IN THE LAHORE HIGH COURT, LAHORE
IN THE LAHORE HIGH COURT, LAHORE
Writ Petition No./2008Khalid Rauf & Co. (Pvt.) Ltd. having
its office at 24/3C, Messon Road, Link Lawrence Road, Lahore
through its Chief Executive Officer Mr. Khalid Rauf.
.Petitioner
VERSUS1. Government of the Punjab through Secretary
Communications and Work Department, old Anarkali Lahore. 2.
Director General, Lahore Development Authority, LDA Plaza Egerton
Road Lahore. 3. Chief Traffic Engineer TEPA, LDA, 4-C, Layton Road,
Lahore.4. PDPMU Project Management Unit, Project Manager Lahore
Ring Road Project, 37-A, Al-Noor Centre, Township, PECO Road,
Lahore.5. Chief Engineer Highway Punjab, 2-Lake Road, Lahore.
.Respondents
WRIT PETITION UNDER ARTICLE 199 OF THE CONSTITUTION OF ISLAMIC
REPUBLIC OF PAKISTAN, 1973.
= = = = = = = = = = = = = = = = = = = = = = = = = = = = = = =
Respectfully Sheweth:
1.That the addresses of the parties have been correctly given in
the title of the petition for the services of processes which may
be issued by this Honble Court from time to time.
2.That the petitioner is a private limited company incorporated
under the laws of Pakistan having its registered office at 24/3C,
Messon Road, Link Lawrence Road, Lahore and this petition is being
filed through Mr. Khalid Rauf who is duly authorized representative
of the petitioner and is fully conversant with the facts of the
case and is duly authorized by resolution of board of directors
dated 24/08/2008 to sign, verify and institute these proceedings
and do such other acts which are necessary and incidental thereto.
(Copy of the Memorandum and Articles of Association are attached as
Annex A & B) (Copy of the board resolution is attached as Annex
C)3.That the brief issue involved in this case is that the
petitioner, who is a highly reputed company involved in the
business of providing services of engineering and construction of
highways and bridges for the past 32 years, has been blacklisted
for future projects by the respondent No.3 on the behest of
respondent No.2. This so-called blacklisting of the petitioner has
been done by the respondents absolutely contrary to the law,
against the judgments pronounced by the Supreme Court of Pakistan,
without show cause notice and any enquiry, in contravention of the
principles of natural justice, contrary to the terms and conditions
of the contract, arbitrarily, unlawful and for malafide reasons. In
this writ petition the action of the respondents in blacklisting
the petitioner has been challenged. 4.The facts forming the
background of this writ petition are narrated below: -BRIEF
FACTS(i) That the petitioner is involved in the business of
providing services of engineering and construction of highways and
bridges for the past 32 years. In its business history the
petitioner has successfully completed the engineering and
construction on projects worth billions of rupees. These include
recently completed/near completion mega projects like Lahore Ring
Road (Package 3) Construction of Road Portion from Niazi Chowk to
Bund Road, Lahore (for Rs.2472 Million); Lahore Ring Road
(Package-1) Construction of Interchange at Niazi Chowk, Lahore (for
Rs.644 Million); Construction of Lahore-Sheikhupura-Faisalabad Dual
Carriageway (BOT Project) (For Rs.1200 Million); Dualization of
G.T. Road from Daroghawala to Wahgha Border (for 577 Million
Rupees). Owing to the reputation and good work of the petitioner
the petitioner is a no limit contactor and has contributed to the
national exchequer by depositing a tax of approximately 133.82
million in the last financial year 2007-2008. It is a record of the
petitioner that the petitioner has never breached any contract with
the Government of Punjab during its entire 32 years of doing
business. (Copy of petitioners profile with a list of its
achievements is attached as Annex D)(ii) That the petitioner owing
to its reputation was awarded the contract for improvement and
rehabilitation of Maulna Shaukat Ali Road from UBD Canal to
Ferozepur Road (Chungi Amer Sidhu) on 14/05/2008 which included the
construction of a dual carriage. The petitioner agreed to complete
the project for a sum of Rs30,25,15,421/. The acceptance of the
work was done on 26/06/2008 and the work was commenced within 3
days thereof on 29/08/2008. The project was to be completed within
four months on 29/10/2008. The petitioner after commencing this
work continued to execute the work as per the specifications and
timeline contained in the aforesaid contract. At the commencement
of construction of works, the petitioner also duly gave all notices
