KEY ORGANIZATIONAL RISK FACTORS: A CASE STUDY OF HYDROELECTRIC
POWER PROJECTS IN MYANMAR
by
Aung Myo Hein
A thesis submitted in partial fulfillment of the requirement for
the Degree of Master of Engineering in Construction Engineering and
Infrastructure Management
Examination Committee :
Dr. Chotchai Charoenngam (Chairperson) Dr. B.H.W. Hadikusumo Dr.
Noppadol Phien-wej
Nationality: Previous Degree:
Myanmar Bachelor of Civil Engineering Yangon Technology
University Myanmar AIT Fellowship
Scholarship Donor:
Asian Institute of Technology School of Engineering and
Technology Bangkok, Thailand May, 2009
i
ACKNOWLEDGEMENTS First of all, I express my wholehearted
gratitude to my beloved parent who supported financially and
encouraged mentally during study in AIT. They ever give forgiveness
and show their kindness whenever I fell down. To begin with, I
would like to express my sincere gratitude to Dr. Chotchai
Charoenngam, the intellectual giant as my admire thesis advisor who
trained me to become as a warrior. I would like to thank him for
the guidance, patient, promoting development comments and all
unforgettable memorial events for the accomplishment of this study.
I am grateful for working with the brilliant adviser who assembled
my mind how to struggle the challenges without being scared. I
would like to express my gratefulness to thesis examination
committee members as well as academic adviser, Dr. Bonaventura H.W.
Hadikusumo who encouraged and gave valuable advice during academic
study and Dr. Noppadol Phien-wej who provided substantial study
support in the early stages of the study. Their guidance, helpful
recommendation and valuable comments made the study to be brighter
and were of great contribution to the study. Grateful
acknowledgements are extends to Minister of Electric Power-1
(Myanmar) who gives me opportunity to study in DHPIs projects, top
managements of Department of Hydropower Implementation (DHPI),
senior management and all participants who shared their valuable
time from Construction Division (2) and (3). Their sincere
cooperation and attention lead to the successful surveys. My great
thankfulness belongs to all dear CEIM friends especially Karma G.,
Thotsaphol R., and Panwimon J., for their warmly assistance and
patient on me. In conclusion, I would like to say many thanks to
all peoples who help me partially to complete this study. I will
never ever forget your help and our friendship will continue as
long as my breathing.
ii
ABSTRACT Organizational risk, generally defined as the risk that
the organizational configuration of a company does not support the
achievement of its strategy, therefore becomes vital to manage for
companies in the post-industrial era. The study focused on the
internal key risks factors of construction project organization and
how the organizational risk factors cause the problems and
deficiency of construction lead to project delay. Then the
objectives of study is to identify key organizational risk factors
which cause deficiency of project and the rationale of
organizational risk factors to project risk which create the
negative outcomes of the project. Eventually, recommendation for
the improvement of organizational risk management that is
appropriate for construction project organization is followed.
Multiple cases study approach (two construction divisions) is
conducted in order to have robust results of the study. Opening
process of study is risk factors identification which consists of
initial factors and verification of the factors. Then, data
collection is followed by interviewing practitioners in the
projects with verified checklist, collecting project documents and
site observation. Data analysis is conducted by description of
differences risk factors between construction divisions and
explanation of overall risk factors of both cases study towards the
gathered information. Research findings confirm that different risk
factors are influenced in both construction divisions and overall
top rank risk factors are embedded in nine internal organizational
networks which are necessary to control for improvement of project
organizations. These top risk factors are 1) Technology
constraints, 2) Time constraint resource scheduling, 3) Inaccurate
information, 4) Technical Incompetency, 5) Lack of skilled
workforce, 6) Delay major equipment, 7) Insufficient human
resource, 8) Resource constraint project scheduling, 9) Sub-quality
resource, 10) Lack of regular meeting and 11) Mistrust between
parties. The proposed guideline of organizational risk management
assists the top management of DHPI in order to make precise
decision for managing risks in organization. Multi-dimensional
causes, effects, rationale of organizational risk factors to
project risks and recommendation for manageable factors mentioned
above were discussed in this study.
iii
TABLE OF CONTENTS CHAPTER TITLE Title Page Acknowledgement
Abstract Table of Contents List of Figures List of Tables
Abbreviation 1 INTRODUCTION 1.1 Background 1.2 Climate of Myanma
Hydropower Development 1.3 Problem Statement 1.4 Objectives of
Study 1.5 Scope of Works 2 LITERATURE REVIEW 2.1 Risk and
Construction 2.2 Organizational Risk 2.3 Managing Risk in
Organization 2.3.1 2.3.2 2.3.3 Communication and Coordination
Inter-firm cooperation Cross-functional team 6 7 9 10 12 12 13 14
15 15 17 18 19 20 21 22 23 23 23 24 24 1 1 4 5 5 PAGE i ii iii iv
vii ix x
2.4 Practical Limitation of Risk Management 2.4.1 2.4.2 2.4.3
Risk Identification Assessing Impacts of Risk Events and Evaluation
Process Risk Response Planning
2.5 Risks Interlocked Networks of Project Organization 2.6
Internal Organizational Networks 2.6.1 2.6.2 2.6.3 2.6.4 2.6.5
2.6.6 2.6.7 2.6.8 2.6.9 Social Network Knowledge Network
Information Network Resource Network Resource Usage Requirements
Inter-operability and Co-usage requirements Assignment Network
Knowledge Requirements Resource Requirementsiv
2.6.10 Precedence and Dependencies 2.7 Summary 3 RESEARCH
METHODOLOGY 3.1 Introduction 3.1.1 3.1.2 3.1.3 Selection of
Research Method Research Approach Research Methodology
Framework
24 24
26 26 27 28 31 32 34 35 35 35 35 36 38
3.2 Risk Factors Identification 3.2.1 Interviewing and
Verification of Initial Risk Factors
3.3 Data Collection 3.3.1 3.3.2 3.3.3 3.3.4 Question Design
Pilot Test Project Selection for Case Studies Interview Plan
3.4 Data Analysis and Validation 3.5 Case Study Report 4 CASES
STUDY ANALYSIS 4.1 Organizational risk management 4.1.1 Risks in
Internal Organizational Networks
39 40 42 42 44 44 45 47 48 49 52 53 56 59 61 63 65 68
4.2 Organization Background 4.2.1 4.2.2 4.2.3 Construction
Division (A) Construction Division (B) Case Study Overview
4.3 Practical Risk Management in Organization 4.4 Differences
Risk Factors between Cases Study 4.4.1 4.4.2 4.4.3 4.4.4 4.4.5
4.4.6 4.4.7 4.4.8 4.4.9 4.4.10 Social Network Knowledge Network
Information Network Resource Network Resource Usage Requirements
Inter-operability and Co-usage requirements Assignment Network
Resource Requirements Precedence and Dependencies Summaryv
4.5 Overall Ranking of Key Organizational Risk Factors 4.5.1
4.5.2 4.5.3 4.5.4 4.5.5 4.5.6 4.5.7 4.5.8 4.5.9 4.5.10 4.5.11
4.5.12 Technology Constraint Time Constraint Resource Scheduling
Inaccurate Information Technical Incompetency Lack of Skilled
Workforce Delay Major Equipment Insufficient Human Resource
Resource Constraint Project Scheduling Sub-quality Resource Lack of
Regular Meeting Mistrust between Parties Guideline of
Organizational Risk Management
71 73 74 75 76 77 78 79 81 81 82 83 86 86 88
4.6 Activation the Logic Model of Organizational Risk Management
4.7 Recommendation for improvement of DHPIs Projects Efficiency 5
CONCLUSION AND RECOMMENDATIONS 5.1 Introduction 5.2 Research
Findings 5.3 Difference Top Rank Risk Factors in Con (A) and (B)
5.4 Overall Risk Factors in Internal Organizational Networks of
DHPI 5.5 Recommendation for Organizational Risk Management in DHPI
5.6 Recommendation for Further Study 6 REFERENCES APPENDIX (A)
Checklists APPENDIX (B) Analysis results of Checklists APPENDIX (C)
Cases Study
89 89 89 90 91 91 92 96102 109
vi
LIST OF FIGURES FIGURE 1.1 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 3.1
3.2 3.3 3.4 3.5 3.6 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 4.11
4.12 4.13 4.14 4.15 4.16 4.17 4.18 4.19 TITLE PAGE
Major elements in organization 4 Probable outcome of
construction project 6 Characteristic of risks in construction 7
Direct and indirect of organizational risks 8 Risk Management
process 10 13 Comparison of traditional and modern functional model
Risk identification process 15 Strategies to cope with risk 16
Organization risk analyzer 18 28 Research approach Research
Methodology Framework 30 Organization risk analyzer 31 Verification
risk factors and questionnaire process 33 Verified organizational
risk factors 34 Data analysis procedure 37 Location of cases study
43 Limitation of accountability and decision making process 47
Senior Management progress and coordination meeting, Con (A) 51
Weekly Project Meeting, Con (A) 51 Quality control of input
