General instructions
DOCUMENT STATUS: FOR APPROVAL
E15.08.04Revised after DRCR-M1&2-I-0037
D30.01.04Fourth issue
C09.10.03Third issue
B30.09.04Second issue
A14.09.03First issue
Rev.DateDescriptionDrwn.Chkd.Appd.
UONG BI 300 MW EXTENSION POWER PLANT
Owner:
EPC Contractor:
Subcontractor:
Document Title:
Power Island
Measuring, Control and Logic Function Concept
Project No.Format: A4Total Pages: 12
Designed by:
FunctionNameSignDate
Approved Seredenko 30.01.04
CheckedShvydchenko25.01.04
Draw Seredenko20.12.03
Document No.: UBEX1-M1&2-I-51-0011Date:
15.08.04Rev:
E
File:UBEX1-M1&2-I- 51-0011eFormat 4
1. ForewordThe operation and control concept provided in this
document represents general description of the Unit control
principles but does not detail the control logic.
More detailed information of the interactions between the
different systems reference will be provided in the corresponding
engineering documents:
P&I diagrams;
Technical Descriptions of the different systems;
Functional Control Diagrams;
Measuring Point Lists;
Alarm & Interlock Lists;
Command Signal Lists;
Information Transfer Lists;
etc.
Systems not determining the Unit operation and control concept
are not considered in this document.
2. Requirements
The coal-fired Unit is designed for operation in the base mode
of electric load control from the minimum load of 90 MW up to the
rated load of 303 MW.
The Unit is able to be operated continuously in the range of
70-100% of the nominal output power at coal firing.
The Unit is also able to be operated continuously in the range
of 30-70% of the nominal output power at coal firing using the
reduced fuel oil.
The minimum load admissible for long-term period operation of
the Unit is 30% of the rated.
The Unit operates in the constant pressure mode in the range of
90%-100% of the nominal rated load and the Unit is able to operate
in the sliding pressure mode at normal operating conditions in the
range of 30%-90% of the rated output load.The Unit is designed for
base load operation.
The admissible level of the load changing rate in the adjusting
range is 1 - 3% of the nominal power per minute.
These conditions are not applicable during the Unit
start-up.
The Unit is capable to provide maximum load 318,15 MW at the
turbine valves fully opened.
Power reserve above the nominal is provided to take part in
frequency regulation in the grid of 220 KV.
This reserve is provided by the control valves of the steam
turbine which should not be fully opened at the rated load 303
MW.
The Unit is be capable to withstand sudden loss of the load
318,15 MW without tripping. The Unit remains on plant auxiliaries
load or on idle run using the turbine bypasses and is capable to
resume maximum load within the shortest time.
After total unloading the Unit operation at the idle run or at
the plant auxiliary load is limited to 120 minutes.
The Unit control system will provide the automatic mode of the
Unit operation by the operators command from the moment of the
boiler is available for ignition.
During the start-up the boiler ignition, pressure raising and
the turbine run up, loading up to the set power are effected
automatically.
The operator at the Plant Control Room (PCR) takes part in the
Unit control only with the following purpose:
selection of the working and stand by equipment;
setting of the required load;
separate command for start-up or switching off the selected
group of the Unit equipment;
separate command for the generator synchronization after
receiving the permission from the power grid dispatcher.
Automatic start-up is also effected for the Unit auxiliary
equipment.
The Unit automatic control is provided for normal operational
modes complying with the project in all respects. If the Unit is
not used in accordance with the project i.e. if part of the
equipment is put shutdown (i.e. some stand by mechanisms or
auxiliary equipment, without which it is permissible to operate the
Unit, e.g. part of the regenerative heaters of the turbine) then
this equipment is controlled manually.
Automatic protections, closed and opened control loops provide
the safe operation of the Unit within the manual control mode.
The Unit is also started up in the manual control mode after
considerable overhauls or because of necessity to perform tests
during the start-up.
The task of the automatic control system is to keep operating
parameters and in general the operation of the equipment in certain
limits at changing the operation modes. If due to failure of the
equipment or faults with automatic devices the process exceeds the
above mentioned the limits but there is no necessity to trip the
Unit the actuation of non urgent alarm is provided.
At the same time such automatic operations as:
- load limitation;
- load decreasing;
- automatic start-up of the auxiliary equipment;
- switching off, if possible, faulty equipment, etc.
will be effected to transfer the Unit into the mode providing
its long-term operation.
In case of a trip of the 220 KV circuit breaker in the
switchyard of the Unit due to external fault the Unit remains in
operation providing house load.
The subsequently synchronization of the turbine-generator unit
is effected automatically by the operators command and the Unit
coordinator effects necessary control functions for preparation of
automatic load restoration.
The Unit cannot be start-up at the inhibiting action of the
protections.
In case of two or more excess plants or mechanisms (drives) the
automatic switching functions are provided.
All valves, gate valves, etc. which should change their position
in the process of the operation or under the safety requirements
during start-up, trip and normal operation are equipped with motors
and are controlled automatically and remotely. If during start-up
some actions (air displacement, draining, etc.) are not to be done
at the strictly fixed moments and could be performed some time
later (eg. within 12 hours), then such actions are performed by a
plant attendant by means of manual valve.
Manual valves, gate valves, etc. are used for maintenance, first
filling up, air displacement and draining.
3. The Unit Main Features
3.1 Power Generation:
The electric power generation supplied to the grid is three
phases of 50 Hertz AC, at a nominal voltage of 220 kV after the
Main Step-Up Transformer.
The total power output of the Unit is 303 MW at the design
conditions and the main fuel as specified in the Contract (i.e.
ambient temperature = 32.2C, cooling water temperature = 26C).
3.2 Standard Voltages:
The following voltages rated values are applied:
Transmission voltage220 kV
The generator voltage19 kV
The intermediate voltage 11 kV
The medium voltage bus
(3-phase, 3 wire system)6.6 KV
The low voltage bus
(3-phase, 4 wire system)400 V
The low voltage bus
(2 wire system)230 V
Uninterrupted Power Supply (UPS)400/ 230 V
Main DC voltage220 V DC
DC voltage for electronic equipment48 V DC
Regulating valves with thyristor amplifiers24 V DC
The rated frequency of the AC voltages is 50 Hz.The frequency
variation range is +/- 5%.
3.3 Fuel Supply:
3.3.1 Coal supply and firing system
Coal is the main fuel.
Coal is delivered from fuel supply to the pulverized coal
system.
Four pulverized coal systems are provided:
Each system has the following equipment:
raw coal bunker;
bayonet gate;
raw coal feeder;
ball-tube mill;
separator;
pulverised coal cyclone collector;
mill fan.
Each two pulverized coal systems operate for its pulverised coal
bunker. There are two pulverised coal bunkers are provided.
Pulverized coal is supplied to the boiler burners through the
pulverized coal feeders, located at the outlet from the pulverized
coal bunkers, by means of high concentration pulverized coal
system. Pulverized coal delivery is effected by air from 2x100% air
blower.
