Page 1
KERALA WATER AUTHORITY
KIIFB- AUGMENTATION OF WSS TO KOLLAM
CORPORATION PHASE II- PACKAGE II-
CONSTRUCTION OF 20LL OHSR AT VASOORICHIRA
TENDER NO.06/2018-19/SE/Q
DUE DATE :18-06-2018 at 3.00 pm
NOTICE INVITING TENDER
VOLUME II
SCOPE OF WORK
OFFICE OF THE SUPERINTENDING ENGINEER
KERALA WATER AUTHORITY
JALABHAVAN, KOLLAM
KERALA STATE
TELE .0474 – 2745293
Page 2
Tenderer Superintending Engineer
CONTENTS
Page No.
1. General information -
2. Scope of the Tender -
3. Detailed Scope of Tender -
4. General Specification & Requirement -
5. Vendors List -
6. Additional Information -
7. Maintenance -
8. Assessment Cost of work -
9. Implementation schedule -
10. Clarifications -
11. Corrections and Nodifications -
12.. Annexures -
Page 3
2
KERALA WATER AUTHORITY
KIIFB- AUGMENTATION OF WSS TO KOLLAM
CORPORATION PHASE II- PACKAGE II-
CONSTRUCTION OF 20LL OHSR AT VASOORICHIRA
SCOPE OF WORK
1. GENERAL INFORMATION
Kollam is a coastal city on the banks of Ashtamudi Lake that took the title God's
Own Country without much doubt. The city lies about 71 kilometers north of the state
capital, Thiruvananthapuram. The city hosts the administrative offices of Kollam
district and is a prominent trading city for the state. It is connected to all the important
towns in Kerala both by roads and railways.
Kollam town is provided with water supply from Sasthaamcottah lake, a fresh water
lake, situated about 26 Km away from Kollam city. Supply of water from this scheme is
limited due to shortage of water in Sasthamcottah Lake. Hence it is proposed to
augment the scheme with source as Kallada River. The scheme is proposed to be
implemented in three phases. Phase– I is sanctioned under AMRUT and Phase –II under
KIIFB. Phase - III will be taken up later.
2. SCOPE OF THE TENDER
Scope of the tender covers the following components and auxiliaries.
2.1 Design & Construction of 20 LL Capacity OHSR at Vasoorichira.
2.2 Maintaining the components supplied, installed and constructed as part of this
contract during the maintenance period from the date of commissioning of the
scheme in a satisfactory manner acceptable to the Executive Engineer, in
accordance with clause 8.24 of Volume 1.
2.3 Handing over all the components supplied, installed and constructed under this
contract to Kerala Water Authority with necessary documents and list of items after
completing the works, in accordance with clause 8.26 of Volume 1.
Page 4
3
3 DETAILED SCOPE OF TENDER
Detailed scope of the work is as follows
3.1 Design of the OHSR considering the specific site conditions, soil investigation report
and design requirements.
3.2 Construction of the OHSR as per the approved design and requirements mentioned
in this scope of work.
3.3 The Over Head tank at Vasoorichira shall be rectangular in shape of capacity 20
Lakh litres. The out let level and inlet level of the service reservoir shall be +23.960m
& + 27.560 m respectively. The average ground level at site is +3.630m.
3.4 The tank shall be provided with the following pipe specials, valves etc.
a. 500 mm CI wall casting pipes for outlet
b. 2 Nos. of 350mm CI wall casting pipes for inlet & overflow
c. 1 No. 350mm CI wall casting pipes for scour arrangements
d.1 No. 500mm CI DF sluice valve (class II) for outlet
e. 1 No. 200 mm CI DF sluice valve (class II) for scour
f. 350mm DI Double flanged pipes of sufficient length shall be connected for inlet and
overflow arrangements.
g. 500mm DI Double flanged pipes of sufficient length shall be connected for outlet
arrangements.
h. 200mm CI Double flanged pipes of sufficient length shall be connected for scour
arrangements.
i. CI duck foot bends with proper anchoring should be provided at the ground level
of each vertical connection.
j. DI/CI vertical connection pipes and exposed portion of pipe specials shall be
painted with suitable paint of approved quality and color.
3.5 It is proposed to utilize the bottom portion of the OHSR in ground floor and 1st floor
as staff quarters/store/office. Slabs shall be provided at 1st & 2nd brace levels
suitably designed so that the space can be utilized for the above purpose.
Foundation, columns, Braces, slabs etc. shall be designed considering the probable
load due to the weight of partition walls and live loads on slabs as per standard
specification.