Materials in Con (A) 55 Technical incompetency of organization, Con
(B) 57 Implemented projects of organization in five decades 59
Percentage of project received required resources in quarterly 60 A
part of gantry crane transportation to project 61 Maximum installed
capacity in each decade 62 Delay resource of Con (B-1), Kun Project
65 Percentage of organization supported resource in 1st quarter to
Con (A) 67 Percentage of organization supported resources in first
three quarter to Con (B-1), Kun Project 67 Percentage of
organization supported resources in first three quarter to Con
(B-2), Phyu Project 68 Logic model of organizational factors and
project risk in precedence and dependencies 73 Logic model of
organizational factors and project risk in inter Operability and
co-usage requirement 74 Logic model of organizational factors and
project risk in information network 75 Logic model of
organizational factors and project risk in knowledge usage
requirement 76 Logic model of organizational factors and project
risk in resource usage requirement 78
vii
FIGURE 4.20 4.21 4.22 4.23 4.24 4.25 4.26 4.27 4.28 4.29
TITLE
PAGE 78 79 80 80 81 82 83 85 86 87
Logic model of organizational factors and project risk in
resource requirement Permanent employees of Yeywa Hydroelectric
Power Project In May, 2008, Construction Division (A) Experience
and education background of employees in organization Logic model
of organizational risk factors and project risk in assignment
network Logic model of organizational risk factors and project risk
in precedence and dependencies Logic model of organizational risk
factors and project risk in resource network Logic model of
organizational risk factors and project risk in knowledge network
Logic model of organizational risk factors and project risk in
social network Guideline of organizational risk management
Interrelation of risk factors in project organization
viii
LIST OF TABLES TABLE 1.1 1.2 2.1 3.1 4.1 4.2 4.3 4.4 4.5 4.6 4.7
4.8 4.9 4.10 4.11 4.12 4.13 4.14 4.15 4.16 4.17 4.18 4.19 4.20
TITLE PAGE 2 3 22 36 39 40 42 43 44 45 48 50 52 54 56 59 61 63 63
65 70 71 84 88
Hydropower potential in Myanmar Implemented and commission
hydroelectric Power Project of DHPI Sequence of risk due to lack of
information Cases study interviewees list Internal network of
construction organization Risk factors influencing in network of
organization Profile of Organization, DHPI Profile of Construction
Division (A) Profile of Construction Division (B) Practical
overview of risk management checklist in project organization Data
analysis results of social network in Con (A) and (B) Data analysis
results of knowledge network in Con (A) and (B) Data analysis
results of information network in Con (A) and (B) Data analysis
results of resource network in Con (A) and (B) Data analysis
results of resource usage requirement in Con (A) and (B) Data
analysis results of inter-operability and co-usage requirement in
Con (A) and (B) Data analysis results of assignment network in Con
(A) and (B) Permanent employees in Con (A) Data analysis results of
resource requirement in Con (A) and (B) Data analysis results of
precedence and dependencies in Con (A) and (B) Comparison of top
ranks key risk factors in Con (A) and (B) Analysis of overall
organizational factors influencing project Different parties in Con
(A) with their responsibilities Recommendation for improvement of
project efficiency
ix
ABBREVIATION MOEP (1) DHPI CPE NEPS CGGC CNEEC CCYW CHMC Con (A)
Con (B) Con (B-1) Con (B-2) DG DDG PD DPD AD SO JEPIC POW Ministry
of Electric Power (1), Myanma Department of Hydropower
Implementation Colenco Power Engineering Co.ltd (Switzerland) China
Gezhouba Water & Power Group Co.,Ltd China National Electric
Equipment Corporation Joint Venture Consortium of CITIC Technology
Co.Ltd and Sino Hydro Corporation Limited China National Heavy
Machinery Corporation Construction Division (A), Yeywa
Hydroelectric Power Project Construction Division (B), Kun and Phyu
Hydroelectric Power Project Kun Hydroelectric Power Project Phyu
Hydroelectric Power Project Director General Deputy Director
General Project Director Deputy Project Director Assistant Director
Staff Officer Japanese Electric Power Information Center Plan of
Work
x
CHAPTER 1 INTRODUCTION 1.1 Background In a society, an
organization is a social arrangement which pursues collective goals
controlling its own performance and has a boundary separating it
from its environment. It is difficult to achieve the faultless
success by individual effort. To attain the victory from different
perceptive for individually or organizationally, all the people
must struggle, work, share and understand as well as trust
together. Thus collective efforts can accomplish the mission. In
the competitive business industry, every organization finds itself
in a state of continuous risk. Risk taking is necessary for all
construction organization. If one doesnt think big, one loses the
capacity to think big. If one does not try the untried, soon the
untried becomes frightening and mysterious (Mark, 1993). The risk
management of construction organization involves indirect and
direct risks. Construction projects are one-off endeavors with many
unique features such as long period, complicated processes,
abominable environment, financial intensity and dynamic
organization structure and such organizational and technological
complexity generates enormous risks (Zou et al, 2007). Since the
nature of the construction industry is competitive, dynamic, and
all projects are unique, the contractors have seriously developed
the effective risk management system that they apply when dealing
with risks during the life cycle of the project. The more we
discover about the nature and level of risk we face, the better we
are able to prepare for it (Flanagan and Norman, 1993). Risk events
are concatenation, so one problem link to another which may cause
to another and so on. Consequently, a major damage is occurred due
to a small problem. If the organization fails to access the risk
management, the organization will encounter the various sequences
of risks directly or indirectly and then it will have adverse
effect. 1.2 Climate of Myanma hydropower development Nowadays,
according to Myanma Government strategies, the construction
hydropower developments in Myanmar is one of the priority for
social and economic development and which are developed under the
Department of Hydropower Implementation (DHPI), a branch of
Ministry of Electric Power (1), (MOEP 1), Myanmar. Because of
topography and tropical monsoon climate, Myanmar possess abundant
hydropower potential of about 39,720 MW of which about 25,000 MW is
of large scale and remaining is of medium and small scale. Due to
topography, rainfall and drainage pattern Kayin, Shan and Kayah
States on tremendous potential. The table 1.1 shows the hydropower
potential of Myanmar (Greater Mekong subregion, Regional power
trade coordination committee (RPTCC) meeting, 2008).
1
Table 1.1: Hydropower potential in MyanmarUnder 1 MW No. of
State and Division Project . Kachin State Chin State Shan State
Sagaing State Mandalay Division Magway Division Rakhine State Kayah
State Bago Division Kayin State Mon State Taninthayi Division Total
Total number of Projects Total Capacity (MW) 17 11 35 5 3 1 6 2 4 3
5 9 101 Total Capacity (MW) 5.33 3.48 10.64 0.806 0.65 0.1 1.915
0.158 1.89 0.864 1.248 1.706 28.787 1 MW to 10 MW No. of Project .
14 2 24 3 2 2 1 2 50 Total Capacity (MW) 48.18 2.8 63.9 13.3 6.25
11 3 19.5 167.93 Above 10 MW No. of Project . 6 1 11 6 9 2 4 4 7 4
2 2 58 Total Capacity (MW) 1852 200 4161 2889 3475 93 804.5 3740
391 16268 254.5 440 34568 Grand Total No. of Project . 37 14 70 14
14 5 10 6 11 8 7 13 209 Total Capacity (MW) 1905.02 206.28 4235.603
2903.106 3481.9 104.1 806.415 3740.158 392.89 16271.864 255.748
461.206 34764.29 209 34764.29
Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12
Myanmar is cooperating with four Asian neighboring countries of
Thailand, China, Bangladesh and South Korea in hydropower
development, initiating major hydropower projects in recent years
(English.people.com.cn, June 6, 2007). India has joined two
Myanmar's hydropower projects under a memorandum of understanding
(MoU), 2008. (Xinhua). In addition to the projects with the Asian
nations, Myanmar is currently giving priority to implementing some
six hydropower projects scattered in the country's Shan and Kachin
states to increase electricity production and solve the country's
power shortage. According to the government's National Investment
Commission, the electric power sector dominated foreign investment
in Myanmar with 6.311 billion U.S. dollars as of the end of January
this year, 2007 (Xinhua). As long as the infrastructure projects
like hydropower are high investment, longtime period and
complexity, the various kinds of risk are embedding in each phrase
of project such as the budget deficit, technical risk, political
risk and resource shortages, and etc. encounter during the project
life cycle. In case, the maturity of organization is one of the
barriers that have come in the way of project implementation. 1.