The secondary air supply to the burners is effected by two FD
fans. Primary air supply is effected by four primary-air fans.
Mill exhausters provide discharge of dusty air from cyclone
collectors to the discharge nozzles of the boiler furnace.
Coal design parameters for the mills are as follows:
- ash 31.0 wt%
-total moisture 12.00%
- surface moisture 10%
- self- moisture 2.0%
- Hargrove milling index (HGI) 40
- raw coal average size maximum 20 mm
The mills provide the following degree of fineness min. 90%
through the sieve with the mesh 200.Total capacity of raw coal
bunkers and pulverised coal bunkers provides 14 hours of the boiler
operation at the maximum steam output.At that:
raw coal bunker capacity provides 10 hours of the boiler
operation at the maximum load (BMCR);
pulverised coal bunker capacity provides 4 hours of the boiler
operation at the maximum load (BMCR).
3.3.2 Fuel oil supply and firing system
Fuel oil is the back-up fuel.Fuel oil is used for the Boiler
ignition and lighting at firing solid fuel in the range 30%-70% of
the nominal output.Fuel oil firing system provides 40% thermal load
of the (BMCR) duration steam output.Fuel oil firing system is
designed for continuous operation.Fuel oil firing system
includes:
fuel oil intake and storage system;
2x100% fuel oil pumps of the 1st stage;
2x100% fuel oil pumps of the 2nd stage;
fuel oil cleaning filters;
fuel oil heaters;
fuel oil nozzles and auxiliary equipment.
Fuel oil is heated by steam heaters in the fuel oil storage
tanks and fuel oil supply system. Minimum fuel oil heating
temperature is 22C.
The boiler fuel oil pumps are able to start at fuel oil
temperature 22C.For fuel oil firing the atomising steam fuel oil
nozzles are used.The fuel oil nozzles are of withdrawable
construction but on the lower elevation where they are permanently
in the burners are cooled by steam.
The fuel oil nozzles are equipped with electric devices of fuel
oil ignition and flame monitoring.The flame monitoring for each
kind of fuel is provided by separate flame scanners. Besides, the
general flame monitoring in the boiler furnace and monitoring
cameras system are provided.
The characteristic of the main and back-up fuel is mentioned in
ITB (Book 4.V1 Part A1 General Technical Requirements, paragraph
2.1.3.2).3.3.3 Cooling water supply
Cooling water supply is effected from the circulation water pump
station which has 2x50% circulating water pumps for the Unit
auxiliaries.The designed value of the cooling water temperature is
26C.Long-term operation of the turbine at the cooling water
temperature 30,5C is possible.In order to limit the growth of water
organisms the chlorination system in the circulating water pump
plant area should be provided for water chlorination in the top
flanges area.Each input pipeline of the circulating water should
have debris filter with the mesh size approx. 10 mm.The ball
cleaning system is used for cleaning of the condenser tubes from
mineral and sludgy sediments by means of elastic balls made of
porous rubber.When the ball cleaning system is in operation the
load does not decrease.3.3.4 Water treatment systemThe influent
water for the water treatment plant is the water from the Uong Bi
river, the chemical composition of which is indicated in p. 2.1.3.1
ITB Book 4. VI. Part 2.1.Distilled water quality for boiler make-up
after water treatment plant must satisfy the following rate, not
more:General hardness, g/dm3 ................................. ...
0,2
Silicon acid content in translation to SiO2, g/dm3
........................15
Sodium compound content, g/dm3 ......... 5
Specific electric conductivity, S/m...................... .....
0,15
Chloride content, g/dm3 .. 3
Sulphate content, g/dm3 .... .. 3
General organic carbon, g/dm3 ... .. 300
4. Major Components of the Unit4.1 The Steam Generator
The steam generator -920-17, 6-543 (Model 318.) is the drum,
gas-tight steam generator with natural circulation, with balanced
draft.The boiler is designed for operation with the condensing
turbine K-300-170-1P and the generator TBB-320-2T3.The main fuel is
pulverised anthracite coal, the back-up fuel is fuel oil.The boiler
is equipped with sixteen swirl burners mounted on the front and
rear walls of the furnace in the opposite order on two decks by
eight burners per each deck.Each burner is equipped with the
atomising steam fuel oil nozzle.
Eight nozzles of the drying agent discharge are located over the
burners in the opposite order on the front and rear walls of the
furnace.
Brief characteristic of the boiler ander nominal load (303
MW):
rated steam output is 861,32 t/h;
drum pressure is 195 kgf/cm2;
main steam temperature is 543C;
reheat steam temperature is 543C;
main steam pressure is 179 kgf/cm2;
reheat steam pressure is 38.9 kgf/cm2.
4.2 The Steam TurbineThe steam turbine K-300-170-1P is a tandem
three-cylinders unit consisting of single-flow HP cylinder with the
flow turn, single-flow IP cylinder and double-flow LP cylinder.HP
cylinder has nozzle steam distribution which is performed in the
form of two HP valves sets consisting of one stop and two control
valves.HP cylinder blading is of the reactive type. HP cylinder has
eighteen stages, the first one of them is the control stage.After
HP cylinder the steam is supplied to the reheat.IP cylinder has
throttle steam distribution which is performed in the form of two
valves sets consisting of one stop and one control valves.IP
cylinder blading is of the active type. IP cylinder has fifteen
stages.
All stop and control valves are of the balanced type.After IP
cylinder the steam is supplied by two receiver pipes to LP
cylinder.
LP cylinder has four stages in each flow. The length of the last
stage turbine rotor blade is 1000 mm.LP cylinder steam inlet is
effected by two pipelines located in the upper part of the
cylinder.HP, IP and LP rotors are solid-forged.
The turbine rotors and the generator rotor are connected by
rigid couplings.
The rotor rotation direction is clockwise looking from the HP
cylinder towards the generator.The rotor rated rotation speed is 50
sec.-1 (3000 r/min.).The turbine is designed for operation at the
following rated parameters:
main steam absolute pressure ahead of stop valves of HP
cylinder. 171 kgf/cm2;
main steam temperature ahead of stop valves of HP
cylinder...... 538C;
main steam absolute pressure ahead of stop (shut off) valves of
IP cylinder.. 37,57 kgf/cm2;
steam temperature after the reheat ahead of stop (shut off)
valves of IP cylinder...... 538C;
design absolute pressure in the condenser at the cooling
water
temperature of 26C 0,065 kgf/cm2.
The design cooling water temperature 26,02C.
The mass flow of main steam at the rated parameters. 861,32
t/h.
The maximum mass flow of main steam at the rated
parameters 920,0 t/h.4.3 The Main CondenserThe turbine condenser
is of two-flow, single-pass on the cooling water side design. The
condenser is designed to operate with brackish water. The cooling
surface area is 17900 m2.The rated volume flow of the cooling water
is.. 38580 m3/h.The hydraulic resistance of the condenser at the
rated flow of the cooling water is max. .. 0,50 kgf/cm2.The maximum
admissible overpressure of the cooling water in the condenser water
boxes is . 2,5 kgf/cm2.The turbine is able to operate with one half
of the condenser that allows cleaning other half of condenser
during of the turbine activity.The supply and discharge of the
cooling water from each half of the condenser is separate which
enables to clean the half of the condenser when the turbine is in
operation.The condenser is mounted on spring supports for
compensation of thermal expansions.
