the dam ring height as
well as on the shape of the dam ring. Diagram 2 gives an overview of the correlation
between the different dam ring heights and the throughput as a function of different hydraulic
pressure.
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 23
340
350
360
370
380
390
400
410
115 120 125 130 135 140 145
hydr. pressure [bar]
Trou
ghpu
t [t/h
]
30 mm40 mm50 mm70 mm
Diagram 2: Throughput as function of hydraulic pressure and dam ring height
Diagram 2 shows that the highest output for the raw mill is with a dam ring of 30 mm height.
It can also be seen that for reaching the same throughput of 400 t/h the hydraulic pressure
increases by 10 bars from using a dam ring with a height of 30 to 40 mm. By changing the
dam ring height of a vertical mill, not only the throughput is changed. If the dam ring is too
low, vibrations, because of a too low grinding bed height can occur and lead to a safety-
shutdown of a mill. On the other hand it is possible to adjust the internal circulation of the
material leading to a change of the particle size distribution especially regarding the
inclination of a particle size distribution curve. So, it is always necessary to consider, which
changes will happen by adjusting the dam ring height.
Yet not only the height of the dam ring, but also its shape plays an important role. The
vertical mill in Slite for example is only running smoothly, when the dam ring has a defined
and sharp corner. The vertical mill in Hannover instead has an continuous increasing dam
ring height, working like an extension of the grinding table (see Figure 16).
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 24
Figure 16: Different shapes of a dam ring
Left: shape of the dam ring of the Polysius vertical mill RM 46/23 in Slite Right: shape of the dam ring of the Gebr. Pfeiffer vertical mill MPS 3750 C in Hannover
The shape and the height of the dam ring depend on the flow characteristics of the material
to be ground. Does the material tend to stick, a lower height would be better for the material
flow characteristics on the grinding table. Is the material very fluent, a high dam ring and
sharp corners of the dam ring would be beneficial.
Optimization of fineness
Over the years, there have been many modifications carried out to improve the fineness of
the products, being ground on the vertical mill. One big alteration was the change from a
static to a dynamic separator. With this modification it was possible to increase the output
while keeping the same fineness.
A second step was to overhaul the rotary cage in need of repair. After years of production,
the single blades of the rotary cage have been bent and/or twisted by deformation due to the
torsion moment of the motor and the mass inertia of the rotary cage (see Figure 21). Thus
the old and apparently too small rotary blades have been replaced by new and bigger ones.
So, the dimensions of the old blades changed from 8 mm thickness and 90 mm width to
10 mm thickness and 140 mm width. Additionally a support ring was installed in the central
height of the blades for additional stiffness. With this measure it was on the on hand possible
to reinforce and stiffen the rotary cage without endangering the motor or the bearing to take
damage. On the other hand it was possible to insert more energy into the separation process
which leads to a better performance of the separator.
A third measure to improve the fineness was to reduce the possibility of the ground and lifted
material to bypass the separator, causing coarse particles to leave the mill without
separation. These bypasses are enabled on the one hand by too big rotor sealing gaps (see
Figure 22). The left picture is a top view onto the rotary cage. The sealing gap should be kept
as narrow as possible. If this gap is too wide, as it was in Slite, too coarse material bypasses
the separator at the top, getting into the finished product without getting separated. Solving
Grinding table
Dam ring
Grinding table
Dam ring
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 25
this issue is possible by closing this gap either by adjusting the gap or by installing a labyrinth
seal, preventing the coarse material to bypass the separator.
On the other hand, wear spots, especially at the bottom of the separator, caused by the
abrasive, dust loaded hot-gas enable a bypass for coarse material, getting into the finished
product without separation. Solving this issue is possible by removing the wear spots (see
following paragraph).
Optimization of wear condition
The newly installed dynamic separator was built with a distribution plate (see Figure 18). The
coarse material, falling through the nozzle ring was transported via bucket elevator to the top
of the mill and was fed onto the distribution plate. From here, the material was blown by the
hot gas, coming from the bottom of the mill, against the mill housing causing a high wear
rate.
Thus the mill was modified in a way that the coarse material was not longer fed onto the
distribution plate. A new material chute for the coarse material was installed, right above the
material chute for the raw material inlet (see Figure 21). So the coarse material could get
directly onto the grinding table and the wear of the mill housing was reduced by this means.