and warnings of safety and took all precautionary measures for the
safety and convenience of the public. (Copy of the Contract,
Acceptance letter, site drawings are attached as Annex E, F &
G) (iii)That it is pertinent to mention here that the contract had
an engineer in-charge who duly verified and monitored works
including the precautionary measures which were undertaken by the
petitioner on the site. The respondents never complained or
required the petitioner to increase the number of notice board
warnings etc. and this was because the petitioner had already duly
fulfilled all those requirements. The respondent No.3 was fully
satisfied with the performance of the petitioner regarding the
fulfillment of safety requirements. As proof of the fact that the
petitioner had done what is necessary, the petitioner is attaching
some photographs taken at the relevant time as (Copies of the
photographs are attached as Annex H/1 to H/3 respectively).
(iv)That on Tuesday, August 12, 2008 the city of Lahore experienced
one of the heaviest rainfalls in its near history (the estimated
rainfall was about between 38mm to 48 mm which rainfall has not
taken place for 12 years). The rainfall started in the morning and
by the afternoon most parts of the city were inundated with and
under water. The site at which the petitioner was carrying on the
works was also similarly fully submerged in 4 to 5 feet of water.
The entire surrounding area of the site was also completely
submerged to the extent that it was impossible to determine the
location of the road, the green belt and the drain. At about 4:00
pm on this day a person by the name of Amir Iqbal tried to cross
the work side (which was closed for traffic from both sides, due to
construction work) on Maula Shaukat Ali Road, near Satu-katla over
bridge from one end to the other. As he was crossing, he slipped
and in the process drowned at some point. It is possible that he
may have swept by the water, struck a boundary wall of the under
construction drain pipe and fallen in the muddy waters. A rescue
attempt was made but the accident proved fatal. The death was
obviously unfortunate but accidental and due to no fault of any
person. The warning signs and precautionary measures were available
at the site albeit many of the warning signs may have been
submerged. The work had been going on since June 2008 and every
person in the locality knows that the site is under construction
and is therefore dangerous. The rain waters were unexpected and
created further danger which would have normally not present and
the unfortunate person opted voluntarily on his own to try and
cross in that situation. In spite of not being at fault, the
petitioner voluntarily gave a heavy compensation to the legal heirs
of the deceased who were fully satisfied and have given in writing
to the petitioner and have also made a statement to this effect
before the relevant magistrate that the petitioner is not to blame
and that this was a purely accidental death. (Copy of the statement
of the father of the deceased is attached as Annex I)(v)That
however it appears that for some reason the respondents are bent
upon canceling the existing contracts of petitioner for the
purposes of awarding fresh contracts to their own favoured
contractors. The respondents were looking for an excuse and as soon
as the occurrence was reported in the press, the petitioner,
without enquiry and without any show cause, declared and decided
that the petitioner is guilty and ordered that the petitioner be
blacklisted for future projects. (vi)That in this connection it is
very interesting to note that the respondent No.3 at the behest of
the respondent No.2 evidently drafted and wrote, but never sent a
letter No CTE/TEPA/LDA/572 dated 15/08/2008 addressed to the
petitioner stating that due to non-compliance of the Clauses 13,
14, 15 and 20 of the contract a Pedestrian drowned into the rain
water and died and hence why not action should be taken against the
petitioner for gross negligence. This letter was delivered to the
petitioner on 18/08/2008. Without waiting for any response from the
petitioner or giving an opportunity of hearing or defense to the
petitioner, the respondent No.3 then issued another letter dated
17/08/2008 (which happened to be a Sunday) when the respondents
were not even working, stating that since no response has been
received from the petitioner to the previous letter dated
15/08/2008 (which letter was never even sent till 18/08/200)
therefore this office presumes that you have nothing to say at your
end, accordingly, you are hereby blacklisted for future projects.