The condenser shell is welded of sheet carbon steel. The tubes
of condensing surface are made of titanium, the tube sheets are
made of carbon steel coated with titanium.The air-steam mixture
evacuation from the condenser is effected by steam-jet ejectors.The
working steam of the ejectors is the steam from the auxiliary
header with the pressure 14 kgf/cm2 and from the deaerator vented
steam line.4.4 The GeneratorThe steam turbine is connected to the
synchronous three-phase AC generator of TBB-320-2T3 type which has
combined cooling (water and hydrogen) and static excitation
system.The generator has the following technical specification:
total power 356.5 MVA;
active power 303 MW;
generator output voltage 19 KV;
stator current 10830 A;
coefficient of efficiency 98,7%;
frequency 50 Hz;
rated hydrogen pressure 4.0 kgf/cm2;
maximum hydrogen pressure 5.0 kgf/cm2;
cooling hydrogen temperature 42C;
distilled water temperature in the stator winding 40C.4.5 The
Turbine Bypass SystemThe turbine bypass system provides:
- keeping of main steam and reheat steam pressure required for
the Turbine start-up;
- uninterrupted operation of the Unit (operation with
auxiliaries load) in case of disconnection from the grid and total
load runback.4.5.1 HP BYPASS
1 x 60 % HP steam bypass plant connects the main steam lines
with the cold reheat lines. Main steam pressure is reduced by
throttling in the steam valve.Steam cooling is provided by water
injection from the feed water pumps pressure header. The bypass
valve has a hydraulic drive with the closed fault-tolerant
position.4.5.2 LP BYPASS2 x 50% LP steam bypass valves are located
near the turbine and connect the hot reheat steam system with the
turbine condenser. Hot reheat steam pressure is reduced by
throttling in the steam valve, hot reheat steam temperature is
decreased by water injection from the condensate pumps pressure
header. The valves have hydraulic drives with the closed
fault-tolerant position.4.6 The Air-Flue Gas Plant4.6.1 Forced
Draft Fans2x70% forced draft fans are provided for supplying
secondry air to the burners.The forced draft fans are of
centrifugal type with aerodynamic blade and hydraulic coupling for
rotation speed control.The guide vanes are not provided.4.6.2
Induced Draft Fans2x70% induced draft fans are provided for
evacuation of flue gases from the boiler and atmospheric emission
through the Flue Gas Desulphurization system and the chimney.The
induced draft fans are of centrifugal type with aerodynamic blade
and hydraulic coupling for rotation speed control.The guide vanes
are not provided.4.6.3 Primary Air Fans4x25% primary air fans with
the constant rotation speed are provided for supplying primary air
to the boiler burners.4.7 DeaeratorThe Deaerator provides water
deaeration at the pressure corresponding to the current load of the
Turbine and also at the operation with low pressure heaters
partially off (LPH-3).Increasing pressure thermal deaerator with
horizontal column has the following characteristics:
- rated output 1000 t/h;
- absolute rated working pressure.. 11,0 kgf/cm2;
- design pressure, gauge pressure. 10,35 kgf/cm2;
- design temperature. 200C;
- water temperature rise at the rated output.. ~33C;
- dissolved oxygen content in the deaerated water
at the Deaerator outlet, maximum.. 7 g/kg;
- dissolved oxygen content in the main condensate
at the Deaerator inlet, maximum 20 g/kg.At changing the rated
load of the Unit from 30% to 105% of the nominal the Deaerator
should operate in sliding pressure mode at changing the working
pressure in the Deaerator shell from 2,85 to 10,38 kgf/cm2 in
accordance with the pressure in the Turbine extraction.In the load
range from 30% to 15% of the nominal the Deaerator operates at the
constant working pressure in the Deaerator shell in the possible
range from 1,2 to 2,85 kgf/cm2 (set by operator) and water heating
in the Deaerator from 40 to 70.The Deaerator provides stable
operation during Turbine load runback from nominal to bypass
operation at the output not more than 30% of the nominal, pressure
2,85 kgf/cm2 and water heating in the Deaerator from min. 40 to
saturation temperature.5. Steam-Water CycleThe steam-water cycle is
described in brief as follows:Condensate collected in the condenser
is supplied to the feed water deaerator by means of 2 x 100%
condensate pumps. The pumps operate at fixed speed. The condensate
flow to the Deaerator and feed water storage tank is controlled by
two control valves downstream the pumps. The pumps are protected by
minimum flow valves.The condensate is heated in the condenser of
gland steam supplied from glands labyrinths of the turbine (gland
heater) and in three LP heaters.From the feed water tank the feed
water is transferred to the boiler by means of 3 x 50% feed water
pumps, equipped with variable speed couplings.Between the boiler
feed pumps and the boiler economizer the feed water is heated in
two HP heaters and steam cooler of HPH 5.The flow control of the
boiler is established before HP heaters.The feed-water on
injections to superheater goes from a pressure piping of the boiler
feed pumps before flow control valves. The feed-water on injections
to reheater goes from a pressure piping of feed pumps before flow
control and from intermediate stage of the boiler feed pumps.Feed
water is also utilized as spray water to the HP bypass plant and
sprays to the Boiler.Superheated steam generated in the boiler is
supplied to the turbine connected to the generator.The steam
extractions from the turbine and cold reheat line provide the
heating of feed water and condensate in HP and LP heaters,
deaerator.The data of the steam extractions for regeneration at the
rated power mode at the rated parameters according to the p.4.2,
regeneration system being totally switch on and absence of
additional steam extractions are listed in the table 1.