A second reason for the high wear condition is the too small diameter of the riser duct of the
vertical mill (see Figure 20). By a small diameter of the duct, the velocity of the highly dust
loaded gas is too high and thus the dust particles in the gas-stream are highly abrasive. A
bigger diameter of the duct could solve this problem.
A third way to get rid of such a high wear rate was to cover critical wear-spots inside of the
mill (see Figure 20). Especially in the area of the newly installed dynamic separator there are
critical wear spots. These locations at the separator are especially critical, because they
cause shortcuts for the coarse material, being able to exit the mill without separation and so
creating a bad quality of the finished product. After removing the distribution plate of the new
dynamic separator, for reducing the wear of the mill housing, some sharp corners as well as
some dead spots occurred (see Figure 18 left picture). These spots are very susceptible to
wear, because the flow direction of the highly dust loaded gas-flow is disrupted and thus the
dust particles are working extremely abrasive. So by covering these sharp corners and dead
spots by a casing the wear condition improved.
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 26
Optimization of false air situation
Depending on the area where false air occurs there are different effects on the grinding
process. In Slite one big reason for a high false air amount was that the sealing of the
alignments of the separator guiding plates haven’t been at place (see Figure 22). So air from
outside of the mill was sucked inside. By that the pressure drop inside of the mill falls down
and the mill fan needs to work more, leading to an increasing consumption of electrical
energy. Additionally the amount of gas through the mill and thus the velocity of the gas flow
are reduced causing a reduction of the output. These problems were solved just by placing
the sealing in the right position and fix them by welding to prevent further misalignment.
Other spots where false air could enter the mill were at the mill housing and the riser duct.
These areas were generated by wear. With the normal wear repairs this false air spots have
been removed (see Figure 20).
5.2 Gebrüder Pfeiffer mill MPS 3750 C in Hannover
The vertical mill in Hannover produces slag cements. An overview of the Blaine- values and
the output of the different cement types are listed in Table 5.
Cement Type Blaine [cm²/g] Output [t/h]
CEM II B/S 32,5 R 3674,8 70
CEM III A 32,5 N – LH/NA 4741,5 42,1
CEM III A 42,5 N – NA 4701,2 40,4
CEM III B 32,5 N – LH/HS/NA 4950,5 42,4
MC 5 6030,3 48,6
Table 5: Blaine and Output for different cement types in Hannover 2009
As it can be seen in Table 5, the fineness of nearly all cement types exceeds a fineness of
4000 Blaine by far. Usually a fineness of 4.000 Blaine is the maximum for a vertical mill to
grind without problems. For reaching this high fineness, the vertical mill has to be run in
harsh conditions. To increase the specific grinding force the input of the mill is set to a
minimum of sometimes lower than 36 t/h. At the same time the hydraulic pressure of the
grinding rollers is increased to a maximum of approximately 230 bar.
With the combination of a low material input and high hydraulic pressure of the grinding
rollers it is possible, that the grinding rollers penetrate the material bed and are rolling upon
the grinding table. This metal contact leads to high vibrations as seen in Diagram 3.
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 27
Diagram 3: records of the ZM 11 from the control room in Hannover
As it can be seen in Diagram 3, the whole grinding process reacts very sensitive on changes
of the grinding bed height. If the material bed is decreasing, the vibrations are increasing.
With the alternating vibrations, the mill power, the pressure drop of the mill and the hydraulic
pressure of the rollers are fluctuating. The vibrations are measured at three places of the mill:
the gear box, the separator and the mill fan. If the vibration of the gear box reaches a
maximum value (10 mm/s in Hannover) the safety circuit of the mill shuts the mill down to
protect it against major damage.
For enabling a smooth and constant running of the mill, different modifications inside of the
mill have been carried out (see Annex chapter 9.4).
As it can be seen in Figure 23 a material deflector plate for generating a smooth and even
grinding bed has been welded directly after the material inlet chute. This plate creates an
optimal material bed for the first grinding roller.
The second modification was the installation of two water injection nozzles after the first and
the second grinding roller. If the material is ground too fine by the first roller, the second roller
can cause vibrations. This is due to a penetration of the material bed by the rollers because
the inner support strength of the grinding bed is too low. Injecting water into this fine material
should increase the stability of the grinding bed and thus ease the grinding of the second
roller.
