Semi-annual Environmental Monitoring Report Project Number: 42171-013 December 2019 Khulna Water Supply Project January-December 2019
25

Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

Mar 26, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

Semi-annual Environmental Monitoring Report

Project Number: 42171-013 December 2019

Khulna Water Supply ProjectJanuary-December 2019

Page 2: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

This Semi-annual Environmental Monitoring Report is a document of the borrower. The views

expressed herein do not necessarily represent those of ADB's Board of Directors, Management,

or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any

designation of or reference to a particular territory or geographic area in this document, the Asian

Development Bank does not intend to make any judgments as to the legal or other status of any

territory or area.

Page 3: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

Environmental Monitoring Report

Final Environmental Monitoring Report

January-December 2019

BAN: Khulna Water Supply Project

Page 4: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report i | Page

TABLE OF CONTENTS

I. INTRODUCTION 4

A. Project Background 4

B. Observations and lesson learn 4

II. SAFEGUARDS COMPLIANCE PERFORMANCE OF KHULNA WATER SUPPLY PROJECT 6

C. Compliance with the Environmental Provisions of the Loan Covenant 6

D. Compliance with the Environmental Management Plan 7

III. CONCLUSIONS AND RECOMMENDATIONS 10

APPENDIX A: PHOTOGRAPHS OF SITE VISITS 11

APPENDIX B: Project status of contract packages 12

TABLES

Table II-1. Status of Compliance with the Environmental Provisions of the Loan Covenant 6

Table II-2: Compliance to Environmental Management Plan (EMP) 8

Page 5: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report ii | Page

ABBREVIATIONS

ADB Asian Development Bank

BDT Bangladesh Taka

BOQ Bill of Quantities

BCCSAP Bangladesh Climate Change Strategy and Action Plan

DOE Department of Environment

EMP Environmental Management Plan

IEE Initial Environment Examination

KWASA Khulna Water Supply and Sewerage Authority

NGO Nongovernment Organization

O&M Operation and Maintenance

ROW Right of Way

SPM Suspended Particulate Matter

SPS Safeguard Policy Statement

Page 6: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report iii | Page

Executive Summary

The Khulna water supply project will expand the access to water supply service by extending the distribution network to cover the whole city. The outcome of the project will be expanded access to water supply with improved service standard in Khulna. The outputs of the project will be (i) expanded capacity of water supply system with sustainable water sources, (ii) strengthened corporate management system, and (iii) improved project management capacity. Physical infrastructure includes: Distribution Pipe Network, Distribution Reservoirs, Overhead Tanks, Clear Water Transmission Pipes and KWASA Office Buildings.

The major findings are: All project locations have adequate rainwater drainage line and outlets

are present but at Sonadanga Moha Sarak Reservoir site inadequate drainage outlet is observed;

fire extinguisher is present in office building. Need to place fire extinguisher in all reservoir site;

plantation is present in all reservoir sites; open electric cables is observed at Sonadanga Moha

Sarak reservoir, office building sites has proper and functioning septic tank without having any

damage.

The following mitigation measures is suggested for smooth operation of subprojects as per

environmental management plan and expert opinion.

Need to provide adequate fire extinguisher;

PPE and First aid box should be provide;

Adequate draiage outlet should be construct at Sonadanga Moha Sarak Reservoir site;

Need to cover the electric cable proper insulation should be maintained for protection.

No significant adverse impacts or unanticipated impacts were recorded during site visit. But it is

recorded that no monitoring is observed after completion of civil works.

Page 7: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 4 |Page

I. INTRODUCTION

A. Project Background

1. The Project commenced in June 2011 and has been completed in March 2019. The total

project cost is estimated at $75 million. Khulna Water Supply and Sewerage Authority is the

Executing Agency (EA). The project will expand the access to water supply service by

extending the distribution network to cover the whole city. The impact of the project will be

sustainable improvement of urban environment in Khulna. The outcome of the project will be

expanded access to water supply with improved service standard in Khulna. The outputs of

the project will be (i) expanded capacity of water supply system with sustainable water

sources, (ii) strengthened corporate management system, and (iii) improved project

management capacity.

2. The Project proposes a surface water system sourced from the Mollarhat intake point on the

bank of Modhumati River in Bagherhat District. The raw water from the Modhumati River will

be stored into an impounding reservoir and then transmitted to a water treatment plant at

Samonto Sena with the purified water to be distributed through a system of smaller storage

reservoirs and overhead tanks and delivered to consumers in Khulna City Corporation.

Physical infrastructure includes: Distribution Pipe Network, Distribution Reservoirs,

Overhead Tanks, Clear Water Transmission Pipes and KWASA Office Buildings.