Table 1
Steam consumerSteam parameters in the extraction chamberMass
flow of the turbine extracted steam, t/h
Absolute pressure, kgf/cm2Temperature, C (relative humidity,
%)
HPH No.640,9932789,8
HPH No.517,2342233,8
Deaerator9,6834126,6 to 12,8
LHP No.34,2123851,0
LHP No.21,2111637,8 to 1,9
LHP No.10,26365,7 (5,4)22,7
Exhaust steam of the LP cylinder is led to the main condenser
where steam is condensed and deaerated.Air extraction from the
condenser during start up as well as during normal operation is
provided by means of a steam ejector system.Steam turbine gland
sealing during start-up is provided from the auxiliary steam system
(auxiliary header). During normal operation it is taken from the
turbine (self-gland).6. The Unit Control System6.1 Degree of
AutomationThe Unit control system utilizes advanced microprocessor
technology, which provides the high degree of automation.The
control of a technological process of the unit is executed as
follows:
main process control is performed from the Plant Control Room
(PCR);
water treatment system control, etc. is performed from the
corresponding Local Control Rooms (LCR).All signals required for
control and monitoring of the equipment are supplied to the
corresponding control room. The information exchange between PCR
and Local Control Rooms is provided.Various other station equipment
systems are provided with local control units (PLC). The equipment
operates fully automatically. All necessary control and monitoring
functions are carried out by the local control units. Remote
operation and control (on/off commands and respective feedback
signals) for the local control units are executed only via PCR or
corresponding LCR. Remote individual operation and control are not
executed via the PCR or corresponding LCR.Start-up, trip and other
operation modes set beforehand are performed by the piggy-back
control function of the distributed control system from the
PCR.Cold, warm and hot start-ups of the Unit are absolutely
automated starting from the boiler ignition but for the Generator
synchronization the operator confirmation is required.At the very
hot start-up with the operation of the turbine bypasses and
auxiliary equipment being in the hot stand-by the total automation
up to the start-up level by one pushbutton is provided with an
operator confirmation for the Generator synchronization.Normal
operation, load variations and run backs are performed
automatically.All processes control is effected from PCR or
corresponding LCR through PWS (Operator Workstation) as man-machine
interface.6.2 Control System StructureThe control system structure
has vertical hierarchy and is independent of the Unit protections
system.6.2.1 Control of Main Plant.
The control system has the following structure and control
levels:6.2.1.1 The structure of the open loop controls:
Level 1: Unit Level Control:
- Boiler Control;
- Turbogenerator Control;
- the common Unit equipment control.Level 2: Group Control level
(FG)Individual control for each function group (FG) within the Unit
level control.Level 3: Sub Group Control Level (FG-S).Individual
Control for each Sub-Group within the group level control.Level 4:
Drive Level ControlIndividual drive control within the subgroup
level control, or individual control beyond the subgroup level
control (as the trip of separate mechanisms).The drive control
level is the lowest automation level, control and monitoring for
each drive is effected individually, including the processing of
protection and interlocking signals which cannot be avoided in the
remote control mode.The group and subgroup control level perform
all tasks for automatic start and stop of the respective mechanisms
groups. The Function Groups control clearly defined particular
process depending on the technological structure.The following
functions are provided at the function groups (subgroups) control
level:- information exchange between the groups including the Unit
Coordinator;
- formation of the control commands sequence in accordance with
the technological algorithm;
- forming of the information about sequence program carry-out
and completion;
- checking of the specified process conditions taking into
account the time factors (checking of the execution terms of the
functional group step actions within the defined time).The Unit
control level coordinates the operation of the function groups of
major parts of the Unit, such as the Boiler, the Turbine, the
Generator and also evaluates state of the Unit equipment and takes
a decision with regard to start-up modes (cold, warm hot start-up,
etc.), shutdown modes (scheduled, emergency, etc.) and also the
other operation modes (load runback up to the safe load or
auxiliary load, etc.)6.2.1.2 The structure of the closed loop
controls:Level 1: The Unit Level ControlThe Unit Coordinator.Level
2: The Group Control levelMaster controllers of the functional
group parameters control.Level 3: Sub Group Control LevelIndividual
and submaster controllers.Level 4: Drives Level ControlThe
regulators operate under the standard control rules on the
actuating devices with constant rotation speed. Commands to control
actuating devices are pulse-modulating.On moving the regulators
into automatic mode the following types bumpless switching are
provided:
- for the set value of the controlled parameter (dynamic
balancing with the rate of changing the current value of the
controlled parameter set beforehand);
- for the current value of the controlled parameter (static
balancing).Bumpless switching on is provided as at automatic step
sequenser step logic as at remote (operator) switching of the
regulator.Automatic switching off the regulator with change-over to
remote control of the regulating device and corresponding alarming
is performed in the following cases:
- at failure of the sensor measuring the controlled
parameter;
- at failure or lack of power supply to the scheme of the
regulating device control.6.2.2 Control of Auxiliary Equipment
One of such systems for example is the water treatment
plant.These control systems have the following structure and
control levels:Level1: The Group Control level (FG).This level
starts and controls the slave subgroups (FG-S) of open and closed
control loops automatically and in the required sequence.Level 2:
Sub Group Control Level (FG-S).Individual control for each subgroup
within the limits of the Group Control Level.Level 3: Drives Level
Control.These systems will be operated and controlled separately
from the corresponding LCR.All the control levels are accessible
from LCR and only Group Control Level is accessible from PCR.6.3
Main Open Loop Controls (Discrete Control)The single function
groups are combined at the Unit level within the main function
groups of the boiler, turbogenerator and common unit equipment in
order to obtain the overall automatic function of the process.6.3.1
The Unit Coordinator
The Unit Coordinator automatically and in the required sequence
starts the boiler coordinator, the turbogenerator coordinator,
functional groups of the common station equipment.6.3.2 The Boiler
Coordinator
The Boiler Coordinator controls the boiler function groups (FG)
of the upper control level within the Unit level limits.These
function groups, operated in the required sequence, start the
automatic ignition and loading of the boiler and will keep the
boiler metal conditions within the control system limits.6.3.3 The
Turbogenerator Coordinator
The turbogenerator coordinator controls the function groups (FG)
of the turbine upper control level operating within the Unit level
limits.These function groups in the required sequence, start the
groups, the automatic start and loading of the turbine up to the
set power , with all that the control system limits of the turbine
Stress Monitor will be kept.6.3.4 The Common Station Equipment
Function Group
This function group in the required sequence effects the start
of the Unit auxiliary equipment.Appendix 1 contains the structural
scheme of the Unit Discrete Control.
If necessary the List of functional groups could be changed.6.4
The Main Closed Control Loops of the Unit (Analogue Control)The
single controllers are combined at unit level within the Unit
Coordinator limits in order to obtain the overall process automatic
control.The structural scheme of the Unit automatic control is
indicated in the Appendix No.2.6.4.1 The Unit Coordinator (Unit
Master)
The Unit coordinator operates interacting with the Boiler
Master, forming the set value on fuel flow for the fuel controller
and the Turbine Controller governing the control valves of the
Turbine.Together with the above regulators the Unit Master provides
the following modes of the Unit control:
- Manual mode (Mode a);
- Boiler follows mode (Mode b);
- Turbine follows mode (Mode c);
- Local Coordinated mode (Mode d);
- Remote Coordinated mode (Mode e).6.4.1.1 Manual mode of the
Unit controlThere are three possible modes of the manual
control:Manual mode 1. In this mode all regulators are switched
off. Control of the Turbine, fuel and air supply to the Boiler is
effected by operator remotely from PCR.Manual mode 2. In this
control mode of the Turbine and fuel supply to the Boiler is
effected by operator remotely from the PCR.Air flow to the Boiler
is controlled by the common air (FD fans) regulator according to
the ratio fuel-air without correction on oxygen.Manual mode 3. In
this mode the Turbine control is effected by operator remotely from
PCR. The fuel regulator is in automatic mode and controls fuel
supply to the Boiler according to the command from the Unit
coordinator. Regulator of the steam pressure ahead of the Turbine
is disconnected from the fuel regulator. Common air regulator is in
operation according to the ratio fuel-air.6.4.1.2 Boiler follows
ModeIn this mode the Turbine control is effected by operator
remotely from PCR. The common air regulator is in operation. The
fuel regulator is in the automatic mode and keeps the steam
pressure ahead of the Turbine (the regulator of the steam pressure
ahead of the Turbine is connected to the fuel regulator). The
regulator of the steam pressure ahead of the Turbine can operate in
the mode of keeping the constant pressure (170 kgf/cm2) or in the
mode of sliding pressure. At operation in the sliding pressure mode
the task to the regulator is formed depending on the Unit load. In
the Boiler follows mode the regulator of valves position and
frequency-response equalizer are off.6.4.1.3 Turbine follows ModeIn
this mode the keeping of the steam pressure ahead of the Turbine is
effected by the regulators of the Turbine Controller. The modes of
keeping the steam constant pressure and steam sliding pressure are
possible.Fuel and air regulators are in operation. The fuel
regulator operates under the task coming from the Unit coordinator.