Grinding bed
height [mm]
Mill vibration [mm/s]
Material
input [t/h]
Mill power [kW]
Gasflow [m³/h]
Hydr. Pressure
of rollers [bar]
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 28
A third modification was to install a material trap at the inner wall of the mill. These traps are
installed behind the first and the second roller. They are designed to collect material out of
the gas flow and guide it back onto the grinding table in front of the next roller. By doing so,
more material is drawn under the grinding rollers increasing the grinding bed height and thus
stabilizing the grinding process referring the vibration.
As the current situation of the grinding process of the vertical mill in Hannover shows, all
these modifications did not solve the vibration-problems. This is due to the production of
cements with high fineness of far more than 4.000 Blaine.
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 29
6 Optimization charts
For optimizing a vertical mill it is important to know all the different parameters having an
influence on the grinding process. By displaying the grinding process as detailed as possible
it is possible to find optimization potentials for grinding on a vertical mill. The so called
optimization charts have gathered these important parameters and linked their interferences.
With these optimization charts it is possible to find the right measures to enable a smooth
operation under the given requirements on the product. These optimization charts have been
generated for the parameters: fineness, temperature, vibrations, output, mill power and
pressure drop. They are described in the following chapter.
6.1 Optimization chart: Fineness
For describing the parameter fineness there are three possible conditions:
Fineness is in range
If the fineness of a product is within the defined range, there are no problems and thus there
is no need of changing any parameter of the running grinding process.
Fineness is too high
If the fineness of the produced material is too high, this means, that the material is too fine,
the speed of the rotary cage of the dynamic separator needs to be checked. If the separator-
speed is too high, the reduction of the speed should decrease the fineness.
Is the separator-speed reduced to it’s minimum or there is only a static separator installed,
increasing the volume flow and thus the air velocity could also decrease the fineness of the
product. By increasing the gas-velocity, the gas-stream can lift up larger particles and the
diameter of particles being able to pass the separator will also increase.
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 30
If the fineness is still too high, one possibility to adjust the fineness is to reduce the hydraulic
pressure of the grinding rollers. By doing so, the specific grinding-energy is reduced and thus
the particle size is increasing.
In some cases vertical mills are equipped with a cascade gearbox. With this gearbox it is
possible to change the speed of the grinding table. If the fineness is still too high, increasing
the speed of the grinding table can lead to coarser particles. By doing so, the circumferential
speed of the table is increased and thus the centrifugal force on the material.
By increasing the speed of the grinding table, the residence time of the material in the area of
the grinding rollers is reduced. In addition, the grinding time, the period in which the material
is strained is also reduced. That leads to an insufficient utilization of the grinding forces and
thus to larger particles.
Is the fineness still too high, false air after the mill can cause this problem. Are there too
many wear spots or gaps between the outlet of the vertical mill and the mill fan, the volume
flow inside of the mill is too low. With a too low volume flow, the size of the particles being
lifted up for separation is decreasing leading to a too high fineness of the product. Solving
the false air situation should solve this problem.
Fineness is too coarse
If the fineness of the produced material is too low, this means, that the material is too coarse,
the speed of the rotary cage of the dynamic separator needs to be checked. If the separator-
speed is too low, the increase of the speed should increase the fineness.
Is the fineness still too low and the separator-speed can’t be increased anymore or there is
only a static separator installed, decreasing the volume flow and thus the air velocity could
also increase the fineness of the product. By decreasing the gas-velocity, the gas-stream can
lift up only smaller particles.
If the fineness is still too low, increasing the hydraulic pressure of the grinding rollers could
increase the fineness. By doing so, the specific grinding-energy is increased and thus the
particle size is decreasing.
The wear condition of the separator can also lead to bad results of the fineness. By a too
high wear condition, bypasses may occur, causing coarse particles to get into the finished
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 31
product without separation. Repairing the separator wear should lead to a higher fineness
(see also chapter 5.1).
Some mills have a cascade gear box installed. With this gearbox it is possible to adjust the
fineness by decreasing the speed of the grinding table. By doing so, the circumferential
speed of the particle is decreased and thus the centrifugal force on the material. (explanation
see above).
If none of these measures have gained an increased fineness oft the finished product, the
last possibility to adjust the fineness is to reduce the input. By doing so, the specific grinding
force is increased and thus the compressive strength on a particle is increased, leading to a
higher comminution of the material.