3.6 The site shall be leveled properly. 1 No. of suitably designed RCC stair case of
minimum width 0.90m shall be provided to facilitate movement of men and
Page 5
4
materials from ground to floor level of the reservoir. Two Nos.M.S. Ladder 50cm
inside spacing using 50 X 12mm M.S.flats and 2 Nos 16mm MS Rods welded to the
stringers at 30cm c/c shall be provided for stepping from floor slab to roof slab. 1
No. MS ladder shall be provided for inside of the tank. Balcony slab of minimum 1.0m
width and 12cm thickness shall be provided around the reservoir.
3.7 Minimum 34 Nos. 100mm C.I S&S, Slotted Vent Cowl (Terminal Guard with
mosquito net and 4 Nos. – Rectangular CI manhole cover 455x610 mm with frame
(low duty) shall be provided.
3.8 Hand rails using 25mm GI class B pipes @1m C/C as verticals, 25mm GI Class B pipes
@ 0.50m as horizontals and each vertical post immersed in cement concrete shall be
provided around roof slab and balcony slab and the hand rail shall be painted with
approved steel primer and aluminum paint two coats. Stainless steel hand rails
approved by the Engineer – in- charge shall be provided around the stair slab
wherever necessary.
3.9 The OHSR shall be tested before plastering for its water tightness by filling with
water supplied by the contractor.
3.10 All the design shall be in accordance with IS 456:2000, IS 3370 (Part II) - 2009 with
latest amendments. Levelling course with M15 shall be provided below column
footing. Concrete Mix not leaner than M25 for piles, pile caps, column footings,
columns, braces and floor beams, and M30 for floor slab, balcony, side wall, column
inside tank, roof beam and cover slab shall be used. If pile foundation is proposed,
method of piling is to be specifically mentioned in the design. If strip footing or other
foundations are proposed, the way of execution is to be specifically mentioned in the
design. Earth quake resistant design is to be followed. High yield strength deformed
bars or tor steel bars as per NIT shall be used as reinforcement. Plastering shall be
in cement mortar 1:3, 12mm thick 1 coat for all exposed surfaces. Inside the
reservoir shall be plastered with cement mortar 1:3, 12mm thick 2 coat including
flushing coat with 2% water proofing compound.
3.11 A minimum free board of 15 cm below the bottom of the roof beam shall be
provided.
3.12 Soil investigation details are attached with the NIT for reference. If necessary the
contractor has to carry out his own soil study for design and construction. The
Page 6
5
design shall be got approved by the Design wing of Kerala Water Authority
(WASCON) before construction work is started.
3.13 The site for OHSR is the WTP site at Vasoorichira. The land is marshy and piling is
proposed as foundation for WTP components and OHSR. However the foundation
shall be finalized and approved as per clause 2.2.12 above.
3.14 The access to the tank site shall be formed suitably by cutting or filling earth as per
site requirements for enabling the conveyance of materials. Painting exterior walls
with two or more coats of Acrylic Smooth exterior paint of required shade including
priming coat of exterior primer applied @ 2.20 kg/ 10 sqm) as directed shall be
done.
3.15 Painting letters or figures of approved size (Block, Roman, Italic/Indian) 30.00cm
height with black Japan paint of approved brand and manufacture etc as per
direction. (KERALA WATER AUTHORITY - KIIFB 2016-17 - AUGMENTATION OF
WSS TO KOLLAM CORPORATION- PHASE -II – 20 LAKH LITRES OHSR-
VASOORICHIRA) as directed by the departmental officers shall be done.
3.16 All steel work including GI hand rails shall be painted with Deluxe Multi Surface
Paint two or more coat applied @ 0.90 ltr/10 sqm over an under coat of primer
applied @ 0.80 ltr/10 sqm of approved brand and manufacturer to give an even
shade as approved by the Engineer in charge.
3.17 Suitable capacity lightning arrestors as approved by the engineer in charge shall be
provided at suitable location.
3.18 Properly designed water level indicator as approved by the Engineer in charge for
easily identifying the water level in the tank at any time shall be provided.
3.19 2 Nos. RCC valve chambers of inside size 2.0mx1.50m and 1.50m height with
bottom leveling course shall be provided.
3.20 A common chamber of suitable size to collect the wash water and overflow from
the OHSR shall be provided in the compound and the water collected in this chamber
shall be conveyed to the “waste water recycling unit constructed as part of 100 MLD
WTP” by laying 160mm or higher dia. uPVC pipe with pressure rating 6 kg/cm2 of
sufficient length. (If the waste water recycling unit is not constructed even at the end
period of this work, the pipe should be laid near to the location of “waste water
recycling unit as per approved layout of WTP and connected components”.