Poor Project Management 2. Lack of Updating of Technical
Development 3. Dearth of Competent Indigenous Construction Agencies
4. Lack of Adequate Experienced Construction Manpower (Technical
and Managerial) Table 1.2 illustrated the implemented and
commission hydropower project of DHPI. Total thirteen hydroelectric
power projects were constructed by organization in the past.
According
2
to a executive said, most implemented project were time
overrun.. Alternatively, as for a country, the frequency of
developments is low and its necessary to promote the rate of
developments. Table 1.2: implemented and commission hydropower
project of DHPI No. Commission Hydroelectric Installed Construction
Duration Project Capacity Period 1. Be Lu Chaung (2) 168MW
1960-1974 14 2. Kin Tar 56 MW 1981-1986 6 3. Se daw gyi 25MW
1984-1989 6 4. Be Lu Chaung (1) 28MW 1987-1992 6 5. Zaw Gyi (1)
18MW 1993-1995 3 6. Zaung Tu 20MW 1994-2000 7 7. Zaw Gyi (2) 12MW
1995-1998 4 8. Pa Ti 2MW 1996-1997 2 9. Mone 75MW 1997-2004 8 10.
Paung Laung 280MW 1997-2005 9 11. Thaphanseik 30MW 1999-2002 4 12.
Ye New 25MW 20__-2006 13. Kabaung 30MW 20__-2008 Due to the above
reasons, it is necessary to identify the regarding risks for the
continuous projects development of organization. Risk management
must be a fully integrated part of planning and executing any
operation, executing any operation routinely applied by management,
not a way of reacting when some unforeseen problem occurs (Mille
and Lessard, 2001). According to the SWOT analysis and based on the
knowledge accumulated in organizational risk research, generally
the construction organization risk is ubiquitous which arises from
both internal and external sources. For instances; market,
business, political risks are external risks whereas internal risks
are organization behavior, communication, competency of human
resource and so on. To a large degree, risk is tied to information
and knowledge. The better information and knowledge we have, more
comfortable we are. Nevertheless, the study only focuses on the
internal key risks factors of Project Organization then how the
organization risk factors cause the problems and deficiency of
construction lead to project delay. To understand organizational
risk management clearly, the internal risk factors are identified
and analyzed through the meta-metric (Carley and Reminga, 2004). By
examining the networks of relations nodes entities in meta-metric,
the major factors and their mutual connection is explored and can
assess the impact of factors in the project. Generally, these four
primary components are related to each others and play as a
distinctive way for different purposes during the life cycle of the
project. The following figure 1.1 illustrates the general features
of the major elements which embedded in the construction
organizations.
3
Figure 1.1: Major elements in organization 1.3 Problem statement
An organization is an amalgamation of relationship, power,
authority, roles, activities, and communications. A truly complex
framework encompasses people, knowledge, resources and
tasks/projects. When we look into it, there have different people
with different social, culture and heritage are participating in
the constructed project and which is vulnerable to various
disputes. Since the organization consists of people with different
social and cultural background and different level of knowledge,
the skill and expertise of people have been unrecognized and
unappreciated. Moreover, it is difficult to synchronize, integrate
and connect among different type of knowledge inside the
organization. Therefore, it is necessary for organization to set up
the proper mechanism of risk management in order to have efficiency
of project. According to initial site observation, it is obviously
that the practical risk management of organization is poor in
project although organization implemented many projects. Therefore,
many risks causing construction defect are expected on the
efficiency of the project. As aforesaid, most projects of
organization were delay so identification the risk factors causing
problems is being a crucial which fulfill the deficiency of project
development. To great understanding of the organizational risk
management, it is required to discover the embedded risk factors
causing problem during construction stage. Continuously, it is
interesting to realize the interrelation of risks how cause
construction delay. Besides once, it is required to highlight the
exposure of key risk factors to top management in order to make
accurate decision for better improvement of the constructed
project.
4
1.4 Objectives of the study As the nature of construction
organization is the project-oriented organization, the structure
reforming of the project is the essential tools for the project
success. To arrange the systematic structure, the management must
identify the various factors of interlocked networks of the
organization and the probability of risks occurrence in the project
level then mitigate these. The major objectives of this study are
as follow. To identify the risk factors embedded in internal
networks of project organization so that systematic approach of the
risk factors can be defined. To investigate the rational of
organizational risk factors to project risk in hydroelectric power
project base on the approach developed. To purpose the
recommendation for organizational risk management that is
appropriate for construction project organization.
1.5 Scope of the study The study focuses particularly on the
internal organizational risk management which is one of the crucial
key successes for construction project. The initial stage of this
study is identifying the organizational risk factors which
influence to the constructed project. The respondents of the study
will be the medium and senior management of stateowned company
which construct hydroelectric power project. Description of the
impact of the organizational risk factors which cause inefficiency
of project during construction stage. The study scope will cover
construction project oriented organization which act as a main
contractor in the infrastructure project.
5
CHAPTER 2 LITERATURE REVIEW 2.1 Risk and Construction Risk in a
construction project is unavoidable and affects productivity,
performance, quality and budget significantly by considering the
complex, dynamic and challenging nature of construction projects,
however, risk can be minimized, control, transferred, shared or
insured. Proper risk management has the potential to reduce the
effects of unexpected events. Risk is the possibility that events,
their resulting impacts and dynamic interactions may run out
differently than anticipated (Miller and Lessard, 2001). Project
risk is an uncertain event or condition that, if it occurs, has a
positive or a negative effect on at least one project objective. A
risk may have one or more causes and, if it occurs, one or more
impacts (PMBOK Guide). Constructions custom is more risky than a
routine, repetitive business because of long time period, nature of
complexity, high level difference of management and employees and
modern technology appliance. There are many definitions of risk
that vary by specific application and situational context. Risk is
defined a state of uncertainty where some of the possibilities
involve a loss, catastrophe, or other undesirable outcome (Hubbard,
2007).Construction projects are high-stakes games characterized by
substantial irreversible commitments, skewed reward structures in
case of success and high probabilities of failure. Figure 2.1
illustrates the probability of project success and outcome of
general risks categories in construction firm.
Figure 2.1: Probable outcome of Construction Project Source:
http://www.atocrates.com/Atocrates/ProjectOffices.aspx Combining
the holistic approach of general system theory with the discipline
of a work breakdown structure as a framework, (Flanagan and Norman,
1993) suggested three way of
6
classifying risk by identifying the consequence, type and impact
of risk. Risk events do not need to have catastrophic consequences,
but the commutative consequences add up and can eventually lead to
dire results. One common consequence of coping with many small risk
events is that if lead to inefficiency of operations. If risk
events are not handled properly, we may find that we are
continuously redoing things that werent handle properly the first
time. Ultimately, this increase the cost of doing business, slow
operations, and lead to customer disaffection. The figure 2.2
presents the categories of risks in construction industry.
Figure 2.2: Characteristic of risks in construction 2.2
Organizational risk Every organization is running within the
market. There may have many numbers of projects which generate
profit for the organization. Organization risk and project risk are
intrinsically linked because the organization bears ultimately the
potentially losses of the risk events. Organization Risk such as
cost, time and scope objectives that are internally inconsistent,
lack of prioritization of projects, inadequacy or interruption of
funding, and resource conflicts with other projects in the
organization (PMBOK, 2000). Organizational risk, broadly defined as
the risk that the organizational configuration of a company does
not support the achievement of its strategy, therefore becomes
vital to manage for companies in the post-industrial era (Jeppesen,
2007). As mentioned previously, organizational risk are
multi-dimensional and thus need to be unbundled for clear
understanding of causes, outcomes and drivers. In general, the risk
management can be divided in to number of risk categories in the
constructed project. According to Shrivastava et al., (1988); cited
in Smallman, (1996), Human, organizational and technological (HOT)
risks, which are frequently directly responsible for crises; and
Regulatory, infrastructural and political (RIP) risks, which act as
crisis accelerators, and so may be considered as indirect risks.
The figure 2.3 presents direct and indirect of organization
risk
7
Human
Regulatory
Organization
ORGANIZATION
Infrastructure
Technology
Political
Direct Risks
Indirect Risks
Figure 2.3: Direct and Indirect of Organizational Risks Source:
Risk and organization behavior (Smallman, 1996) The following are
various direct organizational risks which link to the life cycle of
the project emerge overtime. All the risks combine together and
create turbulence of project. 1. Residual risk 2. Communication
risk 3. Critical employee risk 4. Personal interacting risks 5.
Performance risk 6. Resource allocation risk 7. Operation failure
risk 8. Supplier provisioning risk 9. Construction defect 10.