The regulator of steam pressure in the Boiler Master is off. The
frequency-response equalizer is also off in this mode.6.4.1.4 Local
Coordinated ModeIn this mode task and speed of changing under the
load is controlled by operator from the PCR.The fuel regulator is
put into operation according to the scheme described in the part
Boiler follows mode.Valves position regulator is connected in
addition to the Boilers Master steam pressure regulator. This
valves position regulator provides open position of three control
valves of the Turbine at the load lower than 90% in the sliding
pressure mode.The Turbine regulator keeps the Unit power in
accordance with the setting coming from the Unit coordinator.When
the Power Unit takes part in grid frequency control the
frequency-response equalizer is connected to the power regulator.
In case of the frequency deviation from the dead band limits the
frequency-response equalizer changes the task on the static
characteristic frequency-power.The regulator of steam minimum
pressure ahead of the Turbine is also in operation. This regulator
does not permit to decrease the pressure ahead of the Turbine in
the process of load changing lower than the set point of the set
minimum pressure (SPmin LS Pressure). The set point is sliding and
it is determined by the following ratio:SPmin LS Pressure = SP Load
Turb Act P, whereSP Load Turb Act the set point on the steam
pressure ahead of the Turbine;P admissible deviation from the set
value.Limitation on high limit pressure ahead of the Turbine is
effected by the HP Bypass, which starts to operate when the set
point is exceeded.The set point is determined by the ratio:SPmax LS
Pressure = SP Load Turb Act + PWhen forming the set value of the
power (SP Load Unit Act) the limitations on minimum and maximum
power are taken into consideration which are determined by the
quantity of operating mechanisms, pulverized-coal feeders, nozzles;
load of fans groups.Set point of power what coming to the Turbine
Controller is formed by means of the Boiler model SP Load Turb Act
= f(SP Load Unit Act) which takes into account the Boiler
persistence. In a similar manner the task on pressure ahead of the
Turbine is formed by means of the Boiler model SP Load Turb Act =
f(SP Load Unit Act).In order to provide acceleration of the Boiler
the speed up signals on SP load Turb Act and the frequency-response
equalizer are introduced in the scheme of setting formation for the
fuel regulator.6.4.1.5 Remote Coordinated ModeIn this mode the load
setting is specified by operator from the dispatch center, speed of
load variation is specified by operator from the PCR.In all other
respects the operation of the regulators is the same as in the
Local Coordinated Mode.6.4.2 Boiler Master
The Boiler Master is the part of the Unit Coordinator.See the
structural scheme of the Unit automatic control provided in the
Appendix No.2.In the modes Boiler follows, Local Coordinated Mode
and Remote Coordinated Mode the Boiler Master keeps the constant
steam pressure at the Boiler outlet.The Boiler Master forms the
setting for all modes regulator of fuel supply and current load
setting for the Turbine Controller.6.4.3 Turbine Controller
The structural scheme of the Turbine Controller is provided in
the Appendix No.3.The Controller performs the following
functions:
- speed control;
- load control;
- frequency correction;
- inlet steam pressure control;
- valves control;
- minimum pressure control;- maximum pressure control in the
control stage;
- control valves position control;
- thermal stress evaluation;
- control system tests;
- UCTE test;
- improvement of the Turbine overspeed protection in case of
failure in
hydraulic control system.More detailed information about the
Turbine Controller functions is given in UBEX1-M1&2-I-52-0001
Control System Concept and Configuration Diagrams, incl. Fail Safe
Protection.6.4.4 HP Bypass Control
HP-Bypass provides main steam pressure control and temperature
of the steam discharged to the steam lines of the cold reheat at
the Unit start-up and the Turbine trip and also as a safety valve
for main steam maximum pressure exceeding ahead of the Turbine.The
structural scheme of the Turbine bypasses control is given in the
Appendix No.4Main steam pressure control by HP-BypassDuring
start-up the set point for HP-bypass is developed by the scheme of
the required value (RV) formation which forms the current set point
of live steam pressure according to the requirements of the Boiler.
When the current set point reaches the value set for the turbine
start, which depends on start-up conditions (cold, warm or hot) the
current set point remains unchanged and is controlled by HP-bypass
pressure regulator.In the process of start-up proceeding as the
control valves of the turbine HP cylinder are opened, HP-bypass
will be closed.The Unit coordinator takes upon itself the setting
function for HP-bypass by the signal the turbine HP cylinder
switching on.When this mode of operation begins the set point of
main steam pressure for HP-bypass plant is increased immediately by
10 kgf/cm2 of the working pressure that is specified by the Unit
coordinator and depends upon the Unit load.If failures take place
which result in pressure increase the HP-bypass valve is opened
while the main steam pressure exceeds the set point of main steam
pressure for HP-bypass plant consequently limiting the maximum
pressure of main steam.When the turbine turbine is not to take up
the complete main steam flow (the Unit runback load) the set point
of main steam pressure for HP-bypass is decreased immediately up to
the working pressure set point depending on the load specified in
the Unit coordinator.HP-bypass is opened and controls the main
steam pressure under this working pressure set point. It continues
until either the turbine starts to accept steam in full or the
boiler shut down takes place.HP-bypass has an attemperation system
which is effected by the injection to the HP-bypass steam
attemperator and maintains the set steam temperature at the
HP-bypass outlet.Depending on water pressure to the spray and steam
pressure in the reheat line the gain factor of the temperature
regulator is changed.Injection valve is closed automatically if the
steam pressure control valve is opened less than 3%.Manual
operationsThe main steam pressure set point for HP-bypass could be
switched over to the manual mode and adjusted by operator. It
enables to set manually the required main steam pressure for the
turbine during the boiler start-up and the pressure set point for
HP-bypass during the Unit operation.6.4.5 LP Bypass Control
LP-Bypass serves as a control valve of reheat steam pressure and
temperature of the steam discharged to the condenser during the
Unit start-up and in the Unit emergency modes. If steam discharge
to the condenser is impossible due to vacuum decay, temperature
increase in the condenser, injection water pressure decrease, the
steam discharge from the reheat header is provided by means of the
safety valves opening and LP-bypass is used as a safety shutoff
valve.Reheat steam pressure control by LP-BypassThe automatic
regulator LP-bypass keeps the constant reheat steam pressure set at
the level 12-15 kgf/cm2 within the 0-30% range of the turbine load.