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 32
Diagram 4: Optimization Chart: Influence on the fineness
Fineness
OK?
Reduce
Separator speed
Increase
Separator speed
Too fine Too coarse
Increase
Volume flow
Reduce
Volume flow
Separator
Wear?
Increase
Hyd. pressure
Reduce
Table speed
Reduce input
Increase
Table speed
Yes
Repair
No
Reduce
Hyd. pressure
False air
After mill
Repair Yes
Side-effects:
-pressure drop
-output
-vibration
-pressure drop
-vibration
-output
-mill-power
-mill power
-output
-fineness
-pressure drop
Side-effects:
-pressure drop
-output
-vibration
-pressure drop
-vibration
-output
-mill power
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 33
6.2 Optimization chart: Temperature behind mill
For describing the parameter temperature behind the mill there are three possible conditions:
Temperature behind mill is in range
If the Temperature behind the mill is within the defined range, there are no problems and
thus there is no need of changing any parameter of the running grinding process.
Temperature behind mill is too low
If the temperature behind the mill is too low, there are little possibilities to increase it.
First of all it needs to be checked, if the hot gas amount is enough for reaching the defined
temperature. If there is sufficient hot gas, increasing the volume flow of the hot gas will also
increase the temperature behind the mill.
Is the amount of hot gas insufficient, reducing the amount of water injected into the mill can
cause an increasing temperature.
If none of the parameters described above lead to an increase of the temperature behind the
mill, the last possibility to increase the temperature is by reducing the feeding of the mill.
Especially during winter times, when the material, fed into the mill is wet, a reduction of the
feed will increase the temperature behind the mill.
Temperature behind mill is too high
If the temperature after the mill is too high, reducing the amount of hot gas is one option to
reduce the temperature. Yet, the grinding process in the vertical mill reacts very sensitive on
changing the amount hot gas. Thus the margin of changing the hot gas amount is very
narrow.
Is the temperature after reducing the hot gas amount still too high or there is no possibility to
reduce the hot gas, increasing the circulating gas is another step in reducing the temperature
behind the mill. The amount of circulating gas can usually be adjusted by the opening or
closing of a flap. Is the temperature after the mill too high, the flap is opened more and so the
hot gas, coming from the kiln, is mixed with colder gas coming out of the mill. The amount of
hot gas entering the mill is not only mixed with the colder circulating gas, but is reduced and
thus leading to a decreasing temperature (see Figure 17). So the total volume entering the
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 34
mill is the same and no further changes of the grinding process are done, except lowering
the mill temperature.
Figure 17: schematic drawing of the gas flow outside of a vertical mill
If the temperature after the mill is still too high, the last possibility to reduce it is by inserting
more water into the mill. But the material bed, which is an important parameter of the
grinding process, reacts very sensitive on changes of the water amount. Small changes of
the water amount injected into the mill have a great impact on the running of a mill.
Sometimes vertical mills are equipped with a fresh air flap. These flaps are for emergency
cases if the temperature rises too quickly. These flaps shouldn’t be used for adjusting the
temperature after the mill.
Flap
Fan
dedusting
Vertical mill
Hot gas entering mill
T~ 350 °C
Temperature after mill
T~ 90 °C
Circulating gas
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 35
Diagram 5: Optimization chart: Influence on the temperature
6.3 Optimization chart: Vibration
Vibration is a very important parameter regarding the safety of the mill. If the vibrations are
too high and last over a too long period of time, damages on the grinding rollers, the grinding
table and the gear box can occur. For this reason, every mill has a safety shutdown
procedure when vibrations occur.
For describing the parameter vibration there are two possible conditions:
Vibration is in range
If the Vibration of the mill is within an acceptable range, there are no problems and thus there
is no need of changing any parameter of the running grinding process.
Vibration is too high
Is the vibration of a vertical mill too high, there are several possibilities to reduce it.
If no changes of the parameters of the grinding process have happened and yet vibrations
occur, this is a sign for having foreign material inside of the mill. Foreign material, mainly
metal parts, entering the mill can’t be ground by the grinding rollers. So they are rolling over
it, are lifted up and after passing, the rollers are falling back onto the grinding table. This
Temperature
OK?