Internal capability Generally, there are three nature risks in
large engineering projects; market-related risks, completion risks
and institutional risks. Major concerning about the organization is
to have expected return for the investment. In order to optimize
the expected return, projects must complete within a deadline and
definable costs and standards. Construction schedules are affected
by uncertainties in weather, productivity, design, scope, site
conditions, material delivery time, equipment efficiency, etc
(Flanagan and Norman, 1993). Therefore, the
8
organization needs to have mitigation for the all risks as well
as uncertainty. If the organization fails to take it, the counter
sequence will come as potential losses on the organization. As
mentioned previously, although the nature of the construction
project are high risk, companies and governments are investing in
ambitious and demanding large scale construction projects more than
ever especially in developing countries. These developments are
typically valued in the hundreds-of-millions of dollars (often in
the billions), with 5-10 year lifecycles, and attract a high level
of public and political interest due to their size, visibility and
economic and social impact (Moavenzadeh, 2006). According to Miller
et al, 2001, risk can be classified into different type of
projects. For example, off-shore platform has technical risks but
low institutional risks because of far away from the public
attention. Hydroelectric-power projects are moderately difficult
insofar as engineering is concerned but they pose high social
acceptability because of the environmental impact. Nuclear-power
plant project tend to be high technical risk but still higher
social and institutional risks. Road and tunnel systems are very
risky when user fees are applied, social acceptability difficulties
bound. Finally, in urban transport projects are high technical
risks as they involve underground geological work so they are
necessary to deal with market, social, and institutional risk. 2.3
Managing risk in organization Risk management is a stepwise
procedure consisting of risk identification, risk classification,
risk analysis and risk response tasks (Flanagan and Norman, 1993).
Organizational survival in todays world is achieved by pursuing
opportunity within this spectrum of uncertainty and projects are
typically launched to take advantage of these opportunities. Thus,
the whole point of undertaking a project is to achieve or establish
something new, to venture, to take chances, so risk has always been
an intrinsic part of project is to achieve or establish something
new, to venture, to take chances, so risk has always been an
intrinsic part of project work. However, in todays market, with
heavy competition, advanced technology and tough economic
conditions, risk taking has assumed significantly greater
proportions. No one can deny the importance of risk management on
modern day projects. Different approaches have been developed by
many researchers over the years for project risks, for example
project selection, as well as micro-level risks, such as scheduling
risks. Risk management, according to the PMBOK (2003), consists of
five phases starting with planning and finishing off with
monitoring. This process is repeated as cycles throughout the
duration of the project. The following figure 2.4 shows the
systematic risk management procedure.
9
Figure 2.4: Risk management process Each of these processes is
further sub-divided into sub-process with PMBOK (2000) clearly
showing the inputs, tools and techniques and outputs for each. The
fore researcher did many various investigations for the risk
regarding financing, contractual, operation risk and insurable
risks. It seems to neglect how the organizational risk factors
influence the project operation during construction stage. This
paper addresses the risk factors specifically focusing in
interlocked networks of project organization. To achieve
organizations long-term objectives, clearing the residual risks is
really important. The managing pressures for enhanced risk
assessment and reporting on internal control have increased around
the world. The reasoncorporate accounting failures, frauds,
internal control violations, and governance failures have been seen
in companies and countries that thought they were immune to these
events. These risks relate not only to reporting and compliance;
they also include strategic and operations risks. Although risk
assessment processes generally have improved, inadequate risk
reporting in some organizations has led to a failure to fully
integrate identified risks into strategic and operational
decisions. When planning a merger or an acquisition, for example,
how confident can one be about the expected gains without carefully
considering all potential risks, including their assessed magnitude
and probability of occurrence? Thus, decision-makers need to
understand the various organizational risks, to minimize the
production cost and unproductive time that can cause significant
organizational risks. To increase productive time, managers need
good risk reporting systems to integrate risk evaluation into
review of performance. Improved organizational risk assessment and
internal risk reporting is critical also for senior management and
boards of directors, who are responsible for carefully establishing
and reviewing corporate processes for identifying, assessing and
managing risk. The following are the principle of managing risk in
organization. 2.3.1 Communication and Coordination Effective
communication and coordination of project team members is a vital
role to achieve efficiency of construction project. Lack of
communication and coordination support heavily to happen project
failures and conflicts and to the dissatisfaction of project team
members. Industrial owner studies of failures, near failures and
problems with newly constructed projects indicate that at least 25
recent of those failures resulted from poor communication or
10
lack of coordination among the project team (Hensey, 1987 cited
in quality in constructed project, 1988). Communication Plan The
purpose of a project communication plan is to express what, who,
how and when information will be transmitted to project
stakeholders so schedules, issues and action items can be tracked
(Gray and Larson, 2008). The plan of communication is needed to be
done by the project manager and project team member since before
the project implemented. It may have some change during the
implementation to have effective communication. There are four
steps of identification make satisfy the communication which are as
follow (PMBOK, 2003). 1. 2. 3. 4. Communication planning
Information distributing Performance reporting Manage
stakeholders
Establishing a proper communication plan can have advantages of
project manager to control the flow of information instead of
responding to information requests. Moreover it reduces the
ambiguous and unnecessary interruptions of project team member, and
it can provide management greater autonomy. Coordination
Coordination of team members is occurred when multiple actors
pursue goals together, they have to do things to organize
themselves that a single actor pursuing the same goals would not
have to do. It is the act of coordinating, making different people
or things work together for a goal or effect. According to the
Grant and Baden-Fuller, 1995, these coordination mechanisms
include: 1) Rules and directives, 2) Sequencing Routines, 3)Group
problem solving and decision making. The effectiveness of
coordination mechanisms depends on the existence of common
knowledge, including the existence of common language and other
forms of symbolic communication (e.g. statistics), the commonality
of specialized knowledge, shared meaning, and the recognition of
individual knowledge domains (Grant, 1996). Decentralizes design
responsibility and increases the potential problems and the need
for effective coordination between the different types of systems.
The knowledge contained by the coordination tool is the most
critical factor for its effectiveness. Internal and external
knowledge sharing will be positively related to performance
(Cummings, 2001).This knowledge is represented as characteristics
of objects and applied to identify several types of problems with
preliminary designs and possibly give advice regarding solutions
that satisfy the multiple constraints. It also allows the tool to
identify detailed criteria that the coordinated construction
specific design must satisfy. The knowledge that the tool applies
to identify and assist in resolving problems in coordination
includes design requirements, construction requirements, and
knowledge related to the
11
remainder of the facility lifecycle. Although the most visible
parts of coordination focus on the geometry and functionality of
the systems, perhaps the greatest value added by the process
relates to construction, operation, and maintenance of the systems.
However, Coordination has many advantages as an analytic concept
here. For example, (a) it gives a powerful analytic grip by
immediately implying components such as goals and multiple agents,
and (b) it encompasses an intellectually coherent set of phenomena.
2.3.2 Inter-firm cooperation Inter-firm collaboration involves
explicit initiatives to enhance competitiveness through
organization cooperation. Organization may collaborate with one
another and with other organizations to integrate in learning
production, design and technology deployment of shared areas of
shared needs and opportunities. Views on the role of inter-firm
collaboration differ significantly on the issue of whether such
collaborations should be used to enhance existing
knowledge/capabilities of each partner (convergent development)
(Beamish, 1997) or to allow access to complementary capabilities of
others while focusing on exploitation of existing capabilities
within each firm (Dyer and Singh, 1998). Uniqueness of the human
asset is high and the value to the firm is high, the firm should
develop this asset internally, building a longterm relationship
based on mutual commitment (e.g. Intel engineers). 2.3.3
Cross-functional team It is a group of employees from various
functional areas of the organization research, engineering,
marketing, finance, human resources, and operations, for example
who are all focused on a specific objective and are responsible to
work as a team to improve coordination and innovation across
divisions and resolve mutual problems (Ford and Randolph, 1992).To
face today's complex challenges, organization needs to incorporate
a wide range of styles, skills, and perspectives. Cross-functional
teams are regarded as a means to manage social collaboration and
concept creation. Purpose of establishing the cross-functional team
in project organization: Design and develop new project; Chose and
implement new technologies throughout organization; To improve the
service-profit chain, and To control product costs To use the
resources effectively To accomplish the objectives efficiently The
following figure 2.5 shows the comparison of traditional and modern
functional model of project management.
12
Figure 2.5: Comparison of traditional and modern functional
model 2.4 Practical limitation of risk Management The process of
risk Management does not aim to eliminate all risks but to identify
appropriate strategies to assist project stakeholder to manage them
(Perry and Hayes, 1985). Risk management is defined as a systematic
controlling procedure for predicted risks to be faced in an
investment or project of organization. Risk management is the
systematic process of planning for, identifying, analyzing,
responding to, and monitoring project risk (Project risk management
hand book, 2007). It involves processes, tools and techniques that
will help the project manager maximize the probability and results
of positive event and minimize the probability and consequences of
adverse event as indicated and appropriate within the context of
risk to the overall project objectives of cost, time, scope and
quality. According to Murch (2000), several factors can influence
the success of risk management as follow. Senior managements
expectations about risk - do they understand the value of risk
management and, if not, how can they be persuaded? The corporate
culture and attitudes toward accountability - is there a culture
that can accept the need for accountability? The background,
skills, and experience of the project teams - management of risks
should be an important skill for all project teams.