3. The Khulna Water Supply Project is classified as environmental category B and the conduct

of semiannual environmental monitoring is required as per loan covenant. Initial

Environmental Examination (IEE) and Environmental Assessment and Review Framework

(EARF) is sufficient to meet the environmental requirements as per ADB SPS (2009).1 The

compliance to environmental safeguards of the Khulna Water Supply is assessed based on

the following: (i) environmental provisions of the loan covenant; (ii) Initial environmental

examination (IEE); and (iii) environmental management and monitoring plan (EMP) and

integration in the civil works bidding documents.

4. This EMR covers the entire project of ADB components. Compliance information were

gathered through the review of secondary data available in the ADB website, key staff

interviews, and site-visits.

5. Khulna Water Supply project are visited during field survey.

6. Local people are very happy due to implementation of water supply project. Khulna is saline

prone area and ground water is salty. This project provide fresh water and improve the water

supply capacity of Khulna City Corporation. No negative impact is address by local people

due to implementation of the subprojects.

B. Observations and lesson learn

7. Some observations and lesson learn have been noted during field visit are illustrated below:

A. Khulna water supply project in Khulna City Corporation:

Intervention:

I. Water Reservoir and Overhead Tanks & KWASA office areas

Adequate rainwater drainage line and outlet is present.. However at Sonadanga Moha Sarak reservoir site drainage outlet is not adequate. Inadequate drainage line will create water stagenant problem during rainy season. Adequate draiage outlet should be

construct at Sonadanga Moha Sarak Reservoir site.

1https://www.adb.org/projects/documents/khulna-water-supply-project-initial-environmental-examination-board-approval

Page 8: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 5 |Page

Fire extinguisher is not present in reservoir site, which increase the fire hazard risk. Need to provide adequate fire extinguisher. In addition regular inspection is required for

minimize the fire hazard risk.

Personal Protective Equipment (PPE) and first aid box are inadequate. Adequate PPE, First aid facility; arrangement of safe drinking water and sanitation facilities will decrease the occupational health risks of employees. Need to provide PPE and first aid box.

At Sonadanga Moha Sarak Reservoir open electric cables is observed; which may increase fire risk and fatal incidents. This electric wires need to cover and proper insulation should be maintained for protection.

During site visit it is observed that (Mango; Mangifera indica, Lemon; Citrus limon, Coconut; Cocos nucifera) local trees on the boundary line of the intake, OHT & KWASA office areas has been planted. It will enrich the local biodiversity.

II. KWASA office areas

Office building sites has proper and functioning Septic tank without having any damage.

8. Non-compliance issues and corrective actions are illustrated below:

Projects Issues Action taken by executing agency

Need Corrective Actions/mitigation

Remarks

Khulna Water Supply

Fire extinguisher is not present in reservoir site, which increase the fire hazard risk.

No action taken. Need to provide adequate fire extinguisher.

As per EMP.

Inadequate fire extinguisher will increase the fire hazard risk.

PPE and First aid

facility are

inadequate at

reservoir site

which increase the

occupational

health risk of

employees.

No action taken. PPE and First aid box should be provide.

As per EMP.

Adequate PPE, First aid facility; arrangement of safe drinking water and sanitation facilities will decrease the occupational health risks of employees.

Sonadanga Moha

Sarak Reservoir

site does not have

adequate draiage

outlet.

Adequate rainwater drainageline and outlet is constructed except Sonadanga Moha Sarak Reservoir site.

Adequate draiage outlet should be construct at Sonadanga Moha Sarak Reservoir site.

Inadequate drainage line will create water stagenant problem during rainy season.

Open electric

cables is observed

at Sonadanga

Moha Sarak

Reservoir

No action taken. Need to cover the electric cable proper insulation should be maintained for protection.

Expert judgment.

Open cable may increase fire risk and fatal incidents.

Page 9: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 6 |Page

II. SAFEGUARDS COMPLIANCE PERFORMANCE OF KHULNA WATER SUPPLY

PROJECT

C. Compliance with the Environmental Provisions of the Loan Covenant

9. Overall, this project has complied with the environmental provisions of the loan covenant. It

has complied the integration of the construction-phase environmental management plan

(EMP) into the bidding documents. Status of compliance with the environmental provisions

of the Loan Covenant to the Khulna water supply project are shown in Tables II-1.2

Table II-1. Status of Compliance with the Environmental Provisions of the Loan Covenant

Environmental Provision Status of Compliance

Schedule 4. Conditions for Award of Contract. The

Borrower shall not award, and shall ensure that an

Implementing Agency does not award: 18 (a) any

Works contract which involves environmental impacts

until (i) all government environmental clearances have

been obtained for the IEE; (ii) the IEE has been cleared

by ADB; and (iii) relevant EMP provisions have been

incorporated into the respective Works contract;

Complied with: Relevant EMP provisions were

incorporated into works contracts.

