1 Build it Green Conference – Beirut – March 30 th 2011 KAUST Project First LEED ® certified project in the Kingdom & biggest LEED® Platinum Certified Project in the world Dr Gauthier BELHOMME PhD, PE Environmental Engineering & Sustainability Director
65
Embed
KAUST LEED Présentation 30 03 2011 it green...1977: Birth of Saudi Oger & Oger International, with Hotel Massarah, Taif, Saudi Arabia. 4 Build it Green Conference – Beirut – March
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
1 Build it Green Conference – Beirut – March 30th 2011
KAUST ProjectFirst LEED® certified project in the Kingdom
& biggest LEED® Platinum Certified Project
in the world
Dr Gauthier BELHOMMEPhD, PE
Environmental Engineering & Sustainability Director
2 Build it Green Conference – Beirut – March 30th 2011
Outline
• OGER Presentation
• KAUST Project Overview
• Project Sustainable Strategy
• LEED Achievements
� Sustainable Site
� Energy & Atmosphere
� Water Efficiency
� Materials & Resources
� Indoor Enviroment Quality
� Innovation In Design
• Project Sustainabilty Benefits
3 Build it Green Conference – Beirut – March 30th 2011
Company Foundation
1950: Marcel Oger founded OGER Co.
1970: Oger uses highest crane in the
world to build the UAP Tower in La
Défense, Paris.
1977: Birth of Saudi Oger & Oger International,
with Hotel Massarah, Taif, Saudi Arabia.
4 Build it Green Conference – Beirut – March 30th 2011
Staff & workforce (Nov. 2009)
More than 4,500
completed projects
Engineering work force
Subsidiaries and Affiliates
Incl. UAEIncl. UAE
Company Overview Today
5 Build it Green Conference – Beirut – March 30th 2011
OGER over the world
6 Build it Green Conference – Beirut – March 30th 2011
King Abdullah Financial District
85 000 m²- LEED® CS v2 Silver
Phare Tower - la Défense - 145 000 m²
LEED® CS v2 Gold
Jabal Omar – LEED® NC v2.2 Silver
Abu Dhabi financial City - 600 000 m²
LEED® CS v2 Gold
PNU -1 000 000 m² - LEED® NC V2.2 Gold
King Abdullah Financial District - 60
000 m² -LEED® NC v2.2 Silver
CARPE DIEM Tower la Défense
50 000 m² - LEED® CS v2 Gold
KAUST – 500 000 m2 - Certified LEED® NC Platinum
LEED® Projects & References
7 Build it Green Conference – Beirut – March 30th 2011
KAUST Project Overview
8 Build it Green Conference – Beirut – March 30th 2011
• Post – Graduate University – Thuwal on the Red Sea (Kingdom of Saudi Arabia)
• Capacity: 3500 residents et 2500 students
• 21 Academic & Administration Buildings
Project Description
9 Build it Green Conference – Beirut – March 30th 2011
ACADEMIC BUILDINGS ADMINISTRATION BUILDINGS
Research Laboratories
Engineering & Science Building
Applied Mathematics Building
High Bay Lab
Greenhouse
4 x 57,000 m²
18,500 m²
32,000 m²
4,000 m²
1,500 m²
Administration & Conference
Library
University Center
Data Center
Auditorium
Mosque
Commons
28,500 m²
17,000 m²
8,000 m²
8,000 m²
14,000 m²
2,000 m²
8,500 m²
Total 284,000 m² Total 86,000 m²
Garage Buildings Area: 105,000 m²
TOTAL BUILDINGS AREA : 475,000 m²
Key numbers
10 Build it Green Conference – Beirut – March 30th 2011
Client
ContractorA/E Company
HOK (USA)
Project Stakeholders
11 Build it Green Conference – Beirut – March 30th 2011
Architectural Complexity
12 Build it Green Conference – Beirut – March 30th 2011
Monumental Canopy (h = 18 m)
Architectural Complexity
13 Build it Green Conference – Beirut – March 30th 2011
Two Solar Towers : h=70m
Architectural Complexity
14 Build it Green Conference – Beirut – March 30th 2011
Architectural Complexity
Laboratoires on Cantilevers (L=13 m) connected by skywalks
15 Build it Green Conference – Beirut – March 30th 2011
Super computer SHAHEEN
Technical Challenges
16 Build it Green Conference – Beirut – March 30th 2011
December 2007
Septembre 2009
Project Schedule
17 Build it Green Conference – Beirut – March 30th 2011