Page 7
6
3.21 The approved layout of TP and other components will be furnished to the
contractor and the contractor shall accept the location of the OHSR in the approved
layout. Soil investigation is to be carried out by the contractor at this location before
submitting the design. If pile foundation is proposed and approved for the OHSR,
piling works are to be completed before starting the work of superstructure of the
TP components in the compound. The contractor shall wait for completion of piling
works of TP components to start the super structure of OHSR. The selected
contractor shall submit proposed time schedule for execution and the same will be
approved by the Executive Engineer considering the time schedule for execution of
the TP components. Both contractors shall work in harmony to safeguard the
interest of the department and their own. Disputes if any with the contractor of TP
shall be informed in writing to the Executive Engineer and the decision of the
Executive Engineer or higher authority shall be accepted.
3.22 Land scaping shall be done at the OHSR premise as directed by the Engineer in
charge
Any further requirements related to the construction work if directed by
concerned Engineers have to be met with. All technical specifications as per NIT
have to be fully satisfied. All the design shall be in accordance with IS 456:2000, IS
3370 (Part II) - 2009 with latest amendments. Soil investigation details are attached
with the NIT for reference. If necessary the contractor has to carry out his own soil
study for design and construction. The design shall be got approved by the Design
wing of Kerala Water Authority (WASCON) before construction work is started. The
access to the tank sites shall be formed suitably if necessary as per site
requirements. Minimum M 30 mix has to be used for reinforced concrete water
retaining portions of all structures. Other reinforced concrete components shall be
with minimum M25 design mix. Excavation is to be carried out through all classes
of soil including rock if any up to the required level. If pile foundation is necessary,
the same has to be carried out by the contractor as per approved design and
recommendations of design approving authority.
4 GENERAL SPECIFICATIONS AND REQUIREMENT
These Specifications cover the items of work in structural and non-structural
parts of the Works coming under purview of this document. All work shall be
carried out in conformation with this unless specified otherwise. In general,
Page 8
7
provisions of Indian Standards, Indian Roads Congress Codes, MORTH
Specifications for Roads and Bridge Works (III Revision) and other national
standards have been followed. These Specifications are not intended to cover the
minute details. The work shall be executed in accordance with best modern
practices. All codes and standards referred to in these Specifications shall be the latest
edition including all applicable Official Amendments and revisions thereof.
4.1 Storage of materials:
The conveyance, unloading and stacking of materials procured for the project will
be the responsibility of the tenderer. Authority takes no responsibility for
providing material stack yard. Tenderer will not be allowed to stack the materials
on road side in such a way to causes hindrance to normal traffic.
4.2 Safety at site:
Tenderers alone shall be responsible for any damage to men and materials and that
may occur at site due to lapses in safety measures. During night hours, contractors
shall provide sufficient lighting and watching at the site. Failure to adhere to these
clauses shall attract fine and penalties by way of deductions from the payments to
contractors at an amount worked out at department rates.
4.3 Approval of Materials
4.3.1 Approval of all sources of material for Works shall be obtained in writing
from the Executive Engineer before their use on the project. The contractor shall
verify that the entire quantity required for the work could be obtained from the
approved locations from where material is to be taken. Any extra lead, in the
eventuality of material not being available at the said locations, will not be allowed,
should be locations subsequently approved be located at a distance involving more
lead.
4.3.2 Where the terms crushed gravel/shingle, crushed stone, broken stone or
stone aggregate appear in any part of the Tender Documents for work, they refer to
crushed gravel /crushed shingle / crushed stone aggregate obtained from an
integrated crushing plant having appropriate primary crusher, secondary crusher and
vibratory screen.
4.3.3 Raw and processed samples of the mineral aggregates from the approved
quarry shall be submitted by the Contractor at no extra cost.
4.4 Use of equipment of work
The following conditions regarding use of equipment’s on works shall be followed
Page 9
8
4.4.1 The Contractor shall be required to give a trial run of the equipment(s) or
establishing their capability to achieve the required Specifications and tolerance to the
satisfaction of the Engineer before commencement of the work.
4.4.2 All equipment’s provided shall be proven efficiency and shall be operated
and maintained at all times in a manner acceptable to the Engineer.
4.4.3 No equipment or personnel will be removed from site without permission of
Engineer.
4.5 Quality Control on Works and Materials
4.5.1 The Contractor shall be responsible for the quality of the work in the entire
construction work within the contract. He shall, therefore, have his own independent
and adequate set-up for ensuring the same.
4.5.2 The Engineer shall inspect the work from time to time during and after
execution of work and ascertain the quality of the work tested (by himself, by his
Testing and Quality Control Units or by any other agency deemed fit by him) generally
as per the requirements of the CPHE EO Manual. Additional tests may also be
conducted where, in the opinion of the Engineer, need for such tests exist.
4.5.3 The Contractor shall provide necessary cooperation and assistance in
obtaining the samples for tests and carrying out the field tests as required by the
Engineer from time to time.