Project risk management is an uncertain event or condition that,
if it occurs, has a positive or a negative effect on at least one
project objective. A risk may have one or more causes and, if it
occurs, one or more impacts (PMOBOK, third edition). Project risk
management is most effective when first performed early in the life
of the project and is a continuing responsibility throughout the
projects life cycle. Moreover, risk management encourages the
project team to take appropriate measures to:
13
Minimize adverse impacts to project scope, cost, and schedule
(and quality, as a result). Maximize opportunities to improve the
projects objectives with lower cost, shorter schedules, enhanced
scope and higher quality. Minimize management by crisis.
Alternatively, sometimes risk management is a temptation to
dismiss a risk because we cannot do anything about it anyway. There
are no viable mitigation strategies for some exception risks for
instances, currency exchange rates, and terrorist attack (9/11)
result in an estimated $31.7 billion loss. 2.4.1 Risk
Identification
Risk identification is the first step in the risk assessment
process. Careful determination of risk, along with analysis and
control of the hazards they create results in a plan of action that
anticipates difficulties that might arise under varying conditions,
and predetermines ways of dealing with there difficulties (Miller
and Lessard, 2001). The purpose is to surface risk events as early
as possible, thereby reducing or eliminating surprises. As a
consequence of risk identification, risk analysts can develop a
good sense of possible source of problems (or opportunities) that
will affect their organizations projects and operations (Frame,
2003). The organizational risk can be identified by different way.
(1) Checklists (2) Brainstorming sessions (3) Issues logs (4)
Behavioral models (5) Diagramming techniques (6) Flowcharting
project and process models (7) Regular meeting (8) Documentation
review (9) Interviewing (10) SWOT analysis (11) External audit Risk
identification is a repetitive process because new risks may become
known as the project progresses through its life cycle and
previously-identified risks may drop out (Project risk management
hand book, 2nd edition). Its important to specify the risk
correctly. For instance, a risk has a cause and if it occurs and
impact on a project objective. Simple and effective risk responses
can often be developed and even implemented as soon as the risk is
identified. There are many different tools and techniques for
practical risk identification as mentioned previously. The figure
2.6 shows the simple risk identification for the project
management.
14
Figure 2.6: Risk identification process Source: (PMBOK, Second
Edition) 2.4.2 Assessing impacts of risk events and evaluation
process
The risk analysis and evaluation process is the vital link
between systematic identification of risks and rational management
of the significant ones. It forms the organization for decision
making between different management strategies. The attempt to
assay the consequences of aking the occurrence of risk events is
called risk impact analysis. As a matter of convenience, risk
impact analysis split into two parts qualitative and quantitative
analysis. Qualitative risk analysi analysis is the process of
assessing the impact and likelihood of identified risks (PMBOK, 2nd
edition). It includes methods for prioritizing the identified risks
for further action, such as quantitative risk analysis or risk
response planning (Project risk management hand book, uantitative
2007). The method intends to examine the impacts of risk events
primarily through the application of a logical reasoning process.
By finding out the high-priority risks, organizations priority
risks can improve the projects performance effectively. Moreover,
it is one way to determine the importance of addressing specific
risks and guiding risk responses. Generally, the quantitative
analysis follows qualitative analysis but sometime it use together.
Due to the time and cost constraint, most researchers could not use
these together. The qualitative risk analysis is a way of
numerically estimating the probability that a project will meet its
cost and time objectives. Quantitative analysis is based on a
simultaneous evaluation analysis of the impact of all identified
and quantified risks. Although there are many tools and technique
for the method, Monte Carlo simulation is common run for
quantitative risk quan analysis based on the cost complexity or
high profile of the project (Project risk management Project hand
book, 2007). 2.4.3 Risk response planning
Risk response planning is the process of developing options, and
determining actions to enhance opportunities and reduce threats to
the projects objectives ((Project risk management
15
hand book, 2007). In case, risk identification allows to
determine what good and bad things might encounter when undertaking
and effort to do something. Risk impact analysis, both qualitative
and quantitative provides understanding the impact and consequences
of the occurrence of the identified good and bad things. The
question; what can be done to deal with the qualified risk events?
Risk response planning is concerned with how best to handle risk
events that can arise (Frame, 2003). Project Management is the most
widely found because for failure to meet project objects and goals
within todays project management bodies of knowledge, risk
management techniques are evolving as a key tool to maximize
achievement of the stakeholder goals (Nielsen, 2006). Generally
there have four approaches to mitigate the risks in large
engineering projects which those managerial strategies to cope with
risks are as follow (Miller and Lessard, 2001). (1) (2) (3) (4)
Shape and mitigate Shift and allocate Influence and transform
institutions and Diversify through portfolios.
Broad/systemic
Diversify Portfolios of project
Embrace residual risks of ownership
Influence and transform Institutions: rules and regulations
Indirect Direct shaping
Type of risks Specific to Project
Direct allocation and mitigation of controllable project
Shifting of indeterminate risks to co-specialized firms
Extent of control over risks
Figure 2.7: Strategies to cope with risks Source: Miller and
Lessard, 2001
16
2.5 Risks in interlocked networks of project organization An
organization can be modeled and characterized as a set of
interlocked networks connecting entities such as people, knowledge
resources, tasks and groups (Carley and Reminga, 2004). The
Metamatric shows ten significant controllable networks to improve
efficiency of the organization by setting up the accurate
preplanning. Risk management is a process of harnessing information
to help people make informed decision (Frame, 2003). If information
is lacking, this restricts the amount of effective risk management
that can be carried out. The collective power of team members is
the critical success factor of the construction project. The
effectiveness of coordination mechanisms depends on the existence
of common knowledge, including the existence of common language and
other forms of symbolic communication (e.g. statistics), the
commonality of specialized knowledge, shared meaning, and the
recognition of individual knowledge domains (Grant, 1996). Lack of
coordination among the cross-functionality which is the bottle neck
of the information coordination and knowledge sharing cause the
delay in task performing and decision making. The general
resourceconstrained project scheduling problem (RCPSP) arises when
a set of interrelated activities (precedence relations) is given
and when activity can be performed in one of the several ways
(modes) (Chelaka L. et.al., 2000). If the required resources are
not available on time, the management could not set up the logical
dependencies and resources for alternative activities of links.
Alternatively, if the workforce could not utilize the existing
resource effectively, the performance risk will be occurred in the
project. All the above factors are the priority to consider for the
efficiency of the project organization. If the organization fails
to take these risks properly, the project will move slowly while
the organization has to struggle the troubles. Finally, the unity
of stakeholders will be broken and the organization will meet
unexpected situation. The following figure 2.8 is the
organizational risk analyzer including internal organizational
networks.
17
Figure 2.8: Organization risk analyzer Source: Carley and
Reminga (2004) 2.6 Internal organizational networks Organization
risk analyzer consists of ten internal organizational networks for
organizational risk management. These are 1) Social network, 2)
Knowledge network, 3) Information networks, 4) Resource network, 5)
Resource usage requirement, 6) Inter-operability and Cousage
requirements, 7) Assignment network, 8) Knowledge requirement, 9)
Resource requirement and 10) Precedence and dependencies. As
mentioned in previous chapter, major four elements play in
organization as a vital role in the organization to achieve
long-term organization objectives. These can make the either
potential loss or gain as well reputation of the organization. In
the top management strategies, mitigation the risks is a priority
of organization to drive safely in the modern market economy.
However, controlling the critical risk factors which is occurred
due to the inter relationship among the elements is one of the ways
to mitigate the probable risks occurrence. This way enables the
organization to run the continuous projects efficiently. The
following section will explain deeply about the preferable to
control the internal organizational networks in organization.
18
2.6.1 Social Network Social network in construction organization
is examined how functional department and different interact with
each other, characterizing many formal or informal connections in
order to have effective communication and coordination. Social
network define as social relationship in which the members are the
individual actors within networks and ties are the relationships
between the actors. The power of social network is assumed by the
individual actors whether they are friendly or unfriendly, smart or
dumb, etc because 70 to 80% learning may be from informal
communication (Davenport and Prusak, 1998). Therefore, informal
communication is priority for knowledge sharing and continuous
learning for the team members. According to the literature,
upgrading knowledge networks is truly depended upon the social
relationship inside organization. Communication is the process by
which the information is exchanged and understood by two or more
people, usually with the intent to motivate and influence behavior
(Daft, 2006). These networks provided ways for organization to
gather information, deter competition, and even collude in setting
policies and strategies. Alternatively, social networks allow
members to organize around a persons relationships or interests
rather that just focused on objectives. People that know each other
(or want to meet each other) will connect by a variety of common
interests. These are great tools to get people of like interest to
connect to each other and share information. Social network theory
is the view that the structure of social relations in which actors
are embedded affects their behavior. These effects are assumed to
operate at the individual, organizational and even national level
(Mizruchi & Marquis, 2005). People are working together to
achieve of the organization objective which become their individual
objective beyond. To achieve the individual objective, first of
all, all must perform with their ultimate effort to complete their
respective specific objectives then which becomes the objective of
organization target. In order to accomplish organization mission,
the project, top management must understand the important of social
network how work it is because everything is done by people.