Schedule 5. Execution of Project; Financial Matters

Environment Safeguards. The Borrower shall ensure,

and shall cause each Implementing Agency to ensure,

that the preparation, design, construction,

implementation, operation and decommissioning of the

Project and each subproject under the Project comply

with: (a) all applicable laws and regulations of the

Borrower relating to environment, health, and safety;

(b) the Environmental Safeguards; (c) the EARF; and

(d) all measures and requirements set forth in the IEE

and the EMP, and any corrective or preventative

actions set forth in the Safeguards Monitoring Reports.

Complied with: Submission of semi-annual

environment monitoring reports (EMRs) to ADB

were compliance.

Schedule 5. Safeguards – Related Provisions in

Bidding Documents and Works Contracts

6. The Borrower shall ensure, and shall cause each

Implementing Agency to ensure, that all bidding

documents and contracts for Works contain provisions

that require contractors to: (a) comply with the

measures and requirements relevant to the contractor

set forth in the IEE, the EMP and …, and any

corrective or preventative actions set out in a

Safeguards Monitoring Report; (b) make available a

budget for all such environmental and social safeguards

measures; and (c) provide the Borrower and ADB with

a written notice of any unanticipated environmental and

other safeguards-related risks or impacts that arise

during construction, implementation or operation of the

Project that were not considered in the IEE, the EMP …

Complied with: Relevant EMP provisions were

incorporated into works contracts.

2https://www.adb.org/projects/42171-013/main#project-documents

Page 10: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 7 |Page

D. Compliance with the Environmental Management Plan

10. The environmental management plan (EMP) attached in the Initial Environmental

Assessment (IEE) is prepared for all the identified environmental impacts during construction

and operation stages due to implementation of various project activities and associated

development. The aim of the EMP is to ensure implementation of the recommended

mitigation measures effectively. The mitigation measures are designed either to prevent

impacts or by mitigating those to reduce the effect to an acceptable level that complies with

the environmental guidelines of DOE and with the guidelines of the ADB’s SPS (2009) by

adopting the most suitable cost-effective options. The EMP also ensures that the positive

environmental impacts are conserved and enhanced. Compliance to the EMP is shown in

Table II-2.

Page 11: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 8 |Page

Table II-2: Compliance to Environmental Management Plan (EMP)

Project

Activity

Concern Issue Recommended Mitigation Measures Action Taken Remarks

During operation Phase

A total of 52 trees

at OHT & GR was

cutting down

during

construction

phase.

Trees will be planted for compensating

the removal trees.

About 18000 (Mango;

Mangifera indica, Lemon;

Citrus limon, Coconut;

Cocos nucifera) local

trees on the boundary line

of the intake, OHT &

KWASA office areas has

been planted.

Survival of trees

and maintenance

of landscaping,

and the green

buffer zone.

Proper care shall be taken to increase

survival rate of saplings like regular

watering, pruning provision of tree

guards, manure for better nourishment,

etc. Including timely replacement of

perished saplings.

Proper care has been

taken to increase survival

rate of saplings.

Occupational

health and

safety.

Implement suitable safety standards

for all workers and site visitors;

Provision of first aid facility;

Arrangement of safe drinking water

and sanitation facilities for the labors

working in the subprojects;

Adequate Fire extinguisher will be

available.

No action taken for

providing PPE, First aid

box and Fire

extinguisher;

Adequate septic tank is

available.

Page 12: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 9 |Page

Drainage

Networks.

Rainwater drainage line and sufficient

outlet is required.

Adequate rainwater

drainage line and

sufficient outlet is present

except Sonadanga Moha

Sarak Reservoir site

Page 13: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 10 |Page

III. CONCLUSIONS AND RECOMMENDATIONS

11. Khulna Water Supply Project has substantial compliance to the environmental safeguards

requirement set by the ADB and the GoB. On-site monitoring was conducted and no

significant adverse impacts or unanticipated impacts were recorded. Semi-annual monitoring

is being implemented by the KWASA on the implementation of the project with complete

documentation.

12. Non-compliance has been identified to date regarding drainage outlet and occupational

health and safety in the project sites. Corrective actions will require for mitigate the

environmental issues.

13. The important lesson learning from the site visit is that after completion of civil works, no

monitoring is observed. During operation period monitoring program should be execute as

per EMP.