4.5.4 The Contractor shall carry out modification in procedure of work, if any, as
directed by the Engineer in charge during inspection.
4.5.5 Works falling short of quality as per tests indicated in Clause 4.5.3 above
shall be rectified by the Contractor as directed by the Engineer at his own cost.
4.5.6 For testing of samples of soil, soil mix, granular material and mix, bituminous
mix, aggregates, cores etc. Samples in the required quantity and form shall be supplied
to the Engineer in charge by the Contractor at his own cost.
4.5.7 For cement, bitumen and similar other materials where essential tests are to
be carried out at the manufacturer’s plants or at laboratories approved by the
Executive Engineer other than the site laboratory, the cost of samples, sampling,
testing and furnishing of test certificates shall be borne by the Contractor. He shall also
furnish the test certificates to the Executive Engineer.
4.5.8 For testing of cement concrete at site during construction, arrangement for
supply of samples, shall be made by the Contractor as per the frequency and number
Page 10
9
of tests specified in the Handbook of Quality Control for Construction of roads and
runways, IRC Special Publication No. 11, and relevant IS codes or relevant Clauses
(1702, 1704, 1707, 1717 etc.,) as specified for in MORTH Specifications for Roads and
Bridge Works (III Revision).
4.5.9 The method of sampling and testing of materials shall be as required by the
IS Standards. In the absence of relevant Indian Standards, the sampling and testing
procedure to be used shall be as approved by the Executive Engineer.
4.5.10 Where the Executive Engineer considers that in the interest of the control of
the quality on materials or workmanship, modifications, if any, are necessary, such
modifications shall be carried out by the Contractor at no extra cost.
4.5.11. The carriage and stacking of materials shall be done as directed by the
Engineer in charge. Any tools and plants required for the work shall be arranged by
the Contractor.
4.5.12. Responsibility for Loss or Damage - Loading, carriage, unloading and
stacking shall be done carefully to avoid loss or damage to the materials. In case of any
loss or damage, recovery shall be affected from the Contractor at twice the
departmental issue rates of the materials. If the departmental issue rates of the
materials are not available then the recovery shall be affected at twice the prevailing
market rates as determined by the Executive Engineer.
4.6 Carriage of Materials
The carriage and stacking of materials shall be done as directed by the Engineer in
charge. Any tools and plants required for the work shall be arranged by the
Contractor.
4.6.1 Responsibility for Loss or Damage
Loading, carriage, unloading and stacking shall be done carefully to avoid loss or
damage to the materials. In case of any loss or damage, recovery shall be affected from
the Contractor at twice the departmental issue rates of the materials. If the
departmental issue rates of the materials are not available then the recovery shall be
affected at twice the prevailing market rates as determined by the Executive Engineer.
4.6.2 Mode of Carriage
Depending upon the feasibility and economy, the Engineer in charge shall
determine the mode of carriage viz. whether by mechanical or animal transport or
manual labour.
Page 11
10
4.6.3 Stacking, Covering and Protection
4.6.3.1 Material shall be stacked in such a manner as to ensure the preservation of
their quality and fineness for the work. Different types of materials shall be stacked
separately and in such a way that counting and measurements can be done without
disturbing the stacks. Any material that is liable to be affected by rain or other
adverse weather conditions shall be covered and protected against the same.
4.6.3.2 Earth, dismantled materials, malba and other similar materials shall be
stacked as directed by the Engineer in charge.
4.6.3.3 Cement bags, steel bars, structural steel sections, bricks and timber
and other similar materials shall be stacked in regular tiers.
4.6.3.4 Pipes of RCC, DI, PVC, GI, CI, MS etc. shall be stacked in rows.
4.6.3.5 Lime stone, metal, sand and such similar materials shall be stacked as
directed by the Engineer in charge.
4.6.4 Measurements
Length, breadth and height of stacks shall be measured correct to 1(one) cm. The
quantity shall be worked out in cubic meter correct to two places of decimal. The
volume of stacks shall be reduced by percentages as shown against each for looseness
in stacking to arrive at the net quantity for payment. No reduction shall be made in
respect of articles or materials for which mode of payment is by length or weight or
number.
4.7 Earthwork, Erosion Control and Drainage
Earth work excavation shall cover all classes of soil including hard rock, in
accordance with the requirements of lines, grades and cross sections. Hard rock
requiring blasting but where blasting is prohibited for any reason shall be excavated
by chiseling, wedging or any other agreed method.