Therefore, the basic understanding of personal communication
becomes the major concerning for the social network because of the
better communication, the better crossfunctionality. Effective
cross-functionality is very important for all kind of organization
because it plays as a major role of the knowledge sharing and the
flowing information. Moreover, members of cross-functional groups
also have more opportunities than members of functionally
homogeneous groups because each has ties to people in different
domains (Ancona and Caldwell, 1992). A primary advantage of the
cross-functional structure is that it solves an information
processing problem (Davis & Lawrence, 1977; Galbraith, 1971).
It creates lateral communications channels not available in the
classical bureaucratic form of organization. If the
cross-functionality is not working properly, the information will
not flow easy and decision making will be slow. At the same time
the personal interaction will go down. Consequently, the employee
can not use their knowledge to utilize the resource which is
defined as performance risk. Besides, no good communication
channels are happened due to hierarchy structure which causes the
negative effective to the governance structure. According to Daft
(2006), centralization and decentralization pertain to the
hierarchical level at which
19
decision are made. In case we need to consider whether the
organization structure is too much centralize or decentralize not.
Each of the parties in construction- owner, designer, contractor
(or construction manager), and labor- has a distinct culture and
way of measuring the success or failure of a construction project
(Oglesby et al., 1989).The cultural problem is one of the sources
to damage the personal communication channel. Alternatively, Ego is
very influence to the personal interaction. Sometime people
frustrate because of working environment. There was a dispute
between the parties or individually in the construction project and
the dispute and some other factors were considerable mistrust
between parties and lack of constructive communication about
sensitive. Krackhardt (1992) showed that a unionization attempt
failed because the key actors union members had a poor
understanding of the actual friendship network. If there doesnt
have understanding within team members, they become pessimistic to
each other sooner as a result their performance is going down
because they try to compete in incorrect way. Even a superbly
designed work group will not be successful if members cannot create
a common, understanding of both the organizational context and the
task itself through communication about their work (Steines, 1972).
After all the above mentions factors combine together, various
disputes will emerge in the project and the negative result is
appeared finally from the project. To avoid these situations, all
team members must have good communication channels formally or
informally. Therefore, the regular meetings and orientation must
have for all specific tasks and projects which are very important
in order to improve communication and consistence information
flowing among project team members. 2.6.2 Knowledge network
It is transferring the individual knowledge from one to another
in the project team by defining as the provision or receipt of task
information, knowhow, and feedback regarding a product or
procedure. The purpose of knowledge sharing is to maximize the
knowledge, skills and abilities of the employees. Knowledge sharing
is necessary among group members for executing their work
effectively. Along with helping to create a common understanding of
the work being done, internal knowledge sharing can also increase
the awareness of who knows what in the group (Moreland and
Myaskovsky, 2000). As work group members share what they know with
one another over the course of a project, they should become more
efficient at solving problems and allocating responsibilities for
the task. However, knowledge sharing is affected by the distance
among the members of team because of the reducing time of social or
informal communication. According to Cummings (2001), geographic
distribution increases, internal knowledge sharing will decrease as
well as cross-functionality decreases, internal knowledge sharing
will decrease. By the knowledge sharing, within cross-functional
groups may access information and resources that being in different
geographic locations and representing different functional areas
provides.
20
The dynamic theory of organizational knowledge creation relies
heavily on the idea that an organization's primary role is the
integration and explication of tacit knowledge on all
organizational levels (Levina, 1999). The main function of
organizations in amplifying the knowledge is created by individuals
and crystallizing it as a part of the knowledge network of
organization. There are four types of interaction to upgrade the
organization knowledge network: Socialization (tacit to tacit),
Explication (tacit to explicit), and Combination (explicit to
explicit), and Internalization (explicit to tacit).The knowledge
conversion occurs through the spiral of organizational knowledge
creation, encompassing different organizational levels: 1. Sharing
of tacit knowledge by a group of individuals 2. Conversion of tacit
knowledge in teams into concepts and metaphors 3. Combination of
team-based concepts with existing data and external knowledge 4.
Articulation and development of concepts until they emerge into a
concrete form 5. Dissemination of new knowledge to others within
organization Organizational Behavior and Human Decision Processes
(Argote et al., 2000) have featured knowledge sharing as a form of
task communication in groups and organizations. The barrier of
knowledge sharing in organization is peoples boundary spanners.
Generally, people do not like to mix with different group and
different nature. Therefore, they try to avoid from them as much as
they can. If they are being separately longer, their habit becomes
their attitude which make boundary to themselves from the group.
The transfer of knowledge within the same function (horizontally)
is realized by boundary spanners in the organizational level. At
the same time, a vertical transfer of knowledge among different
organizational functions relies on the use of higher-order
organizing principles, sharing of accounting data, and through
formal and informal structures (Levina, 1999). Current theory is
that knowledge resides in people as well as in products or
procedures of the corporation, and this knowledge can be imitated,
copied, or transferred through communication (Zander and Kogut,
1995). Knowledge sharing is not constrained to exchanges within and
across employees of a company, but can occur between employees and
customers, other organizations, or firms in entirely different
industries (Hippel, 1988). 2.6.3 Information network
Information network is defined as the transferring required
information from one point to another and exchange knowledge by
internalization or technology acquisition. It is connections among
types of knowledge, metal model. In general, the concept of
information is closely related to notions of constraint,
communication, control, data, form, instruction, knowledge,
meaning, mental stimulus, pattern, perception, and representation.
The information of the construction project can specify feasibility
studies, drawings, approvals, schedules, specifications, standards,
method of works and other documents. According to the International
Project Collaboration (White Paper), Collaboration between
organizations is at the core of successful of project delivery and
depends largely upon the efficient and accurate exchange of
drawings documents and correspondence between team members. On the
other hand, as projects grow in size and complexity information
coordination becomes as critical success factor (Facility
Management Magazine Australia, 2006). There is no collaboration
within organization mean without the efficient, accurate exchange
and
21
management of information. In case, managing information can be
significant and can potentially support the project success. In
construction period, transmitting information within an
organization based on informal contacts between managers within an
enterprise and on distributed information systems. The effect of
not having a sufficient system in place for managing information
can be significant, and can potentially derail a project
(International Project Collaboration, white paper), the following
table 2.1 highlights how this can impact to the project in term of
time, cost and quality. Table 2.1: Sequence of risk due to lack of
information
Source: International Project Collaboration (white paper),
Aconex Due to the risks outlined above, there is a need for
large-scale international developments to implement a third-party
platform for managing information that allows collaboration between
multiple, dispersed team members. 2.6.4 Resource network
It means the continuous resource available for concurrent
activities in the construction project. It should be kept in mind
that a company is an organization that supports the many projects
undertaken by the company, generally in different geographical
locations and administered by quite autonomous project managers but
relying heavily on the support of the head office. Many problems
with real-life projects arise when activities require resources
that are available only in limited quantities and the demands of
concurrent activities cannot be satisfied (Woodworth and Shanahan,
1998 cited in Abeyasinghe, 2000). Not receiving the require
resource on time in order to start the altering the companion of
activities is major enemy of the construction project. Lack of
require resources lead to construction delay directly. The required
for each activity may be allocated individually or may come from
other activities that share the same resources (Zhang and Li,
2003). Schedulable activities at a time are combined based on the
available resource quantities and all combinations are evaluated
according to their impacts on project duration. In case, therefore
vendor competence and resource shortage are major hindrances for
the procurement to the parallel activities of the project.
22
2.6.5
Resource usage requirement
Resource usage requirement is defined combination of personal
knowledge of employee and supporting construction facilities to
employees in order to optimize the existing resource usage.
Technical competency refers to the physical assets of a company
such as machinery and equipment and the extent of technical knowhow
available that is necessary to undertake specific projects.
Improved information flow and flexibility of responses by team
members in a matrix can allow resources to be quickly and easily
disengaged from unproductive uses and applied to new opportunities
as they are discovered (Davis Lawrence et al., 1977). Nevertheless,
utilization the resource is depended upon not only the employee
competency on specific resource usage but also communication
channels and knowledge sharing within the project members.