Page 14: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 11 |Page

APPENDIX A: PHOTOGRAPHS OF SITE VISITS

Khulna Water Supply Project

Component Name: KWASA HQ Office building

KWASA HQ building Fire extinguisher

Component Name: Khalishpur Charerhat River Ghat Reservoir and Overhead tank

Khalishpur Charerhat River Ghat Reservoir Plantation at Khalishpur Charerhat River Ghat Reservoir

Page 15: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 12 |Page

Khalishpur Charerhat River Ghat Overhead Tank Septic tank at Khalishpur Charerhat River Ghat Reservoir

Rainwater drainageline at Khalishpur Charerhat River Ghat Reservoir

Drainage outlet Khalishpur Charerhat River Ghat Reservoir

Component Name: Sonadanga Moha Sarak Reservoir

Page 16: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 13 |Page

Overhead tank at Sonadanga Moha Sarak Reservoir

Pump house at Sonadanga Moha Sarak Reservoir

Septic tank at Sonadanga Moha Sarak Reservoir

Page 17: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 14 |Page

Inadequate drainage outlet Open electric cable at Sonadanga Moha Sarak Reservoir

Plantation in Sonadanga Moha Sarak Reservoir

Component Name: Rayermmohal reservoir

Page 18: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 15 |Page

Rayermmohal reservoir

Rayermmohal overhead tank Pump house at Rayermohal Reservoir

Page 19: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 16 |Page

Drainage outlet Rainwater drainageline at Rayermohal Reservoir

Plantation at Rayermohal Reservoir Septic tank at Rayermohal Reservoir

Component Name: Lobonchara reservoir

Page 20: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 17 |Page

Lobonchara overhead tank Lobonchara pump house

Rainwater drainageline at Lobonchara Reservoir Drainage outlet

Page 21: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 18 |Page

Plantation at Lobonchara Reservoir Septic tank at Lobonchara Reservoir

Component Name: Natunbazar reservoir

Overhead at Natunbazar Reservoir Pump house at Natunbazar Reservoir

Page 22: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 19 |Page

Septic tank at Natunbazar Reservoir Adequate drainage line

Adequate drainage line Outlet of Rainwater drainage line

Page 23: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 20 |Page

APPENDIX B: PROJECT STATUS ON CONTRACT PACKAGE

ADB financed contracts

Package # KWASA/KWSP/ADB/DROT-01: Construction of Distribution Reservoirs and Over

head Tanks.

Name of contractor RANKEN – MAX JV

Contract Amount BDT 1,909,085,281.15

Date of commencement 26 June 2014

Date of completion 30th June 2019

Financial progress BDT 1,909,085,281.15

Physical Progress 100%

Elapsed time 5 years

Incurred delay 2 Years

Progress status Completed

Remarks Work Delayed due to land acquisition.

Package # KWASA/KWSP/ADB/CWTM-02: Construction of Clear water transmission main

including River Crossing.

Name of contractor China Geo Engineering Corporation

Contract Amount BDT 2,124,207,620.52

Date of commencement 27th November 2014

Time of completion 30th June 2019

Financial progress BDT 2,124,207,620.52

Physical Progress 100%

Page 24: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 21 |Page

Elapsed time 4 Years and 7 Months

Incurred delay 1 Year and 7Months.

Progress status Completed

Remarks Worked Delayed due to Road cutting permission from RHD, KCC

and Bangladesh Railway.

Package # KWASA/KWSP/ADB/DPN-03: Construction of distribution pipe network.

Name of contractor China Geo Engineering Corporation

Contract Amount BDT 3,545,973,654.16

Date of commencement 11th April 2015

Time of completion 30th June 2019

Financial progress BDT 3,545,973,654.16

Physical Progress 100%

Elapsed time 4 Years and 3 Months

Incurred delay 1 Year and 3Months.

Progress status Completed

Remarks Worked Delayed due to Road cutting permission from RHD, KCC

and Bangladesh Railway.

JICA financed Contracts:

Package no. KWASA/KWSP/ICB-01: Construction of Water Intake Facility and Raw water

Transmission pipeline

Name of contractor China Geo Engineering Corporation

Contract Amount BDT 1,403,521,270.89 + USD 71,735,201.64

Date of commencement 30th March 2016

Page 25: Khulna Water Supply Project January-December 2019 · BOQ Bill of Quantities BCCSAP Bangladesh Climate Change Strategy and Action Plan ... Sarak reservoir, office building sites has

BAN: Khulna Water Supply Project

Environmental Monitoring Report 22 |Page

Time of completion 30th June 2019

Financial progress BDT 1,403,521,270.89 + USD 71,735,201.64

Physical Progress 100%

Elapsed time 3 Years and 3 Months

Incurred delay 3Months.

Progress status Completed

Remarks Worked Delayed due to Road cutting permission from RHD and

Bangladesh Railway.

Package no. KWASA/KWSP/ICB-02: Construction of surface water treatment plant and

impounding reservoir.

Name of contractor China Harbour Engineering Corporation ltd.

Contract Amount BDT 1,972,099,717.91 + USD 37,192,779.40

Date of commencement 1st July 2015

Time of completion 30th June 2019

Financial progress BDT 1,972,099,717.91 + USD 37,192,779.40

Physical Progress 100%

Elapsed time 4 years

Incurred delay 1 Years

Progress status Completed

Remarks Work Delayed due to land acquisition.