Hot gas
Enough
Reduce
Hot gas
Too low Too high
Reduce
Input
Increase
Circulating air
Increase
Water injection
Increase
Hot gas
Yes No
Side effects:
-volume flow
-fineness
-pressure drop
-vibration
-mill power
-Vibration
Side effects:
-vibration
-mill power
-mill power
-output
-fineness
-pressure drop
Reduce
Water injection
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 36
falling back usually leads to a tremendous increase of the mill-vibration causing a safety
shutdown. For solving this problem, the mill has to be opened and the foreign material to be
removed.
If there is no false material inside of the mill and vibrations occur, this can be due to difficult
material that has to be ground. Is the material too dry, the support of the inner-material
structure of the grinding bed is too low and thus the grinding rollers can break through the
grinding bed causing the mill to ‘rumble’. Insufficient water injected into the mill can be due to
blockage of the water-nozzle, demolished water pipe or false adjustment. So it needs to be
checked, if the water amount injected into the mill is normal compared to the material which
has to be ground.
Is the water amount in the normal range and no foreign material is found a third big reason
for vibrations of a vertical mill can be due to a false grinding bed height (see Diagram 6).
Diagram 6: Vibrations of a VRM due to false grinding bed height (Hannover)
In Diagram 6 the vibrations of the gear box (blue) and the separator (green) in mm/s as well
as the grinding bed height of the different rollers in mm are recorded over the time.
If the grinding bed is too high, the tapering of the grinding rollers is not sufficient and the
material is pushed aside. When the amount of material is too high, the rollers are rolling over,
causing a lifting of the rollers and a following drop back onto the grinding table causing high
vibration. A second effect of a too high material bed is the so called ‘stick and slick effect’.
Stick-slip is caused by the surfaces alternating between sticking to each other and sliding
over each other in. This will lead to a rumbling of the rollers. On the other hand, if the
grinding bed height is too low, the grinding rollers have no contact to the grinding bed or are
breaking through causing a contact between grinding table and grinding rollers causing
vibrations (see Diagram 6).
Mill-vibration Grinding bed
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 37
It is possible to adjust the height of the grinding bed by several parameters (see Diagram 8).
Varying the mill feed will have an influence on the grinding bed height. Less material fed into
the mill will decrease the material height and vice versa.
A second reason for affecting the material bed height is changes of the dam ring height. Is
the dam ring too high, too much material is on the grinding table and the material bed is too
high and vice versa. Adjusting the dam ring to the proper height for the material to be ground
can adjust the material bed height.
Another possibility for having a false grinding bed height is a false amount of water injected
into the mill. The effects of a wrong water amount are described above.
Changing the volume flow will also exert an influence on the grinding bed height. Increasing
the volume flow will take more material out of the mill and thus decrease the mill-internal
material circulation. Thus the mount of material getting back onto the grinding table is
reduced.
A wrong temperature of the material on the grinding table will influence the flow
characteristics of the material bed. At a temperature lower than approximately 110 °C the
material will get off the table easily. Increasing the temperature to approximately 130 °C will
also increase the flowability of the material, causing the material to get off the grinding table
more easily.
The last possibility to have an impact on the grinding bed height is the particle size. Too big
or too small particles may influence the grinding process in a negative way. Thus it has to be
checked, if any changes in the granulometry of the material to be ground have occurred.
If the hydraulic pressure of the grinding rollers is high enough and still vibration occurs, the
last reason for vibrations can be a bad wear condition of the grinding elements. If the wear of
the grinding rollers or the grinding table is too high, vibration occurs. This wear has to be
removed either by removing the worn parts or by welding repairs.
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 38
Diagram 7: Optimization chart: Influence on mill-vibration I
Vibration
High
Foreign
material
yes
Water injection
normal
Grinding bed height
normal
Hyd. pressure
normal
Wear of
grinding elements
no
OK!
no
yes
yes
no
no
yes
yes
no
remove
check
check
rewelding
yes
Side effects:
-mill power
-temperature
-mill power
-output
-vibration
-fineness
-pressure drop
-fineness
-output
-mill-power
See
Diagram 8
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 39
Diagram 8: Optimization chart: Influence on mill-vibration II
Influence of the grinding bed height
Grinding bed height
normal
Volume flow
normal
Check
Input
Check
Dam ring height
Check
Water injection
Material check
-Vibration
-Mill power
no
yes
See
-Diagram 7 (Vibration)
-Diagram 10 (Mill power)
adjust
Side effects:
-fineness
-temperature
-output
-mill power
-pressure drop
-mill power
-temperature
-pressure drop
-output
-fineness
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 40
6.4 Optimization chart: Output
For describing the parameter output there are three possible conditions:
Output is in range
If the output of a mill is within the defined range, there are no problems and thus there is no
need of changing any parameter of the running grinding process.