4.8 Slips and Slides
If slips, slides, over-breaks or subsidence occur in cuttings during the
process of construction, they shall be removed at the cost of the Contractor as ordered
by the Engineer- in- charge. If slips occur, the slipped material shall be removed and
dressed to a modified stable slope. Removal of the slipped earth will not be paid for if
the slips are due to the negligence of Contractor. Adequate precautions shall be taken
to ensure that during construction, the slopes are not rendered unstable or give rise to
recurrent slides after construction. If finished slopes slide into the roadway
Page 12
11
subsequently, such slides shall be removed and paid for at the Contract rate for the
class of excavation involved, provided the slides are not due to any negligence on the
part of the Contractor. The classification of the debris material from the slips, slides
etc., shall conform to its condition at the time of removal and payment made
accordingly regardless of its condition earlier.
4.9 Dewatering
If water is met within the excavations due to springs, seepage, rain or other causes,
it shall be removed by suitable diversions, pumping or bailing out and the excavation
kept dry whenever so required or directed by the Engineer- in- charge. Care shall be
taken to discharge the drained water into suitable outlet as not to cause damage to the
works, crops or any other property. Due to any negligence on the part of the
Contractor, if any such damage is caused, it shall be the sole responsibility of the
Contractor to repair / restore to the original condition at his own cost or compensate
for the damage. Sumps made for dewatering must be kept clear of the excavations /
trenches required for further work. Method of pumping shall be approved by
Engineer; but in any case, the pumping arrangement shall be such that there shall be
no movement of subsoil or blowing in due to differential head of water during
pumping. Pumping arrangements shall be adequate to ensure no delays in
construction.
4.10 Filling, Backfilling
All fill material will be subject to Engineer's approval. If any material is rejected by
Engineer- in- charge, Contractor shall remove the same forthwith from the site at no
extra cost. Surplus fill material shall be deposited / disposed off as directed by
Engineer- in- charge after the fill work is completed. No Quarry dust/earth fill shall
commence until surface water discharges and streams have been properly
intercepted or otherwise dealt with as directed by Engineer- in- charge.
The Backfilling should be done with Red Earth / Quarry dust wherever necessary.
Fill material shall be free from clods, salts, sulphates, and organic or other foreign
material. If any selected fill material is required to be borrowed, Contractor shall
make arrangements for bringing such material from outside borrow pits. The
material and source shall be subject to prior approval of Engineer- in- charge. The
approved borrow pit area shall be cleared of all bushes, roots of trees, plants, rubbish
etc. top soil containing salts / sulphate and other foreign material shall be removed.
Page 13
12
The materials so removed shall be burnt or disposed off as directed by Engineer.
Contractor shall make necessary access roads to borrow areas and maintain the
same, if such access road does not exist, at his cost.
4.11 General site grading
1. Site grading shall be carried out as insisted by the Engineer- in- charge.
Excavation shall be carried out as specified in the Specification. Filling and
compaction shall be carried out as specified.
2. If no compaction is called for, the fill may be deposited to the full height in one
operation and leveled. If the fill has to be compacted, it shall be placed in layers not
exceeding 225 mm and leveled uniformly and compacted.
3. To ensure that the fill has been compacted as specified, field and laboratory tests
shall be carried out by Contractor at his cost.
4. Field compaction test shall be carried out at different stages of filling and also
after the fill to the entire height has been completed. This shall hold good for
embankments as well.
5. Contractor shall protect the earth fill from being washed away by rain or
damaged in any other way. If any slip occurs, Contractor shall remove the affected
material and make good the slip at his cost.
6. The fill shall be carried out to such dimensions and levels as indicated on the
Drawings after the stipulated compaction. The fill will be considered as incomplete
if the desired compaction has not been obtained.
8. If so specified, the rock as obtained from excavation may be used for filling and
leveling to indicate grades without further breaking. In such an event, filling shall be
done in layers not exceeding 500 mm, approximately. After rock filling to the
approximate level, as indicated above has been carried out, the void in the rocks
shall be filled with finer materials such as sand, broken stone, etc. and the area
flooded so that the finer materials fill up the voids. Care shall be taken to ensure
that the finer fill material does not get washed out. Over the layer so filled, a 100
mm thick mixed layer of broken material and earth shall be laid and consolidation
carried out by a 12 tonne roller. No less than twelve passes of the roller shall be
accepted before subsequent similar operations are taken up.
Page 14
13
4.12 Fill density
The compaction, only where so called for, in the schedule of quantities / items shall
comply with the specified (Proctor / Modified Proctor) density at moisture content
differing not more than 4 percent from the optimum moisture content. Contractor
shall demonstrate adequately at his cost, by field and laboratory tests that the
specified density has been obtained.
4.13 Inclusive documents
The provisions of special conditions of contract, those specified on the tender as
well as execution Drawings and notes or other Specifications issued in writing by
the Engineer shall form part of these Specifications.
4.14 Order of precedence, clarifications and interpretation
When the various Specifications and codes referred to in preceding portion are at
variance with these Specifications and with each other, the following order of
precedence will generally be accepted.