Therefore, the project team members have good communication, and
coordination to optimize the available resource usage by
preplanning. However, sometime the nature of knowledge
(high-technology appliance) and sub-quality of resources play just
as the barrier for optimizing resource usage practically. 2.6.6
Inter-operability and co-usage requirement
It means that connections among resources and substitutions to
integrate the proper project schedule during execution period. Time
constrained resource scheduling in which the time constraints are
fixed and seek to resolve capacity overloads by manipulating the
timing of activities within their total float, and without
affecting the initial project completion time (Matthews, 1994).
Resource scheduling problem is depended upon the type of
construction project. For example, hydropower project located in
the remote area so geological barrier is the main constraint of
resource allocation such as mobilization of heavy equipments,
resource shortage for high technology equipment such as tunneling
machine. Therefore, preplanning resource allocation is necessary to
prevent the schedule delay. 2.6.7 Assignment Network
Assignment network is examined assigning tasks to employees
inside project and transferring employees within according to the
job requirement. There are many factors influence the job assigning
in the construction project such as insufficient workforce, job
satisfaction, functional workload. Different attitude and behavior
make people not to satisfy their new place. Moreover, perceptions
of work situations and environments which hinder desire out comes
will lead to dissatisfaction with certain aspect of the job (Judge
et al., 1995). On the other hand, assigning the incompetency of
critical employee in the project make conflict in project due to
lack of communication and coordination. 2.6.8 Knowledge
Requirements
The knowledge requirements mean the combination of individual
competency and supporting relevant document in task performing. The
knowledge for the task means shop drawings, schedules,
specifications, method of works, standards, procedures and other
relevant documents for the constructive design. Providing the right
information to the right people at 23
the right time, and helping people create knowledge and share
and act upon information in ways will measurably improve the
performance of organization itself and its partners. Frequent
information exchange or task communication seems crucial for
getting work accomplished in many groups and helping them performs
well (Allen et al., 1977). 2.6.9 Resource Requirements
Resource requirements means organization supporting the require
resource to project to perform the task effectively. Construction
managers need to develop activities schedule (Plan of Work) for
directing and controlling resources of workers, machines, and
materials in a coordinated and time-efficient fashion in order to
deliver a project within the limited funding and time available
(Halpin and Woodhead, 1998, cited in Lu et al., 2007). Personal
compulsory skill of each employee (watch over resource and
knowledge) which is required to look over the demand of next task
and systematic report to the management is important for the
resource scheduling. 2.6.10 Precedence and dependencies It is
defined as generation, verification and modification of
construction project schedule networks in PERT/CPM (Project
Evaluation and Review Technique/Critical Path Method) chart in
order to complete within estimated project period. Conventional
critical path method (CPM) and program evaluation and review
technique (PERT) scheduling procedures start with an assumption of
unlimited availability of resources for each project activity
(Cooke B and Williams P, 1998). In the real-life project, resource,
technology and information are the principle constraints of the
task precedence and dependencies. Logical dependencies and
resources (e.g., workforce, construction materials and equipments)
required when scheduling activities in a construction project.
Resource-constrained project scheduling accepts the priority of
fixed resource availability and permit not only sequencing and
float time to be altered (Matthews, 1994). Generally, this kind of
problem occurs when a set of interrelated activities (precedence
relations) is given and when each activity can be performed in one
of the several ways. The early and late dates calculated with the
critical path algorithm are based on the duration of the activities
in the project and the relationships or technologies constraints
between them (Chelaka L et al., 2000). It is noteworthy that the
scheduling logic of deterministic CPM which is necessary to define
by activity times, precedence relationships, resource requirements
and availabilities. 2.7 Summary System accident is born from the
confusion and interrelationships inherent in complex organizations
and mechanism. They have been termed normal accidents because they
are the unavoidable that comes with running improper systems. Most
of the construction project delay because of lack of communication
and coordination inside the project organization. Cross-functional
teams are regarded as a means to manage social collaboration and
concept
24
creation. Since different people come from the unlike
background, cultural and countries make distinct decisions which
cause various disputes in social network. If the conflict cannot
solve in the initial stage, it will become the critical risks of
the organization. Frequently, consequence of dealing with many
small risk events leads to inefficiency of project. If there has no
effective action taken in order to mitigate the risk events, we may
find that we are continuously redoing things that increase the cost
of doing business, slow operations, and lead to customer
disaffection which threat to efficiency of the project. As a
result, the organization face the commutative consequences add up
and can ultimately lead to terrible results. Therefore, top
management has to concern about the organizational risk factors
which make inefficiency of project.
25
CHAPTER 3 RESEARCH METHODOLOGY 3.1 Introduction The research
methodology is the guideline which tells a detailed plan or
explanation in setting standards for collecting and analyzed in
systematic way. It is important to comprehend because the
methodology framework which is the backbone of the research
studies. Therefore, it has to be explained what appropriate method
will be used and why this method is chosen in order to obtain the
research objectives. Furthermore, it prevents the prospected and
unforeseen problems during the study period. This Chapter shows all
of the thesis process in identifying the key risks. However there
are three main implementation steps suggested by Ashley and Bonner
(1987). It includes three main parts: 1) Information gathering, 2)
Organizational risk identification, 3) Qualitative impact
assessment. With respect to aforesaid implementation steps, the
methodology of thesis is relied on an information gathering
composing of reading from relevant literature, interviewing and
questionnaire will be discussed. However, the concept of risk
identification and analysis will be sued to obtain subjective
information. Influence diagram and knowledge map technique will be
used as research approach to communicate knowledge among people and
to gather or coordinate the fragment pieces of information that are
relevant to the event in question. 3.1.1 Selection of Research
Method According to Yin (1994), the selection of research strategy
depends on three condition consist of (a) the type of research
question posed, (b) the extent of control an investigator as over
actual behavioral events, and (c) the degree of focus on
contemporary as opposed to historical events. In order to obtain
the research objectives, there has five major research strategies
in the social sciences are experiments, surveys, archival,
analysis, histories, and case studies. The strategy chosen to
conduct the research is multiple cases study for it is answering
what and how research question, no control is required over
behavioral events and focusing on contemporary events. The evidence
from multiple cases is often considered more compelling and the
overall study is therefore regarded as being more robust (Herriott
and Firestone, 1983, cited in Yin, 2004). This study involves the
solicitation of information from the individuals using
questionnaires and interview (structure/unstructured). Thus it is
categorized as self report research (Gay, 1990). Besides, this
study requires the investigation of the current risk events,
rational of risk factor and events, practical limitation of risk
management so that case study is the most suitable method to carry
out. This strategy gratifies constraints of time, cost and
requirements of in depth understanding of the problems. A key
strength of the case study method involves using multiple sources
and techniques in the data gathering process (Soy, 1997).
Furthermore, a case study is an exploration of a bounded system or
a case over time
26
through detailed, in-depth data collection involving multiple
sources of information rich in context (Creswell, 1998). 3.1.2
Research Approach
Research approach is a modeling process. It is the fundamental
process in this study. The approach of research consists of six
stages of cognitive knowledge. Each part has its own value during
the process. The purpose of it is to fill gaps between what is
currently and what could be in the future by changing the
heuristics over time through various types of knowledge that can be
acquired: knowledge, comprehension, application, analysis,
synthesis, and evaluation (Arciszewski and Rossman, 1992). Research
approach is needed to set up a better job in solving problems.
Following research approach will enable researcher to experience
specific problem solving technique. It allows researcher to carry
out the study from the wide perspective down into detail aspect.
The first three processes are proposed to achieve descriptive
knowledge which is about identifying general (conscious)
heuristics. It helps the researcher to be familiar with the overall
general information regarding risk events particularly in
hydroelectric power implementation. Analysis process allows the
researcher to attain in depth facts and information of the elements
in rational of risk factors and their impact hydroelectric power
project. The knowledge being acquired here is procedural knowledge
which is about identifying routine procedures/ tasks. Structured
and unstructured interview, process tracing and simulations are
suggested to gain this kind of knowledge. Synthesis and Evaluation
processes make use the gathered information, organizing the facts
and components in the previous processes to be able to combine all
the elements and produce explanations to acquaint the phenomena and
to construct judgments based on standards application. Moreover,
comments and recommendations will be made. By following these two
respective processes, the researcher is able to gather semantic and
episodic knowledge. Semantic knowledge is to identify concatenation
of risk events. Task analysis and process tracing are suggested to
gain this knowledge. Research approach is the effective way to
achieve the objectives of the study. It allows systematic approach
in order to ensure smooth process, indicate the important aspects,
and avoid missing critical data. Additionally, the overall
processes support the development of the appropriate
recommendations for improvement for each phenomenon revealed.
Figure 3.1 shows the process of research for the study.