(Copies of letter dated 15/08/2008 and 17/08/2008 are attached as
Annex J & K)(vii)That the said letter of 17/08/2008 was also
delivered to the petitioner at 4 pm on 18/08/2008 (which was merely
few hours after the delivery of letter dated 15/08/2008). It is
submitted that the manner in which the petitioner has been
blacklisted as narrated above, without giving an opportunity of
hearing and by trying to camouflage as if a show cause notice has
been given, smacks of malafide apparent on the face of the record.
The Peon book of 16/08/2008 of TEPA is clear evidence of this
illegality. (Copy of the Peon book of TEPA is attached as Annex L/1
& L/2).viii)That the petitioner vide letter No.KRC/4147 dated
21/08/2008 and letter No.KRC/4148 dated 22/08/2008 duly responded
to the letters dated 15/08/2008 and 17/08/2008 but to no avail,
hence this writ petition. (Copies of the letters are Annex M/1 to
M/8 & N/1 to N/9)(ix)That the respondent No.6 have initiated a
smear campaign in the media against the petitioner and in this
regard huge advertisements have been published on the front pages
of the newspapers (Jang, Nawa-i-waqt and Khabrain) stating that the
petitioner has been black listed for his negligence in the incident
of 12th August, 2008. The respondent No.6 has also made a
completely false statement that it paid a compensation of
Rs.500,000/- to the deceased. In fact the compensation was paid by
the petitioner in order to alleviate the loss of the legal heirs of
the deceased victim. (Copies of the advertisements in Jang and
Nawa-i-waqt are attached as Annex O & P)
(x)That the respondents are not allowing the petitioner to
participate in the bidding/tendering of other projects of the
government department merely due to the illegal and unwarranted
blacklisting letter of 17/08/2008. The livelihood of the petitioner
is in jeopardy now. (xi)That this and shall be a subject matter of
separate legal proceedings, it is pertinent to mention here that in
pursuance of the agenda to cancel all the contracts of the
petitioner the respondent No.3 on behalf of respondents No.2 has
also issued cancellation notices regarding the following projects
of the petitioner: -
a) Notice on Contract for Improvement & Rehabilitation of
Maulana Shaukat Ali Road from UBD Canal to Ferozepur Road (Chungi
Amer Sidhu), Lahore RD 0+000 to 3+500) (Section-I) vide letter
dated 22/08/2008.
b) Notice on Contract for Improvement & Rehabilitation of
Maulana Shaukat Ali Road from UBD Canal to Ferozepur Road (Chungi
Amer Sidhu), Lahore RD 3+500 to 5+600) (Section-II) vide letter
dated 22/08/2008.
c) Notice on Contract for Improvement & Rehabilitation of
Maulana Shaukat Ali Road from UBD Canal to Ferozepur Road (Chungi
Amer Sidhu), Lahore (Link Road-Jail Road to Ferozepur Road via
Katcha Jail Road) (Section-III) vide letter dated 22/08/2008.
d) Notice on Improvement & Remodeling of Khurshid Alam Road
from Shami Road to R.A. Bazar Lahore Cantt. vide letter dated
22/08/2008.
e) Notice on Improvement of Shami Road from Khalid Butt Chowk
vide letter dated 22/08/2008.
f) Notice on Construction of Pedestrian Overhead Bridge infront
of Kinnaird College Jail Road, Lahore vide letter dated
22/08/2008.