Output is too high
If the output of a mill is too high then there are no problems.
Output is too low
If the output of a vertical mill is too low, there are several possibilities to reduce it.
Increasing the mill feed will also increase the output of the mill. But this will only be possible,
if the hydraulic pressure of the grinding rollers as well as the volume flow for lifting the
particles up to the separator is enough.
After increasing the mill feed, the second parameter to influence the output of a vertical mill is
the hydraulic pressure of the grinding rollers. By increasing this pressure, more material is
ground fine enough to be lifted up and passing the separator.
If the output of a vertical mill is still too low, optimizing the mill power will lead to an increase.
The mill power and its influences will be described in chapter 6.5 in detail.
The last possibility to increase the output is by increasing the volume flow. This increase will
raise the amount of material being able to be lifted up. According to equation 1 coarser
material can pass through the separator. So changing the output by increasing the volume-
flow will always decrease the fineness if no other changes will be made.
If none of these parameters did increase the output, it needs to be checked, if the material
properties, in particular the grindability has changed. Checking these properties have to be
done in laboratory tests.
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 41
Diagram 9: Optimization chart: Influence on mill-output
OK?
Output
too high too low
Everything
OK
Increase
Volume flow
Increase
Input
Increase
Mill power
Change in
Grind ability
Reduce
hyd. pressure
Lab test
Grind ability
Side effects:
-temperature
-mill power
-fineness
-pressure drop
-fineness
-vibration
-fineness
-pressure drop
-pressure drop
-vibration
-fineness
See Diagram 10:
Mill power
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 42
6.5 Optimization chart: Mill power
For describing the parameter mill power there are three possible conditions:
Mill power is in range
If the power of a mill is within the defined range, there are no problems and thus there is no
need of changing any parameter of the running grinding process.
Mill power is too low
Is the power of a mill too low, increasing the input will also increase the mill power. More
material will be on the grinding table causing the motor to increase the power consumption.
A similar effect will have the increase of the dam ring height. More material will be retained
on the grinding table, leading the motor to increase the power consumption.
Mill power is too high
If the power consumption of a vertical mill is too high, there are several possibilities to reduce
it.
First of all it needs to be checked, if the grinding bed is too high or if the height is within the
normal range. If the grinding bed is within the normal range, the only possibility to reduce the
energy consumption is by decreasing the hydraulic pressure of the grinding rollers. This will
lead to a lower resistance to rolling and thus to a decreasing energy consumption for the
motor turning the grinding table.
Is the grinding bed height normal and the hydraulic pressure is reduced to the possible
minimum, the mill feed needs to be reduced in order to reduce the mill power.
If the mill power is too high and the grinding bed is not within the normal range, it is
necessary to check the parameters influencing the grinding bed height (see Diagram 8).
Adjusting the parameters if necessary should decrease the power consumption of the mill.
If none of these parameters did decrease the mill power, the last possibility is to reduce the
mill feed.
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 43
Diagram 10: Optimization chart: Influence on mill power
Mill power
OK?
Increase
Input
Grinding bed
too high
Too low too high
no Reduce
hyd. pressure
yes
adjust
no
Reduce
Input
See:
Diagram 8
no Increase
Dam ring
yes
Side effects:
-temperature
-output
-fineness
-pressure drop
Side effects:
-vibration
-output
-fineness
-pressure drop
-output
-fineness
-pressure drop
-temperature
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 44
6.6 Optimization chart: pressure drop
The pressure drop over the mill is an indication for the amount of material inside of the mill.
For describing the parameter pressure drop over the mill there are three possible conditions:
Pressure drop is in range
If the pressure drop of a mill is within the defined range, there are no problems and thus
there is no need of changing any parameter of the running grinding process.
Pressure drop is too low
If the pressure drop of a mill is too low, the material inside of the mill is not sufficient. Thus
the only way to increase the pressure drop is by increasing the amount of material inside of
the mill.