1. Written instructions of the Executive Engineer.
2. Special Conditions of Contract, Special specifications Item wise Technical
Specifications, if provided, and Execution Drawings.
3. Provisions of Standard Specifications.
4. I.S. Codes.
5. IRC Codes, MORTH Specifications, etc.
6.The Manual on Water Supply and Treatment and the Manual on Sewerage and
Sewage Treatment issued by CPHEEO, Ministry of Urban Development, New Delhi.
7. The attention of the Contractor is drawn to those Clauses of IS codes which
require either Specification by Executive Engineer or the mutual agreement
between the supplier and purchaser. In such cases it is the responsibility of the
Contractor to seek clarification on any uncertainty and obtain prior approval of
the Executive Engineer before taking up the supply/construction.
4.15 Unacceptable work
All defective Works are liable to be demolished, rebuilt and defective
materials replaced by the Contractor at his own cost. Defective materials
demolished from work site for bad work have to be removed from work site by the
contractor, at his own expense, latest within a week, failing limit the Engineer shall
get it removed from the site in a manner he deems fit and the expenditure towards
Page 15
14
this shifting shall be removed from the bills of the contractor delay with penalty as
deemed fit by the engineer. In the event of such Works being accepted by carrying
out repairs etc. as specified by the Engineer, the cost of repairs will be borne by the
Contractor.
The relevant Indian Standards and the rules and regulations of local authorities in
regard to safety provisions shall be observed.
4.16 Water Tightness test
All hydraulic structures, either water supply or drainage etc., such as sewer lines,
joints etc., or any other liquid containers shall have to be tested for water tightness.
The Contractor shall give all such hydraulic tests by making his own arrangements
for water filling and disposal of water after the test and shall repeat this test, if
necessary, until the requisite test results are obtained without any claim for extra
cost or compensation. The water tightness test shall be conducted as specified in IS:
4127- 1983. The tendered rates for hydraulic structures shall include all costs
incurred by the Contractor for water tightness test. If any such hydraulic structure
or fixture is found to be unsatisfactory at the time of giving this test the Contractor
shall either repair or demolish and construct the same as directed such that the
structure is made absolutely water tight and declared as satisfactory by the
Engineer. The decision of the Engineer will be taken as final. The Contractor may
use at the time of construction, for increasing the water tightness, approved
proprietary chemicals only with the express permission of the Engineer to serve the
purpose of the Contractor to facilitate such type of work for his own convenience
and advantage. But in all such cases, the Contractor will not be entitled to any extra
rate. The Contractor shall see that every effort is made to make structures and
fixtures water tight, by resorting to such chemicals and making efficient use of
proportion and grading of materials etc., as provided originally in the Specifications.
4.17 Clearing of site - All surplus materials, and all tools and temporary structures
shall be removed from the site as directed by Engineer and the construction site left
clean to the satisfaction of Engineer.
4.18 Service lines if damaged during excavation shall be made good either by Contractor
or by other agency as Engineer may decide and the cost of the same shall be borne
by the Contractor wholly in either case.
Page 16
15
4.19 Contractor shall not be paid any additional compensation for excess excavation
over what is specified as well as for any remedial measures that are specified.
4.20 All steel materials shall be painted with two coats of anticorrosive epoxy paint over
a priming coat, all approved by the Authority.
4.21 The bidder shall study each item and inspect the site to his satisfaction before
quoting and detailed scope of work, is verified at site. The foundations, pipe lines
and other structures completed as a part of this tender are to be 100% safe, durable
and functional. He shall be responsible to conduct the necessary test on part of the
items of materials used and as a whole after the completion of work as per the
norms stipulated by the Indian Standard codes and satisfy the Engineer in charge/
Agreement authority on the acceptability, quality, performance and adequacy of the
system in parts and as a whole.
4.22 Tenderer should furnish the names of suppliers of each item if he is not a
manufacturer of the same. The full particulars regarding method of execution of
work or any other relevant information shall be furnished to enable the Authority
to have a correct evaluation of the technical bid in Cover B.
4.23 Blasting
4.23.1 Blasting shall be carried out in a manner that completes the excavation to
the lines indicated with the least disturbance to adjacent material. It shall be done
only with the written permission of the Engineer. All the statutory laws, regulations,
rules, etc., pertaining to the acquisition, transport, storage, handling and use of
explosives shall be strictly followed.
4.23.2 The Contractor may adopt any method or methods of blasting consistent
with the safety and job requirements. Prior to starting any phase of the operation
the Contractor shall provide information describing pertinent blasting procedures,
dimensions and notes.
4.23.3 The magazine for the storage of explosive shall be built to the designs and
Specifications of the Explosives Department concerned and located at the approved
site. No unauthorized person shall be admitted into the magazine which when not
in use shall be kept securely locked. No matches or inflammable material shall be
allowed in the magazine. The magazine shall have an effective lighting conductor.