(Copies of the notices are attached as Annex Q/1 to
Q/6)(xii)That it is also pertinent to mention here that in order to
pressurize the petitioner the respondent No.3 has also filed an FIR
No.721/2008 inter alia against the petitioner. Petitioner is
contesting that FIR in accordance with law. It is submitted that
the FIR is also likely to be disproved against the petitioner
accordingly. Infact the legal heirs have filed statements and
affidavits in various proceedings which testify that the petitioner
is not guilty. (Copy of order of Judl Magistrate in the bail
petition of co accused Abdul Rab and Mazhar Abbas, recording the
statements of heirs of deceased before Judl Magistrate Model Town
are attached as Annex R) (Copies of affidavit and of heirs of
deceased in Abdul Rab case are attached as Annex S/1 to S/5)
(Receipt of compensation as Annex T) (Copy of the FIR is attached
as Annex U) (Copies of the affidavits of legal heirs of deceased in
case of State vs Saif Rehman & Khalid Rauf etc are attached as
Annex V/1 to V/6) 5.That briefly the letters dated 15/08/2008
giving show cause notice and the blacklisting letter dated
17/08/2008 are illegal and liable to be set aside inter alia on the
following:Grounds
A) That both letters dated 15/08/2008 (giving so called show
notice) and letter dated 17/08/2008 (the blacklisting letter) were
delivered to the petitioner within few hours on 18/08/2008. This
means that the petitioner was never given a show cause notice in
law and the black listing was done in violation of the judgments of
the Supreme Court of Pakistan and against the principles of natural
justice. This also shows that the decision of blacklisting had
already been done and the show cause notice was a mere formality.
On this ground alone the show cause notice is illegal and liable to
be declared as such by this Honble Court. B)That even if it is
assumed that the show cause notice was issued on 15/08/2008 which
is a Friday and received by the petitioner on the same day, the
letter does not disclose or specify as to within what time the
reply or defense has to be presented by the petitioner. In these
circumstances the law has to presume that the petitioner has
reasonable time within which to respond. The petitioner was
thereafter issued a blacklisting letter on 17/08/2008 which is a
Sunday and which clearly shows that there was no opportunity of
showing cause available to the petitioner. The petition has been
condemned unheard. As the blacklisting is a punishment in law it
cannot be awarded without giving sufficient opportunity of being
heard. The decision on the face of it is against the principal of
natural justice. The respondent in this respect had apparently
decided that the petitioner was guilty and did not even bother for
a reply. The respondent No.3 was obviously acting under the
directions and authority of respondent No.2 and hence did not have
the freedom of mind or the courage to follow the law and deny the
illegal demand or orders of his superior. Not only on this ground
is the action of blacklisting illegal but also exemplary damages
need to be imposed on the respondents for such blatant violation of
the law.C)That the letters of 15/08/2008 and 17/08/2008 are
contradictory and self-defeating. In the letter dated 15/08/2008
the petitioner has been given an opportunity to show a cause,
whereas under 17/08/2008 that opportunity has been taken away and
blacklisting is being done without giving any such opportunity to
the petitioner. It is submitted that the blacklisting being
contrary to the earlier dated 15/08/2008 is liable to be set aside.
D)That even on merits the case of the petitioner has to be fully
adjudicated and it is only if the petitioner is at fault or
negligence that action against the petitioner in accordance with
the contract be taken. This Honble Court is not required of course
in this writ petition to adjudicate upon the merits of the event of
12/08/2008 but with respect it is submitted that even the reference
to Clauses 13, 14, 15 and 20 in the letter dated 15/08/2008 are not
relevant. Clause 13 provides that lightening is to be provided in
case night work is carried on. The unfortunate event took place at
4:00 pm and hence there was no issue of light which is in any case
was provided. Clause 13.2 states that the contractor will maintain
at its own cost of all caution boards etc. as and when required by
the engineer in charge for the protection of the workers or for the
safety and convenience of the public. This was duly done but the
accident happened in spite of these warnings. Clause 14 provides
that the contractor is to ensure that unfinished work is not
damaged in the case of weather condition. Clause 14 accordingly
does not have relevance. Clause 15 of the contract provides that
the contractor is to supply his own materials and plant and
machinery as may be required by the engineer and that the
contractor will provide all fencing and lights required to protect
the public from accident and shall be bound to bear expenses on the
action by any person injured and pay damages to such a person.