Is pressure drop is still not high enough, additional feed material will lead to an increasing
pressure drop. More feed will lead to a higher amount of dust which in turn will lead to an
increased flow resistance.
As the material inside of the mill is the only reason for the pressure drop over the mill other
optimization potentials need to be adjusted to increase the material feed if the feed isn’t
sufficient.
Pressure drop is too high
If the pressure drop over a vertical mill is too high, too much material is inside of the mill. Is
the pressure drop reaching a critical value (over approximately 80 mbar) too much material is
inside of the mill causing the mill to stop. Thus, the only way to decrease the pressure drop is
by decreasing the amount of material inside of the mill.
Is the pressure drop over the mill too high, increasing the volume flow will decrease it. A
higher volume flow will take more material out of the mill which leads to a decreasing dust
content inside of the mill.
Increasing the hydraulic pressure of the grinding rollers will also decrease the pressure drop.
An increase of the grinding force will lead to a finer comminution of the material. Grinding the
material fine enough will decrease the material circulation inside of the mill; more material will
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 45
be fine enough to pass the separator and being transported out of the mill causing the
pressure drop to decrease.
If adjusting the volume flow and the hydraulic pressure didn’t decrease the pressure drop
over the mill, the last possibility to decrease it is by decreasing the mill feed. Thus, less
material enters the mill and less material will lead to a lower pressure drop.
Another item influencing the pressure drop is the free area of the nozzle ring. By uncovering
the covered nozzle area, the speed of the gas-flow is reduced and with it the pressure drop.
Diagram 11: Optimization chart: Influence on the pressure drop
6.7 Comments on the optimization charts
Changing one parameter of the grinding process of a vertical mill can have several
secondary effects. These have to be considered when changing any parameter. In Diagram
7 to Diagram 11 the secondary effects are written in red letters. Changing the volume flow for
a higher fineness of the product might cause vibrations of the mill. A different separator-
OK?
Pressure drop
Increase
Input
too low too high
Other
optimization
Increase
Volume flow
Reduce
Input
Increase
hyd. pressure
70-80 mbar
Side effects:
-fineness
-output
-temperature
-mill power
Side effects:
-fineness
-vibration
-output
-mill power
-output
-fineness
-fineness
-mill power
-output
-temperature
Check
Nozzle ring area
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 46
speed for influencing the fineness can have an impact on the pressure drop of a mill.
Increasing the water injected into the mill for reducing the temperature after the mill can
cause a higher mill power. And increasing the hydraulic pressure of the grinding rollers for
lowering vibrations is leading to a higher fineness of the product (see Table 6).
Parameter Influence (increasing) Influence (decreasing)
Volume flow -pressure drop decreasing
-output increasing
-Vibration decreasing
-fineness decreasing
-pressure drop increasing
-output decreasing
-Vibration increasing
-fineness increasing
Hydraulic pressure -pressure drop decreasing
-output decreasing
-Vibration decreasing
-mill power increasing
-fineness increasing
-pressure drop increasing
-output increasing
-Vibration increasing
-mill power decreasing
-fineness decreasing
-Temperature decreasing -Temperature increasing Water injection
-grinding bed height
-mill power
-output
-vibration
Table speed -fineness decreasing
-output increasing
-Mill power decreasing
-fineness increasing
-output decreasing
-mill power increasing
Input -fineness decreasing
-Temperature decreasing
-output increasing
-mill power increasing
-pressure drop increasing
-fineness increasing
-output decreasing
-mill power decreasing
-pressure drop decreasing
Circulating air -Temperature decreasing -Temperature increasing
Dam ring height -output
-mill power
-vibration
Hot gas -Temperature increasing -Temperature decreasing
Table 6: side effects of changing parameters of grinding process of a vertical mill
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 47
7 Conclusion
There are many different mills from many different manufacturers in use at
HeidelbergCement. They grind a variety of materials like different cement types, raw-
material, slag and coal.
As both mills in Hannover and Slite show, it is adjuvant to have a tool to find optimization
potentials for improving the grinding process of a mill concerning output, quality and safety of
a mill. The optimization charts are an approach to have a procedure for an investigation or
evaluation of a vertical mill system.
The correctness of these optimization charts have to be proven on a case study.
As experiences show, there is a high acceptance for these optimization charts in the different
plants.
The examples have also shown that recording the history of the mills regarding overhaul
works, would be beneficial. This would easily show, which measures have been done to
improve a mill. This would also reveal which measures brought any enhancement and which
ones didn’t show any effect.