At increasing the turbine load above 30% (HP cylinder is on) the
set point for LP-bypass pressure regulator is set as variable
depending upon the pressure in the control stage and it will be 10%
more than the current pressure in the reheat line corresponding to
the given load (it is determined by functional dependence f(x)).At
the turbine load being more than 30% the LP-bypass is closed in the
normal mode.LP-bypass has an attemperation system which is effected
by the injection to the LP-bypass steam attemperator and provides
keeping of the set steam temperature at the LP-bypass
outlet.Depending on steam temperature and pressure in the reheat
line the gain factor of the temperature regulator is
changed.Injection valve is closed automatically if the steam
pressure control valve is opened less than 3%.Manual operationsThe
set point for LP-bypass pressure regulator could be switched over
to the manual mode and adjusted by operator. It enables to set
manually the required pressure in the reheat line during the boiler
start-up and the pressure set point for LP-bypass during the Unit
operation.6.4.6 Fuel Control
The Boiler fuel feeding automatic control system provides fuel
for the required steam rate of the Boiler.The structural scheme of
the regulator is given in the Appendix No.5.Fuel control is
performed by the following means:
- fuel oil pressure regulator;
- fuel oil flow regulator;
- fully-variable mode fuel regulator.Fuel oil pressure regulator
maintains the starting fuel pressure during ignition of oil nozzles
at the Boiler start-up.After turning the oil nozzles off the
regulator remains in operation keeping the pressure in fuel oil
line (ahead of the nozzles) corresponding to the flow 10,5% of the
rated thermal load for eight burners of the lower deck to be
re-ignited in time at the decreased loads.The regulator is
performed under single-loop scheme and receives the signals of the
set and actual pressure of fuel oil.Automatic task setting to the
regulator is provided depending upon the Boiler operation mode.Fuel
oil flow regulator stabilizes fuel oil flow at combined combustion
pulverized coal and fuel oil.In a load range from 30 up to 50%
regulator provides the fixed flow of fuel oil corresponding to
making of a thermal output equal 15 % from BMCR.In a load range
from 50 up to 70% regulator provides the fixed flow of fuel oil
corresponding to making of a thermal output equal 10.5% from
BMCR.Fully-variadle mode fuel regulator keeps the total fuel flow
(fuel oil + pulverized coal) in all operation modes of the Boiler
in accordance with the setpoint.The following signals are supplied
to the regulator input: actual fuel flow coming to the Boiler and
setpoint.Setpoint is formed either by the Boiler Master in normal
operation modes in the control range or by the fuel programmer in
the modes of ignition and Boiler loading during start-up.When the
protections switching the Boiler to the decreased load operate
setpoint equal 30%, 50% or 70% of the nominal fuel flow are
switched automatically to the regulator.The signal characterizing
the total thermal load of the Boiler is formed as total signals of
fuel oil flow and quantity of the pulverized-coal as supplied by
the pulverized coal feeders as fed to the Boiler furnace from the
pulverized coal systems.The signal of the pulverized coal quantity
fed from the pulverized-coal system through the feeding nozzles is
formed by the summation unit by switching on the pulverized-coal
systems.The signal of fuel oil flow is formed as the measured
difference between fuel oil flow to the Boiler and to the
recirculation flow.The signal of the pulverized coal quantity
supplied by the pulverized coal feeders is an indirect signal
calculated from the sum of the control valve position signals of
each pulverized coal feeder. This signal is entered in the
regulator with the Boiler actual heat generation correction. The
correction signal characterizes specific heat productivity of the
Boiler by the coal constituent.The product Rp*Fc1 formed by the
multiplier unit reflects the total Boiler output with reference to
pulverized coal.The regulator effects either on the master
integrator forming the task to the regulators of the pulverized
coal feeders capacity or on the fuel oil control valve.The
regulator switches to the fuel oil control valve after ignition of
all fuel oil burners at the Boiler start-up and loading up to 30%
and also at the Boiler 30% load operation and its change-over to
fuel oil firing.The regulator is connected to the pulverized coal
feeders after switching on all the pulverized coal feeders at the
minimum load during the Boiler start-up and keeps the set load in
the working range 100-30% as at the Boiler pulverized coal
operation as at combined firing of pulverized coal and fuel
oil.Connection of the regulators to the actuating devices is
effected automatically by the logic signals.In the silent state the
dynamic balancing of the regulators is provided for their
subsequent bumpless switching on.6.4.7 Common (Primary &
Secondary) Air Pressure Regulator
The regulator is designed for keeping the set excess air during
fuel firing. The regulator is performed according to the fuel-air
ratio with the correction on the average content of O2 in flue
gases or q3 (chemical underburning).The structural scheme of the
regulator is given in the Appendix No.6.The regulator includes the
ratio regulator and the adjustor.The following signals are supplied
to the ratio regulator: the signals of total air flow to the
burners and discharge nozzles, setting signal of total fuel flow
with O2 or q3 correction and derivative signal of fuel oil flow.The
ratio regulator effects on air supply to the Boiler through the
system of synchronization of actuating devices movement of both FD
fans.The maximum of two correction signals is supplied to the
adjustor inlet (O2 or q3) what enables to perform the setting
correction to the ratio regulator at different furnace modes.The
correction signal is input by means of the multiplier unit; it
enables to improve the accuracy of keeping the ratio fuel-air in
all Boiler modes. The dynamic correction and required static
dependence of the average set correction signal on the total fuel
flow are provided. The adjustor scheme contains the prohibition to
change the output signal for increase at the FD fan hydraulic
coupling being opened in full. The regulator scheme also provides
different operation modes of the ratio regulator and the adjustor
(operation with one FD fan, switching off the adjustor), automatic
balancing of the regulators at their switching off.6.4.8 Primary
Air Flow Regulators
Four air flow regulators are provided in accordance with the
quantity of pulverized coal systems.Each regulator keeps primary
air flow to the pulverized coal feeders of four burners.The
structural scheme of the regulator is given in the Appendix
No.7.The regulator effects on corresponding guide vanes of the
primary air fan.The signal of the primary air flow setting
depending on the Boiler steam load and the controlled parameter
primary air flow, determined by the differential on measuring
device with temperature correction and calculated for one primary
air fan, are supplied to each regulator input.The regulator scheme
provides the limitation on minimum admissible value of the primary
air flow.At switching off the regulator its dynamic balancing is
put in.6.4.9 Furnace Pressure Regulator
It is designed to keep the depression in the furnace during the
Boiler operation at the balanced draught.The structural scheme of
the regulator is given in the Appendix No.8.The regulator is
performed under the scheme air flow flue gases flow with nonlinear
correction by the average set furnace depression.The regulator
includes the ratio regulator and the adjustor. The following
signals are supplied to the ratio regulator: the signal of common
air flow and the signal of flue gases flow (the last one is formed
as the ratio of nonlinearly transformed signal of the total
capacity of ID fans to the maximum pressure produced by one of two
ID fans).The ratio regulator effects on the actuating devices of
the hydraulic couplings of ID fans 1 and 2 through the
synchronizing system.Nonlinearly transformed signal of the
depression deviation from the set value is supplied to the
adjusting regulator inlet. The adjustor changes the setting to the
ratio regulator air flow flue gases flow. The adjustor scheme
contains the prohibition to change the output signal at the ID fan
hydraulic coupling being opened in full.It is provided the
operation mode with one ID fan with the signal of flue gases flow
and at that the self-tuning Kn of the ratio regulator is
performed.