Petitioner did provide all fencing and lights required to protect
the public from accidents. In fact the fence provided around the
drainage work was made of proper bricks. It was apparently because
the entire site was submerged with rain water and because the
unfortunate person decided to take the risk of going through the
water that no fencing or other warning could prevent his injury and
death. In fact Clause 16 negates the very basis of blacklisting
because it specifies that in case any action is brought for an
injury due to petitioners negligence then the petitioner would
defend such a case and pay damages, if necessary. The contract no
where provides that the petitioner would be declared guilty by the
respondents or blacklisted even though the petitioner has not been
sued by the injured party and the petitioners negligence has not
been proved in the court of law. As stated above, in this case, the
legal heirs of the deceased have stated on oath and confirmed that
the accident was not the fault of the petitioner but was purely an
accident of circumstances and the petitioner has also compensated
them in any case voluntarily. Hence there is no violation of Clause
15 as well. Clause 17 provides that the contractor shall provide
skilled engineers and technical engineers, which has no relevancy
to this case.
From the perusal of the above clauses it is obvious that the
action of blacklisting the petitioner, in pursuance of the
aforesaid clauses, is on the face of it wrong and illegal.E) That
even if it is assumed that the petitioner was negligent, the
contract does not provide for the petitioner to be blacklisted by
the respondents. To the contrary the contract and the law is that
if the petitioner has committed a breach of the contract and not
provided the safety requirements then the respondents are required
under the law to first demand from the petitioner to rectify the
breach and provide the necessary safety structures and if the
petitioner thereafter fails to do so then the respondents can issue
notice for termination of the contract in accordance with the
requisite clause. The contract further provides that in case the
petitioner disputes that allegation of breach or termination then
the petitioner can take the matter to arbitration and it is only
the award of the arbitration finally in accordance with law which
can then be the final decision with respect to their dispute. The
contract no where provided that the respondent can simply, on the
executive side, only because it is the Government, ignore the
contract and declare the petitioner blacklisted. It is
well-established by the superior courts of Pakistan that the
Government is as bound by the contracts and more so than the
private individuals and cannot act arbitrarily. The action of
blacklisting the petitioner without following the provisions of the
contract amounts to arbitrary and capricious exercise of powers
which is liable to be set aside by this court in exercise of its
constitutional jurisdiction.F. That it is a fundamental right of
the petitioner guaranteed under the Constitution of Islamic
Republic of Pakistan 1973 that no one can be condemned unheard and
no ones business can be curtailed or restricted except in
accordance with law. It is submitted that petitioner has invested
hundreds of million in the construction business which shall be
ruined due to the arbitrary and capricious nature of respondents
actions. It is the petitioners business to provide services for
engineering and construction of roads and highways and by
blacklisting the petitioner from future projects in this illegal
manner the respondents are violating the Constitution.G.That it is
now well established in various judgments and decisions of the
Supreme Court of Pakistan and the various High Courts that all
public authorities and functionaries, in their dealing with
citizens of the country, have to be fair, transparent, just and
above-board. An equally well established principle of law is that
all public authorities and functionaries must not use powers in an
unreasonable and arbitrary manner. By blacklisting the petitioner,
the respondents have exercised their powers in an unreasonable and
arbitrary manner. Hence this writ petition. H.That the public
functionaries, deriving their authority from or under law, are
obligated to act justly, fairly, equitably, reasonably, without any
element of discrimination and squarely within the parameters of
law, and if their actions are contrary to the above, such actions
are amenable to judicial review, hence this writ petition. The
action of blacklisting the petitioner is illegal because these
principles of law have been violated. 7.That the petitioner is
aggrieved of the aforesaid illegal, unlawful and malafide
conduct/scheme of the respondents for which no other adequate and
efficacious remedy is available to the petitioner except to invoke
the constitutional jurisdiction of this Honourable Court, hence,
this writ petition. Since the case involves the enforcement of
fundamental rights and blatant violation of the law by an authority
which is considered itself above all legal requirements and has
taken the law to its own hands, and because this august High Court
is custodian of such fundamental and private rights of the people,
this petition is only proper remedy available to the petitioner in
these circumstances.