The following shall be hung in the lobby of the magazine.
Page 17
16
1. A copy of the relevant rules regarding safe storage both in English and in the
language with which the workers concerned is familiar.
2. A statement of up-to-date stock in the magazine.
3. A certificate showing the last date of testing of the lighting conductor
4. A notice that smoking is strictly prohibited.
4.23.4 All explosive shall be stored in a secure manner in compliance with all laws
and ordinances, and all such storage places shall be clearly marked. Where no local
laws or ordinances apply, storage shall be provided to the satisfaction of the
Engineer and in general not closer than 300 m from the road or from any building
or camping area or place of human occupancy. In addition to these, the Contractor
shall also observe the following instructions and any further additional instructions
which may be given by the Engineer and shall be responsible for damage to
property and any accident which may occur to workmen or the public on account of
any operations connected with the storage, handling or use of explosives and
blasting. The Engineer shall frequently check the Contractor’s compliance with
these precautions.
4.24 Blasting Operations
4.24.1 The blasting shall be carried out during fixed hours of the day, preferably
during the mid-day luncheon hour or at the close of the work as ordered in writing
by the Engineer. The hours shall be made known to the people in the vicinity. All the
charges shall be prepared by the man in charge only.
4.24.2 The Contractor shall notify each public utility company having structures in
proximity to the site of the work of his intention to use explosives. Such notice shall
be given sufficiently in advance to enable the companies to take such steps as they
may deem necessary to protect their property from injury. In advance of any
blasting work within 50 m of any railway track or structures, the Contractor shall
notify the concerned Railway Authority of the location, date, time and approximate
duration of such blasting operations.
4.24.3 Red danger flags shall be displayed prominently in all directions during the
blasting operations. The flags shall be planted 200 m from the blasting site in all
directions. People, except those who actually light the fuse, shall be prohibited from
entering this area, and all persons including workmen shall be excluded from the
Page 18
17
flagged area at least 10 minutes before the firing, a warning siren being sounded for
the purpose.
4.24.4 The charge holes shall be drilled to required depths and at suitable places.
Blasting should be as light as possible consistent with thorough breakage of
material necessary for economic loading and hauling. Any method of blasting which
leads to overshooting shall be discontinued.
4.24.5 When blasting is done with powder, the fuse cut to the required length shall
be inserted into the hole and the powder dropped in. The powder shall be gently
tamped with copper rods with rounded ends. The explosive powder shall then be
covered with tamping material which shall be tamped lightly but firmly.
4.24.6 When blasting is done with dynamite and other high explosive, dynamite
cartridges shall be prepared by inserting the square cut end of a fuse into the
detonator and finishing it with nippers at the open end, the detonator gently pushed
into the primer leaving 1/3rd of copper tube exposed outside. The paper of the
cartridge shall then the closed up and securely bound with wire or twine. The
primer shall be housed into the explosive. Boreholes shall be of such size that the
cartridge can easily go down. The holes shall be cleared of all debris and explosive
inserted. The space of about 200 mm above the charge shall then be gently filled
with dry clay, pressed home and the rest of the tamping formed of any convenient
material gently packed with a wooden rammer.
4.24.7 At a time, not more than 10 such charges will be prepared and fired. The
man in charge shall blow a siren in a recognized manner for cautioning the people.
All the people shall then be required to move to safe distances. The charges shall be
lighted by the man-in-charge only. The man-in charge shall count the number of
explosions. He shall satisfy himself that all the charges have been exploded before
allowing the workmen to go back to the work site.
4.25. MANMADE STRUCTURES, OTHER UTILITIES- AFFECTING THE WORK
When the works under this contract are executed situations may arise when
the works are affected by other manmade structures either in service or
abandoned. It is also likely that other utility services installed by various
Government bodies are affected by the works under this contract. It shall be the
duty of the contractor to ensure whether adequate sanction has been obtained from
Page 19
18
the authority concerned for the work with the help of Kerala Water Authority
before the works of such affected portions are undertaken. Any damage caused to
any of the manmade structure or any of the utility services will have to be made
good by the contractor at his cost. The contractor has to restore the original
position if he has to demolish any structure like culverts, compound walls etc.
during the course of work at his own cost.
5. VENDORS LIST
Two copies of complete list of Vendors/ Manufacturers from whom the valves,
specials, spares etc. can be procured with the product specification broachers /
product identification number etc. shall be submitted by the contractor.
6.0 ADDITIONAL INFORMATION.
The following items are appended with this document for the information of the
tenderer.