At switching off the regulator its dynamic balancing is put
in.6.4.10 Feed-Water Regulator
The regulator is designed to keep the constant level in the
Boilers drum in all modes of the Boiler operation.The structural
scheme of the regulator is given in the Appendix No.9.Two feed
water regulators are provided: the start-up regulator and the main
regulator.The start-up feed water regulator is in automatic mode
and controls water supply to the Boiler through the control feed
valve in the feeding bypass line according to the level setting in
the start-up mode.The main feed water regulator is put into
operation at change-over of boiler feeding from the bypass line
into the main one. The regulator controls water supply to the
Boiler by means of the control feed valve in the main line
according to the level setting in the main operation mode.
Change-over from the ignition feed water regulator to the main one
is performed automatically.The main feed water regulator is
performed with the main signal of the actual level in the Boiler
drum (with the drum pressure correction) and derivative signals of
the actual flows of the feed water to the Boiler and steam flow at
the Boiler outlet (with temperature and pressure correction).
Correction of the feed water regulator signals enables to improve
the accuracy of the level keeping in the different modes of the
Boiler operation.The ignition regulator is performed as static with
input signals of the Boiler drum level and control valve
position.6.4.11 Boiler Steam Temperature Regulators
6.4.11.1 Main steam temperature control
High-Pressure steam temperature control system provides the
optimum conditions of heating surfaces in the boiler start
conditions from the different heating states and boiler work within
the load range.
For high-quality spray of the injected water and centrifugal
atomizers starting injections reliable operation it is provided for
automatic keeping of the feed water required pressure in the
starting injections lines.
Steam temperature automatic control system consists of 3
interconnected spray regulators 1, 2, 3.
At the unit starting stage, boiler outlet steam temperature
control is being made with the help of three injecting steam
attemperators starting nozzles installed in each branch.
During the unit starting the boiler outlet steam temperature
value is being generated at the temperature programmer depending
from the initial HP cylinder temperature condition of the turbine
and coming to starting regulator of the 3rd spray.
Injection regulator 2 provides 3rd injection control range,
keeping the designed temperature difference. Spray regulator 1
provides 2nd spray control range, keeping the designed temperature
difference.
The permission for starting injections switch on comes at
pressure increase up to ~30 kgf/cm2 in the drum and for main
injections switch on at pressure increase up to ~115 kgf/cm2 in the
drum.
By load increasing, at steam temperature close to the rated
temperature there is a transfer into main injections and starting
injections gradual deactivating.
After starting injections deactivating, the spray atomizers main
injections are being switched on at 1st and at 3rd spray
attemperators. The 1st spray main regulator provides the 3rd spray
operating range, keeping there designed temperature difference. The
3rd spray regulator stabilizes boiler outlet steam temperature.
Water for injection feeds from the feed-pump discharge pipe.
6.4.11.1.1 Spray regulator 1
Spray regulator 1 designed for operating upon starting
conditions and in basic modes of the boiler operation and it
actuates to starting spray control valves (CSV 1S) and main valves
(CSV-1).
The structural scheme of the regulator is given in the Appendix
No.10.
At starting conditions spray regulator 1 provides the 2nd spray
control range, and at basic modes the 3rd spray control range.
The signal concerning the regulated steam temperature before the
second injection T2 , steam temperature high-speed signal after the
1st injection steam attemperator (T1) and set point signal, forming
the temperature drop on the next injection (~ 600C) come to the
regulating unit of starting regulator.
If the limits concerning the steam temperature before the 2nd
spray or the 2nd spray control range finishing (both for more and
for less), or switching the 2nd spray regulator to remote operation
occur then the 1st spray regulator is being switched to keep the
temperature due to which the limits occurred. At this case, change
in these regulator previous values is being frozen.
At the HP-Convention Superheater-3 outlet steam temperature
close to rated temperature (> 530 0C), steam flow > 250 t/h
the integrator is being connected to regulator (to reduce the
values from 60 0C to 00C) and it reduces the difference at the 2nd
spray gradually up to 00C due to opening CSV-1S. The 2nd starting
spray control valve (CSV-2S) will be closing gradually. After its
complete shutdown, the 1st spray starting regulator switches off,
and the shutdown task connects to CSV-1S. Simultaneously, the
actuation of the 1st spray main regulator, providing the designed
temperature difference on the 3rd injection cooler of the main
injection connects to the 1st spray main control valve (CSV-1).
After 2nd spray control valve (CSV-1S) is closed the 1st spray
main regulator switches on.
At the regulator diagram there is provided for the 1st spray
steam temperature control: this temperature must always be higher
then the saturation temperature, not less then 14 0C.
6.4.11.1.2 The 2nd spray regulator The 2nd spray regulator is
being intended for operation by boiler operation starting
conditions only and provides the 3rd spray control range. The
regulator actuates to the spray control valve CSV-2S.
The structural scheme of the regulator is given in the Appendix
No.11
The signal concerning steam regulated temperature before the 3rd
injection, steam temperature high speed setpoint (command) after
the second injection steam attemperator (T2) and the set point,
forming the temperature drop on the next injection (~ 600C) comes
to the regulator inlet.
If the limits concerning the steam temperature before the 3nd
injection or the 3rd injection control range finishing (both for
more and for less), or switching the 3nd spray regulator into
remote operation occur then the 2st spray regulator is being
switched to keep the temperature due to which the limits occurred.
At this case, change in these regulator previous values is being
frozen.
When the 2nd injection is out of operation (CSV-2S shutdown) the
command for shutdown of all nozzles shutoff valves and the 1st,3rd
starting spray control valves is being formed at the regulator
diagram.
Two regulators are being provided for the boiler.
6.4.11.1.3 The 3rd spray regulator The 3rd spray regulator is
being intended for operation within starting conditions and at the
basic modes of the boiler operation, it actuates to starting
(CSV-3S) and a main (CSV-3) spray control valves and keeps the
boiler outlet designed steam temperature.
The structural scheme of the regulator is given in the Appendix
No.12.