PRAYERIn view of the circumstances mentioned above it is most
respectfully prayed that the impugned letters dated 15/08/2008 and
17/08/2007 may kindly be declared to be illegal and accordingly be
set aside. It be directed that the respondents shall take no
further action in respect of the blacklisting on the basis of the
letter dated 15/08/2008 or 17/08/2008. It is further prayed that it
be declared that the petitioner is not blacklisted for any of its
ongoing projects, or for which the petitioner has been
pre-qualified as well as any future projects with the respondents.
The respondents be further directed that petitioners may be allowed
to participate in tenders/bidding for government projects without
any let and hindrance.
It is also further prayed that the respondents be directed not
to take any action against the petitioner in respect of the
incident.It is further prayed that the ongoing projects of the
petitioner may not be cancelled rescinded or cancelled on the basis
of illegal blacklisting letter dated 17/08/2008. It is further
prayed that respondents may be directed to continue making
payments, including running bills, in respect of the on going
contracts strictly in accordance with the respective contracts. Any
other relief deemed to be just and fair may kindly also be granted
to the petitioner in the interest of justice.
PETITIONER
Through:
Syed Ali Zafar
Bar-at-law
CC. No. PLH No.234
Zahid Nawaz Cheema
Advocate High Court
CC. No. PLH No.2385
Muhammad Saqib Jillani
Advocate High Court
Mandviwalla & Zafar
Advocates
Zafar Chambers
Aziz Avenue,
Canal Bank, Gulberg-V
Lahore
CERTIFICATE1.As per instructions, this is the first petition in
this Honble Court on the subject.
2.The petition has been arisen out of the violation and
non-fulfillment of the provisions of law and the petitioner has no
other efficacious and speedy remedy at the moment.
Advocate
IN THE LAHORE HIGH COURT, LAHORE
Writ Petition No./2008
Khalid Rauf & Co. (Pvt.) Ltd.Petitioner
VERSUSGovernment of the Punjab through Secretary, C&W and
others.Respondents
WRIT PETITION UNDER ARTICLE 199 OF THE CONSTITUTION OF ISLAMIC
REPUBLIC OF PAKISTAN, 1973.
= = = = = = = = = = = = = = = = = = = = = = = = = = = = = = =
Affidavit of:Mian Khalid Rauf, Chief Executive Officer, Khalid Rauf
& Co. (Pvt.) Ltd., 24/3C, Messon Road, Link Lawrence Road,
Lahore.I, the above named deponent do hereby solemnly affirm and
declare as under:-
1.That the above named deponent has filed accompanying writ
petition before this Honble Court and the contents of the same may
kindly be read as an integral part of this affidavit.
2.That the contents of the accompanying writ petition are true
and correct to the best of my knowledge and belief and nothing has
been concealed thereof.
DEPONENT
VERIFICATION:
Verified on oath at Lahore on this day of August 2008 that the
contents of the above affidavit are true to the best of my
knowledge and belief.
DEPONENTIN THE LAHORE HIGH COURT, LAHORE
C.M. No./2008
In
Writ Petition No./2008
Khalid Rauf & Co. (Pvt.) Ltd.Petitioner
VERSUSGovernment of the Punjab through Secretary, C&W and
others
.RespondentsAPPLICATION UNDER SECTION 151 CPC FOR GRANT OF
INTERIM RELIEF.Respectfully Sheweth:
1.That the petitioner has filed the accompanying writ petition
the contents whereof for the sake of convenience and brevity may
kindly be read as an integral part of this application.