Annexure - I Tentative Layout Plan of the OHSR and other proposed
components in the land
Annexure – II Location map
Annexure – III Soil investigation report
The bidder shall study each of them and inspect the site to his satisfaction before
quoting. It should be understood that it shall be the contractor’s sole responsibility
that the details under Annexure are verified at site. The foundations and other
structures completed as a part of this tender are to be 100% safe, durable and
functional. He shall be responsible to conduct the necessary test on part of the
items of materials used and as a whole after completion of work as per the norms
stipulated by the Indian standard Codes and satisfy the Engineer in charge /
Agreement authority on the acceptability, quality, performance and adequacy of the
system in parts and as a whole.
6.1 MAINTENANCE
The scope of work includes maintenance of the system for a period of 12 months
from the date of commissioning of the scheme as specified in clause 2.20.
6.2 ASSESSMENT OF COST OF WORK
6.2.1 Tenderer shall assess separately the expenditure that may have to be incurred for
each of the items and provide an itemized schedule of such works without
mentioning rates. Any item of work which has not been specifically mentioned in
Page 20
19
this scope of work but are found imperative for the satisfactory completion of work
shall be considered as included in this scope of work and no claim for any extra
item will be entertained unless specifically approved by the agreement authority.
6.2.2 Bidders shall quote lump sum amount for the work in the prescribed form provided
in the tender document. However, it should be clearly understood that the Authority
can not be charged for any imperfect or incorrect assessment and any unforeseen
items of work, which has not from the unit cost shall be reckoned for payments
under this contract amount.
6.2.3 Tenderer should furnish the names of suppliers of each item if he is not a
manufacture of the same. He should also furnish the full particulars regarding
method of execution of work or any other relevant information of the technical bid
in cover B.
6.3 IMPLIMENTATION SCHEDULE
The work shall be completed in all respects within 15 months and the
commissioned scheme shall be maintained for a period of 12 months from the date
of commissioning of the scheme. In case any maintenance works are attended by
KWA during this period of 12 months due to failure on part of the contractor to turn
up and complete the work, the expense shall be charged from the retention amount
or any other amount due to the contractor.
6.3.1 The contractor shall submit a properly designed schedule bar chart and CPM
network showing his plan of action for the completion of the project. The total
project shall be divided into a minimum of 12 activities and the planed progress
should be indicated clearly.
6.4 CLARIFICATIONS
All clarifications about the work if any should be sought up to 11 am. on
01-06-2018 will be answered through e-mail / published in web and any doubts raised
thereafter will not be entertained.
7 CORRECTIONS AND MODIFICATIONS TO BE INCORPORATED IN VOLUME I OF
THE NIT.
As per proceedings No. KWA/HO/WN 33/97 dated 20/09/2016,
Government Order No. GO(P)No. 429/15/fin dated 28/09/2015 of the Finance
(Industries and Public works-B) Department is implemented in Kerala water
Authority also.
Page 21
20
Again as per proceedings No. KWA/HO/WN 33/97 dated 25/01/2017,
Government Order No. GO(P)No 19/2016/fin dated 03/02/2016 of the Finance
(Industries and Public works-B) Department and Government Order No GO(P)
No.124/2016/fin dated 29/08/2016 of the Finance(Industries and Public works-B)
Department are implemented in Kerala water Authority in toto. (The scanned copy
of the proceedings is attached separately).
Accordingly certain corrections and modifications are to be incorporated in
Volume I of this NIT.The security deposit mentioned in vol. 1 of NIT is redefined as
Performance guarantee. So wherever the term security deposit comes in Vol. 1 of
NIT shall be read as performance guarantee. The collection, repayment and all the
matters regarding Security Deposit in vol. 1 of NIT will be according to Performance
guarantee mentioned in the above Government order.
The performance guarantee mentioned in vol. 1 of NIT is redefined as
Additional performance guarantee. So wherever the term performance guarantee
comes in Vol. 1 of NIT shall be read as Additional performance guarantee. The
collection, repayment and all the matters regarding performance guarantee in vol. 1
of NIT will be according to Additional performance guarantee mentioned in the
above Government order.
The retention amount collected from the bills of the contractor mentioned in
vol. 1 of NIT is redefined as Performance security deposit. So wherever the term
retention amount/retention comes in Vol. 1 of NIT shall be read as Performance
security deposit. The collection, repayment and all the matters regarding retention
and security deposit in vol. 1 of NIT will be according to Performance security
deposit and performance guarantee and mentioned in the above Government order.
As per the above Government order the EMD is redefined and hence the
clause 8.11 of vol. 1of NIT is modified according to item 2 of the above Government
order.All the modifications as per the above proceedings are applicable for this
tender.
The GST implemented by Government of India with effect from 01-07-2017
is applicable for this tender.
TENDERER SUPERINTENDING ENGINEER