Starting regulator keeps designed main steam temperature,
feeding into turbine and ensures its safety warm up during the
starting process.
The signals come to the regulator inlet it concerns the boiler
outlet steam regulated temperature (Tb) the speed of the steam
temperature change after injection (T3) and setpoint. The setpoint
for the starting regulator is being formed by the temperature
programmer.
After the 2nd starting injection shutdown, the setpoint for
shutdown comes to CSV-3S. At the same time, the 3rd spray main
regulator actuates to the main control valve CSV-3.
Two regulators are being provided for the boiler.
6.4.11.2 Reheat steam temperature Control
Reheat Steam Control System ensures the optimal condition of the
heating surfaces and boiler outlet reheat temperature within the
conditions of the boiler starting from the different thermal
conditions and boiler operation within the load range.
The automatic keeping of the feed water required pressure at the
starting injections line.
At the unit starting stages, reheating steam temperature the
regulating at the boiler outlet is being made with the help of two
injection steam attemperators starting nozzles installed in each
branch. Water for injections in this mode is being supplied from
the feed pump pressure line.
The steam temperature control system consists of two
interconnected spray regulators 1, 2.
Boiler outlet steam temperature setpoint at the unit starting,
forms in temperature programmer depending from the turbine
IP-cylinder temperature condition and comes to the 2nd spray
starting regulator.
The 1st spray regulator provides for the 2nd spray regulating
range, keeping the designed temperature difference.
With the load increase, at the steam temperature close to rated
temperature there is a transition to the main injections and
gradual deactivation of all starting injections.
The permission for connecting starting injections to reheater
comes by approaching the pressure level ~ 8 kgf/cm2 at the reheater
outlet.
After starting injections deactivation the main injections are
being switched on at the 1st injection steam attemperator. The 1st
spray regulator stabilizes the boiler outlet steam temperature.
The water supply regulating at starting conditions is being made
in the way of starting regulators actuation to their control
valves.
After each starting spray control valve, before each centrifugal
atomizer, shutoff valve is being installed for the purpose of
switched on nozzles quantity change.
Reheat steam temperature regulating at the boiler operation main
conditions is being made in the way of steam bypassing through the
main steam reheater control valve installed at circuit inlet and
water injection into steam attemperator 1, installed before the
LPConvection Superheater.
Water for injection at this condition is being supplied from the
feed pump intermediate stage.
.
6.4.11.2.1 The 1st spray regulator to reheater
The 1st spray regulator into reheater is being intended for
operation at starting conditions and basic modes of boiler
operation, it actuates to starting (CSV-1RS) and main (CSV-1R)
spray control valves.
The structural scheme of the regulator is given in the Appendix
No.13.
At the starting conditions the 1st spray regulator provides for
the 2nd spray regulating range, keeping there designed temperature
difference.
At the approaching to the conditions of the starting spray
shutdown that are being formed in the 2nd injection regulator
diagram and complete shutdown of CSV-2RS the 1st spray starting
regulator is being switched off and the shutdown setpoint comes to
CSV-1RS. Simultaneously, the actuation of the 1st main regulator is
being connected to the 1st spray main control valve (CSV-1R).
The 1st spray main regulator serves to prevent an unavailable
reheater outlet steam temperature increase at finishing steam
bypass regulating range.
The regulator actuates to the control valve CSV-1S. The
regulator is being turned in the designed temperature value, which
is 10 0C higher of its nominal value and as the reason of it
usually the regulator in holding condition keeping its control
valve in the complete shutdown position.
The regulator receives following signals: superheater outlet
steam temperature TLP CSH, derivative of the temperature after
injection T1R and nonlinearly converted signal according to the
steam bypass control damper position Gsb-cd. This signal is used to
increase the regulator operation efficiency.
Nonlinear element is being turned so that the setpoint at its
outlet appears only by approaching to the opening degree of steam
bypass control valve up to 80 % of full running and at the further
opening of damper valve the setpoint increases, reducing the task
for 1st spray regulator on 7-8 0C in comparison with the initial
value at the full opening Steam Bypass Control Damper.
Due to the setpoint reducing, the 1st spray regulator gets into
operation and keeps steam temperature at the lower level.
6.4.11.2.2 The 2nd spray regulator into preheaterThe 2nd spray
regulator is intended for operation at the boiler operation
starting conditions only and actuates to the control valve, to the
spray CSV-1RS.
The structural scheme of the regulator is given in the Appendix
No14.
The 2nd spray regulator keeps the designed reheating steam
temperature feeding into turbine, ensuring its safety warm up at
starting operations in accordance with the setpoint forming in
reheating steam temperature programmer.
At the LP-convention superheater outlet steam temperature close
to the rated temperature (>540 oC), steam flow > 460 t/h the
1st spray starting regulators switched on and steam bypass, to the
CSV-2RS connects the task for its shutdown.
6.4.11.2.3 The reheater steam bypass regulator
The regulator is intended to keep the designed steam temperature
value at the steam preheater outlet in the operation boiler basic
modes.
The structural scheme of the regulator is given in the Appendix
No15.
The signals concerning the regulating temperature TLP CSH and
its time derivative, derivate signal of the blend temperature Tsm
after main steam reheater bypass and setpoint (Tsp).
The regulator actuates to the bypass control damper of the main
steam reheater.
6.4.12 Control of the Boiler Feed Water PumpsThe structural
scheme of the regulator is given in the Appendix No.16.Capacity of
each feed water pump is effected by shifting the actuator of the
hydraulic coupling.The controlled parameter for the feed water pump
capacity regulator is water pressure differential at the feed
control valve.Each of three feed water pumps capacity is controlled
in such a way to keep the pressure differential at the feed control
valve within the set limits.At that the set ratio of feed water
pressure and flow is observed.The function f(x) determines the
design pressure for the current feed water flow.The following
limitations are provided:
- maximum pressure in the main feed water line;
- minimum admissible feed water flow.6.5 Structure of process
parameters changing systemMainly the sensors with analogue output
are used in the Unit control system.
The signals used for automatic control have double redundancy
and the signals used for process protections of the Unit and the
Boiler have triple redundancy.The control and monitoring system
should provide the following:
- average value of the controlled parameter;
- control of deviation between the average value and each value
of the sensor signal;
- control of deviation value and delay time;
- automatic disconnection from operation the disabled sensor
with corresponding alarming;
- possibility for operator to select or disconnect measuring
sensors from operation.7. Start-Up Procedures7.1 Start-up timeThe
time required to reach the Turbine start-up parameters is
determined by the permissible pressure, temperature and load
gradients of the steam generator. The required steam parameters to
start-up the Turbine depend on the Turbine metal temperatures
before start-up.After Turbine start-up and synchronization the
further load increase is determined by the permissible pressure,
temperature and load gradients of the steam Turbine.The maximum
time of the Unit start-up from the moment of the command for the
Boiler purge (ventilation) up to reaching the rated output
electrical power (full load) is the following:
Cold Start-Up (shutdown >150 h).. 9.67 h;
Warm Start-Up (shutdown