2. The petitioner has a strong prima facie case and there is
very likelihood of its success.
3. The balance of convenience and inconvenience lies in favour
of the petitioner.
4. That the respondents are unduly harassing the petitioner by
threatening to stop the petitioner from working on its on going
projects and in this regard a malicious campaign has also been
initiated by the respondents in the print media. The respondents
actions are not only causing financial losses to the petitioner,
but his reputation is being immensely tarnished.
5. That in case the interim relief is not granted, the
petitioner shall suffer irreparable loss and injury.6. That if the
impugned letters dated 15/08/2008 and 17/08/2008 are not suspended
and the respondents are not directed to stop their malicious
campaign, the petitioner shall suffer irreparable loss and injury.
PRAYER
It is respectfully prayed that in pending the disposal of the
subject writ petition the impugned letters dated 15/08/2008 and
17/08/2008 may kindly be suspended and the respondents be directed
to immediately halt their smear campaign against the petitioner. It
is further prayed that the respondent be directed not to take any
further action against the petitioner till the disposal of the
titled writ petition. It is further prayed that during the pendency
of the writ petition, the respondents may be directed to continue
making payments, including running bills, in respect of the on
going contracts strictly in accordance with the respective
contracts.
Pending disposal of this petition an ad interim relief in the
above manner may also kindly be granted to the petitioner.
Any other relief deemed to be just and fair may kindly also be
granted to the petitioner/applicant in the interest of justice.
PETITIONER/APPLICANTThrough:
Syed Ali Zafar
Bar-at-law
CC. No. PLH No.234
Zahid Nawaz Cheema
Advocate High Court
CC. No. PLH No.2385
Muhammad Saqib Jillani
Advocate High Court
Mandviwalla & Zafar
Advocates
Zafar Chambers,
7/B-1, Aziz Avenue,
Canal Bank, Gulberg-V
Lahore
IN THE LAHORE HIGH COURT, LAHORE
C.M. No./2008
In
Writ Petition No./2008
Khalid Rauf & Co. (Pvt.) Ltd.Petitioner
VERSUSGovernment of the Punjab through Secretary, C&W and
others
.RespondentsAPPLICATION UNDER SECTION 151 CPC FOR GRANT OF
INTERIM RELIEF.
Affidavit of:Mian Khalid Rauf, Chief Executive Officer, Khalid
Rauf & Co. (Pvt.) Ltd., 24/3C, Messon Road, Link Lawrence Road,
Lahore.I, the above named deponent do hereby solemnly affirm and
declare as under:-
1.That the above named deponent has filed accompanying
application for stay before this Honble Court and the contents of
the same may kindly be read as an integral part of this
affidavit.
2.That the contents of the accompanying application for stay are
true and correct to the best of my knowledge and belief and nothing
has been concealed thereof.
DEPONENT
VERIFICATION:
Verified on oath at Lahore on this ______ day of August 2008
that the contents of the above affidavit are true to the best of my
knowledge and belief.
DEPONENTIN THE LAHORE HIGH COURT, LAHORE
C.M. No./2008
In
Writ Petition No./2008
Khalid Rauf & Co. (Pvt.) Ltd.Petitioner
VERSUSGovernment of the Punjab through Secretary, C&W and
others
.RespondentsAPPLICATION UNDER SECTION 151 C.P.C. TO DISPENSE
WITH FILING OF CERTIFIED COPIES OF ANNEXURES WITH THE WRIT
PETITION.
Respectfully Sheweth:
1. That the petitioner has filed the accompanying writ petition
in which no date of hearing has been fixed so far.
2. That the petitioner has annexed certain uncertified copies
alongwith the titled petition.
3. That the petitioner is making serious efforts to secure the
certified copies of the said documents and shall place the same on
record as and when the same are made available to the applicant and
till then the uncertified copies placed on the file may be taken
into consideration.