27
Site Observation
Literature Review
KnowledgeKnowledge Description
Comprehension
Organizational Risk Management
Professional Interview ApplicationPractitioner s
interviewsVerified factors and Framework for questionnaire
design
Procedural Knowledge Semantic and Episodic Knowledge
Analysis
Case Study Practice in real-life Hydropower Projects
(Myanmar)
Synthesis Evaluation
Information Comparison
Case Study Results Research Objectives
Figure 3.1: Research approach 3.1.3 Research Methodology
Framework
This study is consisted of four main parts: 1) factors
identification, 2) data collection, 3) data analysis and 5)
conclusion and recommendation. The first part is the factors
identification which is being carried out by literature reviews for
preliminary factors and verification. Highly concentrated
literature review provides the conceptual approach for
organizational risk factors in general and the operational elements
as the initial risk factors. Verification includes two integral
parts: application and analysis. Project organization has own
characteristics which distinguish it from parent organization. The
knowledge, facts, and information found in literature review then
have to be applied into the specific hydroelectric power project.
The identification approach and initial risk factors are then being
edited and added to adjust to the characteristics of hydropower
project. However, the edited risk factors and framework has to be
confirmed against the professionals. In this study, case study
strategy as one of the qualitative research techniques is utilized
to gain the data. Therefore, the first step is to design the
question for case study based on the approach edited in the
previous process. Utilization of edited approach and factors to
design the questions is found to give specific and effective
questions in order to gather the require information precisely. The
interviews are conducted in 3 places which are Heard Quarter of
Department of Hydropower Implementation (DHPI), Yeywa HPP
(Construction Division-2)
28
and Khun and Phyu HPP (Construction Division-3). Criteria for
judging the quality of research design are as followed: 1.
Construct validity: determining correct operational measures for
the concept being studied by using the evidence from medium to top
management people of two hydroelectric power projects regarding
organizational risk factors during construction stages. 2. Internal
validity by explaining the analysis of data collected from both
projects by applying illustrated research approach; what are the
organizational risk factors and how it influencing the efficiency
of project. 3. External validity: The research design is doing for
the same nature of the projects such as hydroelectric power project
which are located in the same country and participants in projects
are local, European and Chinese so the expected result will appear
from both projects in generally. 4. Reliability: The similar
results will be come out if the later investigator followed the
same procedures and conducted the same case study all over again
due to the appropriate research approach. Data analysis from the
case study enables the researcher to gain in-depth understanding of
influencing factors and interrelationship of risk factors included
in internal organizational networks. Each answer for the question
between two specific hydroelectric power projects in the case study
protocol is examined and compared by pattern matching technique.
Then the exploration of overall risk factors is carried by using
cross-case synthesis technique. The result is then being thoroughly
incorporated to achieve the objectives of the study. The conclusion
and recommendation will mention in the final stage which is then
given against the dilemma and phenomena found from case studies.
The methodology process of the study is in Figure 3.2.
29
Figure 3.2: Research Methodology Framework
30
3.2 Risk Factors identification Improper arrangement of the
organizations structure makes various series of problems affecting
on the project-organization. The Meta-Matrix, organization risk
analyzer (Carley and Reminga, 2004) is a theoretical framework for
representing the various network relations of an organizational
system. By using Meta-Matrix as an analyzer can find out the
organizational risk factors affecting on the project-organization
in term of risks. Moreover, this framework is important to this
study because it allows for the definition key risk factors and
analysis of the rationale organizational factors to project risks
of the study. In the Meta-Matrix framework, organizations are
defined by a set of networks under four classifications: personnel,
knowledge, resource and tasks/projects. The following figure 3.3
shows the organization risk analyzer which include internal
organizational networks.
Figure 3.3: Organization risk analyzer Source: Carley and
Reminga (2004)
31
3.2.1
Interviewing and verification of initial risk factors
Meta-Matrix network analysis can capture higher levels of
complexity and provide specific reason of the problem at different
levels of analysis in organization. Expanding the analysis to
higher organizational levels will provide increasing benefit to
existing. At this step, an interviewing is suggested to obtain
subjective factors. This process involves an investigation with all
possible potential sources of project risks and their consequences.
In addition, their causal interrelationships between each different
risk are discussed. The interviewing material includes the
characteristics of practical risk management and methodology for
collecting data. Objectives of interviewing are to identify the
possible risk factors and sub-factors and practical risk management
process of DHPI. Major input risk factors are come out from the
literature review and professional interviews. Verification of
risks factors In this step, selected professionals advice for the
required studies materials identifies major gaps in the knowledge
base and the simple questionnaire. Then the practical risk factors
are judged in hydropower project and the organizational risk
management process will be highlight. The objectives of factors
validation include the following (Badiru, 1992 cited in Puthamont,
2006): completeness, efficiency, validity, consistency, clarity.
This judgment is based on whether all sub-areas have been included,
and in the correct proportions. The real practices, phenomena, and
important factors are the complementary result from the
verification process. Professional interview Since professional
interviews are important role on determining the objective
achievement of the research, theoretically there are several
criteria to be fulfilled by the professionals to be selected. The
interviewing is especially for the proper practice of factors
applying to the real project. The structured interview was being
for the initial factors identification for the research design and
questionnaire are discussed with the experienced before going to
practice in the cases study. Selected experienced professional is
an Assistant Supreme Engineer (Deputy Project Director) of Planning
and Work Department in order to make sure the organizational risk
factors. The selected professional has 20 years experience in
planning and works of DHPI hydroelectric power projects. The
interviewee is closer friendship with the researcher and eager
interesting in the current study. In the interviews, the researcher
discuss about subjective factors related to organizational factors
which obtained from the literature review, books and other sources.
Finalization the framework of study is made sure by the Project
Director of Con (A) after the second interview based on the
rational understanding of subjected organizational factors of
project organization. The figure 3.4 presents the process of
verification risk factors for questionnaire in order to practice in
project.
32
Figure 3.4: Verification risk factors and questionnaire process
: The verification risk factors in project organization is
important for the study because the rationale of organizational
risk factor to project risk is necessary to find out for the cases
study interviews and checklist in order to gather the concrete
results of the analysis. Therefore, first results practitioner of
verification initial risk factors was from organizational level and
then 2nd in practitioners of interviews for verified questionnaires
based on verified risk factors was views project director of
construction division (2). The following figure 3.5 shows the
verified organizational risk factors for the interview and
checklist.
33
Figure 3.5: Verified organizational risk factors 3.3 Data
Collection As most qualitative case studies, this study combined
different data collection methods, such as archives, interviews,
questionnaires, and direct observations at formal and informal
meetings (Eisenhardt 1989). The primary source of information was
interviews with individual interviewees from two construction
divisions (3 projects). Selected interviewees were selected by
randomly for personal interviews from different part of project
such as Dam portion, tunneling, powerhouse construction and
electromechanical portion. The data is gathered through in depth
question following the factors and their relationship identified in
the previous process to ensure complete information and details as
well as point out the necessary and critical factors. There are
many steps to collect data, as follows: 1. Selecting the projects
by using the researchers network. Since in depth question interview
regarding practical risk management for case studies is very
sensitive 2. The researcher applies to the top management for the
permission of making interview with employees and site observations
in order to avoid the unforeseen barriers in the projects. 3.
Contacting the selected respondents either by telephone or official
mail to make further appointment as well on site. 4. Staying on
sites and conducting the personal interviews and discussions.
34
3.3.1
Checklist Design
There are two kind of checklist for comprehend practical risk
management of organization and for identify the possible risks
considered by professionals from the initial interviewing. What is
needed now is to determine their degree of impact to the efficiency
of project qualitatively asking in checklist which risk factors
already identified are most important in hydropower projects by
practicing in real cases. There are 2 types of question include in
interview with practitioner in the project. These are 1. Why is the
risk happened in the project regarding organization? 2. How does it
impact to the project efficiency which leads to delay? 3.3.2 Pilot
test
It is an initial run of a study (e.g. an experiment, survey, or
interview) for the purpose of verifying that the test itself is
well-formulated. The pilot test is conducted for checking the
degree of accuracy and reliability of gathered information through
interviews, interviewing skills and contents of questionnaire to
make possible corrections and preparation for personal interviews.
Two pilot tests did to an assistant supreme engineer and a staff
officer in order to check the degree of accuracy and reliability of
gathered information through interviews, interviewing skills and
contents of questionnaire to make possible corrections and
preparation for personal interview before practiced in real cases
study. 3.3.3 Project selection for case studies
The selected hydropower projects are undertaken by DHP those
which are in Yeywa, 790MW (Mandalay Division) and Kun (60 MW) and
Phyu (40 MW), Bago Division in Myanmar. Yeywa project is under
construction division (2) and the rest projects are under
construction division (3). Although the size of projects is quite
different, the characteristic is similar to each other due to the
kind of hydroelectric power project. Furthermore, they are
similarities to technology appliance, climate and participants to
ensure similar problem encountered. 3.3.4 Interview Plan
Data collection is carried out in three place 1) Headquarter