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 48
8 Bibliography
Brundiek, Horst Die Wälzmühle- Geschichte und heutiger Stand
Aufbereitungstechnik 30 (1989) Nr. 10
FLSmidth OK vertical roller mill
Gebrüder Pfeiffer Kompetenz in Zement
Jorgensen, MSc S.W. Cement grinding- a comparison between vertical roller mill and
ball mill
Cement international 2/2005 Vol. 3 pages 54-63
Labahn/Kohlhaas Ratgeber für Zementingenieure
6. Auflage, Bauverlag GmbH, Wiesbaden 1982
ISBN: 3-7625-2020-8
Loesche LOESCHE- Mühlen für Zement und Hüttensand
Polysius Polysius Rollenmühlen. Zur Mahlung von …
Schneider, Lohnherr,
Gudat
Rollenmühlen für große Leistungen und schwieriges Mahlgut
Verfahrenstechnik der Zementherstellung, VDZ-Kongress `85,
Fachbereich 3, S. 258-264
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 49
9 Annex
9.1 Cost calculation between vertical mill and ball mill
1. General data Cement production [t/ year] 1.200.000 Total grinding capacity [t/h] 200 Operating time [h] 6.000 Mill type Ball Mill Vertical mill 2. Investment costs Total investment costs [%] 100 101,53 3. Operating costs 3.1 Energy costs Mill drive [kW] 7.000 4.680 Mill drive [%] 100 67 Auxiliaries factor from total [%] 0,20 0,40 Auxiliary drives separator + dedusting +slag dryer [kW] 2.158 3.120 Total power [kW] 9.090 7.800 Specific energy mill [kWh/t] 35,0 23,4 Specific energy mill system [kWh/t] 45,5 39,0 Specific energy costs [%] 100 82,71 3.2 Maintenance costs incl. Grinding media and elements [%] 100 136,37 3.3 Total operating cost Specific operating costs [%] 100 99,61 4. Overview Total operating cost per year [%] 100 99,61 Total investment costs [%] 100 101,53 Table 7: cost comparison between vertical mill and ball mill
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 50
9.2 Calculating the active grinding area per time
RollerTa bdA ∗∗= π Equation 1
60nDv rT,c
π∗∗= Equation 2
60nAA rag ∗∗= Equation 3
Aa Active grinding area m²
dT Dia. Centre of the track m
bRoller Width of rollers m
vc,T Circumferential speed of table m/s
D Diameter of table m
nr Number of revolutions min-1
Ag Active grinding area pert time m²/s
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 51
9.3 Pictures of Raw mill 8 in Slite
Figure 18: changes in mill design for higher output
Left: installation of a new dynamic separator with a distribution plate Right: installation of ploughs to create a smooth grinding bed
Figure 19: mill internals
Left: dam ring Right: nozzle ring with 30° angled guiding blades
Figure 20: critical wear spots
Left: wear-repair done at the riser-duct at the top of the vertical mill Right: wear underneath the old distribution plate
Material inlet
Distribution plate
Grinding table
Plough
Plough
Dam ring
Grinding table
Nozzle ring
Vertical Mills for Raw and Cement Grinding
Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 52
Figure 21: constructive modifications of the mill
Left: new material inlet for coarse material Middle: new, bigger blades for the rotary cage with support ring Right: Sealing of critical wear-spots (compare Figure 18, left picture)
Figure 22: Bad condition of the vertical mill
Left: wide gap between mill housing and rotary cage causing bad quality (top view) Right: big gaps in the mill housing (alignment of separator guiding blades) causing high false air amount
Support ring Old blades
New blades
Raw-material
Coarse-material
Mill housing
Mill housing
Rotary cage
Alignment of guiding blades
Gap
Vertical Mills for Raw and Cement Grinding Inspection and Evaluation HTC
J:\TCman\Rco\T&E\Trainees\2-Abgeschlossen\101_Koch\Thesis\Abschluss final.doc 53
9.4 Pictures of Cement mill 11 in Hannover
Figure 23: changes of the mill design for a smoother grinding process
Left: material collection and slide after 1st and 2nd grinding roller Middle: material deflector plate in front of first grinding roller Right: Water injection
Grinding Roller Material inlet
Grinding Roller
Grinding Roller