It view of the above it is most respectfully prayed that the
present application may be allowed and the certified copy may be
dispensed for the time being and the copies already placed on file
may kindly be taken into consideration.
PETITIONER
Through:
Counsel
Mandviwalla & Zafar
Zafar Chambers
7/B-1, Aziz Avenue
Canal Bank, Gulberg-V
Lahore
IN THE LAHORE HIGH COURT, LAHORE
C.M. No./2008
In
Writ Petition No./2008
Khalid Rauf & Co. (Pvt.) Ltd.Petitioner
VERSUSGovernment of the Punjab through Secretary, C&W and
others
.Respondents
APPLICATION UNDER SECTION 151 C.P.C. TO DISPENSE WITH FILING OF
CERTIFIED COPIES OF ANNEXURES WITH THE WRIT PETITION.
Affidavit of:Mian Khalid Rauf, Chief Executive Officer, Khalid
Rauf & Co. (Pvt.) Ltd., 24/3C, Messon Road, Link Lawrence Road,
Lahore.I, the above named deponent do hereby solemnly affirm and
declare as under:-
1.That the above named deponent has filed accompanying
application for stay before this Honble Court and the contents of
the same may kindly be read as an integral part of this
affidavit.
2.That the contents of the accompanying application for stay are
true and correct to the best of my knowledge and belief and nothing
has been concealed thereof.
DEPONENT
VERIFICATION:
Verified on oath at Lahore on this ______ day of August 2008
that the contents of the above affidavit are true to the best of my
knowledge and belief.
DEPONENTIN THE LAHORE HIGH COURT, LAHORE
Writ Petition No./2008
Khalid Rauf & Co. (Pvt.) Ltd
.Petitioner
VERSUSGovernment of the Punjab through Secretary, C&W and
others
.RespondentsINDEX
S.No.Description of DocumentsDatedAnnexurePages
1.Ground of writ petition alongwith affidavit1-16
2.Memorandum and Articles of AssociationA&B17-34
3.Copy of Board ResolutionC35-36
4.Copy of petitioners profile with a list of its
achievementsD37-47
5.Copy of the ContractE48-113
6.Acceptance letterF114-116
7.Site drawingsG117-137
8.Copies of the photographsH/1 to H/3138-140
9.Copy of the statement of the father of the
deceasedI141-142
10.Letter from Respondent No.3 dated 15/08/2008 J143
11.Letter from respondent no.3 dated 17/08/2008 K144
12.Copy of the Peon book of TEPA16/08/2008L/1 &
L/2145-146
13.Letter No.KRC/4147 dated 21/08/2008 from the petitionerM/1 to
M/8147-155
14.Letter No.KRC/4148 dated 22/08/2008 from the petitionerN/1 to
N/9156-169
15.Copy of the advertisement in Jang O170
16.Copy of the advertisement in Nawa-i-waqt P171
17.Copies of the notices issued by the respondent 22/08/2008Q/1
to Q/6172-177
18.Copy of order of Judl. Magistrate in bail petition of co
accused Abdul Rab and Mazhar Abbas, recording the statements of
heirs of deceased before Judl Magistrate Model Town R178-182
19.Copies of affidavits of heirs of deceased in Abdul Rab
caseS/1 to S/5178-192
20.Receipt of compensationT193
21.Copy of the FIRU194-195
22.Copies of the affidavits of legal heirs of deceased in case
of State vs Saif Rehman & Khalid Rauf etcV/1 to V/6196-207
23.Application to dispense with filing of certified copies of
annexures with the writ petition alongwith affidavit208-209
24.Interim Application alongwith affidavit210-213
25.Power of Attorney
PETITIONER
Through:
COUNSEL
Mandviwalla & Zafar
Zafar Chambers
7/B-I, Aziz Avenue,
Canal Bank Gulberg-V,
Lahore